This document is a Performance Work Statement (PWS) for the Space Weather Observations Mission Operations Services (SWO-MOS) Task Order 01, focusing on the first observatory (SOL-A) of the Space Weather Next (SW Next) project. The PWS outlines requirements for developing a multi-mission mission operations services solution for the SOL observatory, which will be stationed at the Sun-Earth L1 point and is scheduled to launch no earlier than June 2029.
Key objectives include establishing programmatic structures, developing a concept and development roadmap, creating an initial factory baseline, implementing mission operations capabilities, deploying operational and backup solution instances, and maintaining the solution. The contractor must leverage the existing SWFO-L1 Command and Control system as a baseline, with the goal of creating a scalable, multi-mission solution. The performance period runs from January 2026 to June 2030, with incremental builds and releases aligned to specific milestone reviews. The solution must support all phases of the SOL-A observatory lifecycle, including development, testing, launch support, and operations, with capabilities such as mission planning, orbit and attitude management, commanding, data processing, and system maintenance.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Effective Date: February 26, 2025
Expiration Date: February 26, 2030
Check https://ipdtdms.gsfc.nasa.gov to verify that this is the correct version prior to use.
SWGS-MOS-SOW-0003, Revision -
Space Weather Ground Services, Code 492.0
Space Weather Observations
Mission Operations Services
(SWO-MOS)
Task Order 01
Performance Work Statement:
Space Weather Observations at L1 (SOL)
First Observatory
U.S. Department of Commerce (DOC)
National Oceanic and Atmospheric Administration (NOAA)
National Environmental Satellite, Data, and Information Service (NESDIS)
National Aeronautics and Space Administration (NASA)
SWO Reviewed – Not Subject to Export Control
GSFC SWGS CMO
02/27/2025
Released
DRAFT
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -ii
Space Weather Observations
Mission Operations Services
(SWO-MOS)
Task Order 01 Performance Work Statement:
Space Weather Observations at L1 (SOL) First Observatory
Signature/Approval Page
Prepared by:
David Nguyen
Reviewed by:
Ava Afghahi
Susan Jacobs
Scott Schnee
Laura Dunlap
Maria Amaro
David Donovan
Brian Frey
Andrew Royale
Katherine Spotz
Eric Tai
Approved by:
Jill Taylor
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -iii
Preface
This document provides the Task 01 Performance Work Statement for the first observatory of the
SOL of the Indefinite Delivery / Indefinite Quantity (IDIQ) for the Space Weather Observations
(SWO) Mission Operations Services (MOS) contract. It is under SWGS configuration control.
Once this document is approved, changes are handled in accordance with Class I and Class II change control requirements as described in the SWGS Configuration Management Procedures, and changes to this document will be made by complete revision.
Any questions should be addressed to:
SWGS Configuration Management Office
NASA/GSFC
Code 492.0
Greenbelt, MD 20771
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -iv
Change History Log
Revision Effective
Date
Description of Changes
(Reference the CCR & CCB/ERB Approval Date)
Revision - 02/26/2025 Baseline Release following the approval of SWGS-CCR-0008
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -v
Table of TBDs/TBRs/TBSs
Action Item
No.
Location Summary Individual/
Organization
Actionee
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -vi
Table of Contents
1 INTRODUCTION
1.1 Overview
1.2 Scope
1.3 Places of Performance
1.4 Period of Performance
2 RELATED DOCUMENTATION
3 REQUIREMENTS
3.1 Establish Programmatic Structures
3.2 Establish Concept and Development Roadmap
3.3 Establish Initial Factory Baseline
3.4 Implement MOS Capabilities for SOL-A Observatory
3.5 Deploy Operational and Backup Solution Instances
3.6 Deploy Solution Instances to Support Interfacing Developments
3.7 Maintain and Sustain All Solution Instances
4 DELIVERABLES
4.1 Data Deliverables
4.2 Deliveries at Factory and Operational Sites
List of Tables
Table 1. SOL-A capability Builds and Releases aligned to Milestone Reviews 8
List of Figures
Figure 1: Notional Flyout of SWO Observatories at Lagrange Point 1
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -
1 INTRODUCTION
1.1 Overview
The Government requires that the multi-mission Space Weather Observations Mission Operations
Services (SWO-MOS) support the first observatory in the Space Weather Next (SW Next) Space
Weather Observations at L1 (SOL) project, in accordance with the Mission Operations Services
Requirements Document (MOSRD) and meeting maturity milestone provided in the SOL Review
Plan. The SOL project will deploy two observatories, the first, SOL-A, is intended to launch no earlier than June 2029 and subject to appropriation, the second, SOL-B, would launch no earlier than
2032 (See figure 1). The two observatories will be near copies of each other and will also be a near copy of the SWFO-L1 observatory with respect to their observational, operational, orbit, and communications requirements. They will each host solar remote sensing and in situ instruments.
Each observatory will be a Sun-pointed, 3-axis stabilized satellite stationed in a Lissajous orbit around the Sun-Earth L1 point. The SOL observatory payload instruments will consist of the following:
• Coronagraph
• Solar X-ray irradiance sensor
• Solar wind plasma sensor
• Magnetometer
• Solar wind suprathermal ion sensor
• Partner Contributed Instrument (PCI)
Figure 1: Notional Flyout of SWO Observatories at Lagrange Point 1
Ground Services for the SOL Project consist of capabilities and services necessary to enable communication with and management of the observatory, and processing and distribution of payload data and spacecraft telemetry. The primary ground services include:
• Mission Operations Services (MOS), which include observatory control, health and safety monitoring, mission planning, and telemetry analysis. The SWO-MOS Solution is the subject of this task.
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -
• Antenna Services to support space to ground communication. The SWO-MOS Solution will use Antenna Services interfaces to communicate with the observatories for telemetry, tracking, and command (TT&C).
• Product Services, which include secure ingest, storage, data processing into operational and retrospective products, quality assessments, operations monitoring, data access and dissemination, and archive and stewardship. The SWO-MOS Solution will deliver telemetry to the Product Services interfaces.
1.2 Scope
To develop the Solution for support of the first observatory of the SOL Project, the Contractor must leverage and expand upon a separate instance of the one used for NESDIS SWFO-L1 Command and
Control (C2) ground segment hardware and software systems baseline. The Solution will be operated from NOAA’s NSOF by NOAA satellite operators. The Solution must satisfy the
Government’s MOSRD for Task Order 1. The working Solution must be demonstrated to achieve
SOL Project lifecycle maturity milestones in accordance with the SOL Project Review Plan document. The Solution must be designed with the expectation of efficiently extending and scaling the Solution to future observatories including the second observatory in the series and as-yet-undefined future observatories in various locations. As a first task for mission support in what is intended to be a multi-mission Solution, the Contractor must:
• Create the Contractor SWO-MOS programmatic structures to manage this and subsequent tasks
• Develop and deliver all documents in accordance with the CDRL document
• Instantiate an initial Solution based on the as-deployed SWFO-L1 C2 system configuration as the initial development instance in the Contractor facility and demonstrate that it operates correctly
• Iteratively evolve the Solution to achieve the full delivered Solution capability
• Test, deploy, integrate with antenna and product services, and verify the Solution for
Government operation from Government facilities.
The Solution must provide NOAA operators with timely and correct services to support all phases of lifecycle of the first SOL observatory, SOL-A, including satellite and instrument development and test, pre-launch preparations and rehearsals, launch support, nominal operations and analyses, and anomaly resolution activities. Functional capabilities and features including the following:
• Mission planning
• Determining, managing, and predicting orbit and attitude; planning orbital maneuvers, station keeping, momentum management; and planning attitude maneuvers as needed
• Monitoring and sending antenna service requests and ground directives
• Receiving radiometric tracking data from the scheduled ground-based antennas
• Commanding the Observatory (generation and transmission of commands/command loads, encryption, and flight software loads)
• Managing flight software and onboard table loads
• Hosting and interacting with flight simulators to support testing and training
• Receiving housekeeping and mission data from the Observatory as well as downlinks of onboard software
• Storing housekeeping data (temporary and life-of-mission)
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -
• Processing mission and housekeeping data into level 0 data delivered to product services
• Processing (extracting, applying unit transformations, etc.) and displaying housekeeping data for real-time monitoring and long-term trending
• Trending and analyzing data
The SWFO-L1 C2 system configuration, software custom code baseline, hardware inventory, rack drawings, descriptions, and interface control documents are provided as Government-furnished
Property (GFP)/Government-furnished Information (GFI). The Contractor must document and maintain configuration documents pertaining to all deployments and instances of the multi-mission
Solution.
1.3 Places of Performance
A. Mission Operations Services locations for this task order include:
• NOAA Satellite Operations Facility (NSOF) in Suitland, MD
• NESDIS Consolidated Backup Facility (CBU) in Fairmont, WV
• Contractor Facilities
B. Other remote work locations may require ad hoc visits and will be identified by the
Government. These may include sites such as
• NESDIS Wallops Command and Data Acquisition Station (WCDAS) in Wallops, VA
• SOL Spacecraft and Instrument vendor facilities
• End-to-end test locations
1.4 Period of Performance
January 2026 to June 2030 [TBR]
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -
2 RELATED DOCUMENTATION
This task order adds project requirements to the development and sustainment of the multi-mission
SWO-MOS Solution. The SWO-MOS Base PWS is the parent to this task order and all documents referenced in the Base PWS are applicable.
Space Weather Observations Mission Operations Services (SWO-MOS) Applicable and Reference
(A&R) Documents List, SWGS-MS-LIST-0003, provides the list of applicable and reference documents for this PWS with their sources. In the event of any unresolved conflict, the Contractor must request conflict resolution by the Contracting Officer in advance of work performed.
The SWO-MOS Contract Data Requirements List (CDRL), SWGS-MS-CDRL-0001, provides an applicability matrix and defines the required content of document deliverables required for performance of tasks under this contract. The Contracting Officer’s Representative is responsible for ensuring all deliverables are in compliance with the CDRL.
The SWO Program Acronym and Glossary List, SWO-MGMT-LIST-0001, defines terminology as used in this document and throughout the SWOPD. In the event of conflict between terminology in this document and any other dictionary, the SWO terminology will take precedence. In the event of any unresolved conflict, the Contractor must request conflict resolution by the Contracting Officer.
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -
3 REQUIREMENTS
3.1 Establish Programmatic Structures
The Contractor shall create the Contractor SWO-MOS programmatic structures to manage this and subsequent tasks.
The Contractor shall create a document delivery plan, for Government approval, for documents associated with the establishment of the Contractor’s programmatic oversight and engineering processes for the multi-mission SWO-MOS Solution and for the development, deployment, delivery, and sustainment of the Solution to meet the needs of the first satellite observatory of the SOL
Project.
The Contractor shall be responsible for ensuring that all Contractor and subcontractor personnel engaged in performance of this Performance Work Statement have appropriate qualifications, knowledge, and certification to perform work in accordance with this Task Order.
The Contractor shall deliver the CDRLs identified in Appendix A of the CDRL document, SWGS-
MS-CDRL-0001, as a part of this task order. The contractor shall perform work in accordance with its delivered plans and processes.
3.2 Establish Concept and Development Roadmap
The Contractor shall assess the GFP Mission Operations Services capability, based on the SWFO-
L1 system, relative to the requirements of this Task Order and various future missions. The
Contractor shall present any required baseline and mission unique changes in a Contractor-hosted
Mission-Unique Concept Review (MUCR) for assessment by a Government-designated board.
The MUCR assessment for this task order should include, but is not limited to:
a) Cost and schedule assessment for all proposed options
b) Evaluate maximum usage of OS/Comet for satellite command and control
c) Perform assessment for all SWO-MOS functions to recommend re-use without modification, re-use with feature enhancements, or replacement. All assessments that depart from re-use must include justification to include, at a minimum, associated risk and compliance issues with the unmodified GFP baseline.
d) Assess scope to expand GFP infrastructure to multi-mission architecture
e) Address risks for shared infrastructure and partitioning between missions.
f) Develop a Style Guide that will be used to maintain the similar look and feel to the GFP architecture.
g) Evaluate all equipment (routers, switches, modems, servers, etc.) that can be expanded for multi-mission and re-used or would require replacement to meet overall objectives.
h) Define constraints and limitations of expandability to multiple missions with various orbits in line with MOSRD requirements
The Contractor shall prepare a development roadmap that defines the plans and priorities for establishing a multi-mission, scalable architecture and an initial baseline capability for the Mission
Operations Services and incremental buildup of capability for the SOL operational system. The
Contractor shall identify design modifications required to evolve the GFP capability to a SWO-MOS
Solution that supports the SOL observatories and various future missions. The Contractor shall present the roadmap and plan for modifications in a Contractor-hosted Design Modification Review
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -
(DMR) for assessment by a Government-designated board. The DMR shall satisfy PDR and CDR requirements as specified in the SWO-MOS CDRL.
3.3 Establish Initial Factory Baseline
The Contractor shall instantiate a factory environment testbed to use for all development of the
SWO-MOS solution. The initial factory baseline shall include, at a minimum, implementation of the
SWFO-L1 Command and Control System COTS, GOTS, and GFP software designated for full or partial re-use at the MUCR. This should include preliminary capabilities, features, and security controls. This is the Initial Baseline of the SWO-MOS Solution.
The Contractor shall perform a validation test for each software CSCI that demonstrates the SWO-
MOS Solution initial baseline is capable of reproducing SWFO-L1 basic functionality in the factory environment. The Contractor shall work with the Government's Mission Operations Support Team
(MOST) to receive necessary test data sets for designated test scenarios.
3.4 Implement MOS Capabilities for SOL-A Observatory
The Contractor shall decompose requirements and derive user stories from the MOSRD sufficient to describe the full scope of the capability.
The Contractor shall develop and deliver a SWO-MOS Solution that meets the MOSRD requirements and the SOL-A mission needs, consistent with the SOL-A mission timeline.
The Contractor shall develop and use verification, validation, and regression tests of SWO-MOS capabilities appropriate to the first observatory SOL-A.
The Contractor shall develop, deliver, integrate, test, and validate capabilities and features to fulfill user stories and thereby satisfy MOSRD requirements through Program Increments.
3.5 Deploy Operational and Backup Solution Instances
The Contractor shall deliver, install, and test incremental releases of the SWO-MOS Solution to
Government facilities in order to meet Government use, training, and independent test needs and milestones.
The Contractor shall plan for and support Government configuration management processes and installation, test, and checkout processes for all releases to Government sites and use.
3.6 Deploy Solution Instances to Support Interfacing Developments
The Government will develop the SOL flight and ground elements external and connected to the
SWO-MOS. In the course of these developments, the elements will require functional and interface testing with the Solution.
• The Contractor shall prioritize capabilities and functions necessary to support the development, integration, and test requirements and schedules of external elements as well as the integration of the solution within the Government infrastructure and enterprise security.
• The Contractor shall make instances of the Solution available with capabilities to support
Spacecraft development and test.
• The Contractor shall make instances of the Solution available with capabilities to support
Instrument development and test.
• The Contractor shall make instances of the Solution available with capabilities to support
SWGS Product Services development and test.
• The Contractor shall make instances of the Solution available with capabilities to support
SWGS Antenna Services development and test.
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -
3.7 Maintain and Sustain All Solution Instances
The Contractor shall maintain and sustain the instance for the first SOL observatory within the
SWO-MOS Solution at both factory and Government facilities for the duration of this Task Order.
Sustainment shall include performing or responding to regular security scans with expedited security patching for all high vulnerability findings and at least quarterly security updates for all other findings.
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -
4 DELIVERABLES
4.1 Data Deliverables
The Contractor shall develop and deliver all documents in accordance with the SWO-MOS CDRL document and the SOL Project Review Plan or as modified under the Contractor’s document delivery plan. The following table lists selected SOL and element lifecycle reviews as of the issuance of this Task Order that are most relevant to this Task. Changes to this schedule are at the
Government’s sole discretion and will effectively result in changes to this task without task order modification.
Table 1. SOL-A capability Builds and Releases aligned to Milestone Reviews
Fee Milestone Milestone Date Associated
SOL-A
Events
Fee Requirements: Standard QASP criteria also apply to all Solution increments 1/15/2026 Task Order
Award
Program
Increment;
MUCR
3/15/2026 SWO-MOS
MUCR
Project Documentation Plan delivered;
Contractor Conducts SWO-MOS MUCR for MOSRD and SOL Project
Requirements
Program
Increment, Factory Build
6/15/2026 PI Build 1;
SWO-MOS
DMR and
SWGS &
SOL CDRs
A copy of the L3Harris SWFO C2 baseline at the new vendor site;
Regression Equivalent to a SWFO
Mission Rehearsal developed with
MOST; Contractor Conducts SWO-MOS
DMR for SOL Project Requirements;
Contractor Support to SWGS & SOL
CDRs
Program
Increment
9/15/2026 PI Build 2 Features to simplify the configuration;
fix discrepancies uncovered in regression; and implement new features identified in SOL Project MUCR and
DMR
Program
Increment
12/15/2026 MOST Access for MOCI Development
Program
Increment
3/15/2027
6/15/2027
9/15/2027
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -
Fee Milestone Milestone Date Associated
SOL-A
Events
Fee Requirements: Standard QASP criteria also apply to all Solution increments
Program
Increment &
First Release to
NSOF
12/15/2027 E2E 1 18 months ahead of launch, first gov't site install; Solution includes all features necessary to support SOL Project Flight
Readiness End to End Test 1
Program
Increment; First
Release to CBU
3/15/2028 or NLT
E2E-2 minus 4 mo
ORCA Rel 1;
E2E 2; MOR
Release to CBU with capability to failover demonstrated; Solution includes all features necessary to support SOL
Project Flight Readiness End to End Test
2; Support ORCA Rel 1; Contractor
Support to SOL MOR
Program
Increment
6/15/2028 or NLT
E2E-3 minus 3 mo
E2E 3 Solution includes all features necessary to support SOL Project Flight Readiness
End to End Test 3
Program
Increment
9/15/2028 or NLT
FOR minus 3 mo
FOR: E2E 4,
GVT1;
DVT1
Solution includes features necessary to support Flight Readiness; Contractor support to SOL Project FOR; Support
SOL Project Flight Readiness End to End
Test 4; Support to GVT1; Support to
DVT1
Program
Increment
12/15/2028 Mission
Rehearsals 1-
2; GVT2;
DVT2;
Cross-Site
ORCA
Contractor Support to SOL Project
Mission Rehearsals; Support to GVT2;
Support to DVT2; Support to Cross-Site
ORCA
Program
Increment
3/15/2029 SWGS FRR;
Launch
Freeze:
Mission
Rehearsals 3-
5; ORR
Contactor Support to SOL Project FRR;
Contractor Support to SOL Project
Mission Rehearsals; Support SOL ORR
Program
Increment
6/15/2029 FRR; LRR;
Launch SOL-
A
Contractor Support to SOL FRR and
LRR; Contractor Support for SOL-A
Launch
Program
9/15/2029 Freeze Lift
12/15/2029 PLAR Solution includes all features necessary for commissioning; Contractor Support to SOL Post Launch Assessment Review
Program
3/15/2030
6/15/2030
SWO-MOS TO-01 PWS SOL First Observatory SWGS-MOS-SOW-0003, Revision -
4.2 Deliveries at Factory and Operational Sites
The Contractor shall develop, maintain, and operate factory environments necessary to perform development, testing, and sustainment activities.
The Contractor shall deliver and install the Solution to multiple Government sites for operation by the Government. Delivery must comply with Government configuration management processes and guidelines. The deliveries must provide the complete working Solution or agreed upon incremental updates to the Solution, and may include:
• COTS, test, and operational workstation hardware
• Test and operational software, including licenses
• Cryptographic devices for spacecraft communication instances including any required modifications
• NOAA5050-compatible network equipment
• Simulators
• Intra-site network infrastructure
• IT resources
• Documentation