STATEMENT OF WORK
FOR
TOWER 2060 PLATFORM REPAIRS
Prepared by:
Naval Undersea Warfare Center Division Newport Detachment AUTEC
Facilities Branch Code 7032
Donald Rabener, PE
801 Clematis St, West Palm Beach, FL 33401 donald.rabener@navy.mil mailto:donald.rabener@navy.mil
21 May 2021
Table of Contents
1. SCOPE
1.1 Background
1.2 Work Elements
2. APPLICABLE DOCUMENTS
2.1 Important References:
2.2 Drawings
3. ADMINISTRATIVE REQUIREMENTS
3.1 Period of Performance
3.2 Contact List
3.3 Contractor Access and Use of Premises
4. SAFETY
5. ENVIRONMENTAL
5. PERFORMANCE REQUIREMENTS
5.1 Submittals
5.2 Preconstruction Conference
5.3 Existing Work
5.4 Occupancy of Premises
6. PROJECT CLOSEOUT
6.1 Cleanup
6.2 Documentation
6.3 Warranty
1. SCOPE
This Statement of Work (SOW) defines the effort required to repair the existing platform on Tower 2060 at the Atlantic Undersea Test and Evaluation Center (AUTEC), located on Andros Island, Bahamas. The repair work consists of the removal of the existing radome cover, replacement of the existing steel decking that makes up the interior of the floor of the radome, removal and replacement of the steel I-beams which pass under the radome assembly, removal and replacement of associated nuts and bolts, and an exact OEM radome cover replacement for what is currently installed. Existing HVAC inside the radome will be removed by the AUTEC Maintenance and Operations contractor prior to commencement of work and is not included in this scope.
1.1 Background
AUTEC is a Naval testing range under the command of the Naval Undersea Warfare Center (NUWC)
Division Newport. The test range is located on Andros Island, Bahamas, approximately 180 miles southeast of West Palm Beach, Florida. AUTEC operates two aircraft that transport personnel and air freight between West Palm Beach, FL and Andros Island. All other freight and heavy cargo is shipped to the AUTEC main base facility (Site 1) via Military Sealift Command (MSC) barge out of Port
Canaveral, FL.
Facility 2060 is a 60’ OASYS-ESM system tower located at Site 2. AUTEC Site 2 is located on Andros
Island, Bahamas and is a remote location that is approximately 20 miles south of Site 1.
In April 2014, a tower inspection was performed followed by a report. The report identified numerous issues primarily associated with corrosion. As the tower was not in use at the time of the reported findings, repairs were deferred until 2018 when new requirements arose for testing equipment to be installed atop the tower. Repairs to the tower, as identified in the report, were concluded in SEP 2019 however during the time that transpired between the report being furnished and the repair work being completed, additional deficiencies were identified. The existing deck under the existing radome was found to be substantially corroded. During the course of the repairs, the deck was cleaned, treated, and painted, however that work was only guaranteed for a period of 5 years before corrosion overtakes and affects integrity and stability.
1.2 Work Elements
Replacement of the steel deck, replacement of all necessary hardware, and furnish and install a new
L3 Essco radome cover.
1.2.1 Contractor is permitted to utilize AUTEC flights to transport crew members from West Palm
Beach, Florida to Andros Island. Once on Andros Island, contractors are permitted to utilize base transient lodging at a rate of $40 per night stay with the exception of foreign national workforce, who are required to be housed in off-site lodging. Contractor shall provide necessary means to travel to and from tower site on a daily basis. This includes obtaining necessary local insurance and registration paperwork. Contractor may utilize the MSC transport barge for shipment of equipment, materials, and tools from the designated Port Canaveral location to AUTEC Site 1.
1.2.2 All workers must be escorted while working on the tower. Escorts will be provided. Upon execution of the contract, the contractor shall provide a tentative schedule showing dates and times that work will be performed so that escorts can be arranged. This schedule shall be updated weekly.
1.2.3 All work on the tower shall be coordinated with NUWC DET AUTEC Test Operations to ensure mitigation of any potential radio frequency (RF) hazards. This communication will be facilitated through the NUWC DET AUTEC Base Operations on-site representative no less than 14 days prior to commencement of field activities.
1.2.4 If any work requires the use of open-flame or produces heat and/or sparks, a Hot Work permit shall be obtained prior to commencement. The Hot Work permit request will be formally communicated via e-mail to the NUWC DET AUTEC Base Operations on-site representative.
1.2.5 Contractor shall provide a fire extinguisher on site when any hot work is taking place.
1.2.6 Contractor shall make repairs to any damage caused by performance of work.
1.2.7 Contractor shall remove the existing radome assembly. AUTEC will be responsible for the disposal of the existing radome and all other demolished material.
1.2.8 Erection of steel shall be in accordance with “Steel Construction Manual” Fifteenth Edition.
All steel shall be ASTM A36 Except steel pipe, which shall be ASTM A53 Grade B. All steel is to be hot-dipped galvanized in accordance with ASTM A-123 or A-153. Any field drilled hole or cut steel shall be touched up with galvalume zinc rich paint or equal. All bolts shall be A325. No modifications shall be made to the structure without approval of engineer.
1.2.9 Contractor shall remove and replace steel decking which makes up the floor of the radome.
The base of the radome is a pentagon with outside diameter of 16’ (approximately 610 ft2 of steel decking). Radome is to be mounted to meet ±1/8” level requirement per the manufacturer.
Contractor to shim the base ring as necessary by adding washers at bolt hole locations to comply.
1.2.10 Contractor shall remove and replace steel I-beams which pass under the radome assembly.
Platform Framing Assembly, including beams, girts, angle, channel, grating, and plate dimensions and specifications are available on as-built drawing 79601-S05 provided.
1.2.11 All nuts, bolts, and other associated hardware shall be replaced.
1.2.12 A specific list of components shall be furnished upon project award as part of the project submittals.
1.2.13 Contractor shall procure, furnish, and install a new, exact OEM replacement, L3 Essco radome cover Model M16-72-2200. Refer to provided Technical Manual TM01-13 for complete radome specifications.
1.2.14 Crane and operator will be provided by NUWCDETAUTEC Maintenance and Operations
(M&O) contractor.
1.2.15 Contractor shall be self-contained. They shall bring all their own equipment and spare parts, lubricants, tools, mechanics, etc. There are no mechanics and spare parts available to them on the base nor off the base.
1.2.15 Fuel may be purchased at the Base at the Defense Logistics Agency (DLA) price. The contractor must register and establish an account with DLA prior to using the base filling station services.
2. APPLICABLE DOCUMENTS
The following documents are applicable to this Statement of Work:
2.1 Important References:
R444- 14 Tower inspection
2.2 Drawings
C006-00 Fac. 2060 Asbuilts.pdf
3. ADMINISTRATIVE REQUIREMENTS
3.1 Period of Performance
All work must be completed with 180 days from notice to proceed. Any modifications or extensions must be requested through the Contracting Officer for review and discussion. Once work has commenced, the radome shall not be out of service for a period greater than 28 days.
3.2 Contact List
Provide a list of contact personnel. The contact list must contain the names of key contractor and subcontractor points of contact, their title, addresses, and telephone numbers for use in the event of an emergency. Regularly update the contact list as work changes to ensure it is current.
3.3 Contractor Access and Use of Premises
3.3.1 Activity Regulations - Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas.
Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark
Contractor equipment for identification.
3.3.2 Visitors. All personnel visiting AUTEC for unclassified, official business purposes must complete a visit request using JPAS. If your activity does not have access to JPAS, send requested information on Company Letterhead, signed by the Facility Security Officer (FSO). Visitors may not sign their own visit requests. Letters must contain the information noted below and can be sent via fax 561-671-2857 Attn: WPB Security or U.S. mail to: NUWCDETAUTEC, 801 Clematis St Suite #1, WEST PALM BEACH FL 33401-5105.
Visitor's full name:
Date of Birth:
Place of Birth:
Citizenship:
Purpose of Visit:
Dates of Visit:
POC/Sponsor at AUTEC:
Test Number (if applicable):
Organization you are representing:
Name/Tel number of POC at organization (individual signing your visit letter):
Passport Number:
Passport country of issuance:
Passport date of expiration:
3.3.3 Photography - To request photographs/video, submit a form DC0954 (attached) to NUWC_AUTEC_PAE_IA@navy.mil and Cc the Multimedia mailbox at AUTEC_multimedia.fct@navy.mil.
multi-media for approval. Please allow at least five (5) business days for the documentation to make its way through the process. Once approved, the multi-media photographer will contact you to schedule a time to take the photos/videos. If there is an emergency, you will still need to submit a DC954, but may contact multi-media (ext. 6174) to schedule photos/video ASAP.
https://jpasapp.dmdc.osd.mil/JPAS/JPASDisclosure https://jpasapp.dmdc.osd.mil/JPAS/JPASDisclosure https://jpasapp.dmdc.osd.mil/JPAS/JPASDisclosure mailto:AUTEC_multimedia.fct@navy.mil
Once photos/videos are taken, IA must review them prior to their release and usage. Photographs are reviewed for the intended purpose of OPSEC and/or classification and are FOR OFFICIAL USE ONLY. If AUTEC project photos and/or videos are intended to be posted on a Public Facing website by a vendor or a DOD Component or Foreign Range User it must first be approved for release by the NUWCDIVNPT Public Affairs Office via the NUWCDETAUTEC OPSEC Officer.
Please note that photos and/or videos will not be taken and/or processed without written authority
(DC0954).
One last item, ALL PHOTOGRAPHS/VIDEOS OF AUTEC ASSETS MUST BE TAKEN BY AN APPROVED PHOTOGRAPHER ON GOVERNMENT OWNED CAMERAS and reviewed by Security. Extreme caution should be used if you are taking photographs with your personal camera or cell phone. If you should inadvertently take photos and/or videos of classified assets (or incidents) your camera/cell phone will be confiscated and destroyed pursuant to NSA requirements.
If there are any questions or further information is needed, please contact the project’s POC.
3.3.4 Security - AUTEC Andros is a secured facility. Specific information and security requirements for entering the main base are provided at the AUTEC public website:
https://www.navsea.navy.mil/Home/Warfare-Centers/NUWC-Newport/What-We- Do/Detachments/AUTEC/Official-Visits/
3.3.5 Radio Transmitter Restrictions - 2-way radios are prohibited on NUWCDETAUTEC.
3.3.6 No Smoking Policy - Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. If needed, the Government will identify designated smoking areas.
3.3.7 Working Hours - At the preconstruction conference, establish a set of regular working hours.
Regular working hours are between 7:00 a.m. (0700) and 5:30 p.m. (1730), Monday through Friday.
AUTEC is not closed on Government Holidays. Contractor desiring to work on government holidays must coordinate any required base support at least 14 calendar days prior to the date of holiday work.
Any work outside of regular working hours requires Contracting Officer approval. Make application 5 calendar days prior to such work to allow arrangements to be made by the Government, giving the specific dates, hours, location, and type of work to be performed.
3.3.8 Supervision - A Superintendent, Site Safety and Health Officer (SSHO), and Quality Control (QC)
Manager is required for this project. These positions must capable of reading, writing, and conversing fluently in the English language, and must be on the job-site at all times during the performance of contract work. The Superintendent may also serve as the SSHO and as the QC manager.
3.3.9 Environmental Protections - The Contractor shall plan and implement activities in a manner that protects existing site utilities, structures, surface features, service operations, and the general site environment. This includes protecting trees, shrubs, and other vegetation not in the affected zone from dust damage, soil compaction, and physical contact with machines and equipment. If https://www.navsea.navy.mil/Home/Warfare-Centers/NUWC-Newport/What-We-Do/Detachments/AUTEC/Official-Visits/ https://www.navsea.navy.mil/Home/Warfare-Centers/NUWC-Newport/What-We-Do/Detachments/AUTEC/Official-Visits/ appropriate, the Contractor shall conserve uncontaminated topsoil by removal, storage, or redistribution. All reasonable measures shall be taken to minimize and suppress fugitive emissions of dust, vapors, and other site materials during site work. Use all non-contaminated fill materials. The Contractor shall conduct operations and activities with the intent of reducing the amount of pollution generated. Specific areas to be focused on are generation of solid waste, use of hazardous materials, use of ozone depleting chemicals, generation of hazardous waste, and use of energy and water. The Contractor shall plan, construct, operate, maintain, optimize, and commission systems necessary to control storm water run-on and runoff; and transport surface water drainage to a treatment plant, discharge location, or other destination. Hazardous Material and Hazardous Waste
The Contractor shall handle hazardous materials and waste in accordance with applicable, federal, host nation, and local requirements. The Contractor shall provide hazardous materials use and hazardous waste disposal documentation to the installation POC, and shall register with the Hazardous Materials Pharmacy program (if available) at the installation to ensure appropriate and efficient tracking of the Contractor’s hazardous material purchases, inventories, use, and releases (such as required by the Emergency Planning and Community Right-to-Know Act [EPCRA], EOs, or installation reporting requirements).
The Contractor shall comply with state, and local requirements for tasks involving the transportation of hazardous wastes and/or contaminated materials to off-site treatment, storage, and/or disposal facilities. Requirements include 40 CFR 260; 49 CFR 172, 173, 178, 179; and other applicable federal, host nation, and transportation regulations.
4. SAFETY
4.1 Safety Plan - A Safety Plan is required as part of the submittal, for review and approval. It must include a full plan for the use of certified fall protection gear.
4.2 Workplace Safety. Comply with EM 385-1-1, NFPA 70, NFPA 70E, NFPA 241, Federal and State
OSHA regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails.
4.3 Fall Protection and Prevention Plan - The plan must comply with the requirements of EM 385-1-1, Section 21.D and ASSE/SAFE Z359.2, be site specific, and address all fall hazards in the work place and during different phases of construction. Address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. Include fall protection and prevention systems, equipment and methods employed for every phase of work, roles and responsibilities, assisted rescue, self-rescue and evacuation procedures, training requirements, and monitoring methods. Fall Protection and Prevention Plan documentation shall be kept and maintained at the job site for the duration of the project.
4.4 Personal Protective Equipment (PPE). Use of PPE is governed by the nature of the work the employee is performing. Use personal hearing protection at all times in designated noise hazardous areas or when performing noise hazardous tasks. Safety glasses must be worn or carried/available on each person. Mandatory PPE includes:
a. Hard Hat
b. Long Pants
c. Appropriate Safety Shoes
d. Appropriate Class Reflective Vests
e. Personal Fall Protection Harness with fall arrest attachment affixed to the body support
4.5 Sanitation. Contractor is permitted to use on-site sanitary facilities.
4.6 Activity Hazard Analysis (AHA). The principle purpose of an AHA is to reduce the overall risk of the hazards associated with construction work. Provide an AHA for every operation involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform work.
The analysis must identify and evaluate hazards and outline the proposed methods and techniques for the safe completion of each phase of work. At a minimum, define activity being performed, sequence of work, specific safety and health hazards anticipated (slip or trips, cuts, dust or chips in eyes), control measures (to include personal protective equipment) to eliminate or reduce each hazard to acceptable levels, equipment to be used (hand tools, backhoe), inspection requirements (list the inspect ion requirements for the activity to ensure the controls are working, an d equipment is inspected to ensure proper operation), training requirements for all involved (any unique training required to make the established controls work) and the competent person in charge of that phase of work.
The AHA shall be continuously reviewed and, when appropriate, modified to address changing site conditions or operations. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls. Activity Hazard Analysis shall be updated as necessary to provide an effective response to changing work conditions and activities.
4.6 Accident Reporting. For recordable injuries and illnesses, and property damage accidents resulting in a least $2,000 in damages, the prime Contractor shall conduct an accident investigation to establish the root cause of the accident, complete the Navy Contractor Significant Incident Report (CSIR) and provide the report to the Contracting Officer within five calendar days of the accident. The Contracting Officer will provide copies of any required or special forms.
4.7 Accident Notification. Notify the Contracting Officer as soon as practical, but not later than four hours after any accident meeting the definition of recordable injuries or illnesses or high visibility accidents, property damage equal to or greater than $2,000. Information shall include Contractor name, contract title, type of contract, name of activity, installation or location where accident occurred, date and time of accident, names of personnel injured, extent of property damage (if any), extent of injury (if known) and brief description of accident (to include Type of construction equipment used, PPE used, etc.). Preserve the conditions and evidence on the accident site until the Government investigation team arrives on site and Government investigation is conducted.
4.8 Definition of Recordable Injury or Illness. Any work related injury or ill ness that results in:
(1) Death, regardless of the time between the injury and death, or the length of the illness;
(2) Days away from work;
(3) Restricted work;
(4) Transfer to another job;
(5) Medical treatment beyond first aid;
(6) Loss of consciousness;
(7) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (6) listed above.
4.9 Emergency Medical Treatment. Contractor shall arrange for their own emergency medical treatment. The Government has no responsibility to provide emergency medical treatment.
4.10 Periodic Inspections. The work site may be inspected periodically for OSHA and Navy violations.
Abatement of violations will be the responsibility of the Contractor and/or the Government as determined by the Contracting Officer. The Contractor shall provide assistance to the Safety Office escort and the federal or state OSHA inspector if a complaint is filed. Any fines levied on the Contractor by federal or state OSHA offices due to safety/health violations shall be paid promptly.
If the Contractor fails or refuses to promptly comply with safety requirements, the Contracting Office may issue an order stopping all or part of the work until satisfactory corrective action has been taken.
No part of the time lost due to any such stop order shall be made the subject of claim for extension of time or for excess costs or damages to the Contractor.
The Safety Office will investigate all complaints of unsafe or unhealthful working conditions received from Contractor’s employees, federal civilian employees, or military personnel. The Safety Office will notify the Contracting Officer of the results of such investigations.
5. ENVIRONMENTAL
Applicable AUTEC safety and environmental compliance requirements shall be followed for all AUTEC
Facilities Engineering (FE) projects such as Tower 2060 project. This includes requirements of
OPNAVINST 5100.23(current version), OPNAVINST 5090.1(current version), NUWCDETAUTECINST
5090.2(current version) and the Bahamas Final Governing Standards (FGS) (current version). In particular, prior to the start of the tower 2060 project a DC1056 (Environmental Review) shall be submitted, following the guidance in 5090.2(version). In addition, any Hazardous Materials (HM) used in conjunction with the project shall have AUTEC AUL (Authorized Use List) approval before shipping, storing or using the HM at AUTEC. The AUL process includes guidance on proper disposal of HM associated waste. If the HM does not already have AUL approval, a DC0846 and an up-to-date (within 2-years) manufacturer's SDS (Safety Data Sheet) for each HM shall be completed and submitted 10 working days prior to shipment of the HM to AUTEC; one DC0846/SDS per e-mail submittal. All sub-contractor unused HM shall be returned to CONUS at the end of the project.
5. PERFORMANCE REQUIREMENTS
5.1 Submittals - Government approval is required for all submittals. Provide submittals electronically in PDF format, unless otherwise directed by the Contracting Officer. Bookmark files exceeding 30 pages to allow efficient navigation. Attach a cover transmittal sheet to be used to record approval or disapproval. The following submittals are required:
Contact List Accident Prevention Plan Fall Protection and Prevention Plan
Quality Control Plan Environmental Protection Plan Activity Hazard Analysis Construction Schedule Warranty Letter
5.2 Preconstruction Conference. Prior to the start of construction, the Contractor representatives who have a responsibility or significant role in accident prevention must attend the preconstruction conference. At the preconstruction conference, the Government and Contractor will develop a mutual understanding of schedule, the accident prevention plan, and administrative requirements. Work is not permitted to begin until all deficiencies in the accident prevention plan have been corrected and approved by the Contracting Officer.
5.3 Existing Work. In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
5.4 Occupancy of Premises – The tower will not be occupied during performance of work.
Coordination with NUWC Test Operations will be required to ensure mitigation of any potential radio frequency (RF) hazards.
6. PROJECT CLOSEOUT
6.1 Cleanup. Leave premises free of debris, surplus materials, and construction waste.
6.2 Documentation. Within one month of the completion of work, turn in progress and completion photos, as-built drawings, operation and maintenance manuals, and all other related project documentation.
6.3 Warranty. Provide a Warranty Letter guaranteeing the Contractor’s responsibility to remedy, at the Contractor’s expense, any damage to Government-owned or controlled property when the damage is the result of the Contractor’s failure to conform to contract requirements or defective equipment, material, or workmanship. The construction warranty period will begin on the date of project acceptance and continue for one full year. The contractor shall respond to warranty items within 48 hours of being notified.