ZLA Major Mech Responses to letter 03 dated 10-3-2016.pdf

PDF 13 KB Posted

Attached to
MAJOR MECHNICAL MODERNIZATION, ZLA, PALMDALE, CA
Solicitation number
DTFAWN-16-R-01814
Issued by

About this file

ZLA Major Mech Responses to letter 03 dated 10-3-2016 (pdf)

View the file

Other files

File Type Posted
ZLA Major Mech Responses to letter 02 dated 9-30-2016.pdf PDF
ZLA Major Mech Responses to letter 04 dated 10-4-2016.pdf PDF
SF-30 AMEND2.doc DOC document
WP-D-501-41474-CTR-E101.-12pdf.pdf PDF
DTFAWN-16-R-01814 VERSION 2 (BP - Rev 4.BP - Rev 4 (pdf —
ZLA_CWB_MAJOR-MECH - Specs 4.pdf PDF
WP-D-501-41474-CTR-E106.5pdf.pdf PDF
LAX-E-5896-S4.-9pdf.pdf PDF
ZLA_CWB_MAJOR-MECH - Preliminary Commissioning Plan.pdf PDF
LAX-E-5896-S5-10.pdf PDF
LAX-E-5896-S1-7.pdf PDF
WP-D-501-41474-CTR-E105.-13pdf.pdf PDF
LAX-E-5896-S6.-11pdf.pdf PDF
SF-30.AMEND-MMM PALMDALE.doc DOC document
customer satisfaction survey.docx DOCX document
ZLA Site Walk Sign in Sheet 9-13-2016.pdf PDF
LAX-E-5896-S2-8.pdf PDF
ZLA Major Mech Responses to letter 01 dated 9-30-2016.pdf PDF
ZLA Major Mech Responses to letter 03 dated 10-3-2016.pdf PDF
WP-D-501-41474-CTR-E110.5pdf.pdf PDF
1442-modernization at palmdale.pdf PDF
1442-modernization at palmdale.pdf PDF
ZLA_CWB_MAJOR-MECH - Drawings 1(Signed).Signed —
SF-30 AMEND3.doc DOC document
WAGE RATES.txt TXT text file
ZLA_CWB_MAJOR-MECH - HAZMAT Plan 2.pdf PDF
LAX-E-5896-S1-7.pdf PDF
WP-D-501-41474-CTR-E101.-12pdf.pdf PDF
LAX-E-5896-S4.-9pdf.pdf PDF
LAX-E-5896-S5-10.pdf PDF
ZLA Major Mech Responses to letter 01 dated 9-30-2016.pdf PDF
WP-D-501-41474-CTR-E110.5pdf.pdf PDF
LAX-E-5896-S2-8.pdf PDF
ZLA_CWB_MAJOR-MECH - Drawings 1(Signed).Signed —
WAGE RATES.txt TXT text file
WP-D-501-41474-CTR-E105.-13pdf.pdf PDF
WP-D-501-41474-CTR-E106.5pdf.pdf PDF
SF-30 AMEND2.doc DOC document
ZLA_CWB_MAJOR-MECH - Specs 4.pdf PDF
DTFAWN-16-R-01814 VERSION 2 (BP - Rev 4.BP - Rev 4 (pdf —
1442-modernization at palmdale.pdf PDF
ZLA Site Walk Sign in Sheet 9-13-2016.pdf PDF
ZLA Major Mech Responses to letter 04 dated 10-4-2016.pdf PDF
LAX-E-5896-S6.-11pdf.pdf PDF
ZLA_CWB_MAJOR-MECH - HAZMAT Plan 2.pdf PDF
ZLA Major Mech Responses to letter 02 dated 9-30-2016.pdf PDF
ZLA_CWB_MAJOR-MECH - Preliminary Commissioning Plan.pdf PDF
SF-30.AMEND-MMM PALMDALE.doc DOC document
customer satisfaction survey.docx DOCX document
ZLA Major Mech Responses to letter 03 dated 10-3-2016.pdf PDF
Show 40 more

Latest 50 of 140 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

October 3, 2016 Letter No. 02

Project: DTFAWN-16-R-01814 – Major Mechanical Modernization, Palmdale ZLA

RE: Questions

1. Note 9 on sheet M203 states "vacuum piping to extend outside wall furring coordinate with arch", what is the pipe size and length of the pipe run? Piping shall be 2” in size to match existing. Length of pipe is quite short. The current vacuum hose connections of piping on the columns needs to be extended through the new furring around the columns.

2. Is the mechanical seismic engineer required to be licensed in the state of California?

Engineer shall be licensed in the state of California or have licensure reciprocity for the state of California.

3. Specifications for chillers state chillers are a 2 pass system, after reviewing the manufacturer’s drawings of the specified York Chillers. The manufac. specifications state a 3 pass system. 1 and 3 pass chiller systems have cts/ctr and the chr/chs on the same side of the chiller. Plans show cts/ctr and chs/chr on separate sides of the chillers. Please verify. Basis of design chillers (York YMC2) are available as a 2 pass system. York also has waterboxes to be connected on both end of the tubes.

Proceed with chillers as specified, as a 2-pass, and as shown on drawings.

4. Please clarify the temporary equipment responsibilities (temp chiller, pumps, controls, etc.). Responsibilities are as follows (Providing, maintenance, repairs, cleaning, equipment set-up, equipment tear-down, etc). Temporary equipment requirements on M005 outline all responsibilities with regards to the temporary tower system. The FAA is only responsible for the operation only of the towers once the facility has transitioned to temporary service. We are in hopes that the contractors are in contact with a full service rental company such as Aggreko (the basis of design) to help with the bid for the temporary system.

5. For AHU-120 on sheet M203, the note next to the AHU states "typ. 4 places". Are there

4 AHU's in various locations that require piping or is the "typ" note stating the four (4) pipes shown connecting to AHU 120 only. Please advise. Note 11 is a requirement for the all 4 pipes to/from AHU-120.

6. Are Johnson Controls, controls and equipment be allowable products on the project? The

FAA Program Office selected Schneider Electric StruxureWare/Andover Continuum as the national standard for all FAA en-route facilities throughout the country. Therefore, the new Direct Digital Control System (DDCS) shall be StruxureWare Andover Continuum BACnet system by Schneider

Electric, Inc as is required by the SECTION 23 09 00 - INSTRUMENTATION AND CONTROLS

FOR HVAC

7. Is there a current water treatment contract (Inhibitors, corrosion protection and scale protection). If so who is the company responsible for the facility? Contact information as follows: Jess Zablan of Chemco Products Company, Office: (866) 243-6261, Cell: (562) 602-2811.