Draft PWS Green Zone ECP 2021-09-28.pdf

PDF 128 KB Posted

Attached to
Green Zone ECP, Iraq Federal contract opportunity
Solicitation number
PANTAD-21-P-0000-000635
Issued by
Department of the Army Corps of Engineers Engineering District Middle East

About this file

This performance work statement outlines requirements for a security systems installation project along the perimeter of the International Zone in Baghdad, Iraq. The project scope includes procuring and installing hydraulic road blockers, steel gates, road spikes, and generator sets at entry control points. Submittals are due within seven to thirty days of award, including blocker and gate specifications, schedules, and safety plans. Training for Iraqi security forces personnel must also be provided on blocker, gate and generator set operations and maintenance. The performance period is nine months. Interested U.S. contractors meeting Foreign Military Financing guidelines are requested to provide capability statements by October 15, 2021 for consideration under the anticipated fixed price contract to be awarded through full and open competition on sam.gov.

View the file

Other files for this federal contract opportunity

Other files attached to Green Zone ECP, Iraq, newest first.
File Type Posted
Attachments B and C.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Draft

PERFORMANCE WORK STATEMENT

PROCURE AND INSTALL VARIOUS SECURITY SYSTEMS

Baghdad, Iraq

28 September 2021

1. PROJECT DESCRIPTION

1.1 This project consists of all labor, materials, and supplies to acquire, deliver, and install security systems along the perimeter of the International Zone (IZ), also known as the Green Zone in Baghdad, Iraq. See Attachment A for project site location. The security systems include hydraulic road-blockers with a control system, steel gates and road spikes at existing entry control points. Incidental to the equipment to be installed are generator sets to be acquired, deliver, and install at each security system location. Quantities, locations, and technical requirements of the security systems are as described in the following technical requirements and Attachments A and B.

1.2 The majority of materials to be procured for this contract action are anticipated to be provided or manufactured from U.S. However, as this action is funded by Foreign Military Financing, no parts or material shall be procured from prohibited sources, including but not limited to China, North Korea, and Republic of Cuba, as identified by Foreign Assistance Act (Sections a, e, f, and q). This requirement shall comply with the U.S. regulations as stated in the Defense Federal Acquisition Regulation Supplement (DFARS) clauses 252.225-7000, 252.225- 7001, and 252.225-7002.

1.3 Variations to the equipment and materials specified below are possible providing that the contractor demonstrates, via technical data, catalogue cuts, etc. that it is equivalent to the specified system and the requirements listed below, and the Contracting Officer approves. No variation will be accepted without these actions.

1.4 In accordance with Section 42(c) of the Arms Export Control Act, as amended (22 USC §2791(c)), the Foreign Military Financing funds made available for this procurement may not be used to award to other than a United States firm, unless an Offshore Procurement (OSP) determination is made by the Director, Defense Security Cooperation Agency. No OSP determination has been obtained for this procurement. Offers from other than United States firms are ineligible for award. Accordingly, per DoD 5105.38-M, Chapter 9, Table C9.T8, more than 50% of the dollar value of the FMF contract [or CLIN, when there are multiple FMF cases on a single contract], after subtracting from the total costs the cost of items that the FAR or DFARS exclude from Buy American Act or Balance of Payments Program consideration, must be of U.S.

origin. The contractor may not exceed this foreign content percentage during contract performance, unless the Government obtains an OSP determination. If it is determined that the Contractor has used unauthorized content, payments to the Contractor may be reduced by the value of the unauthorized content, or at the Government’s option, the Contractor may be required to remove the unauthorized content at its expense and replace it with authorized content. The

Government will require the contractor to periodically provide it with information concerning the foreign content utilized in performing the contract, to allow the Government to ensure compliance with these OSP foreign content rules. The Government reserves the right, however, to seek an OSP determination at any stage in the procurement, if doing so is in the Government’s best interests.

1.5 This contract will include basic and optional contract line items. See bid schedule for the breakdown of basic and optional contract line items. The Government is not obligated to award all or any portions of the optional contract items. The Government will notify the Contractor within 90 days after contract award which options will be exercised.

2. TECHNICAL REQUIREMENTS:

2,1 Hydraulic Wedge Type Road Blockers: The contractor shall procure and install the vehicular barriers as described in the following paragraphs. The quantities, sizes, and locations are as specified in Attachment B.

2.1.2 The road blockers to be procured by the contractor shall be manufactured by a U.S.

company specializing in the supply of vehicular barrier systems.

2.1.3 Crash Rating shall be M50 as certified by the US Department of State (DOS).

2.1.4 Road blockers shall be at least 80 centimeters (32 inches) in height and shall be completely flush with the roadway surface when installed. Road surface top plate shall be suitable for vehicle traffic constructed of steel plate with a painted anti-skid surface finish. No side pillars or above grade assemblies are required. Enclosure shall be weatherproof.

2.1.5 The road blocker, when in the lowered position, shall be capable of supporting a 32,000-pound (14,515 kg) Axle load or a 16,000-pound (7255 kilogram) wheel load.

2..1.6 Hydraulic Wedge Type Road Blocker operation shall have the following features:

a. Shall operate between 0 degrees C (32 F) to + 60 degrees C (140 F).

b. Be fully opened 3-8 seconds at normal ambient temperatures from push button control

c. Barriers shall be also be opened and closed via the release of a manual valve or manual hand pump

d. Shall be lowered in not more than 3 seconds from push button control.

e. Blockers shall be able to perform at least 135 complete up/down cycles per hour.

f. Blockers shall utilize one of two optional methods of operation during electrical power loss: (1) Stored hydraulic pressure utilizing a hydro pneumatic accumulator, or (2) Integrated manual hand pump to permit raising and lowering of the barrier.

g. Programmable Logic Controller (PLC) System shall have electrical controls and monitoring programmable, utilizing either a ruggedized, industrial type Programmable Logic Controller (PLC) shall be standard commercial, off the shelf PLC, and shall not use a custom sole source printed circuit type control board.

h. Electrical Power: 460 V, 3 Phase, 50 Hz. Shall include high/low voltage circuit protection

i. Shall include low oil level/high oil temperature sensor with hydraulic oil filter

j. Shall include tamper switches.

2.1.7 Hydraulic Wedge Type Road Blocker installation requirements. Contractor is responsible for installation as well as procurement.

a. Shall be designed for shallow in-ground installation requiring an excavation no greater than 61 centimeters (24 inches)

b. Electrical power wiring shall be installed in Schedule 80 PVC conduits and placed at least 61 centimeters (24 inches) below grade.

c. Wiring and conduit size to be selected by the road blocker manufacturer to match their motor size and electrical requirements

d. Foundation Pad shall be not less than 18 centimeters (7 inches) in depth.

e. Power generator at each gate locations requiring installation of blockers, spike strips and steel gates.

f. Road Blockers shall be installed no further than 30.5 M (30 ft) from the hydraulic control box.

2.2 Road Spikes: The Contractor shall procure, deliver, and install road spike system in the quantities, sizes, and locations are as specified in Attachment B. The road spikes system shall be motorized and designed to puncture tires of intruding vehicles through the access control gates. The spikes shall be omnidirectional type and will puncture tires in either direction of traffic.

2.2.1 The road spikes to be procured by the contractor shall be manufactured by company specializing in the supply of vehicular barrier systems such as road spikes. During normal traffic flow at the control gate, the teeth shall be in the down position. The teeth shall be remotely controlled with a switch to deter intruding vehicles in either direction.

2.2.2 Road spikes shall have the following salient features:

a. Designed and manufactured in segments of 36 in (90 cm)

b. The road spikes shall be integrated and synchronized with a Stop/Go Signal lights mounted on a post 48 in high (120 cm) from the ground

c. The road spikes shall be installed flushed with the existing road pavement

d. Top plate and spikes shall be a minimum thickness of ½ in (1.30 cm)

e. Tooth height must be approximately 2.3 in (5.80 cm)

f. In case of power source failure, system must operate manually

g. The system shall be capable of supporting a 32,000-pound (14,515 kg) Axle load or a 16,000-pound (7255 kilogram) wheel load.

2.2.3 Road spikes shall be installed in accordance with the manufacturer’s recommendation. Road strips shall be installed no further than 15 M (50 ft) from the control switch.

2.3 Steel Gates: Contractor shall procure and install steel gates in the quantities, sizes, types, and locations as described in the following paragraphs and in Attachment C. The function of the gates is to form a barrier against civil unrest and terrorist attacks. Gates shall be complete with supporting structures to keep them secured and operational as recommended by the steel gate manufacturer. Gates shall be equipped with electric motor for operation. Gate no. 6 shall have a lockable capability from the inside.

2.3.1 Gates to be manufactured from aluminum or steel and shall be coated to resist corrosion. An aluminum or steel plate, 6 mm in thickness, shall be welded to the face of the gate. Gates include structural steel columns, cables and bearings and gate frame. An external lock is not required for these gates. Final surfaces shall be painted black to match existing painted steel gates.

2.3.2 Gate manufacturer shall certify that the gates are manufactured by a US company in compliance with ASTM F 2200, Standard Specifications for Automated Vehicular Gate Construction. In addition, the manufacturer shall provide independent certification as to the use of documented Welding Procedure Specifications and Procedure Qualification Record to insure conformance to the AWS D1.2 welding code.

2.3.2 Gates shall be vertical lift type, except for the gate number 6, which requires a slide type gate. All gates shall have crash rating of M50. See Attachment C for sizes, quantities, and locations.

2.3.4 Slide gate for Gate number 6 shall be supported from the track of extruded aluminum alloy by two self-aligning, 4-wheeled sealed lubricant, ball bearing truck assemblies.

Gates are to be supplied with gap protectors and guide roller covers.

2.3.5 All steel gates shall be operated from radio, console controls and close at 2 feet per second.

2.3.6 Contractor shall install the equipment in accordance with the gate manufacturer’s printed instructions.

2.3.7 The COR shall be notified at least 5 working days prior to test and validate the gate system to determine if the system is working properly. In addition to the basic operation of the system, the Contractor shall address the of the safety features of the gate operator system.

2.3.7 All gates shall also have the following salient features:

a. Designed so that gate movement from the closed position is impossible except by electric or mechanical means.

b. Equipped with soft-start and soft-stop function to prevent shock load to the gate panel and operator.

c. Operate on 208/230V AC single phase or 208/230 Volt AC or 460 V AC three phase power

d. Electric motor shall be a minimum of 1 HP

e. Barbed wire installed on top of gates to inhibit intrusion by climbing

2.4 Power Generator Sets:

2.4.1 Since the gate locations do not have power source nearby, the Contractor shall acquire, deliver, install, test, and commission Commercially Off-the-Shelf (COTS) Hybrid Power System (HBD) to provide power for the equipment specified in paragraphs above. Units shall supply continuous power back-up power in the event of a loss of generator availability.

The units shall be designed to meet MIL-STD 810G environmental and mechanical specification for outdoor use with a maximum ambient temperature of 55 degrees centigrade. Output capacity of the generator sets shall be of sufficient power at 50 Hertz to operate the electrically powered equipment under this contract.

2.4.2 Generator Control Panels shall also have manual start capabilities as well as automatic features. Provide manual override of the generator controls.

2.4.3 Units shall be supplied with solar panel charging capability to reduce generator set runtime.

2.4.5 Generator sets shall be integrated on a four-wheel trailer with four landing legs.

3. BLOCKERS, SPIKES, AND GATES EXACT LOCATIONS:

The contractor shall perform a site survey in coordination with the Contracting Officer’s Representative (COR) and the Iraqi Force Protection Unit personnel to identify the exact locations of each type of barriers. Result of the survey shall be documented by the contactor in a narrative description of the locations of the barriers with accompanying schematic diagrams.

The documentation shall be provided to the COR not later than 14 calendar days after the survey for approval.

4. PERIOD OF PERFORMANCE AND SUBMITTALS:

4.1 The period of performance for this contract is nine months from contract award. Not later than fourteen calendar days after contract award, the Contractor shall submit an initial schedule of activities associated with performance of this contract. The initial schedule shall include activities such as manufacturing, packaging, shipment, delivery, and general installation timeline. After review and approval of the initial schedule, a detailed schedule of the installation, testing, and training shall be submitted by the Contractor. The detailed schedule shall include the sequence and/or phasing of the barriers to be installed at each gate location.

This schedule shall be coordinated with the COR and Iraqi Security Forces.

4.2 Not later fourteen (14) calendar days after contract award, the Contractor shall begin a site survey with the Iraq Security Force in coordination with the COR. After the site survey, the Contractor shall provide a layout plan indicating the actual sizes and configuration of the road blockers and steel gates.

4.3 The Contractor shall submit the following to the government for approval:

Item Description Submittal Due/Government Review Period

(calendar days) Salient Features of the road blockers with M-rating certification, blocker manufacturer’s self-certification requirements as specified in paragraph 2.1.2. Salient features of the vertical and swing gates with M-rating certification

Seven (7) days after contract award.

Government will review submittal and provided review comments within 14 days of submittal.

Initial general schedule Fourteen (14) days after contract award.

Government will review submittal and return with comments within 14 days of submittal

Accident Prevention Plan Fourteen (14) days after contract award.

Government will review and provide comments within 14 days of submittal

Layout plan of the road blockers, steel spikes, and steel gates, and generators sizes and configuration, Twenty-one (21) days after site survey.

Government will review submittal and return with comments within 14 days of submittal.

Detailed installation, testing, and training schedule

Thirty days (30) days after contract award.

Government will review and return comments within 14 days of submittal

4.4 After approval of the layout plan, no changes shall be made by the Contractor without the written approval from the COR in coordination with the Iraqi Security Forces.

5. WARRANTY:

The Contractor shall warranty all installed items for one (1) year from acceptance and shall provide all ancillary warranties from the in-kind replacement manufacturers. Warranty shall be in accordance with FAR Clause 52.212-4 Contract Terms and Conditions Commercial Items. A point of contact (POC) for warranty implementation shall be identified by the Contractor. The Contractor shall assume responsibility for defects and deficiencies in the software and equipment, not supplied by the Government, for a minimum of twelve (12) months of continuous warranty service. The warranty service shall NOT incur any additional cost to the Government.

6. CONTRACTOR PROVIDED SERVICES:

a. The Contractor shall provide all transportation, meals, and lodging for their employees who travel to Baghdad, Iraq in support of this action. All travel associated with this requirement shall follow the Joint Travel Regulation (JTR).

b. The Contractor is responsible for obtaining all clearances, visas, immunizations, travel arrangements, etc., necessary for their employees to enter the project site and perform work in Baghdad, Iraq.

c. The Contractor shall provide all required tools and ancillary items needed to complete the required installation and follow-on warranty work as needed. The Contractor shall not expect to rely on the Host Nation for this support.

d. The Contractor shall be responsible for shipment, delivery, and storage of all equipment, supplies, tools, and materials associated with this contract.

7. ACCIDENT PREVENTION:

7.1 The Contractor shall comply with all applicable Iraqi laws and regulations and all applicable provisions of the current U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. Manual can be downloaded from the following web site:

http://publications.usace.army.mil/publications/eng-manuals/EM_385-1-1_languages/EM_385- 1-1_English_2008/toc.html

7.2 An Accident Prevention Plan (APP) shall be prepared to preclude potential accident/incidents on the job. The Contractor shall prepare and submit to the Contracting Officer the APP fifteen days after award and shall identify potential hazards found on the job. This shall include an Activity Hazard Analyses (AHA) applicable to the work covered by the plan.

7.3 An AHA is a tool designed to identify and mitigate hazards associated with the work.

This may include situations not experienced in previous project operations or incidents where a new work crew or subcontractor is required to perform specialty work. EM 385-1-1, “Safety and Health Requirements Manual”, provides the form’s suggested format.

7.4 It is the Contractors’ responsibility to ensure that its personnel comply with the requirements of EM 385-1-1 and the APP. Failure to meet this responsibility will result in various actions as directed by the Contracting Officer including, but not limited to, removal of offending Contractor personnel, work stoppage and contract termination.

7.5 Copies of the APP will be maintained in the Contractor’s offices. This plan will be reviewed with the COR on a regular basis to ensure that accident prevention remains a top priority.

8. KEY PERSONNEL:

The Contractor shall provide an in-country point of contact (POC) for the Contracting Officer’s Representative to coordinate actions. The POC shall be an employee of the Contractor or a subsidiary of the firm. The POC shall have the ability to speak on behalf and for the Contractor but does not need to have financial authority.

9. IDENTIFICATION OF EMPLOYEES

The Contractor shall be responsible for furnishing to each employee engaged in the work to display such identification as may be approved and directed by the base security. All prescribed identification shall immediately be delivered to the Contracting Officer or a duly authorized representative for cancellation upon the release of any employee.

10. OPERATION AND MAINTENANCE MANUALS

10.1 Description of Operation and Maintenance (O&M) Manuals. The Contractor shall provide six (6) hardcopies of the standard off-the-shelf O&M manual(s) for the system provided.

All hardcopies of the manual(s) shall be in original format. No other form of printed and prepared data shall be acceptable unless approved in writing by the Contracting Officer.

Included with this submission shall be one (1) set of the Electronic Format O&M Manuals to be emailed to the COR. Hard copies shall be provided to the US Army Corps of Engineers Resident Office below:

Mark Wittrock, Resident Engineer Kuwait Area Office

10.2 Payment for O&M Manuals: No separate payment will be made for the preparation and submittal of O&M manuals. Payment shall be included in the performance of all other scope of work as described in this contract.

11. TRAINING FOR IRAQI SECURITY FORCES PERSONNEL

11.1 The Contractor shall be responsible to provide instruction and training to Iraqi Force Protection Unit Personnel who will become the operating and maintenance personnel as specified below. The duration periods shall be per manufacturers’ recommendations. Training schedule shall be identified in the project schedule and the Contracting Officer or his Authorized Representative shall be notified at a minimum of 10 working days prior to start of the training.

The Contractor shall coordinate the exact time and location of training with the Iraqi Force Protection Unit and the COR. The Contractor may choose to provide additional instructions to ensure the training is sufficient for him to certify that the trainees have met the minimum training requirements. Contractor shall include a translator to conduct instructions delivered in the English language.

DESCRIPTION

Road Blockers, Steel Gates, and Road Spikes:

a) Seminar for Senior Officers - For Senior Management Overview of operational concepts, accident prevention and system maintenance requirements, overview of contract training program for O&M personnel.

b) Equipment Operational Concepts (for Operators)

c) Equipment Maintenance and Repair (Mechanics/Operators)

Generator Sets:

a) Seminar for Senior Officers - For Senior Management Overview of operational concepts, accident prevention and system maintenance requirements, overview of contract training program for O&M personnel.

b) Equipment Operational Concepts (for Operators)

c) Equipment Maintenance and Repair (Technicians/Operators)

11.2 Operation and Maintenance Training

11.2.1 The Contractor shall provide competent instructors for training of the Iraqi Force Protection Unit and other Government of Iraq members. Instructors shall be supplied by the equipment manufacture and shall have a minimum of two years of experience in the operations and maintenance of barrier and generator sets. Personnel to be trained will possess general technical experience in maintenance of equipment and may have limited English language skills.

11.2.2 The contractor shall provide a training program that when complete shall impart the necessary knowledge and skills to insure that:

Iraqi Force Protection supervisory staff shall have acquired sufficient knowledge of the installed security barrier systems and operations to insure they are being safely operated. Iraqi Force Protection Unit operators shall have acquired a full knowledge of the newly installed barriers’ safe operation principles, acquired the understanding and skills of the operational procedures and maintenance procedures to safely employ the security barrier operations.

12. CONTRACTOR LIAISON WITH FOREIGN GOVERNMENT:

All communication by the Contractor with Host Nation’s officials, representatives and/or offices of the Iraqi Force Protection Unit, or any other Iraqi Ministries in all matters pertaining to the work to be accomplished under this contract shall be through and in full liaison with the Contracting Officer and/or the specified Contracting Officer's Representative. The following are the Point of Contact with the US Government:

Contracting Officer Joe Libbey Phone: 540-665-1382

Email: Joe.L.Libbey@uace.army.mil

Contracting Specialist William Mahon Phone: 540 662-4350 Email: William.J.Mahon@usace.army.mil

Project Manager Manuel C. Napenas Phone: 540-665-3786 Email: Manuel.C.Napenas@usace.army.mil

Point of Contact in Iraq Name: Mark Wittrock Phone: 540 665-1231 Email: Mark.A.Wittrock@usace.army.mil

13. DUTIES, TAXES, AND LICENSE FEES:

13.1. All materials, equipment and supplies that are for use and/or incorporation into the project are exempt from taxes, duties, and license fees under the terms of the Agreement between the Government of the United States and the host Government (Iraq). The Contractor warrants his price for this contract is exclusive of any such charges.

13.2. Custom duties, taxes, and fees associated with this contract for shipment of materials, equipment, tools, and supplies is the responsibility of the Government of Iraq. The Contractor shall provide a Notice of Availability (NOA) to the COR prior to arrival of the materials, equipment, tools, and supplies related to this contract. The Government will then notify the Government of Iraq (GoI) representatives of the NOA, and GoI will coordinate with the Contractor to continue the shipment and delivery of the associated items.

13.3. Contractor owned or controlled material, equipment and supplies sold or disposed of by the Contractor may be subject to the imposition of local duties and within the Host country taxes. No reimbursement will be made under this clause for such transactions.

14. SAFEGUARDING OF INFORMATION:

The personnel employed on this contract may, in the performance of their assigned duties, have access to data and information pertaining to location of goods, supplies, parts, equipment, vehicles, and explosives. Knowledge of this nature is considered restricted security information.

This information shall be protected and safeguarded against disclosure to any unauthorized person or party and shall be furnished or used on an official "need to know" basis only.

Safeguarding of information is extended to dependents and guests of employees, who may, in any manner, obtain knowledge of the Host Government military capacity. Taking of photographs on-site is prohibited.

File details come from the government source that posted it. Updated .