DRAWING 1-MH-202A - Exh Fan EF-1 Relocation 630-15-112.pdf

PDF 2 MB Posted

Attached to
Y1DA--630-15-112 RENOVATE RESEARCH AREA - ANIMAL LAB
Solicitation number
36C24222B0034
Issued by

About this file

This solicitation is for a construction contract to renovate a research area and animal lab at a Veterans Affairs Medical Center located in New York. The scope of work includes renovating an existing research area on the 18th floor, extending an exhaust discharge duct at least 25 feet from a new outside air intake in the penthouse, removing demolished materials off site during off hours, and coordinating utility shutdowns. The contractor must provide documentation for all personnel working on VA property, conduct bi-weekly construction meetings and safety inspections, and perform water sampling and testing in accordance with VA and state requirements. The base bid completion time is 730 calendar days, while deduct alternates to remove an autoclave or rack washer would reduce the time to 540 calendar days. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2.

View the file

Other files

File Type Posted
36C24222B0034 0005.docx DOCX document
032221 LSC 1.17.pdf PDF
36C24222B0034 0004.docx DOCX document
032221 LSC 1.15.pdf PDF
1-AS-001.pdf PDF
36C24222B0034 0003.docx DOCX document
36C24222B0034 0002.docx DOCX document
36C24222B0034 0001.docx DOCX document
CONSTRUCTION DRAWINGS 630-15-112 P1-22.pdf PDF
CONSTRUCTION DRAWINGS 630-15-112 P23-45 02.pdf PDF
52-225-2-Buy-American-Certificate.pdf PDF
CONSTRUCTION DRAWINGS 630-15-112.pdf PDF
SPECIFICATIONS 630-15-112.pdf PDF
36C24222B0034_1.docx DOCX document
VA Notice of Limitations on Subcontracting.docx DOCX document
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PENTHOUSE

PARTIAL 19TH FLOOR MECHANICAL PLAN1

MECHANICAL: PARTIAL 19TH

FLOOR DUCTWORK PLAN

1-MH-202

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. ofRevisions: Date

CONSULTANTS: ARCHITECT/ENGINEERS: Office of Construction and Facilities Management

ENGINEERING LLP

www.fellp.com

22 Mulberry St., Suite 2A, Middletown, NY 10940 t 845-343-1481 fx 845-343-4986

181 Church St., Suite 100, Poughkeepsie, NY 12601 t 845-454-9704 fx 855-320-8735

FE PROJECT #: 16-169

FULLY SPRINKLERED

423 EAST 23rd ST. NYC.

06/25/21

630-15-112

DLH / BF

RENOVATE RESEARCH AREA/

ANIMAL LAB 18W

44DSS

100% CONSTRUCTION DOCUMENTS

NY PROFESSIONAL ENGINEER

NO. 076975-1

DANIEL STEINBERG, P.E.

PARTIAL 19TH FLOOR PENTHOUSE ROOF PLAN3PARTIAL 19TH FLOOR PIPING PLAN2

KEYED NOTE: GENERAL NOTE:

GodheimS Arrow

GodheimS Arrow

GodheimS Callout Locate new fan or exhaust discharge at least 25' from new AC-13 OA Intake.

GodheimS Oval

GodheimS Rectangle

GodheimS Arrow

GodheimS Arrow

GodheimS Callout New AC-13 prefilter and OA intake section, 5' W x 14' L x 11' H

GodheimS Text Box

OA

GodheimS Text Box

OA

File details come from the government source that posted it. Updated .