Supplemental Specification FAA C90 280S Asphalt Seal Coating.pdf

PDF 61 KB Posted

Attached to
The Federal Aviation Administration (FAA) has a requirement for Asphalt Replacement Projects at the Canton, MI and LaGrange, IN ARSR Radar Sites.
Solicitation number
DTFAAC-17-R-00011
Issued by

About this file

Supplemental Specification FAA C90 280S Asphalt Seal Coating (pdf)

View the file

Other files

File Type Posted
Attachment Past Performance Questionnaire.pdf PDF
Spec FAA-C90-366 SOW.pdf PDF
C90-367 QTZ Asphalt Drawings.pdf PDF
Contractor's Release.doc DOC document
Supplemental Specification FAA C90 280S Asphalt Seal Coating.pdf PDF
WD IN160005 10-07-2016.pdf PDF
Spec FAA-C90-367 SOW.pdf PDF
0622216 C90-366 QDT Rd Drawings-R.pdf PDF
WD MI160101 09-09-2016.pdf PDF
Question and Answers.docx DOCX document
DTFAAC-17-R-00011.docx DOCX document
Attachment Experience Information Form.pdf PDF
DTFAAC-16-R-05875 A001.pdf PDF
Spec FAA-C90-367 SOW.pdf PDF
Question and Answers.docx DOCX document
Spec FAA-C90-366 SOW.pdf PDF
Contractor's Release.doc DOC document
DTFAAC-17-R-00011.docx DOCX document
Spec FAA-C90-366 SOW.pdf PDF
Attachment Past Performance Questionnaire.pdf PDF
WD IN160005 10-07-2016.pdf PDF
Attachment Experience Information Form.pdf PDF
C90-367 QTZ Asphalt Drawings.pdf PDF
WD MI160101 09-09-2016.pdf PDF
DTFAAC-16-R-05875 A001.pdf PDF
Supplemental Specification FAA C90 280S Asphalt Seal Coating.pdf PDF
Attachment Experience Information Form.pdf PDF
WD MI160101 09-09-2016.pdf PDF
Spec FAA-C90-366 SOW.pdf PDF
Contractor's Release.doc DOC document
WD IN160005 10-07-2016.pdf PDF
Spec FAA-C90-367 SOW.pdf PDF
DTFAAC-17-R-00011.docx DOCX document
C90-367 QTZ Asphalt Drawings.pdf PDF
Attachment Past Performance Questionnaire.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 Department of Transportation

Federal Aviation Administration

Supplemental Specification FAA-GL-918C, Construction of Terminal Facilities.

Division 2

12 October, 2016

Division 2 Supplemental Specifications – Asphalt Seal Coating

Note: This standard specification is used for construction of multiple FAA facilities. Based on the scope of work, some sections of this specification may not apply.

PART 1 GENERAL REQUIREMENTS

1.01 SCOPE OF SPECIFICAITON.

A. Product and application requirements for an engineered resin emulsion sealcoat slurry over new and/or aged asphalt concrete paving.

1.02 RELATED SECTIONS.

A Department of Transportation Federal Aviation Administration Specification FAA-

GL-918C, Construction of Terminal Facilities.

1.03 R E F E R E N C E S .

A. American Society for Testing and Materials (ASTM)

1. C 136 Method of Sieve Analysis of Fine and Course Aggregates

2. D 2939 Method for Testing Emulsified Bitumens used as Protective

Coatings

3. D 244 Standard Specification for Emulsified Asphalt

4. D 3910 Practices for Design, Testing, and Construction of Slurry Seal

1.04 S Y S T E M DESCRIPTION.

A. Provide one application of the coating (emulsion slurry) in all areas.

1.05 S U B M I T T A L S .

A. Product Data

1. Submit manufacturer's printed Product Data Sheet.

2 Department of Transportation

Supplemental Specification FAA-GL-918C, Construction of Terminal Facilities.

1.06 Q U A L I T Y ASSURANCE.

A. Certification

Submit copy of certificate from manufacturer stating applicator is their authorized installer.

B. Certificate of Authenticity

Submit a certificate executed by the manufacturer of the sealer stating the specific product was placed on the pavement.

1.07 P R O J E C T /SITE CONDITIONS.

A. ENVIRONMENTAL REQUIREMENTS

1. Apply coating when pavement temperature is at least fifty (50) degrees

F. and air temperature is fifty (50) degrees F. and rising.

2. Apply coating during dry weather and when rain is not anticipated within eight (8) hours after application is completed.

1.08 W A R R A N T Y .

A. Submit two (2) year written dual warranty by materials manufacturer and contractor.

B. Warranty will include statements that warrant performance of the coating against flaking, chipping, loss of adhesion or other abnormal wear.

C. In the event of abnormal wear within the warranty period manufacturer will supply material and contractor will recoat with specified material to the affected area at no cost to the owner.

3 Department of Transportation

Supplemental Specification FAA-GL-918C, Construction of Terminal Facilities.

PART 2 PRODUCTS

2.01 M A N U F A C T U R E R .

A. Neyra Industries, Inc., Cincinnati, Ohio: Jennite

2.02 M A T E R I A L S .

A. Sealer: Jennite

1. A high solids refined coal tar emulsion with pure high molecular weight polymer rubber hot blended into the tar prior to emulsification.

2. Minimum 52% solids – with ash of non-volatile in a range of 34%-38%

3. Maximum dilution of 15 parts water per 100 parts Jennite

B. Crack Sealant: Thermo-Seal PLS

1. Hot applied, elastomeric type crack sealant compatible with pavement coating.

C. Pavement Primer: Polyprime

(Priming is not required to obtain manufacturers warranty but may be recommended depending on condition of pavement.

1. Acrylic based primer compatible with pavement coating.

D. Sand: As recommended in printed data sheets by sealer manufacturer.

1. Washed, dry silica sand free of dust, trash, clay, organic materials or other contaminants.

2. Gradation: To have an American Foundry Society grain fineness number that is no less than fifty (50) and no more than seventy (70), when tested in accordance with ASTM C 136.

E. Mixing Water

1. Potable and free from harmful soluble salts.

2. Temperature of the water: minimum fifty (50) degrees F.

4 Department of Transportation

Supplemental Specification FAA-GL-918C, Construction of Terminal Facilities.

2.03 E Q U I P M E N T .

A. Use equipment that keeps the mixture homogeneous at all times and is capable of applying required coating weights evenly over entire width of application mechanism in order to provide a uniformly coated surface.

2.04 M I X E S .

A. Add five (5) pounds of sand to the emulsion and mix with power equipment to a homogeneous condition. (Sand to be added after water)

B. Add water to the coating mix as required for application not to exceed fifteen

(15) per cent of emulsion.

5 Department of Transportation

Supplemental Specification FAA-GL-918C, Construction of Terminal Facilities.

PART 3 EXECUTION

3.01 I N S P E C T I O N .

A. Inspect existing pavement surfaces for conditions and defects that will adversely affect quality of work, and which cannot be put into an acceptable condition through normal preparatory work as specified.

B. Do not place coating over unsound oil spots softened by fuel or oil. If this condition exists, notify Architect/Engineer/owner.

C. Starting installation constitutes Contractor's acceptance of surface as suitable for installation.

3.02 P R E P A R A T I O N - AGED PAVEMENT.

A.

B.

C.

Repairing Asphalt Concrete Pavement: Repair areas shown in schedule.] Crack

Sealing: Apply crack sealant as detailed in Section 32 01 17.61.]

Cleaning

1. Clean pavement surface prior to applying coating.

D.

Protection

1. Protect adjacent curbs, walks, fences, and other items from receiving coating.

E.

Priming Oil Spots

1. Clean oil spots and treat with primer.

2. (If priming is required apply Polyprime at a rate of .03-.06 gallons per square yard, as per Polyprime data sheet.)

6 Department of Transportation

Supplemental Specification FAA-GL-918C, Construction of Terminal Facilities.

3.03 P R E P A R A T I O N - NEW PAVEMENT.

A. Curing

1. Allow new asphalt to cure at least thirty (30) days before applying pavement coating.

B. Cleaning

1. Clean pavement surface prior to applying primer coat and coating.

C. Protection

1. Protect adjacent curbs, walks, fences, and other items from receiving primer and coating.

3.04 A P P L I C A T I O N .

A. Apply all coats uniformly at a rate of 0.14 - 0.17 gallons per square yard per coat using mixed diluted material.

B. Allow each coat to cure sufficiently to take traffic without scuffing.

C. Allow final coat to cure a minimum of twenty four (24) hours under good drying conditions before allowing traffic.

3.05 C L E A N I N G AFTER APPLICATION

A. Remove any coating from surfaces other than those requiring coating.

3.06 P R O T E C T I O N .

A. Barricade coated areas until the coating has dried sufficiently for traffic.

7 Department of Transportation

Supplemental Specification FAA-GL-918C, Construction of Terminal Facilities.

3.07 PAVEMENT MARKING.

A. Pavement marking paint shall be Latex, water-base emulsion, ready-mixed, complying with FS TT-P-1952.

1. Color: White.

2. Color: Yellow.

3. Color: Blue.

End Section