Draft_SOW_1.docx
DOCX document 38 KB Posted
- Attached to
- Sources Sought: San Luis NWRC PV System Federal contract opportunity
- Solicitation number
- 140F0322R0003
About this file
This statement of work describes a design-build contract opportunity for the United States Fish and Wildlife Service to install photovoltaic systems at two locations within the Merced National Wildlife Refuge in California. The selected contractor will be responsible for designing, constructing, operating, and maintaining solar PV systems providing a minimum of 100% of the average annual electricity consumption at each site. Key deliverables for the contractor include design drawings, calculations, and cost estimates at 35%, 75%, and 100% completion. Construction must be completed within 365 days of award. The contractor will also be responsible for developing and implementing operations and maintenance plans for both systems and providing annual inspection and maintenance reports. Interested parties were to submit responses by December 15, 2021 providing company information, relevant experience, and a cost proposal not exceeding 15 pages. The work will be awarded on a firm-fixed-price basis to a single contractor.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Project Title Station Name Date
San Luis National Wildlife Refuge Complex Los Banos, CA
Design, Construction, Operation, and Maintenance of Onsite Photovoltaic Systems
DESIGN BUILD PROJECT SCOPE
DRAFT
U.S. FISH AND WILDLIFE SERVICE
Interior Region 10
December 6, 2021
1. GENERAL:
1.1 The United States Department of the Interior (DOI) Fish and Wildlife Service (USFWS) intends to enter a firm fixed-price contract with a single Contractor for the design, construction, operation, and maintenance of onsite photovoltaic (PV) systems at Merced NWR.
1.2 The Merced National Wildlife Refuge encompasses 10,258 acres of wetlands, native grasslands, vernal pools, and riparian areas. It was established in 1951 under the Lea Act to attract wintering waterfowl from adjacent farmland where their foraging activities were causing crop damage. In the last few decades, changes in local agricultural practices and Refuge management activities have reduced these wildlife/crop issues.
The Refuge plays host to the largest wintering populations of lesser Sandhill cranes and Ross’ geese along the Pacific Flyway. Each autumn more than 20,000 cranes and 60,000 arctic-nesting geese terminate their annual migrations from Alaska and Canada to make the Refuge home for six months. Here they mingle with thousands of other visiting waterfowl, waterbirds, and shorebirds – making the Refuge a true winter phenomenon.
The Refuge also provides important breeding habitat for Swainson’s hawks, tri-colored blackbirds, marsh wrens, mallards, gadwall, cinnamon teal, and burrowing owls. Tri-colored blackbirds, a colonial-nesting songbird, breed in colonies of more than 25,000 pairs in robust herbaceous vegetation. Coyotes, ground squirrels, desert cottontail rabbits, beaver, and long-tailed weasels can also be seen year-round.
2. SCOPE OF WORK:
2.1 The USFWS seeks to install two solar PV systems: one at the Sno-Bird location (approximately 210 kW) and the other at the Merced Shop Compound location (approximately 130 kW).
2.2 The Contractor shall design both PV systems to meet 100% of both site’s average annual electricity consumption. The Contractor shall reference Attachment 1 (not yet available) to assist in the design of the PV systems.
2.3 The Contractor shall provide all labor, material, equipment, engineering, maintenance and capital to design, install, commission, interconnect, operate and maintain solar photovoltaic systems as required herein. Contractor is responsible for all permits, approvals, freight, procurement, monitoring, inspection, billing, interconnection fees, and incidentals as necessary to design, install, commission, interconnect, operate and maintain all the complete solar PV systems, described hereinafter. The Contractor is responsible for ascertaining relevant site conditions to verify project feasibility and for determining appropriate solar PV system sizes.
2.4 The map included with the Performance Specifications shows the proposed PV array location on the Sno-Bird site. The footprint area of the array is approximate and shown only for illustration.
2.5 Performance Period: 365 calendar days from NTP.
2.6 The resulting contract will be firm-fixed-price (FFP) or lump sum.
2.7 Bid responses will be evaluated partly based on achieving net zero electricity for both locations. See Section M “Selection Criteria.”
2.8 Definition of Contract Line Items and Description of Work TASK 1: 35% Design: Include a minimum of (1) site visit in this task and (2) min additional stakeholder review meetings (online).
Deliverables:
_1_ electronic set of the Design Drawings for each location _1_ electronic set of Design Calculations _1_ Draft Product Cut Sheets _1_ electronic set of engineer’s opinion of construction cost for each site _1_ List of required federal, state, county, and local permit for the proposed activities.
TASK 2: 75% Design: Upon approval of a 35% Design, refine the design and incorporate all comments.
Deliverables:
_1_ electronic set of responses to the comments received on the Task 1 Deliverables.
_1_ electronic set of Design Drawings _1_ electronic set of Design Calculations _1_ Updated Product Cut Sheets _1_ electronic set of opinion of construction cost
TASK 3: 100% Design: Upon approval of a 75% Design, refine the design and incorporate all comments.
Deliverables:
_1_ electronic set of responses to the comments received on the Task 2 Deliverables.
_1_ electronic set of Design Drawings _1_ electronic set of Design Calculations _1_ Final Product Cut Sheets _1_ electronic set of opinion of construction cost
TASK 4: Construction @ Sno-Bird Site Construction shall be completed no later than 365 calendar days after award of the contract. As- Constructed Drawings completed no later than 21 calendar days after Project Completion.
Deliverables:
_1_ Completed PV Array Construction _1_ As-Constructed drawings in pdf and CAD format _1_ Staff Training for General Operation and Emergency Shut-Downs
TASK 5: Construction @ Merced Shop Site Construction shall be completed no later than 365 calendar days after award of the contract. As- Constructed Drawings completed no later than 21 calendar days after Project Completion.
Deliverables:
_1_ Completed PV Array Construction _1_ As-Constructed drawings in pdf and CAD format _1_ Staff Training for General Operation and Emergency Shut-Downs
TASK 6: Operation & Maintenance @ Sno-Bird Site Deliverables:
_1_ Draft Operations and Maintenance Plan _1_ Final Operations and Maintenance Plan _1_ Annually: electronic copy of the scheduled inspection, operation, and maintenance reports
TASK 7: Opertion & Maintenance @ Merced Shop Site Deliverables:
_1_ Draft Operations and Maintenance Plan _1_ Final Operations and Maintenance Plan _1_ Annually: electronic copy of the scheduled inspection, operation, and
Unless otherwise noted, all electronic deliverables shall be in PDF format and shall not exceed 5 MB in file size.
3. INSPECTION AND ACCEPTANCE
Each Task shall require a formal submittal; a ten-workday period for government review; A-E responses to the comments with agreed upon revisions to the deliverables; and government sign-off in writing. Work shall be performed in accordance with the requirements of this SOW. Work shall be accepted when all the work is completed as described herein.
4. GOVERNMENT FURNISHED INFORMATION
The following data and materials will be provided to the Contractor:
1.
1.1.
1.2.
1.3.
1.4.
1.5.
1.6.
1.7.
1.8.
· Project Performance Specifications
· Proposal Evaluation Criteria Memo
· USFW General Engineering Requirements
· Estimated yearly consumption of each deep well pump (Attachment 1-not yet available)
· Technical Specifications of the well pump (Attachment 2-not yet available)
· List of Pumps and associated PG&E account numbers (Attachment 3-not yet available)
5. REQUESTED PROPOSAL DOCUMENTS
In addition to the cost proposal, please provide the information listed below. Submit a bookmarked pdf, 15 pages maximum (maximum page count does not include the cost proposal). The pdf file size shall not exceed 5 MB.
5.1 Cover Letter
5.2 Relevant Experience
5.3 Resumes and Roles of Proposed Team Members including NEBCEP Certifications
5.4 Proposed Project Approach (1 page)
5.5 Proposed Operations & Maintenance Plan (1 page)
5.6 Proposed Project Schedule (1 page)
5.7 Cost Proposal
6. PROJECT LOCATION AND AVAILABILITY
Refer to the Performance Specifications for the proposed locations of the photovoltaic arrays.
Normal work hours for the Merced NWR staff are 7:30am to 4:00pm, Monday through Friday, excluding Holidays. Coordinate with the Project Leader if contact outside of the normal working hours is needed.
7. CONTACTS
Project Leader (PL): Kim Forrest San Luis NWR Complex US Fish & Wildlife Service P.O. Box 2176, 7376 S. Wolfsen Road, Los Banos, CA 93635 209 -826-3508 ext. 116 Kim_forrest@fws.gov
Contracting Officer (CO): Nick Koston Construction/AE Acquisition Operations US Fish & Wildlife Service Portland, OR 503-231-6117 Nicolas_koston@fws.gov
Contracting Officers Representative (COR): Caroline Kreiser US Fish & Wildlife Service Infrastructure Management Division Sacramento, CA Phone: 916-215-6624 Caroline_kreiser@fws.gov
US Fish & Wildlife Service Station Name Page 1 of 9
US Fish & Wildlife Service Merced National Wildlife Refuge Photovoltaic Arrays Page 8 of 8