DRAFT_Specifications_Milford Haven_95.pdf
PDF 2 MB Posted
- Attached to
- Milford Haven Dredging and Jetty Work
- Solicitation number
- W9123626B0000
About this file
This document is a 95% draft specification for the Milford Haven Jetty and Dredging project, detailing a comprehensive marine construction and dredging contract. The project involves hydraulic or mechanical dredging of the Milford Haven Channel in Matthew's County, Virginia, to a depth of -10 feet mean lower low water (MLLW) with 1 foot of allowable overdepth. The work includes transporting dredged material by pipeline to beach placement sites, performing minor site work, and restoring the adjacent jetty structure.
Key technical requirements include removing existing jetty stone, installing synthetic sheet piling, placing new VDOT Class I armor stone and Class AI bedding stone, and precise material placement within designated beach templates. The contract has a 300-day period of performance from Notice to Proceed, with specific requirements for environmental protection, quality control, safety measures, and surveying. The project will involve careful coordination with local agencies, management of submerged aquatic vegetation areas, and adherence to strict environmental and safety regulations throughout the marine construction and dredging operations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MilfordHavenIndustryDaySlides.pptx | PPTX presentation | |
| MH Industry Day Attendence 15JAN2026.pdf | ||
| DRAFT_Drawings_Milford Haven_95.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Milford Haven Jetty and Dredging MILFORDHAVEN 95% Submittal
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
01 20 00 11/20, CHG 2: 08/21 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 2: 05/22 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 02/15 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 11/16, CHG 2: 11/21 QUALITY CONTROL
01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 57 20.00 05/22 ENVIRONMENTAL PROTECTION
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION AND DECONSTRUCTION
DIVISION 31 - EARTHWORK
31 00 00 08/08, CHG 2: 02/21 EARTHWORK
31 41 16.16 05/23 SYNTHETIC SHEET PILING
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 08/20 DREDGING
35 31 19 01/08, CHG 1: 11/14 STONE, CHANNEL, SHORELINE/COASTAL
PROTECTION FOR STRUCTURES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
DRAFT
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
08/15, CHG 2: 08/21
a description of work covered in this contract and is required for use in all projects
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
1.1.2 Location
1.2 TRANSPORTATION FACILITIES
1.2.1 Use of Roads
1.2.2 Cleated Vehicles
1.3 SPECIAL CONTRACTOR REQUIREMENTS
1.3.1 Site Access
1.3.2 Jetty Stone Stockpile
1.3.3 COORDINATION IN WORK AREAS
1.3.3.1 Channel Traffic
1.3.3.2 Hours of Work
1.3.3.3 Existing Utility Location
1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.4.1 Records
1.4.2 Impacted Days
1.5 HISTORICAL AND ARCHAEOLOGICAL FINDS
1.6 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.6.1 Allowable Costs
1.6.2 Rental Costs
1.6.3 Equipment Costs
1.7 SUBCONTRACTS AND WORK COORDINATION
1.8 CONSTRUCTION MANPOWER AND EQUIPMENT REPORT
1.9 PROFIT
1.9.1 Weighted Guidelines
1.9.2 Value
1.9.2.1 Degree of Risk
1.9.2.2 Relative Difficulty of Work
1.9.2.3 Size of Job
1.9.2.4 Periods of Performance
1.9.2.5 Contractor's Investment
1.9.2.6 Assistance by Government
1.9.2.7 Subcontracting
1.10 BLASTING
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 11 00 Page 1
-- End of Section Table of Contents --
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
08/15, CHG 2: 08/21
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The project is comprised of hydraulic maintenance or mechanical dredging of Milford Haven Channel, transport of material by pipeline with placement within the beach placement sites, minor site-work of the placement sites and repair of the adjacent jetty structure as shown in the drawings and contract specification.
Dredging will include a portion of the authorized channel to a depth of -10 feet mean lower low water (MLLW) and will include 1 foot of allowable overdepth.
Period of performance to complete the work will be 300 days from Notice to Proceed.
1.1.2 Location
The work will be located at Milford Haven Channel in Matthew's County, Virginia. The exact location is as shown on the project plans.
1.2 TRANSPORTATION FACILITIES
The Facility is served by a secondary unpaved road. Road(s) within the Facility proposed to be used by the Contractor shall be subject to prior approval of the Facility authorities and such roads, if used, shall be maintained throughout construction and shall be restored to as good condition as existed prior to their use. The Contractor shall also construct, subject to approval, such temporary haul roads and bridges as may be necessary for conducting his work. Any such temporary construction shall be removed and the affected area restored to its original condition. All costs for the use of existing transportation facilities, for the construction of temporary facilities, and for maintenance, repair, removal and restoration shall be borne by the Contractor. The condition of the construction access route roadways shall be documented in writing and supplemented with pictures and video. The report shall be submitted to the Contracting Officer prior to starting the construction. Any existing roads, structures, or utilities damaged by moving equipment and materials to the construction site shall be repaired and replaced by the contractor at no additional cost to the government.
1.2.1 Use of Roads
Unpaved roads from major and primary municipal roads serve the site. The movement of all vehicles shall be confined to the roads designated and shall comply with traffic regulations. The Contractor shall keep all roads clear of all obstructions and free of mud and other foreign materials resulting from operations. The Contractor's vehicles shall at no time follow a vehicle closer than 50 feet, and all vehicles shall pull
SECTION 01 11 00 Page 3 off the road and come to a complete stop when meeting emergency vehicles, or vehicles with flashing lights. Speed limits and traffic controls shall be observed.
1.2.2 Cleated Vehicles
Cleated vehicles shall not be moved over surfaced roads except at the immediate site of the area where they are to be used.
1.3 SPECIAL CONTRACTOR REQUIREMENTS
1.3.1 Site Access
Contractor will be permitted to ground barges within the Limits of Disturbance, as indicated on contract drawings, when accessing the site from waterside during construction activities. The Contractor will mark submerged aquatic vegetation areas indicated on the drawings and completely avoid construction activities in those areas, to include barge access. Laydown areas will be located upland of the Narrow's Point Beach, and as directed by the Contracting Officer Representative. Landide access to laydown area and construction area will be permitted.
1.3.2 Jetty Stone Stockpile
Upon deconstruction of the existing jetty stone, the contractor is permitted to stockpile the removed stone within the limits of distrubance, exclusive of the SAV areas indicated, and placed as close to upland area as is accessible by equipment.
1.3.3 COORDINATION IN WORK AREAS
1.3.3.1 Channel Traffic
Traffic within Milford Haven is expected to be present on a regular basis.
The Contractor will be expected to cooperate with vessel traffic within the project area during dredging work and as referenced in Section 35 20 23
DREDGING.
1.3.3.2 Hours of Work
The normal work hours for construction shall adhere and comply with local ordinances.
1.3.3.3 Existing Utility Location
Existing utilities must be located before doing any digging work on Facility. The Contractor shall be responsible to contact Miss Utility, obtain all necessary existing utility locations, which may be necessary to accomplish his work, and mark any utility lines in the immediate vicinity of work. It shall be the responsibility of the Contractor to contact Miss Utilities at 1-800-552-7001 for locating commercial utilities 48 hours prior to digging operations.
1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the
SECTION 01 11 00 Page 4 following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
c. All awards or extensions for time shall be at the sole discretion of the Contraction Officer or their representative.
1.4.1 Records
Upon acknowledgement of the Notice to Proceed and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.
1.4.2 Impacted Days
The number of actual adverse weather days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day in each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in the schedule of monthly anticipated adverse weather delays, above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clauses entitled "Default (Fixed Price Construction)".
1.5 HISTORICAL AND ARCHAEOLOGICAL FINDS
Federal legislation provides for the protection, preservation, and collection of scientific, prehistoric, historical, and archaeological data, including relics and specimens which might otherwise be lost due to alteration of the terrain or building features as a result of any Federal construction project. Should the Contractor, or any of the Contractor's employees, or parties operating or associated with the Contractor, in the performance of this contract discover evidence of possible scientific, prehistoric, historical, or archaeological data, the Contractor shall immediately cease work at that location, avoid further disturbance, and notify the Contracting Officer, giving the location and nature of the findings. The Contractor shall forward written confirmation to the Contracting Officer as directed. The Contractor shall exercise care so as not to disturb or damage artifacts or fossils uncovered during excavation operations, and shall provide such cooperation and assistance as may be necessary to preserve the findings for removal or other disposition. Any person who, without permission, injures, destroys, excavates, appropriates, or removes any historical or prehistoric artifact, object of antiquity, or archaeological resource on the public lands of the United States is subject to arrest and penalty of law. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance or changes in the work, or both. If such delays or changes are ordered, an equitable adjustment will be made in the contract in
SECTION 01 11 00 Page 5 accordance with the applicable clauses of the contract.
1.6 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.6.1 Allowable Costs
Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data when the Government can determine both ownership and operating costs for each piece of equipment or equipment groups of similar serial and series from the Contractor's accounting records. When both ownership and operating costs cannot be determined from the Contractor's accounting records, equipment costs shall be based upon the applicable provisions of EP 1110-1-8, "Construction Equipment Ownership and Operating Expense Schedule," Region I or II as applicable. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retrospective pricing, the schedule in effect at the time the work was performed shall apply.
1.6.2 Rental Costs
Equipment rental costs are allowable, subject to the applicable provisions of the Federal Acquisition Regulations, and shall be substantiated by certified copies of paid invoices. Rates for equipment rented from an organization under common control, lease-purchase or sale-leaseback arrangements will be determined using the schedule except that rental costs leased form an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees are allowable. Costs for major repairs and overhaul are unallowable.
1.6.3 Equipment Costs
When actual equipment costs are proposed and the total amount of the pricing action is over $25,000, cost or pricing data shall be submitted on the Standard Form 1411, "Contract Pricing Proposal Cover Sheet". By submitting cost or pricing data, the Contractor grants to the Contracting Officer or an authorizing representative the right to examine those books, records, documents and other supporting data that will permit evaluation of the proposed equipment costs. After price agreement the Contractor shall certify that the equipment costs or pricing data submitted are accurate, complete and current.
1.7 SUBCONTRACTS AND WORK COORDINATION
Contract Clauses "SUBCONTRACTS", "PERMITS AND RESPONSIBILITIES", and "MATERIAL AND WORKMANSHIP" are supplemented as follows:
a. Divisions or sections of specifications are not intended to control the Contractor in dividing the work among subcontractor, or to limit work performed by any trade.
b. Contractor shall be responsible for coordination of the work of the trades, subcontractors, and materials.
SECTION 01 11 00 Page 6
c. The Government or its representative will not undertake to settle any difference between the Contractor and Contractor's subcontractors, or between subcontractors.
d. The Government reserves the right to refuse to permit employment on the work or require dismissal from the work of any subcontractor who, by reason of previous unsatisfactory work on Corps of Engineers projects, or for any other reason is considered by the Contracting Officer to be incompetent or otherwise objectionable.
1.8 CONSTRUCTION MANPOWER AND EQUIPMENT REPORT
The Contractor shall submit executed CENAO Form 987, Construction Manpower and Equipment Report daily. The report shall include manpower and equipment for the general and subcontractors. Forms are available from the Contracting Officer.
1.9 PROFIT
1.9.1 Weighted Guidelines
Weighted guidelines method of determining profit shall be used on any equitable adjustment change order or modification issued under this contract. The profit factors shall be as follows:
Factor Rate Weight Value
Degree of Risk 20 Relative difficulty of work 15 Size of Job 15 Period of performance 15 Contractor's investment 05 Assistance by Government 05 Subcontracting 25
1.9.2 Value
Based on the circumstances of each procurement action, each of the above factors shall be weighted from .03 to .12 as indicated below. The value shall be obtained by multiplying the rate by the weight. The value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.
1.9.2.1 Degree of Risk
Where the work involves no risk or the degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12. Lump sum items will have, generally, a higher weighted value than the unit price items for which quantities are provided. Other things to consider: the portion of the work to be done by subcontractors, nature of work, where work is to be performed, reasonableness of negotiated costs, amount of labor included in costs, and whether the negotiation is before or after performance of work.
SECTION 01 11 00 Page 7
1.9.2.2 Relative Difficulty of Work
If the work is most difficult and complex, the weighting should be .12 and should be proportionately reduced to .03 on the simplest of jobs. This factor is tied in to some extent with the degree of risk. Some things to consider: the nature of the work, by whom it is to be done, where, and what is the time schedule.
1.9.2.3 Size of Job
All work not in excess of $100,000 shall be weighted at .12. Work estimated between $100,000 and $5,000,000 shall be proportionately weighted from .12 to .05.
1.9.2.4 Periods of Performance
Jobs in excess of 24 months are to be weighted at .12. Jobs of lesser duration are to be proportionately weighted to a minimum of .03 for jobs not to exceed 30 days. No weight where additional time not required.
1.9.2.5 Contractor's Investment
To be weighted from .03 to .12 on the basis of below average, average, and above average. Things to consider: amount of subcontracting, mobilization payment item, Government furnished property, equipment and facilities, and expediting assistance.
1.9.2.6 Assistance by Government
To be weighted from .12 to .03 on the basis of average to above average.
Things to consider: use of Government owned property, equipment and facilities, and expediting assistance.
1.9.2.7 Subcontracting
To be weighted inversely proportional to the amount of subcontracting.
Where 80 percent or more of the work is to be subcontracted, the weighting is to be .03 and such weighting proportionately increased to .12 where all the work is performed by the Contractor's own forces.
1.10 BLASTING
Blasting will not be permitted.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 8
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/20, CHG 2: 08/21
payment instruction paragraphs required for use in all projects
PART 1 GENERAL
1.1 FIXED PRICE PAYMENT ITEMS
1.1.1 Payment Item No. 0001 MOBILIZATION & DEMOBILIZATION OF LAND
BASED EQUIPMENT
1.1.1.1 Mobilization
1.1.1.2 Demobilization
1.1.2 Mobilization
1.1.3 Demobilization
1.1.4 Payment Item No. 0003 SITE WORK
1.1.5 Payment Item No. 0004 CONSTRUCTION OF SHEET PILE
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Payment Item No. 0005 DREDGING
1.2.1.1 MISPLACED MATERIAL
1.2.1.2 EXCESSIVE DREDGING
1.2.2 Payment Item No. 0006 Armor Stone (VDOT Class I Stone)
1.2.3 Payment Item No. 0007 Bedding Stone (VDOT Class AI Stone)
1.2.4 Payment Item No. 0008 Demolition of Mooring and Sheet Piles
1.3 MONTHLY PARTIAL PAYMENTS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 20 00 Page 1
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/20, CHG 2: 08/21
PART 1 GENERAL
1.1 FIXED PRICE PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the Bid Schedule as shown in the contract documents and as described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Payment Item No. 0001 MOBILIZATION & DEMOBILIZATION OF LAND BASED
EQUIPMENT
All costs connected with the mobilization and demobilization of all of the Contractor's equipment for all phases of the demolition, jetty construction, earthwork and site work as defined below will be paid for at the contract lump sum price for this item, exclusive of items 0002, 0003, 0004,0005, 0006, 0007 and 0008. Sixty percent of the lump sum price will be paid to the Contractor upon completion of mobilization at the work site. The remaining forty percent will be paid to the Contractor upon completion of demobilization. In the event the Contracting Officer considers that the amount in this item, sixty percent which represents mobilization and forty percent which represents demobilization, does not bear a reasonable relation to the cost of the work in this contract, the Contracting Officer may require the Contractor to produce cost data to justify this portion of the bid. Failure to justify such price to the satisfaction of the Contracting Officer will result in payment of actual mobilization costs, as determined by the Contracting Officer, at the completion of mobilization, and actual demobilization costs, as determined by the Contracting Officer, at the completion of demobilization. The determination of the Contracting Officer is not subject to appeal.
1.1.1.1 Mobilization
Mobilization shall include all costs for operations accomplished prior to commencement of actual construction operations. This shall include as a minimum the following:
a. Transportation of personnel, equipment, and materials to the job site.
b. Any required labor and materials to set up working operations (i.e.
administrative, electricity, telephone, lay down area preparations, etc.)
c. Construction of access to construction area.
d. All costs for any other associated work that is necessary in advance of the actual project.
SECTION 01 20 00 Page 2
1.1.1.2 Demobilization
Demobilization shall include general preparation for closeout of project including, but not limited to Transportation of personnel, equipment, and materials from the job site, decommissioning of temporary facilities, etc.
Payment Item No. 0002 MOBILIZATION & DEMOBILIZATION OF DREDGING EQUIPMENT
All costs connected with the mobilization and demobilization of all of the Contractor's equipment for all phases of the dredging operation work as defined below will be paid for at the contract lump sum price for this item, exclusive of items 0001, 0003, 0004, 0005, 0006, 0007 and 0008.
Sixty percent of the lump sum price will be paid to the Contractor upon completion of mobilization at the work site. The remaining forty percent will be paid to the Contractor upon completion of demobilization. In the event the Contracting Officer considers that the amount in this item, sixty percent which represents mobilization and forty percent which represents demobilization, does not bear a reasonable relation to the cost of the work in this contract, the Contracting Officer may require the Contractor to produce cost data to justify this portion of the bid.
Failure to justify such price to the satisfaction of the Contracting Officer will result in payment of actual mobilization costs, as determined by the Contracting Officer, at the completion of mobilization, and actual demobilization costs, as determined by the Contracting Officer, at the completion of demobilization. The determination of the Contracting Officer is not subject to appeal.
1.1.2 Mobilization
Mobilization shall include all costs for operations accomplished prior to commencement of actual construction operations. This shall include as a minimum the following:
a. Transportation of personnel, equipment, and materials to the job site.
b. Any required labor and materials to set up working operations (i.e.
administrative, electricity, telephone, lay down area preparations, etc.)
c. Construction of access to construction area.
d. All costs for any other associated work that is necessary in advance of the actual project.
1.1.3 Demobilization
Demobilization shall include general preparation for closeout of project including, but not limited to Transportation of personnel, equipment, and materials from the job site, decommissioning of temporary facilities, etc.
1.1.4 Payment Item No. 0003 SITE WORK
Payment for "SITE WORK" will be made for costs associated with all methods material and labor required for performing all pre and post construction survey work,containment of material, and site-work associated with the construction of the jetty structure and establishment of dredged material in the beach placement templets, exclusive of items 0001, 0002, 0004, 0005, 0006, 0007 and 0008.
SECTION 01 20 00 Page 3
1.1.5 Payment Item No. 0004 CONSTRUCTION OF SHEET PILE
Payment for "CONSTRUCTION OF SHEET PILE" will be made for costs associated with all methods material and labor required for performing all pre and post construction survey work,containment of material, and site-work associated with the construction of the sheet pile associated with the jetty structure exclusive of items 0001, 0002, 0003, 0005, 0006, 0007 and 0008.
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.2.1 Payment Item No. 0005 DREDGING
Payment to be made for all costs associated with dredging shall include the cost of removal, transportation and disposal of dredged material in the placement area, exclusive of items 0001, 0002, 0003, 0004, 0005, 0006, 0007 and 0008.
The total amount of material removed and to be paid for under these payment items will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last surveys made before dredging, and the bottom surface shown by the soundings of surveys made as soon as practicable after the work has been completed.
The volume for measurement and payment shall include the material within the limits of overdepth and side slopes described in paragraph "Required Dredging Prism, Overdepth, and Side Slopes" of Section 35 20 23 DREDGING, less any deductions that may be required for misplaced material described in subparagraph "Misplaced Material", below.
The drawings are believed to accurately represent conditions at the time of the surveys indicated. New soundings will be taken immediately before dredging as specified in paragraph "Before Dredging Surveys" of SECTION 35 20 23, DREDGING. The Contractor's unit price for dredging, based on the above method of computation of the quantity for payment, shall include his evaluation of shoaling, other natural changes in the waterway, or changes caused by the Contractor's operations that might occur during the period between the surveys before dredging and the surveys for acceptance of the work. Computations for payment purposes will be made by the Government for the scheduled dredging using, as defined in the USACE Hydrographic Survey Manual EM 1110-2-1003 , the Average End Area (AEA) method, Triangulated Irregular Network (TIN) method, or a combination of these methods at the discretion of the Government, utilizing electronic data processing software and machines for the calculations. Determination of quantities removed and the deductions made to determine quantities in place to be paid for in the areas specified, after having once been made, will not be reopened except on evidence of collusion, fraud, or obvious error.
SECTION 01 20 00 Page 4
1.2.1.1 MISPLACED MATERIAL
Any material that is deposited elsewhere than in places designated or approved by the Contracting Officer will not be paid for, and the Contractor may be required to remove such misplaced material and deposit it where directed by the Contracting Officer at the Contractor's expense.
1.2.1.2 EXCESSIVE DREDGING
Material taken from outside the specific areas to be dredged or beyond the limits as extended in paragraph "Required Dredging Prism, Overdepth, and Side Slopes" will be considered as excessive overdepth dredging, or excessive side slope dredging, for which payment will not be made.
Nothing in these specifications shall be construed to prevent payment for the removal of shoals performed in accordance with the applicable provisions of Paragraphs SHOALING and FINAL EXAMINATION AND ACCEPTANCE of Section 35 20 23.
1.2.2 Payment Item No. 0006 Armor Stone (VDOT Class I Stone)
Payment will be made for costs associated with furnishing, transporting, stockpiling, placing, and constructing the imported VDOT Class I armor stone into the restoration of the new jetty as specified. Imported Armor Stone (VDOT Class I) will be measured for payment by the ton (2,000 pounds) by certified Weight Scale Tickets furnished by a public weighmaster provided for each truckload,barge and/or scow to the nearest
0.1 ton, and the final quantity of each truckload, barge and/or scow will be rounded to the nearest whole ton. All weigh scale tickets shall be furnished to the Government. A copy of the Weight Scale Certification shall be furnished from the regulatory agency attesting to the scale's accuracy. The Contracting Officer may elect to accept weighing imported armor stone on the project site. Scale(s) shall be inspected, tested and sealed as directed to assure accuracy within 0.5 percent throughout the range of the scales. If commercial scales are readily available in close proximity 10 miles of site of work, the Contracting Officer may approve the use of the scales. The imported stone shall be weighed in the presence of the Government representative.
1.2.3 Payment Item No. 0007 Bedding Stone (VDOT Class AI Stone)
Payment will be made for costs associated with furnishing, transporting, stockpiling, placing, and constructing the bedding stone into the restored jetty as specified. Bedding Stone (VDOT Class AI) (VDOTRBS) will be measured for payment by the ton (2,000 pounds) by certified Weight Scale Tickets furnished by a public weighmaster provided for each truckload, barge, and/or scow to the nearest 0.1 ton, and the final quantity of each truckload, barge, and/or scow will be rounded to the nearest whole ton.
All weigh scale tickets shall be furnished to the Government. A copy of the Weight Scale Certification shall be furnished from the regulatory agency attesting to the scale's accuracy. The Contracting Officer may elect to accept weighing imported bedding stone on the project site.
Scale(s) shall be inspected, tested and sealed as directed to assure accuracy within 0.5 percent throughout the range of the scales. If commercial scales are readily available in close proximity 10 miles of site of work, the Contracting Officer may approve the use of the scales.
The imported armor stone shall be weighed in the presence of the Government representative.
SECTION 01 20 00 Page 5
1.2.4 Payment Item No. 0008 Demolition of Mooring and Sheet Piles
This pay item includes all costs associated with demolition and removal of all timber mooring piles and sheet pile associated construction of the jetty as shown in the design drawings. Costs include transport and disposal of the removed item.
1.3 MONTHLY PARTIAL PAYMENTS
Monthly partial payments will be based on Section 01 32 01 PROJECT SCHEDULE, paragraph 3.2.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 20 00 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 2: 05/22
general administrative and procedural requirements for Contractor management and coordination
PART 1 GENERAL
1.1 SUBMITTALS
1.2 PROGRESS AND COMPLETION PICTURES
1.3 MINIMUM INSURANCE REQUIREMENTS
1.4 PRECONSTRUCTION
1.4.1 Scheduling
1.4.2 Purpose
1.4.3 Discussion Items
1.4.4 Attendees
1.5 OTHER MEETINGS DURING THE CONTRACT
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 2: 05/22
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Progress and Completion Pictures
1.2 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions during clearing and excavation operations. Provide during the first month and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color 1200 dpi minimum resolution in JPEG file format showing the work. Take a minimum of 20 digital photographs at the dredged material placement site. Show final completed Dredged Material Placement area and key features. Submit two sets of digital photographs each set on a separate CD-R, in the first and last month of the project. Include on the second CD all photos taken. Include photographs demonstrating environmental procedures. Photographs for the two months shall be in a separate monthly directories and each file shall be named to indicate its subject, location and direction in which the camera is looking. All file names shall include a date designator. Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.
1.3 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract.
1.4 PRECONSTRUCTION
Prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction. The purpose of this is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to:
daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
SECTION 01 30 00 Page 2
1.4.1 Scheduling
After award of the construction contract and prior to the start of any construction work, the Contracting Officer's Representative (COR) will schedule and conduct an initial preconstruction conference. Subsequent preconstruction conferences will be required and scheduled by the COR prior to the start of any construction work. The Contractor's Project Manager, Superintendent and Quality Control System Manager shall attend these meetings. The Contractor is encouraged to have an officer of his company (Project Manager could be this person) and representation from each of his sub-contractors and major construction work divisions at the conferences. The conferences will be held at a location and time as specified by the COR.
1.4.2 Purpose
The purpose of the preconstruction conferences is to enable the COR to outline the procedures that will be followed by the Government in its administration of this construction contract and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's supervision and inspection of contract work, about security requirements, regulations, and other similar matters. The COR may invite other Government personnel involved in the work to attend this conference.
1.4.3 Discussion Items
The following is a sample list of items for discussion during the preconstruction conference; however, the Contracting Officer's Representative may modify this list or include additional items for discussion as conditions and the work require.
a. Authority of the Contracting Officer/Contracting Officer's Representative.
b. Contractor's Progress Schedule.
c. Correspondence Procedures.
d. Contractor Labor Standards Provisions.
e. Contract Modifications and Administrative Procedures.
f. Contractor's Administrative, Laydown and Storage Areas.
g. Procedures for Processing Submittals.
h. Payment Estimate Data and Procedures.
i. Contractor Utilities.
j. Security Requirements and Other Regulations, if applicable.
k. Government Furnished Equipment, if applicable.
l. Disposition of Salvage Property, if applicable.
m. Contractor Insurance Requirements.
SECTION 01 30 00 Page 3
n. Environmental Protection Plan.
o. Contractor Performance Evaluation.
p. Emergency and Safety Procedures.
q. Plant and Suitability to Perform the Work.
r. Contractor Required Notification Procedures.
s. Contractor's Submittal Register.
t. Contractor's Survey and Information Reporting Procedures.
u. Contractor's Quality Control Plan and Activity Hazard Analysis.
1.4.4 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.5 OTHER MEETINGS DURING THE CONTRACT
Other meetings may be held after the Preconstruction Conference, for the purpose to discuss concerns and deficiencies that may include the following:
a. Contractor's Site Safety and Health Plan.
b. Quality Control Plan.
c. Environmental Protection Plan.
d. Progress Schedule updates.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 30 00 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15 the preparation and maintenance of the project schedule for construction projects or design-build construction projects
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 QUALITY ASSURANCE
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.1.1 Approved Project Schedule
3.1.2 Schedule Status Reports
3.1.3 Default Terms
3.2 BASIS FOR PAYMENT AND COST LOADING
3.2.1 Activity Cost Loading
3.2.2 Withholdings / Payment Rejection
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 PROGRESS SCHEDULE FORMAT
3.3.2 Level of Detail Required
3.3.3 Activity Durations
3.3.4 Procurement Activities
3.3.5 Critical Activities
3.3.6 Government Activities
3.3.7 Contract Milestones and Constraints
3.3.7.1 Project Start Date Milestone and Constraint
3.3.7.2 End Project Finish Milestone and Constraint
3.3.8 Calendars
3.3.9 Open Ended Logic
3.3.10 Early Completion Schedule and the Right to Finish Early
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Periodic Schedule Updates
3.4.2 Standard Activity Coding Dictionary
3.5 OWNERSHIP OF FLOAT
-- End of Section Table of Contents --
SECTION 01 32 01.00 10 Page 1
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (2017) Administration -- Project Schedules
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule; G
1.3 QUALITY ASSURANCE
The Contractor CQC representative shall be responsible for the preparation and certification as complete all required project Progress Schedule submittals and reports.
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.1.1 Approved Project Schedule
Use the approved Project Schedule to measure the progress of the work and
SECTION 01 32 01.00 10 Page 2 to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
3.1.2 Schedule Status Reports
Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.1.3 Default Terms
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The Contractor shall submit his Progress Schedule to the Contracting Officer for approval at the Pre-Construction Conference specified in SECTION ADMINISTRATIVE REQUIREMENTS. The Progress Schedule shall be
SECTION 01 32 01.00 10 Page 3 submitted and certified as complete by the Contractor's Quality Control Representative in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed, arrival date of Contractor's plant to the job site, all activities scheduled prior to dredging, dredging start and completion dates, calendar days to completion of all work, and contract completion date.
The Contractor shall indicate on the chart the important work activities that are critical to the timely overall completion of the project. Key dates for important features or portions of work features are milestone dates and shall be so indicated on the chart.
3.3.1 PROGRESS SCHEDULE FORMAT
Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule and prepare the Project Schedule using the Precedence Diagram Method (PDM) OR prepare the Progress Schedule in the form of a Gantt Chart.
3.3.2 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.3 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
3.3.4 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.
3.3.5 Critical Activities
The following activities shall be listed as separate line activities on the Contractor's Project Schedule and may be submitted on a separate sheet. This list represents a partial lists and is not considered complete:
a. Submission and approval of Accident Prevention Plan.
b. Submission and approval of pipeline Routing.
c. Submission and approval of Quality Control Plan.
d. Coast Guard Notification and VADEQ notification.
e. Submittal of current marine plant certification and recent plant inspection.
f. Submission and approval of List of Floating Plant
SECTION 01 32 01.00 10 Page 4
3.3.6 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or effect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.3.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.3.7.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay work days provided in the Special Contract Requirementns.
Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends .
SECTION 01 32 01.00 10 Page 5
3.3.9 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.10 Early Completion Schedule and the Right to Finish Early
In the event the project schedule calculates an early completion date of the last activity prior to the contract completion date, identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The Government will not approve an early completion schedule with zero float on the longest path. The Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion.
3.4 PROJECT SCHEDULE SUBMISSIONS
Submit the initial Project Schedule, defining the Contractor's planned operations for approval within 15 calendar days after the NTP is acknowledged. The approved Project Schedule will be used for payment purposes . Cost load the Project Schedule to balance the contract award Contract line item numbers (CLINS) shown on the Price Schedule.