This is a Direct Solicitation issued by the Michigan Department of Environment, Great Lakes, and Energy for plugging, drilling, re-drilling, and site restoration services at three orphan wells located in Gratiot County: S.S. Smith 2, MCGC NH-333-A, and MCGC NH-350A. All three wells are gas storage wellheads with orbit valves operated by New Haven Energy LLC. Eligible bidders must have been prequalified and awarded contracts through one of five specified RFPs (210000000834, 220000000547, 220000001850, 220000002631, and 240000000951), and attendance at the mandatory pre-proposal meeting on July 9, 2026, at 10:00 a.m. Eastern at the New Haven Compressor Station in New Haven Township is required for proposal submission eligibility. The proposal deadline is 3:00 p.m. Eastern on July 21, 2026, with submission required through the Michigan SIGMA VSS electronic system. The pre-bid meeting will include site inspection at well locations, for which contractors are responsible for gathering project information. A pre-construction meeting will be scheduled with the successful vendor prior to project mobilization.

Bidders must submit detailed pricing for all rated items and provide a project timeline broken down into minimum categories of Site Prep, Mobilization/Demobilization, Plugging, and Site Restoration. The winning bidder will be selected based on best value determination combining technical evaluation and pricing; technical proposals are scored on key personnel (25 points), business-owned equipment list (25 points), technical experience and ability (25 points), and vendor questions worksheet (25 points), with a minimum score of 80 points required for award consideration. The awarded contractor and all subcontractors must comply with Davis-Bacon prevailing wage requirements, as federal funds are being used for this project. Pricing must be firm for the duration of the project with no permitted price changes, and the state will use bidder information to determine fair market value without obligation to accept the lowest price proposal. Service-disabled veteran-owned business status will be considered under MCL 18.1261(8) during evaluation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF MICHIGAN

Department of Environment, Great Lakes, and Energy New Haven Energy LLC Section 3 Orphan Well Plugging Project (Gratiot County) – 3 Wells

Direct Solicitation No. 260000000032 Solicitation Manager Name: Lisa VanOstran Direct Phone: 517-599-7680 Email: vanostranl@michigan.gov

This is a Direct Solicitation (DS) for:

Plugging, drilling, re-drilling, and site restoration at following 3 wells located in Gratiot County: S.S. Smith 2, MCGC NH-333-A, and the MCGC NH-350A.

Only vendors who have been awarded a Contract through the prequalification process under RFP# 210000000834, 220000000547, 220000001850, 220000002631 and 240000000951 are eligible to submit a proposal for these services. All terms, conditions, specifications agreed upon during the RFP process remain in effect for this project.

DS Timeline

Event
Time
Date
DS issue date
N/A
Monday, June 29, 2026
Pre-Bid Meeting
10:00 a.m. Eastern
Thursday, July 9, 2026
Deadline for bidders to submit questions about this DS
3:00 p.m. Eastern
Tuesday, July 14, 2026
Anticipated date the State will post answers to bidder questions on www.michigan.gov/SIGMAVSS
Thursday, July 16, 2026
Proposal deadline*
3:00 p.m. Eastern
Tuesday, July 21, 2026
Pre-construction meeting

TBD

Anticipated project begin date

TBD

*A bidder’s proposal received at 3:00:01 p.m. Eastern is late and subject to disqualification.

This DS is subject to change. Check www.michigan.gov/SIGMAVSS for current information.

MANDATORY PRE-PROPOSAL MEETING

A pre-proposal meeting will be held on Thursday, July 9, 2026, at 10:00 a.m. Eastern. Only those Contractors who attend the meeting will be able to submit a proposal. The meeting will be held at the project site:

Site Location: The meeting will commence at the entrance driveway at the New Haven Compressor Station, which is located on north side of W. Fillmore Road, approximately 0.25 miles west of the intersection with Warner Road and West Fillmore Road, in New Haven Township, Section 4, Gratiot County. It will be the Contractor’s responsibility to visit well locations to gather important information for project bid. The State of Michigan will not be visiting well locations. See well location map below in this DS document.

The purpose of the pre-proposal meeting will be to inspect the site and discuss the work to be performed. Statements made by the Solicitation Manager or designee at a pre-proposal meeting are not considered modifications to the DS. If, however, the Solicitation Manager determines modifications to the RFP are warranted after the meeting, modifications will be posted in writing on www.michigan.gov/SIGMAVSS as explained in the Modifications section of this document.

The meeting will start promptly at 10:00 a.m. EST.

MODIFICATIONS

The State may modify this DS at any time. Modifications will be posted on www.michigan.gov/SIGMAVSS. This is the only method by which the DS may be modified.

QUESTIONS

Bidder questions about this DS must be emailed to the Solicitation Manager no later than the time and date specified on the Cover Page. In the interest of transparency, only written questions are accepted. Answers to questions will be posted on www.michigan.gov/SIGMAVSS. Submit questions using the format below; a Microsoft Excel format or similar is suggested.

Q #
Document and Section
Page #
Bidder Question

DELIVERY OF PROPOSAL

Electronic – The bidder must submit its proposal, all attachments, and any modifications or withdrawals electronically through www.michigan.gov/SIGMAVSS. The bidder should submit all documents in a modifiable (native) format (examples include but are not limited to Microsoft Word or Excel and Google Docs or Sheets). In addition to submitting documents in a modifiable format, the bidder may also submit copies of documents in PDF. Attachment file size is limited to 6 MB per document. Bidder’s failure to submit a proposal as required may result in disqualification. The proposal and attachments must be fully uploaded and submitted prior to the proposal deadline. Do not wait until the last minute to submit a proposal, as the SIGMA VSS system requires the entry of certain information, in addition to uploading and submitting the materials. The SIGMA VSS system will not allow a proposal to be submitted after the proposal deadline identified in the solicitation Closing On/Closing Date fields (Summary view/Detail view), even if a portion of the proposal has been uploaded.

Questions on how to submit information or how to navigate in the SIGMA VSS system can be answered by calling (517) 284-0540 or (888) 734-9749. The Solicitation Manager will not provide assistance related to the submittal of the proposal and all attachments on the day of the proposal deadline. Responsibility for a complete submission lies with the bidder.

EVALUATION PROCESS

If all mandatory minimum requirements are met, the State will evaluate each proposal based on the following factors:

Technical Evaluation Criteria
Weight
1.
Key Personnel – (adequate personnel available to perform the work requested)
25
2.
Business Owned Equipment List – (equipment adequate to perform the work requested)
25
3.
Company’s Technical Experience and Ability – (experience/ability relative to the work requested)
25
4.
Vendor Questions Worksheet (experience relative to the work requested)
25
Total
100

Only those proposals receiving 80 or more technical evaluation points will be considered for award.

The State may utilize all bidder information, without regard to a proposal’s technical score, to determine fair market value for goods or services sought. The State is not obligated to accept the lowest price proposal. If applicable, the State’s evaluation will include consideration of a bidder’s qualified disabled veterans/service-disabled veteran owned business (QDV/SDVOB) status under MCL 18.1261(8). Additional information on the SDVOB preference is available at: Michigan.gov/SDVOB.

SCHEDULE A - STATEMENT OF WORK

Properly Plug and Abandon 3 Wells and Restore Locations in Gratiot County

Well Name
Permit Number
Operator of Record
Comments
S.S. Smith 2
3537
New Haven Energy LLC
Gas storage wellhead with orbit valve
MCGC NH-333-A
27638
New Haven Energy LLC
Gas storage wellhead with orbit valve
MCGC NH-350A
32241
New Haven Energy LLC
Gas storage wellhead with orbit valve

Prior to mobilization, a pre-construction meeting will be conducted with the successful vendor to review and confirm items.

SCHEDULE B – PRICING MATRIX

New Haven Energy LLC Section 3 Orphan Well Plugging Project (Gratiot County) – 3 Wells

SEE ATTACHED PRICING MATRIX FOR BID TABLE

BID AMOUNT (should be the same as Grand Total from Pricing Matrix)

Bidders should provide pricing for ALL items in the ‘Price per Unit’ column of the pricing matrix (even if not necessarily needed for this project). These ‘per unit’ prices are referred to as ‘rated items’ by EGLE staff in the event a change order or approved change to the scope of work is required to complete the project.

Should an award result from this DS, all rates quoted in response to this DS will be firm for the duration of the project. No price changes will be permitted.

Bidders must submit a project timeline in conjunction with their Schedule B - Pricing Matrix. The timeline must be broken down into a minimum of four categories as follows: Site Prep, Mobilization/Demobilization, Plugging, Site Restoration.

An example of a single well project timeline might look like this: 1 day to clear/grub the site, 1 day to mobilize to site, 1 day to rig up, 3 days to plug well and flush/abandon/remove flowline, 1 day to rig down, 2 days to restore site for a total of 9 days to plug the well and finish project.

An example of a multi-well and facility project might look like this: 3 days to clear/grub locations, 1 day to mobilize equipment to project area, 50 days to plug wells (includes time needed to mob between wells, and address flowlines), 15 days to decommission facilities, 5 days to restore sites, 1 day to demobilize equipment from project area for a total of 75 days to complete the project.

The state will review your estimated timeline and pricing to determine the winning bidder. The winning bidder will be the bidder that we determine provides the best value to the state.

The winning bidder and all of its subcontractors must adhere to Davis Bacon Prevailing Wages for this project. It is the responsibility of the winning bidder to ensure that its subcontractor’s pricing for this bid includes Davis Bacon Prevailing Wages.

Please make sure that when you obtain pricing for this bid. that you inform all subcontractors that they must adhere to Davis Bacon Prevailing Wages. The state will not approve a change order related to improper bidding due to the awarded contractor or its subcontractor failing to include Davis Bacon Prevailing Wage rates when calculating their bids.

Federal funds will be used on this project. The awarded Contractor must comply with the Davis-Bacon Act as agreed upon in the signed Contract (Master Agreement) within the Federal Provisions Addendum.

Davis-Bacon Act (Prevailing Wage) If this Contract is a prime construction contract in excess of $2,000, the Contractor (and its Subcontractors) must comply with the Davis-Bacon Act (40 USC 3141-3148) as supplemented by Department of Labor regulations (29 CFR Part 5, “Labor Standards Provisions Applicable to Contracts Covering Federally Financed and Assisted Construction”), and during performance of this Contract the Contractor agrees as follows:

1) All transactions regarding this contract shall be done in compliance with the Davis-Bacon Act (40 U.S.C. 3141- 3144, and 3146-3148) and the requirements of 29 C.F.R. pt. 5 as may be applicable. The contractor shall comply with 40 U.S.C. 3141-3144, and 3146-3148 and the requirements of 29 C.F.R. pt. 5 as applicable.

2) Contractors are required to pay wages to laborers and mechanics at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor.

3) Additionally, contractors are required to pay wages not less than once a week.

Print Name

Print Title

Signature

Date

NEW HAVEN ENERGY PRE-BID MEETING LOCATION MAP

NEW HAVEN ENERGY SECT. 3 WELL PLUGGING LOCATION MAP

image1.jpeg image2.jpeg image3.jpeg image4.jpeg image5.jpeg image6.jpeg image7.jpeg image8.jpeg