Attachment 2 - Sample Course Development Timeline

View the file

Other files

File Type Posted
Attachment 6.pdf PDF
Amendment 1.PDF PDF
Attachment 5 Task Area B C.xlsx XLSX spreadsheet
Attachment 3.docx DOCX document
Attachment 4.pdf PDF
Attachment 5 - Task Area E.xlsx XLSX spreadsheet
Attachment 5 - Task Area D.xlsx XLSX spreadsheet
Attachment 5 - Task Area A.xlsx XLSX spreadsheet
Attachment - 1.pdf PDF
RFP- DTFH61-11-R-00030.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP DTFH61-11-R-00030 Page 1 of 2

Attachment 2: Sample Course Development Timeline

NHI 141029 Basic Relocation Dates Product Responsibility Status

10/30/07 Kick Off Meeting Team Complete 11/13/07 Detailed Draft Outline to Tech Panel Contractor 11/8/07 11/21/07 Review Outline & Send Edits to Tech Panel Complete 11/27/07 Consolidate Edits & Send to Contractor & COTR COTR Complete 11/27/07 Review & Approve Detailed Outline COTR Complete 01/29/08 Draft PLP to Tech Panel Contractor 01/25/08 02/05/08 Review PLP & Send Edits to COTR Tech Panel Complete 02/08/08 Consolidate PLP Edits & Send to Contractor &

COTR

COTR 02/8/08

02/12/08 Final Review & Approval of PLP COTR Complete 03/21/08 Draft Module 1 to Tech Panel Contractor 03/18/08 03/25/08 Module 1 Webinar Team 03/25/08 03/26/08 Written Comments Module 1 to COTR Tech Panel 03/26/08 03/31/08 Consolidate Module 1 Comments to Contractor &

COTR

COTR 03/31/08

04/09/08 Final Module 1 to COTR Contractor 04/04/08 04/15/08 Review & Approval of Module 1 COTR 04/08/08 05/08/08 Draft Module 2 to Tech Panel Contractor 05/09/08 05/15/08 Module 2 Webinar Team Complete 05/16/08 Written Comments Module 2 to Tech Panel 05/16/08 05/21/08 Consolidate Mod 2 Comments & Send to

Contractor & COTR

COTR 05/21/08

05/28/08 Final Module 2 to COTR Contractor 06/04/08 06/04/08 Review & Approval of Module 2 COTR 06/10/08 06/03/08 Draft Module 3 to Tech Panel Contractor 05/30/08 06/05/08 Written Comments Module 3 to Tech Panel Complete 06/09/08 Consolidate Mod 3 Comments to Team COTR 06/07/08 06/09/08 Module 3 Webinar Team Complete 06/11/08 Final Module 3 to COTR Contractor 06/11/08 06/17/08 Review & Approval of Module 3 COTR 06/17/08 06/20/08 Draft Module 4 & 5 to Tech Panel Contractor 06/20/08 06/26/08 Written Comments Module 4 & 5 to COTR Tech Panel 06/26/08 06/30/08 Consolidate Mods 4 & 5 Comments to Team Marshall 06/30/08 06/30/08 Module 4 & 5 Webinar Team Complete 07/02/08 Final Module 4 & 5 to COTR Contractor 07/02/08 07/08/08 Review & Approval of Module 4 & 5 COTR 07/08/08 07/08/08 Draft Module 6 & 7 to Tech Panel Contractor 07/08/08 07/11/08 Written Comments Module 6 & 7 to COTR Tech Panel 07/11/08 07/15/08 Consolidate Mods 6 & 7 Comments to Team COTR 07/15/08 07/15/08 Module 6 & 7 Webinar Team Complete 07/23/08 Final Module 6 & 7 to COTR Contractor 07/23/08

RFP DTFH61-11-R-00036 Page 2 of 2

07/28/08 Review & Approval of Module 6 & 7 COTR 07/28/08 07/30-31/08 Technical Walk Through Team Complete 08/12-14/08 Pilot- Portland, OR Team Complete

9/30/08 Final Curriculum Materials Contractor Complete

COTR
COTR
Marshall
COTR