This is a Draft Statement of Work for the installation of a new conduit pathway and wiring infrastructure for a GRAB barrier security system at United States Coast Guard Base Portsmouth, Virginia. The scope encompasses excavation and exposure of existing underground utilities, trenching from the GRAB barrier to the security guard shack, installation of new conduits with three quazite handhole boxes, installation of 18/3 EFO wire, termination to the Master Control Panel and Barrier Control Panel, trench backfilling with site restoration, and full operational testing of the GRAB system. All labor, materials, and equipment are contractor-furnished. The contractor must coordinate underground utility markings before excavation and arrange base access for all employees through the Contracting Officer's QA Evaluator, Nathan Chappell (757-483-8792, Nathan.C.Chappell@uscg.mil). A mandatory site visit must be pre-arranged at least three business days in advance.

The period of performance cannot exceed 30 calendar days from award date, with work generally performed Monday through Friday between 0700 and 1530 EST, though weekend and holiday work may be required with written approval. The contractor's project manager must be available by telephone during business hours and respond to technical issues within 24 hours. All contractor personnel must be pre-vetted for base access, provide valid identification (Real ID or acceptable alternatives), and comply with Department of Homeland Security regulations, OSHA standards (29 CFR 1910 and 1926), and EPA environmental regulations (40 CFR). The contractor must submit employee lists five days before work commencement, obtain all necessary permits and licenses, and ensure all work meets experienced trade standards. Upon completion, the QAE will conduct inspection and acceptance, with authority to reject deficiencies requiring contractor correction.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PR #: 31040PR260000472

STATEMENT OF WORK

STATEMENT OF WORK (SOW)

FOR

New Conduit and wiring run for Security Barriers

1.0 GENERAL

1.1 SCOPE

The work consists of providing all labor, materials and equipment to establish a new, reliable conduit pathway for the GRAB barrier system, installing upgraded 18/3 EFO wiring, and integrate the new infrastructure with existing Master Control Panel (MCP) and Barrier Control Panel (BCP) in the security guard shack to ensure proper barrier operation.

2.1 TASK ONE. Excavation & Exposure

2.1.1 Contractor will be responsible for arranging all underground utilities to be marked and identified before any digging begins. Identify existing conduits originating from the GRAB barrier and to the security guard shack. Carefully expose these conduits to prepare for connection with the new conduit run.

2.1.2 Trench from the GRAB barrier to the designated area where conduits cross beneath the inbound lane and goes into the security guard shack.

2.1.3 Lay new conduits within the excavated trench and connect to existing conduits at both ends. Contractor will need to furnish and install three (3) quazite handhole boxes along the trench route to facilitate current and future wire pulling operations.

2.1.4 Install mule tape to pull new 18/3 EFO wire to the GRAB barrier.

2.1.5 Furnish and pull new 18/3 EFO wire, terminate the new wire to both the MCP and the BCP of the GRAB system.

2.1.6 Backfill and properly compact the trench once all conduit and wiring tasks are complete. Restore the disturbed area to its original state by applying seed and straw over the filled trench.

2.1.7 Following the physical installation and termination of the 18/3 EFO wire to the MCP and BCP, the Contractor shall conduct a full operational test of the GRAB system.

3.0 CONTRACTOR PERSONNEL

3.1 QUALIFIED PERSONNEL

The Contractor must provide qualified personnel to perform all requirements specified in this SOW.

3.2 KEY PERSONNEL

3.3 PROJECT MANAGER

3.3.1 The Project Manager must be available to the QAE via telephone between the hours of 0700 and 1530 EST, Monday through Friday, and must respond to a request for discussion or resolution of technical problems within 24 hours of notification.

3.5 EMPLOYEE IDENTIFICATION

3.5.1 The contractor shall provide a detailed list of all employees to the QAE Representative five (5) days prior to commencing work. The QAE will provide a base access spreadsheet to be fill out and returned.The USCG Base Portsmouth Security Office will be given a copy of the employee list, and a pass will be issued for entry. A valid state license plate and safety inspection sticker are required. All vehicles operated on government property shall be maintained in a good state of repair.

3.6 EMPLOYEE CONDUCT

Contractor’s employees must comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, and possession of weapons) when visiting or working at Government facilities. The Contractor must ensure Contractor employees present a professional appearance at all times and that their conduct must not reflect discredit on the United States or the Department of Homeland Security. The Project Manager must ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.

3.7 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS

The Government may, at its sole discretion (via the Contracting Officer), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.

3.8 SITE VISIT

A site visit is required to conduct field verification of any/all quantities and measurements before submitting bids. Interested parties shall make arrangements for a site visit with the QAE.

3.8.1 DESIGNATED CONTRACTING OFFICER’S QA EVALUATOR (QAE) REPRESENTATIVE

Nathan Chappell. 757-483-8792 Nathan.C.Chappell@uscg.mil.

3.8.2 All site visits are to be pre-arranged a minimum of three (03) days in advance. To arrange a site visit, fill out a base access request that will be provided by the QAE.

3.8.3 CONDITIONS AFFECTING THE WORK

The Offeror should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, the general and local conditions which can affect the cost of the work thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work. The government will assume no responsibility for any understanding or misrepresentations concerning conditions made by any of its officers or agents prior to the execution of the contract, unless included in the request for quotes, the specification or related documents. All contractors that require Base access will have to be pre-vetted for entry prior to commencement of work. All work that exceeds a completion time greater than 10 days, may be subject presenting RapidGate as a method of Base entry.

3.9 SECURITY

Coordinate with the CSO Office upon arrival for your scheduled site visit.

Contractor access to classified information is not currently required under this SOW. However, the Government at a later date may require all Contractor personnel to have Secret clearances. Accordingly, all Contractor employees provided for this requirement must be eligible for a Secret Clearance.

Each contractor that does not have Real ID on their Driver licenses will need to present one of the following credentials:

. U.S. Department of Defense ID, including IDs issued to Active Duty, Reserve, National Guard, retirees and dependents.

. RAPIDGate Credential . HSPD-12 PIV card . State-issued Enhanced Driver's License . U.S. passport . U.S. passport card . DHS trusted traveler cards (Global Entry, NEXUS, SENTRI, FAST) . Permanent resident card . Border crossing card . Federally recognized Tribal Nation/Indian Tribe, including Enhanced Tribal Cards (ETCs) . Foreign government-issued passport . Canadian provincial driver's license or Indian and Northern Affairs Canada card . Transportation worker identification credential . U.S. Citizenship and Immigration Services Employment Authorization Card (I-766) . U.S. Merchant Mariner Credential . Veteran Health Identification Card (VHIC)

4.0 AWARD OF THE CONTRACT: The contractor must immediately notify the contracting officer’s QAE representative of his intended start date. The work shall be done in accordance with the specification.

4.1 PERIOD OF PERFORMANCE

The period of performance for this contract must not exceed 30 calendar days from the date of award.

4.2 PLACE OF PERFORMANCE

The primary place of performance will be a combination of the Contractor’s facilities and the United States Coast Guard at 4000 Coast Guard Blvd, Portsmouth, VA 23703. Custom manufacturing will be conducted at Contractor’s facility and installation will be conducted at the USCG Base Portsmouth.

4.3 HOURS OF OPERATION

Contractor employees must generally perform all work between the hours of 0700 and 1530 EST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees must be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW. If the contractor desires to carry on work on Saturday, Sunday, holidays or outside the station’s regular hours, he may submit his request in writing to the Contracting Officer’s QAE Representative for approval consideration. The contractor shall allow ample time to enable satisfactory arrangements to be made by the government to inspect the work in progress.

4.5 GENERAL REPORT REQUIREMENTS

The Contractor must provide all written reports in electronic format with read/write capability using applications that are compatible with DHS workstations (Microsoft Office Applications).

4.6 CONTRACTOR FURNISHED PROPERTY

The Contractor must furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract.

4.7 GOVERNMENT ACCEPTANCE PERIOD

Upon completion of work, contact the Contracting Officer QAE Representative to arrange for inspection/acceptance of work.

4.7.1 The QAE will conduct an inspection of the work conducted by the Contractor and will have the right to reject or require correction of any deficiencies found that are contrary to the information contained in the Contractor’s accepted proposal. In the event of a rejected deliverable, the Contractor will be notified in writing by the QAE of the specific reasons for rejection. The Contractor may have an opportunity to correct the rejected deliverable and return it per delivery instructions.

5.0 OTHER APPLICABLE CONDITIONS

5.1 SECURITY/SAFETY

All contractors working on CG Base Portsmouth shall abide by all federal safety regulations as published by the Occupational Health and Safety Administration, 29 CFR 1910 (series) and 29 CFR 1926 (series). Contractor written safety programs shall be reviewed by the Base Safety Officer prior to starting work.

Written notification must be provided to the Base Safety Officer; in their capacity as Base Fire Marshal of any activity that could potentially cause fire or explosion or that changes or reduces the capability of fighting a fire or explosion. Some examples of qualifying activities are: a fire hydrant or fire suppression system that must be taken out of service for any reason, electrical work that affects fire alarm systems, introduction of hazardous or flammable material onto the Base, and blocking of any egress routes or emergency vehicle routes. Inclusion of this information in the contract constitutes written notification as long as the outsource review sheet is signed by Base Safety Officer.

Lock Out/Tag Out requires notification and coordination with facilities and will not be conducted by a contractor on Base Portsmouth. A Facilities Division representative is required for all contractors Lock Out/Tag Out needs.

Every employee working on Base Portsmouth has the right to a safe and healthy work place. The contractor has the responsibility and right to stop unsafe work. QAE’s and the Safety Officer may also institute a work stoppage relating to unsafe practices or immediate danger to life and health situations.

5.2 ENVIRONMENTAL PROTECTION REQUIREMENTS:

All contractors working on CG Base Portsmouth shall abide by all federal environmental regulations as published by the Environmental Protection Agency, 40 CFR (series). Contractors written environmental management and pollution prevention programs shall be reviewed by the Environmental Protection Specialist prior to starting work and must be in accordance with ICSPORTSVA INSTM5090.2, the Unit Environmental Guide.

Written notification must be provided to the Environmental Protection Specialist of any activity that could potentially cause a permit violation on Base Portsmouth. Some examples of qualifying activities are: any activity that could result in a spill or discharge into a waterway or introducing a hazardous material into the environment.

Copies of the following must be provided to the Environmental Protection Specialist prior to starting work in affected areas: Material Safety Data Sheets, permits, and notices of intent.

Hazardous materials used by a contractor are required to be disposed of by that contractor. Disposal must be in accordance with federal, state, and local guidelines.

5.3 PERMITS: The contractor shall, without additional expense to the government, obtain all appointments, licenses, and permits required for the prosecution of the work. The contractor shall comply with all applicable federal, state and local laws.

5.4 WORKMANSHIP: All work shall be accomplished with the best standard practices, and by workmen thoroughly experienced in the required trades. The work shall be supervised by experienced personnel and shall be satisfactory for the Contracting Officer.

5.5 ORAL MODIFICATION: No oral statement of any person other than the contracting officer shall in any manner or degree, modify or otherwise affect the terms of this contract.

PAGE 8/17