DRAFT RTA SPECIFICATIONS FY20 OMA ARMY MUNS FACILITIES REPAIR PHASE I KAB.pdf
PDF 3 MB Posted
- Solicitation number
- W912HV20B0011
About this file
This is a solicitation for a firm-fixed-price design-build contract to repair and modernize munitions storage facilities at Kadena Air Base in Okinawa, Japan. The scope of work includes repairing and replacing ventilation systems, lighting, electrical systems, concrete, roofing membranes, and applying protective coatings. It also involves abating lead-based paint and asbestos. The work will be performed at 12 munitions structures over a period of performance of 730 days after notice to proceed. A solicitation will be issued by the end of June 2020, with award made to the responsible bidder offering the most advantageous price. The Army Corps of Engineers Engineering District Japan is the contracting agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pre-Solicitation Notice W912HV20B0011 FY20 Army Muns.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. W912HV-20-B-0011
US Army Corps of Engineers Japan District
FY20 OMA ARMY MUNS FACILITIES REPAIR
(PHASE I), KAB, OKINAWA, JAPAN
SPECIFICATIONS
RTA Submittal
MAY 2020
DRAFT
FY20 OMA ARMY MUNS FACILITIES REPAIR (PHASE I), KAB 19SF0011
W912HV-20-B-0011 PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 STATEMENT OF WORK
01 11 00-A DESIGN CRITERIA
01 11 00-B CONCEPT DRAWINGS
01 11 00-C HAZARDOUS MATERIALS SURVEY REPORT
01 11 00-D ACCEPTABLE ALTERNATIVE JAPANES STANDARDS
01 11 00.00 10 GENERAL CONTRACT REQUIREMENTS
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 16 DESIGN AFTER AWARD
01 33 00-A ENG FORM 4025-R
01 33 00-B SUBMITTAL REGISTER
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 26-A USACE ACCIDENT PREVENTION PLAN CHECKLIST
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 42 15 METRIC MEASUREMENTS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 50 00-A PROJECT SIGN
01 50 00-B TEMPORARY TOILET FACILITY
01 57 19.01 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01-A HAZARDOUS MATERIALS INSPECTION REPORT
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 00-A FORM DD 1354
01 78 23 OPERATION AND MAINTENANCE DATA
-- End of Project Table of Contents --
SECTION 01 11 00
STATEMENT OF WORK
PART 1 GENERAL
1.1 General
The Contractor shall design and perform repairs for the Munitions Structure Repair project at Kadena Munitions Site, Okinawa Japan resulting in complete and usable facility.
The intent of this section is to specify the minimum design and construction requirements for quality, function, materials, and types of construction in sufficient detail for Contract completion.
Basis of design, design submittal requirements, construction document drawings, and specifications shall be prepared to comply with this section and Section 01 33 16 DESIGN AFTER AWARD. No deviations from these sections shall be allowed unless prior approval is obtained from the Contracting Officer. All questions or problems encountered by the Contractor in following the requirements in this section shall be promptly submitted with recommendations to the Contracting Officer for resolution.
1.2 Phasing Requirements
The contractor construction schedule shall incorporate the following requirements.
1.2.1 Order of Structure Repair
Structures will be repaired in order of the following groups. The contractor will work in one group at a time, and start follow-on group after acceptance of current group.
Group 1: 48244, 48245, and 48255 Group 2: 48246, 48247, and 48256 Group 3: 48249, 48252, 48257, and 48277 Group 4: 48253, 48254, 48258, and 48259
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 ATTACHMENTS
Information provided in the attachments is intended to provide design requirements and information.
3.1.1 01 11 00-A
Design Criteria: Design and construction for this project shall comply with Attachment 01 11 00-A. Secure any necessary reference at Contractor's own expense and resources.
W912HV-20-B-0011 SECTION 01 11 00 Page 1
3.1.2 01 11 00-B
Concept Drawings: Provided for design and coordination purposes.
Information depicted in the Concept Drawings serves as a guide only.
Further development shall require coordination with the using agency and base personnel.
3.1.3 01 11 00-C
Hazardous Materials Inspection Report: Refer to section 01 57 19.01 and attachment 01 57 19.01-A.
3.1.4 01 11 00-D
Listing of "Acceptable Alternative Japanese Standards" which are considered acceptable alternatives to the US standards within the Contract specifications. This list is provided for design and coordination purposes. The Designer of Record shall be responsible for incorporating the applicable standards from this list into each relevant individual technical section specification.
3.2 DESIGN COORDINATION, SUBMITTALS, AND OTHER REQUIREMENTS
Refer to Section 01 33 16 DESIGN AFTER AWARD.
-- End of Section --
W912HV-20-B-0011 SECTION 01 11 00 Page 2
ATTACHMENT 01 11 00-A
STATEMENT OF WORK
TOC - 2
TABLE OF CONTENTS
CHAPTER 1 DESIGN AND CONSTRUCTION OBJECTIVES – NOT USED .............. 1-1
CHAPTER 2 CIVIL ENGINEERING .......................................... 2-1
2-1 DESIGN GOALS AND OBJECTIVES ..................................... 2-1
2-2 DESIGN CRITERIA ............................................... 2-1
2-3 EXCAVATION PERMITS ............................................ 2-1
2-4 SOILS, PAVEMENT AND EARTH WORK .................................. 2-1
2-5 DEMOLITION ................................................... 2-2
2-6 SITE PLANS ................................................... 2-2
2-7 GRADING AND DRAINAGE ........................................... 2-3
2-8 LANDSCAPING .................................................. 2-3
2-9 SCOPE OF WORK BY BUILDING ....................................... 2-4
2-10 DETAILED SPECIFICATIONS ........................................ 2-5
CHAPTER 3 ARCHITECTURAL DESIGN ....................................... 3-1
3-1 DESIGN GOALS AND OBJECTIVES ..................................... 3-1
3-2 REFERENCES ................................................... 3-1
3-3 DESIGN ...................................................... 3-1
3-4 DETAILED SPECIFICATIONS ........................................ 3-2
CHAPTER 4 STRUCTURAL DESIGN .......................................... 4-1
4-1 DESIGN GOALS AND OBJECTIVES ..................................... 4-1
4-2 STRUCTURAL WORK ............................................... 4-1
4-3 DESIGN CRITERIA ............................................... 4-1
4-4 MINIMUM MATERIAL STRENGTHS AND PROPERTIES .......................... 4-2
4-5 BIDDING INFORMATION ............................................ 4-3
4-6 DETAILED SPECIFICATIONS ........................................ 4-3
CHAPTER 5 MECHANICAL WORK ............................................ 5-1
5-1 DESIGN GOALS AND OBJECTIVES ..................................... 5-1
5-2 APPLICABLE CODES AND STANDARDS ................................... 5-1
5-3 MATERIALS AND EQUIPMENT ........................................ 5-1
5-4 SCOPE OF WORK BY BUILDING ....................................... 5-2
5-5 DETAILED SPECIFICATIONS ........................................ 5-5
CHAPTER 6 ELECTRICAL ENGINEERING ..................................... 6-1
6-1 DESIGN GOALS AND OBJECTIVES ..................................... 6-1
6-2 APPLICABLE CODES AND STANDARDS ................................... 6-1
6-3 MATERIALS AND EQUIPMENT ........................................ 6-2
W912HV-20-R-0009
TOC - 3
6-4 SCOPE OF WORK BY BUILDING ....................................... 6-3
6-5 DETAILED SPECIFICATIONS ........................................ 6-6
CHAPTER 7 FIRE PROTECTION ENGINEERING – NOT USED ..................... 7-1
CHAPTER 8 ENVIRONMENTAL REQUIREMENTS ................................. 8-1
8-1 ENVIRONMENTAL ISSUES ........................................... 8-1
8-2 ASBESTOS ..................................................... 8-1
8-3 LEAD ........................................................ 8-2
8-4 DETAILED SPECIFICATIONS ........................................ 8-2
TOC - 4
INTENTIONALLY LEFT BLANK
01 11 00-A SOW CHAPTER 1-1
CHAPTER 1
DESIGN AND CONSTRUCTION OBJECTIVES – NOT USED
End of CHAPTER 1
01 11 00-A SOW CHAPTER 1-2
01 11 00-A SOW CHAPTER 2-1
CHAPTER 2
CIVIL ENGINEERING
2-1 Design Goals and Objectives
Clean existing drain line passage inside the building footprint and remove excess soil build-up outside building footprint for positive drainage.
Provide additional sodding in Building 48255.
Refer to Architectural SOW for detailed instruction and repair of existing concrete floors.
Requirements discussed in this Chapter shall take precedence over any conflicting requirements in other Chapters and/or any other criteria and shall be brought to the attention of the Contracting Officer for resolution in writing prior to submission of a bid.
2-2 References
Unless otherwise noted, the following reference(s) are available via the internet at the Whole Building Design Guide Website http://www.wbdg.org/ccb/browse_cat.php?c=4
UFC 3-201-01 Civil Engineering, dated 01 April 2018.
2-3 Excavation Permits
The contractor shall obtain approved dig permits from 718 Civil Engineering Squadron one (1) month prior to beginning excavation work or the commencement of any construction repairs. The link to fill-out the electronic digging permit form request is:
https://kadena.eis.pacaf.af.mil/18CEG/18%20CES/CEO/CEOE/CEOES/Lists/103%20Dig %20Permit/Customer%20Service.aspx.
2-4 Soils, Pavement and Earth Work
2-4.1 Erosion and Sediment Control Measures
Provide erosion and sediment control measures in accordance with JEGS and applicable GOJ or local laws and regulations. Preserve vegetation to the maximum extent practicable.
Erosion control inspection reports may be compiled as part of a stormwater pollution prevention plan (SPPP) inspection reports.
2-4.2 Erosion Prevention
Prevent erosion by mulching, Compost Blankets, Geotextiles, and temporary slope drains. Stabilize slopes by chemical stabilization, sodding, seeding, or such combination of these methods necessary for effective erosion control.
Use of hay bales is prohibited.
01 11 00-A SOW CHAPTER 2-2
Provide seeding in accordance with Section 32 92 19 SEEDING. Any disturbed area with exposed soil that is not being worked on must be seeded or sodded no later than two weeks from the last disturbance regardless of the installation of any other erosion control measures in place. Remove any temporary measures after the area has been stabilized.
2-5 Demolition
Identify the safety and health aspects, and prepare in accordance with Section 02 41 00 DEMOLITION and referenced sources. Remove rubbish and debris from Government property and dispose in accordance with Japanese law. Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store any salvageable materials resulting from demolition activities within the fenced area described above or at the supplemental storage area. Neatly stack stored materials not in trailers, whether new or salvaged.
2-6 Site Plans
2-6.1 Visual survey
Building must be visually surveyed for existing finish, materials and painted surfaces which are suspected containing ACM or LBP.
2-6.2 Overall Site Plan
Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
2-6.3 Storage of Material and Field Office
Storage of materials and field office or assembly area on base will be authorized for this contract if available. The contractor shall prepare all documents and submit 45 days in advance to Contracting Officer for approval.
2-6.4 Erosion Control Plan
Prepared in accordance with JEGS, Chapter 13, and all applicable Federal, GOJ national or prefectural laws and regulations, and installation requirements.
Ensure that temporary erosion controls are adequate. All erosion and sediment control measures should be employed by the contractor to minimize any additional erosion that may be caused by the construction activities.
01 11 00-A SOW CHAPTER 2-3
2-7 Grading and Drainage
Contractor shall prevent oily wastes or other hazardous substances from entering the ground, drainage areas, or local bodies of water. Keep construction activities under surveillance, management, and control, and monitor all water areas affected by construction activities in order to prevent pollution of surface and ground waters. Toxic or hazardous chemicals shall not be applied to soil or vegetation when such application may cause contamination. Prevent oily wastes or other hazardous substances from entering the ground, drainage areas, or local bodies of water. Comply with JEGS and all applicable Federal, GOJ national or prefectural laws and regulations, and installation requirements.
Contractor is not authorized sewage holding tanks on base and must procure a portable toilet service Contract. The portable toilet Contract must include the correct removal of sewage and maintenance of the facilities.
2-8 Landscaping
Provide seeding in accordance with Section 32 92 19 SEEDING. Any disturbed area with exposed soil that is not being worked on must be seeded or sodded no later than two weeks from the last disturbance regardless of the installation of any other erosion control measures in place. Remove any temporary measures after the area has been stabilized. The Contractor shall place emphasis on the protection of habitats favorable to the reproduction and survival of indigenous flora and fauna. The Contractor shall use indigenous flora for planting/sodding. Green waste is the vegetative matter from landscaping, land clearing and grubbing, including, but not limited to, grass, bushes, scrubs, small trees and saplings, tree stumps and plant roots.
Marketable trees, grasses and plants that are indicated to remain, be re-located, or be re-used are not included.
01 11 00-A SOW CHAPTER 2-4
2-9 Scope of Work by Building
2-9.1 Building 48244. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.2 Building 48245. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.3 Building 48246. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.4 Building 48247. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.5 Building 48249. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.6 Building 48252. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.7 Building 48253. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.8 Building 48254. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.9 Building 48255. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-11.9.1 Provide 110 square meters of seeding on earth covered roof, located on top of entrance door, and where patches are visible.
01 11 00-A SOW CHAPTER 2-5
2-9.10 Building 48256. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.11 Building 48257. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.12 Building 48258. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.13 Building 48259. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage.
2-9.14 Building 48277. Clean drain line passage inside the building footprint. Remove excess soil build-up outside building footprint for positive drainage
2-10 Detailed Specifications
During the design stage, submit UFGS specifications to specify the quality, characteristics, installation procedures and testing requirements for all applicable sections. UFGS documents can be found at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.
Some of the following specification sections apply but are not limited to those listed:
UFGS 32 92 19 SEEDING
UFGS 02 41 00 DEMOLITION
End of CHAPTER 2
01 11 00-A SOW CHAPTER 2-6
01 11 00-A SOW CHAPTER 3-1
CHAPTER 3
ARCHITECTURAL DESIGN
3-1 Design Goals and Objectives
The architectural scope of work consists of coating the interior concrete wall/ceiling surfaces of all (14) earth covered munitions facilities. The structural portion of this RFP addresses the repair of cracks and spalling.
The electrical portion of this RFP addresses the removal of wall and ceiling mounted equipment and devices. Both of these activities must be completed prior to the coating application within each ECM. Refer to photos included with the RFP for the general condition of the existing structures.
Requirements discussed in this Chapter shall take precedence over any conflicting requirements in other Chapters and/or any other criteria and shall be brought to the attention of the Contracting Officer for resolution in writing prior to submission of a bid.
3-2 References
IBC 2018 International Building Code 2018, International Code Council
UFC 1−200−01 General Building Requirements (Latest Version)
UFC 3-101-01 Architecture, with Change 5
UFC 3-190-06 Protective Coatings and Paints
UFGS 09 97 23.17 Corrosion Inhibitor Coating of Concrete Surfaces
USAF MFSG U.S. Air Force Munitions Facilities Standards Guide, Vol. 1 (2004)
JDDG v1.0 Japan District Design Guide (2017)
KAB ACG 2012 Kadena Air Base Architectural Compatibility Guide, revised 1 March 2012
3-3 Design
After the structural defects have been repaired in accordance with this RFP and the wall/ceiling mounted devices and equipment have been removed, provide a high-performance corrosion inhibiting coating system in accordance with UFGS 09 97 23.17. The coating system shall include the entire barrel vaulted wall/ceiling surface and the front and back vertical walls down to the slab intersection on both sides.
01 11 00-A SOW CHAPTER 3-2
3-3.1 Structures to Repair
Fourteen (14) existing ECM at Kadena Muns are as follows;
48244 48245 48246 48247 48249 48252 48253 48254 48255
48256 48257 48258 48259 48277
3-3.2 Corrosion Inhibitor Coating System
Provide a corrosion inhibiting coating system for the concrete wall/roof assemblies in accordance with UFGS 09 97 23.17 CORROSION INHIBITOR COATING OF CONCRETE SURFACES. The requirements include, but are not limited to:
3-3.2 The system will include a vapor phase inhibitor, ionic phase inhibitor or a combination and a reactive silicone surface sealant or surface protection coating.
3-3.2 Applicator must have a minimum of 5-years of specialized experience with this type of system.
3-3.2 Submittal of an environmental protection plan.
3-3.2 Proper substrate conditions and surface preparation.
3-3.2 Suitable weather conditions during application and curing period.
3-4 Detailed Specifications
During the design stage, submit UFGS specifications to specify the quality, characteristics, installation procedures and testing requirements for all applicable sections. UFGS documents can be found at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.
Some of the following specification sections apply but are not limited to those listed:
UFGS 09 97 23.17 CORROSION INHIBITOR COATING OF CONCRETE SURFACES
End of CHAPTER 3
01 11 00-A SOW CHAPTER 3-3
01 11 00-A SOW CHAPTER 4-1
CHAPTER 4
STRUCTURAL DESIGN
4-1 Design Goals and Objectives
Scope of work includes concrete repairs for ECMs. The Contractor's DOR is required to provide engineered solutions to repair the ECM concrete wall/ceiling and slabs on grade. Requirements discussed in this Chapter shall take precedence over any conflicting requirements in other Chapters and/or any other criteria and shall be brought to the attention of the Contracting Officer for resolution in writing prior to submission of a bid.
4-2 Structural Work
4-2.1 Concrete repair. Repair all ECM concrete cracks and spalls at wall/ceiling and slab on grade by epoxy resin injection method and V-cut method, and replace the deteriorated concrete with polymer mortar as required. Perform visual inspection and hammer tapping, chain drag sounding, or other methods acceptable by the Contracting Officer to uncover potentially deficient concrete.
Fourteen (14) existing ECM at Kadena Muns to be upgraded are as follows;
48244 48245 48246 48247 48249 48252 48253 48254 48255
48256 48257 48258 48259 48277
4-3 Design Criteria
4-3.1 Relevant Codes & Criteria
IBC 2018 International Building Code 2018, International Code Council
ASCE 7−10 Minimum Design Loads for Buildings & Other Structures, American Society of Civil Engineers
UFC 1−200−01 General Building Requirements (Latest Version)
UFC 3−301−01 Structural Engineering (Latest Version)
UFC 3-320-
06A
Concrete Floor Slabs on Grade Subjected to Heavy Loads (Latest Version)
USAF MFSG U.S. Air Force Munitions Facilities Standards Guide, Vol. 1 (2004)
JDDG v1.0 Japan District Design Guide (2017)
01 11 00-A SOW CHAPTER 4-2
4-3.2 Relevant Protective Construction Standards
UFC 4-420-01 Ammunition & Explosive Storage Magazines (2015)
Japanese Renovation Criteria
Reinforcement Criteria of Existing RC structure, Japan Building Disaster Prevention Association (NIHON BOUSAI KYOUKAI), dated
4-4 Minimum Material Strengths and Properties
4-4.1 Concrete
4-4.1 Reinforced Concrete. Portland cement shall conform to JIS A 5308.
Minimum concrete strength for buildings: 24N/mm2 with water-cement ratio not more than 0.55
4-4.1 Concrete Rehabilitation.
Polymer cement shall conform to JIS A 6203, and Epoxy resin shall conform to
JIS A 6024.
Polymer Mortar. Apply polymer mortar to exposed loose materials by manufacture recommended method.
Polymer grout. Apply polymer grout to exposed loose and unsound materials mainly columns by manufacture recommended method.
Epoxy resin. Apply epoxy resin to concrete cracks mainly over slab on grade and beams by manufacture recommended method.
4-4.2 Reinforcing Steel
4-4.2 Bars. Deformed reinforcing bars shall conform to JIS G 3112, if required, material properties are shown below.
D10 to D16 GRADE SD295A D19 and Larger GRADE SD345
01 11 00-A SOW CHAPTER 4-3
4-5 Bidding Information
4-5.1 Repair concrete cracks: Bidders shall base their bid on providing an average of 75 linear meters of crack repairs per ECM.
4-5.2 Replace the deteriorated concrete: Bidders shall base their bid on providing an average of 60 SM of concrete wall and slab demolition and replacement per ECM. The concrete replacement shall consist of the half wall thickness of the deteriorated area.
4-5.3 Coatings & sealants: For coating and sealant requirements, including internal marking and the exterior wall, refer to the Architectural section.
4-6 Detailed Specifications
During the design stage, submit UFGS specifications to specify the quality, characteristics, installation procedures and testing requirements for all applicable sections. UFGS documents can be found at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.
Some of the following specification sections may apply specification section include but not limited to:
UFGS 03 01 00 REHABILITATION OF CONCRETE
UFGS 03 30 00 CAST-IN-PLACE CONCRETE
UFGS 03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
End of CHAPTER 4
01 11 00-A SOW CHAPTER 4-4
01 11 00-A SOW CHAPTER 5-1
CHAPTER 5
MECHANICAL WORK
5-1 Design Goals and Objectives
Repair or replace the ventilation systems for munitions storage buildings on Kadena Air Base, Okinawa.
Requirements discussed in this Chapter shall take precedence over any conflicting requirements in other Chapters and/or any other criteria and shall be brought to the attention of the Contracting Officer for resolution in writing prior to submission of a bid.
5-2 Applicable Codes and Standards
Mechanical design criteria and guidance are contained in the following documents. Latest editions for the RFP shall apply, applicable codes and standards include but are not limited to the following. UFC documents can be found at http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc.
5-2.1 US Government Standards:
Unified Facilities Criteria (UFC):
UFC-3-420-01 Plumbing Systems
UFC-3-410-01 Heating, Ventilating and Air conditioning
UFC 3-440-05N Tropical Engineering
UFC 4-420-01 Ammunition and Explosive Storage Magazines
5-3 Materials and Equipment
All materials and equipment shall be the standard catalogued products of manufacturers regularly engaged in the production of such equipment and material, and shall be the manufacturer’s latest design. All equipment and material shall conform to the requirements of American National Standards Institute (ANSI), American Society of Testing and Materials (ASTM), National Fire Protection Association (NFPA), Japanese Industrial Standards (JIS) or other national trade association as applicable. Where standards exist, materials and equipment shall bear the label and be listed by Underwriters Laboratories, Inc. (UL) or other recognized testing organization.
5-3.1 Gravity Ventilators
Provide stationary roof ventilators fabricated of galvanized steel with seamless spun conical-shaped weather-cap, and having straight-through drainage for eliminating the possibility of air-borne debris collecting in the ventilator openings. Insect screens shall be provided.
Ventilators shall be fabricated in accordance with approved shop drawings.
Welds, soldered seams, rivets and fasteners shall be clean, secure, watertight, and smooth. Edges shall be wired or beaded, where necessary, to ensure rigidity. Joints between sections shall be watertight and shall allow
01 11 00-A SOW CHAPTER 5-2
for expansion and contraction. Galvanic action between different metals in direct contact shall be prevented by nonconductive separators.
Screens shall be furnished by ventilator manufacturer as part of ventilator assembly. Screen (with frames) shall be manufactured of material to match ventilators, and shall be designed to be easily removed for cleaning purposes.
Ventilator bases for curb-mounted installations shall be of size required to fit the existing stack opening of the buildings, and shall be designed specifically for the type of ventilator and roofing system approved for this project. Design wind shall be 298 kilometers per hour (185 mph) in accordance with UFC 3-301-01 (Okinawa, Risk Category III). Curb bases shall be factory-formed and flashed for a watertight installation. Curb bases shall be fabricated of material and finish to match the ventilator. Roof ventilators and curbs shall be certified (US or JIS) for static and cyclic wind loading and impact. US test certifications are Large Missile Impact Test ASTM E1996 (TAS 201), Uniform Static Air Pressure Test (ASTM E330) and Cyclic Wind Pressure Load Test.
5-3.2 Air Intake Vents
Air intake vents that are to be replaced shall be constructed to match the existing equipment design as shown on the drawings and confirmed during site inspection prior to proposal.
5-3.3 Fire Damper Mechanisms
Fire dampers in the air intake and outlet openings of the munitions buildings are designed to close when an exterior heat source (fire) melts the fusible link. The dampers close by gravity alone. Fire damper mechanisms that are to be replaced shall be constructed to match the existing equipment design as shown on the drawings and confirmed during site inspection prior to proposal.
5-3.4 Physical Security Bar Assembly
At the interior opening of the roof mounted gravity ventilators, install a physical security bar assembly to prevent personnel intrusion from the roof stack. Bars shall be made of steel with a minimum diameter of 6mm and be welded to a frame of a minimum of 6mm thick steel. The entire assembly shall be hot dipped galvanized and bolted to the interior wall with concrete anchors.
5-4 Scope of Work by Building
5-4.1 Building 48244
5-4.1 Remove/replace the roof mounted gravity ventilator
Removal Work
Remove the roof mounted gravity ventilator, the curbing lumber that it is mounted on, and the fire damper inspection access door on the stack.
New Work
01 11 00-A SOW CHAPTER 5-3
Replace the roof mounted gravity ventilator with a new factory-painted galvanized steel gravity ventilator of the same form and function with a cap that prevents the entry of wind-driven rain. Replace the curbing lumber that the hood is mounted on and caulk all joints. Replace the fire damper inspection access door with a new galvanized and field painted door of the same design and material thickness. Lubricate the fire damper mechanism with calcium sulfonate grease and test to ensure the damper closes when the fusible link is removed.
Provide an insect screen in the roof opening (stack) beneath the ventilator, hurricane-rated stainless steel tie-downs secured to the structure, and braided grounding wire.
5-4.1 Paint the front wall ventilation intake hoods and fire damper mechanisms.
Removal Work
Use abrasive blasting to remove the existing paint and corrosion from the intake hood and fire damper mechanism.
New Work
Paint the intake hoods and fire damper mechanisms and all associated components. Apply paint to match the existing color or the building color.
Lubricate the fire damper mechanism with calcium sulfonate grease and test to ensure the damper closes when the fusible link is removed.
5-4.1 Replace the intake grates/screens on the interior side
Removal Work
Remove the existing ventilation grates/screens from the interior opening for the intake hoods and at the opening within the building for the roof mounted ventilator.
New Work
Replace the ventilation grates/screens with new galvanized steel grates and screens. Include physical security bar assembly as well insect screens.
5-4.2 Building 48245;
Same scope of work as building 48244
5-4.3 Building 48246;
Same scope of work as building 48244
5-4.4 Building 48247;
Same scope of work as building 48244
5-4.5 Building 48249;
Same scope of work as building 48244
5-4.6 Building 48252;
Include the scope of work as noted for building 48244 and the additional following work;
01 11 00-A SOW CHAPTER 5-4
5-4.6 Replace the fire damper mechanism for the roof mounted gravity ventilator
Removal Work
Remove the fire damper and closing mechanism (arm, weight, fusible link connections) for the stack beneath the roof mounted gravity ventilator.
New Work
Replace the fire damper and closing mechanism for the roof mounted gravity ventilator with a new mechanism of the same form and function. Exterior components should be factory-painted galvanized steel. New mechanism should include a factory-painted heavy-gauge steel plate inside the ventilation stack that is appropriately sized to seal off the stack when closed. Include a new counter weight, anchoring point, and wire with fusible link. Ensure that the steel plate fully closes under its own weight. Lubricate the fire damper mechanism with calcium sulfonate grease and test to ensure the damper closes when the fusible link is removed.
5-4.7 Building 48253;
Same scope of work as building 48244
5-4.8 Building 48254;
Same scope of work as building 48244
5-4.9 Building 48255;
No Work
5-4.10 Building 48256;
Same scope of work as building 48252
5-4.11 Building 48257;
Same scope of work as building 48252
5-4.12 Building 48258;
5-4.12 Replace the fire damper mechanism for the roof mounted gravity ventilator
Removal Work
Remove the fire damper and closing mechanism (arm, weight, fusible link connections) for the stack beneath the roof mounted gravity ventilator.
Remove the roof mounted gravity ventilator and store for reinstallation.
New Work
Replace the fire damper and closing mechanism for the roof mounted gravity ventilator with a new mechanism of the same form and function. Exterior components should be factory-painted galvanized steel. New mechanism should include a factory-painted heavy-gauge steel plate inside the ventilation stack that is appropriately sized to seal off the stack when closed. Include a new counter weight, anchoring point, and wire with fusible link. Ensure that the steel plate fully closes under its own weight. Lubricate the fire
01 11 00-A SOW CHAPTER 5-5
damper mechanism with calcium sulfonate grease and test to ensure the damper closes when the fusible link is removed. Reinstall the existing roof ventilator.
5-4.12 Paint the front wall ventilation intake hoods and fire damper mechanisms.
Removal Work
Use abrasive blasting to remove the existing paint and corrosion from the intake hoods and fire damper mechanisms.
New Work
Paint the intake hood and fire damper mechanism and all associated components. Apply paint to match the existing color or the building color.
Lubricate the fire damper mechanism with calcium sulfonate grease and test to ensure the damper closes when the fusible link is removed.
5-4.12 Replace the intake grates/screens on the interior side
Removal Work
Remove the existing ventilation grates/screens from the interior opening for the intake hoods and at the opening within the building for the roof mounted ventilator.
New Work
Replace the ventilation grates/screens with new galvanized steel grates and screens. Include physical security bar assembly as well insect screens.
5-4.13 Building 48259
No Work
5-4.14 Building 48277
Same scope of work as building 48244
5-5 Detailed Specifications
During the design stage, submit UFGS specifications to specify the quality, characteristics, installation procedures and testing requirements for all applicable sections. UFGS documents can be found at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.
Some of the following specification sections may apply but are not limited to those listed:
UFGS 07 72 20 Gravity-Type Roof Ventilators UFGS 23 00 00 Air Supply, Distribution, Ventilation Air and Exhaust System UFGS 23 03 00 00 20 Basic Mechanical Materials and Methods
End of CHAPTER 5
01 11 00-A SOW CHAPTER 5-6
01 11 00-A SOW CHAPTER 6-1
CHAPTER 6
ELECTRICAL ENGINEERING
6-1 Design Goals and Objectives
Repair or replace the electrical systems for munitions storage buildings on Kadena Air Base, Okinawa.
Requirements discussed in this Chapter shall take precedence over any conflicting requirements in other Chapters and/or any other criteria and shall be brought to the attention of the Contracting Officer for resolution in writing prior to submission of a bid.
6-2 Applicable Codes and Standards
Electrical design criteria and guidance are contained in the following documents. Latest editions for the RFP shall apply, applicable codes and standards include but are not limited to the following. UFC documents can be found at http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc.
6-2.1 US Government Standards:
Unified Facilities Criteria (UFC):
UFC-3-501-01 Electrical Engineering
UFC-3-520-01 Interior Electrical Systems
UFC-3-530-01 Interior and Exterior Lighting Controls
UFC-3-575-01 Lightning and Static Electricity Protection System
UFC-4-021-02 Electronic Security Systems
UFC 4-420-01 Ammunition and Explosive Storage Magazines
National Fire Protection Association (NFPA):
NFPA 70 National Electrical Code
NFPA 70E Standard for Electrical Safety in the Workplace
NFPA 780 Standard for the Installation of Lightning Protection Systems
Underwriters Laboratories (UL):
UL 1598 Luminaries
UL 8750 Safety LED Equipment
Institute of Electrical and Electronics Engineers (IEEE):
IEEE C62.41.2 Recommended Practices on Surges in Low-Voltage AC (1000V and Less) Power Circuits
01 11 00-A SOW CHAPTER 6-2
6-3 Materials and Equipment
All materials and equipment shall be the standard catalogued products of manufacturers regularly engaged in the production of such equipment and material, and shall be the manufacturer’s latest design. All equipment and material shall conform to the requirements of American National Standards Institute (ANSI), American Society of Testing and Materials (ASTM), National Fire Protection Association (NFPA), Japanese Industrial Standards (JIS) or other national trade association as applicable. Where standards exist, materials and equipment shall bear the label and be listed by Underwriters Laboratories, Inc. (UL) or other recognized testing organization.
6-3.1 Flood Light System
Provide exterior LED wall sconce, full cut off, trapezoidal shape, die-cast aluminum housing construction, IP65 rated, dark bronze powder coat finish, mounted approximately 3400 mm AFF above the door. Include LED array, 4000K, 70+ CRI, electronic driver, 120V, 60Hz system. Exterior light shall be minimum 0.2 foot candles (UFC 4-420-01, 3-8.3). Exterior photocell shall be mounted on south-facing exterior wall. Photocell shall determine the on limit for exterior light. Exterior light shall have an occupancy sensor integral to the fixture increasing light output to 100% of the maximum lumens with motion detected. Otherwise exterior light shall be at 50% of the maximum lumens. Include rigid metal conduits, weatherproof metallic junction boxes and metallic liquid tight flexible raceways. Reuse circuit breaker at distribution panel. Include UL 1598 and UL 8750 requirements for lighting systems in wet locations. Provide surge protection integral to lighting fixture to meet IEEE C62.41.2 standards.
6-3.2 Bonding and Grounding Systems
Provide grounding and bonding systems for all roof-mounted metallic gravity ventilators, wall-mounted metallic ventilation intake hoods, wall-mounted metallic intake grates/screens, metallic doors, and metallic door frames to the primary grounding system ground ring. Bond door frame to door with 2 each woven wire braided copper straps (1 top and 1 bottom). Bond door frame to ground ring including maximum 1 ohm resistance (UFC 4-420-01, 3-8.6).
Provide bonding to all doors (new doors on Option 1 and existing doors on base bid). All bonding connections to existing ground ring and lightning protection system must be exothermically welded. No mechanical connections are permitted, except in test wells. Grounding and bonding systems include 20 mm diameter x 3000 mm long copper-clad steel ground rods, woven wire braided copper straps equal to 60 sq mm or 2/0 AWG (UFC 4-420-01, 3-8.5) bare copper conductors, and earthwork to the nearest ground ring connection.
Coordinate with Mechanical and Architectural.
6-3.3 Test Well Systems
Provide inspection housing and screw type cover. Cover to be marked “ground” and include 2 each pull slot spaces. Top of the cover to be flush with grade. Housing dimensions approximately 600 mm deep and 250 mm diameter.
Reuse cable to ground rod mechanical connections and 20 mm x 3000 mm copper clad steel ground rods. Clean out any mud or debris in the inspection housing area that resulted from the grass cutting machines damaging the inspection housings and screw type covers.
01 11 00-A SOW CHAPTER 6-3
6-3.4 Intrusion Detection System / Electronic Security System (IDS/ESS)
In support of Architectural wall and ceiling repair work, remove, protect and reinstall IDS/ESS. Include ceiling-mounted junction boxes for passive infrared motion sensors running in the center of the MUNS and also junction boxes for door contact balance magnetic switches, electrical metallic tubing, wiring, and connections to the existing IDS/ESS panel. Include existing IDS/ESS panel. Replace all existing wiring with new. Test IDS/ESS system together with Kadena Air Base 18 Security Forces Squadron and Zukeran Resident Office before removal and after reinstallation. Coordinate with Architectural.
6-4 Scope of Work by Building
6-4.1 Building 48244
6-4.1 Remove/replace bonding and grounding system. See bonding and grounding systems above for details.
Removal work
Remove bonding and grounding system from roof-mounted metallic gravity ventilators, wall-mounted metallic ventilation intake hoods, wall-mounted metallic intake grates/screens, metallic doors, and metallic door frames to the primary grounding system ground ring.
New work
Provide new bonding and grounding system from roof-mounted metallic gravity ventilators, wall-mounted metallic ventilation intake hoods, wall-mounted metallic intake grates/screens, metallic doors, and metallic door frames to the primary grounding system ground ring.
6-4.2 Building 48245
Same scope of work as Building 48244.
6-4.3 Building 48246
Same scope of work as Building 48244.
6-4.4 Building 48247
Same scope of work as Building 48244.
6-4.5 Building 48249
6-4.5 Remove/replace bonding and grounding system. See bonding and grounding systems above for details.
Removal work
Remove bonding and grounding system from roof-mounted metallic gravity ventilators, wall-mounted metallic ventilation intake hoods, wall-mounted metallic intake grates/screens, metallic doors, and metallic door frames to the primary grounding system ground ring.
01 11 00-A SOW CHAPTER 6-4
New work
Provide new bonding and grounding system from roof-mounted metallic gravity ventilators, wall-mounted metallic ventilation intake hoods, wall-mounted metallic intake grates/screens, metallic doors, and metallic door frames to the primary grounding system ground ring.
6-4.5 Remove/replace test well system. See test well systems above for details.
Removal work
Remove inspection housings and covers.
New work
Provide new inspection housings and covers.
6-4.6 Building 48252
Same scope of work as Building 48249.
6-4.7 Building 48253
Same scope of work as Building 48244.
6-4.8 Building 48254
Same scope of work as Building 48249.
6-4.9 Building 48255
6-4.9 Remove/replace bonding and grounding system. See bonding and grounding systems above for details.
Removal work
Remove bonding and grounding system from roof-mounted metallic gravity ventilators, wall-mounted metallic ventilation intake hoods, wall-mounted metallic intake grates/screens, metallic doors, and metallic door frames to the primary grounding system ground ring.
New work
Provide new bonding and grounding system from roof-mounted metallic gravity ventilators, wall-mounted metallic ventilation intake hoods, wall-mounted metallic intake grates/screens, metallic doors, and metallic door frames to the primary grounding system ground ring.
6-4.9 Remove/reinstall Intrusion Detection System / Electronic Security System (IDS/ESS). See IDS/ESS above for details.
Removal work
Remove ceiling mounted IDS/ESS system to the IDS/ESS panel.
New work
Reinstall ceiling mounted IDS/ESS system to the IDS/ESS panel.
01 11 00-A SOW CHAPTER 6-5
6-4.9 Remove/replace wall-mounted flood light system. See flood light system above for details.
Removal work
Remove wall-mounted flood light system from flood light to distribution panel.
New work
Provide new wall-mounted flood light system from flood light to distribution panel.
6-4.10 Building 48256
6-4.10 Remove/replace bonding and grounding system. See bonding and grounding systems above for details.
Removal work
Remove bonding and grounding system from roof-mounted metallic gravity ventilators, wall-mounted metallic ventilation intake hoods, wall-mounted metallic intake grates/screens, metallic doors, and metallic door frames to the primary grounding system ground ring.
New work
Provide new bonding and grounding system from roof-mounted metallic gravity ventilators, wall-mounted metallic ventilation intake hoods, wall-mounted metallic intake grates/screens, metallic doors, and metallic door frames to the primary grounding system ground ring.
6-4.10 Remove/reinstall Intrusion Detection System / Electronic Security System (IDS/ESS). See IDS/ESS above for details.
Removal work
Remove ceiling mounted IDS/ESS system to the IDS/ESS panel.
New work
Reinstall ceiling mounted IDS/ESS system to the IDS/ESS panel.
6-4.10 Remove/replace test well system. See test well systems above for details.
Removal work
Remove inspection housings and covers.
New work
Provide new inspection housings and covers.
6-4.10 Remove/replace wall-mounted flood light system. See flood light system above for details.
Removal work
Remove wall-mounted flood light system from flood light to distribution panel.
01 11 00-A SOW CHAPTER 6-6
New work
Provide new wall-mounted flood light system from flood light to distribution panel.
6-4.11 Building 48257
Same scope of work as Building 48255.
6-4.12 Building 48258
Same scope of work as Building 48255.
6-4.13 Building 48259
Same scope of work as Building 48256.
6-4.14 Building 48277
Same scope of work as Building 48255.
6-5 Detailed Specifications
During the design stage, submit UFGS specifications to specify the quality, characteristics, installation procedures and testing requirements for all applicable sections. UFGS documents can be found at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.
Some of the following specification sections may apply specification section include but not limited to:
UFGS 26 00 00.00 20 Basic Electrical Materials and Methods
UFGS 26 05 00.00 40 Common Work Results for Electrical
UFGS 26 05 19.10 10 Insulated Wire and Cable
UFGS 26 05 26.00 40 Grounding and Bonding for Electrical Systems
UFGS 26 09 23.00 40 Lighting Control Devices
UFGS 26 05 48.00 10 Seismic Protection for Electrical Equipment
UFGS 26 41 00 Lightning Protection System
UFGS 26 56 00 Exterior Lighting
UFGS 28 08 10 Electronic Security System Acceptance Testing
UFGS 28 10 05 Electronic Security System (ESS)
End of CHAPTER 6
01 11 00-A SOW CHAPTER 6-7
01 11 00-A SOW CHAPTER 7-1
CHAPTER 7
FIRE PROTECTION ENGINEERING – Not Used
End of CHAPTER 7
01 11 00-A SOW CHAPTER 7-2
01 11 00-A SOW CHAPTER 8-1
CHAPTER 8
ENVIRONMENTAL REQUIREMENTS
8-1 Environmental Issues
All work shall be conducted in accordance with the Japan Environmental Governing Standards (JEGS 2018), version 1-1, applicable US Federal, Government of Japan, and local regulations, the requirements outlined below, and the referenced specifications. Below is a list of the major environmental aspects associated with the project.
a. Proper abatement, handling and disposal of asbestos containing materials which may be disturbed as part of the renovation work.
b. Proper handling and disposal of lead containing paint which may be disturbed as part of the renovation work.
8-2 Asbestos
Asbestos material survey results for this project are shown in specification section 01 57 19.01-A.
Per the JEGS, ACM shall be defined as any materials containing more than one tenth of one percent (0.1%) asbestos.
The contractor shall abate any ACM that would otherwise be disturbed during the normal work practices required to execute the work included in the scope of this project. ACM which would not be disturbed during normal work practices shall be left in place. The contractor shall dispose of all removed ACM at an approved off-base disposal location. Work shall generally be done in accordance with the standard United Facilities Guide Specification (UFGS) Section 02 82 13.00 10 – Asbestos Abatement and U.S. Army Corps of Engineers (USACE) EP 1110-1-11 – Engineering and Design Asbestos Abatement Guideline Detail Sheets as applicable. These standards shall be revised to incorporate the JEGS, and applicable Government of Japan and local regulations.
The contractor shall designate an Industrial Hygienist (IH)/Private Qualified Person (PQP) to oversee the asbestos work. The IH/PQP shall be a registered Architect, Professional Engineer (licensed) or US Certified Industrial Hygienist who has successfully completed training in, and is accredited under a legitimate Model Accreditation Plan, as described in 40 CFR 763, as a certified Building Inspector, Abatement Worker, Contractor/Supervisor, Management Planner, and Project Designer and has successfully completed the National Institute of Occupational Safety and Health (NIOSH) 582 course "Sampling and Evaluating Airborne Asbestos Dust" or equivalent. The IH/PQP shall also have working knowledge of applicable U.S. Federal and Japanese occupational safety and health regulations for asbestos in construction and shall be considered a competent person as defined in 29 CFR 1926.62. The IH/PQP shall be a third party contractor and have no employee/employer relationship or financial relationship which could constitute a conflict of interest.
The contractor’s IH/PQP shall prepare and submit an Asbestos Hazard Abatement Plan (AHAP) for Government approval. The AHAP shall describe the abatement
01 11 00-A SOW CHAPTER 8-2
process for each type of ACM to be abated, including containment and control procedures, air monitoring methods, and storage, transportation, and disposal plans. All asbestos work shall be conducted in accordance with the approved
AHAP.
8-3 Lead
Lead-Based paint test results for this project are shown in specification section 01 57 19.01-A. For purposes of worker protection and protection of adjacent areas, the contractor shall assume that all painted surfaces contain lead. The contractor shall use appropriate engineering controls, best management practices, and personal protective equipment to manage any lead hazards to the contractor’s workers, the general public, and the environment when disturbing any painted surfaces. All work shall generally be conducted in accordance with UFGS Section 02 83 13.00 20 – Lead in Construction as applicable. This standard shall be revised to incorporate the JEGS, and applicable Government of Japan and local regulations.
8-4 Detailed Specifications
During the design stage, submit UFGS specifications to specify the quality, characteristics, installation procedures and testing requirements for all applicable sections. Some of the following specification sections may apply specification section include but not limited to:
UFGS 02 82 13.00 10 Asbestos Abatement
UFGS 02 82 13.00 20 Lead in Construction
End of CHAPTER 8
01 11 00-A SOW CHAPTER 8-3
ATTACHMENT 01 11 00-B
CONCEPT DRAWINGS
(Provided Separately)
ATTACHMENT 01 11 00-C
Hazardous Materials Inspection Report: Refer to section 01 57 19.01 and attachment 01 57 19.01-A
Section Section Title/Material Description US Standard Acceptable Alternative
Japanese Standard
Year JIS published
(revised)
Japanese Standard Title in English
03 20 00.00 10 Concrete…
This is the start of the file's text. The full file is on GovTribe.