DRAFT_SOW_JRTO1_18NOV2025.pdf
PDF 122 KB Posted
- Solicitation number
- W9123626Z1AUOb
About this file
This document is a Draft Summary of Work for a James River Indefinite Delivery/Indefinite Quantity (IDIQ) Task Order 1 for dredging operations. The project involves maintenance dredging on two specific channel segments of the Upper James River: Richmond Deepwater Terminal Channel and Richmond Deepwater Terminal to Hopewell Channel. The contractor will dredge these channels to specified depths (-22 and -25 Feet Mean Lower Low Water) with one foot of overdepth allowed, completing the work within 240 calendar days after receiving notice to proceed.
The Bid Schedule outlines 11 line items with estimated quantities, including mobilization/demobilization, dredging at two channel locations totaling 300,000 cubic yards, pipeline installation, transportation, sitework, and standby time. The work order requires a Before Dredging survey for each acceptance section, with the Government providing drawings indicating dredging locations, required depths, and available pay volume. The dredging will be performed in two sequential stages: first the Richmond Deepwater Terminal Channel, then the Richmond Deepwater Terminal to Hopewell Channel.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| James River IDIQ Industry Day AGENDA 18NOV2025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JAMES RIVER IDIQ
Task Order 1
DRAFT SUMMARY OF WORK
The work to be performed under this IDIQ Contract Task Order will be on the Upper
James River and includes Richmond Deepwater Terminal and Richmond Deepwater
Terminal to Hopewell. The work to be performed are the items defined in the contract and specification section 01 22 00, payment line items number 0001, 0002, 0004, 0005, 0006, 0007, 0008, 0010, 0011 and all associated work as defined in the contract specifications. Plan Drawings will not be issued for this Task Order. A Before Dredging survey of each dredging area will be performed upon receipt of the Contractor’s advance notice for dredging, as stipulated in Section 01 11 00, paragraph 1.2.1. In accordance with specification section 35 20 23, paragraph 1.4.4 acceptance sections, Contractor designated acceptance sections shall be for contiguous areas, the full width of the channel, identified by station numbers, and shall not exceed two acceptance sections for each channel segment identified for maintenance dredging within the task order issued.
All work specified in this task order shall be performed in accordance with the contract documents and specifications applicable to the respective payment Items indicated and as stated in this Summary of Work. The Contractor shall begin work as soon as the
Notice to Proceed (NTP) is given from the Contracting Officer. The Contractor shall begin performance within 10 calendar days and complete all work within 240 calendar days after receiving notice-to-proceed.
Portions of Richmond Deepwater Terminal and Richmond Deepwater Terminal to
Hopewell channels on the James River Federal Navigation Project are to be dredged in the order indicated below, up to full channel width, to the following elevations:
Richmond Deepwater Terminal Channel, Stations 23+00 to 74+00 & 30+00 to
51+50; -22 Feet Mean Lower Low Water
Richmond Deepwater Terminal to Hopewell Channel, Stations 825+00 to 877+00;
-25 Feet Mean Lower Low Water
One foot of overdepth will be allowed. Actual dredging areas, dredging widths, and associated dredging volume will be determined based on results of the Before Dredging
(BD) Surveys for each channel as indicated. The Contractor's Dredging reports, the
Dredged Material Placement Plan, and Progress Schedule shall be coordinated with this requirement for completing the scheduled work in suitable sections for timely acceptance by the Government.
Order of Work:
1. Richmond Deepwater Terminal Channel, Stations 23+00 to 74+00 & 30+00 to
51+50
2. Richmond Deepwater Terminal to Hopewell Channel, Stations 825+00 to 877+00
Prior to commencement of work, a Before Dredging (BD) Survey will be performed for each acceptance section to be dredged. For each acceptance section surveyed, the
Government shall provide the Contractor in a timely manner, BD drawings indicating the required dredging locations, required and allowable dredging depths, and available pay volume.
BID SCHEDULE
BID SCHEDULE – TASK ORDER 1
ITEM DESCRIPTION ESTIMATED
QUANTITY
UNIT UNIT
PRICE
AMOUNT
0001 Mobilization/
Demobilization
1.0 Job $ $
0002 Additional Pipeline Mob 1.0 Job $ $
0004 Dredge Richmond
Deepwater Terminal
250,000 CY $ $
0005 Dredge Richmond
Deepwater Terminal to
Hopewell
50,000 CY $ $
0006 Transportation of Plant 50 Mile $ $
0007 Installation/Removal
Additional Pipeline
3,000 LF
0008 Upper Pipeline >7,500 lf 150,000 CY $ $
0010 Sitework 2.0 LS $ $
0011 Standby Time 2.0 Day $ $
TOTAL ESTIMATED AMOUNT: