Draft PWS Door and Dock Repair .pdf
PDF 334 KB Posted
- Attached to
- Door & Dock Repair - Tobyhanna Army Depot
- Solicitation number
- W51AA126QA055
- Issued by
-
Department of the Army
About this file
This is a Performance Work Statement (PWS) for door and dock repair services at Tobyhanna Army Depot (TYAD) in Pennsylvania, effective February 2026.
The contractor shall provide non-personal services to assess and repair approximately 500 overhead doors, 150 roll-up doors, 80 sliding doors, 40 high-speed doors, and one bi-fold hangar door, along with approximately 95 pieces of dock equipment including dock locks, levelers, shelters, and bumpers. Current manufacturers include Raynor, Cornell, Cloplay, C.H.I., and Wayne Dalton. The contractor must respond to assessment requests from the Contracting Officer's Representative (COR) within five business days and provide detailed repair proposals within one week of assessment, including labor, parts, travel, and all associated costs. All repairs require prior COR approval before commencement and must be scheduled at least 48 hours in advance. The contractor shall furnish all personnel, equipment, supplies, materials, tools, and transportation necessary for performance. Work is performed at TYAD, 11 Hap Arnold Boulevard, Coolbaugh Township, PA 18466, during facility operating hours of 0700-1530, Monday through Friday.
Key deliverables include a Quality Control Plan (due within 30 days of award), key personnel information (due within 5 days), repair proposals (due within one week of assessment), and quarterly status reports detailing parts consumed, associated costs, and labor hours. The contractor must comply with security requirements, complete required training (Anti-Terrorism Level I, OPSEC Level I, and iWATCH), maintain contractor identification signage, and follow all applicable safety standards. Government-provided training includes AT Level I, iWATCH Army, and OPSEC training. The contract is non-personal services with performance evaluated against a Quality Assurance Surveillance Plan focusing on assessment timeliness (5 business days) and repair work approval compliance (100% inspection, zero deviations).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Draft CDRL A004 Status Report.pdf | ||
| Draft CDRL A001 QCP.pdf | ||
| Draft CDRL A003 Repair Proposal.pdf | ||
| Draft W51AA1-26-Q-A055 .pdf | ||
| Draft CDRL A002 Key Personnel.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AUG 22
Performance Work Statement (PWS) (Includes associated Performance Requirements Summary) (PRS)
TYAD Door and Dock Repair Service
FEB 2026
Part 1 General Information
1. General: This is a non-personal service(s) contract under which the personnel rendering the service(s) are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees.
1.1 Description of Services/Introduction: This is a non-personal service(s) contract to assess and repair existing overhead doors, dock equipment and their closely associated components at Tobyhanna Army Depot (TYAD). The Government shall not exercise any supervision or control over contract service providers who are subcontractors performing services herein. Such contract service providers shall be accountable solely to the contractor who, in turn is responsible to the Government. The Contractor shall perform to the standards specified in this PWS. The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary as defined in this
PWS.
1.2 Background: Tobyhanna Army Depot (TYAD) has a requirement to maintain operational overhead doors and dock equipment to stay on mission. Safety, compliance and efficiency are cornerstone requirements. TYAD has approximately five hundred (500) overhead doors, one hundred fifty (150) roll up doors, eighty (80) sliding doors, forty (40) high speed doors and one
(1) bi-fold hangar door. All of the aforementioned must be operational and safe with minimum downtime.
1.3 Scope: The Contractor shall provide non-personal service(s) to assess and repair the overhead doors, dock equipment and their closely associated components at Tobyhanna Army Depot (TYAD) on an as needed basis. Services shall include assessments for proposals to repair and repair work to keep the overhead doors and dock equipment in a safe and proper working order.
1.4 Objectives: The object of this service contract is to assess and repair overhead doors, dock equipment and their closely associated components on an as needed basis. These tasks are in accordance with this PWS.
1.5 General Information:
1.5.1 Quality Control Plan (QCP): The Contractor shall develop and maintain a QCP to ensure services are performed in accordance with (IAW) this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor's QCP is the means by which it assures that the work provided complies with the requirements of the contract.
The Contractor’s Proposed QCP shall be submitted to the Contracting Officer (KO) through the Contracting Officer’s Representative (COR) for review within thirty (30) days after date of contract award. Deliverable D.01
The Government will review and either notify the Contractor in writing of acceptance of the plan or return their comments to the Contractor within ten (10) days. If the Government has provided comments, the Contractor shall then have seven (7) days to submit a Final QCP.
After receipt of the Final QCP, the Contractor may receive the Contracting Officer’s acceptance in writing. Any proposed changes to the accepted QCP are required to be resubmitted for acceptance by the Contracting Officer no later than seven (7) days prior to the anticipated change and before implementation by the Contractor. The timeline noted above will apply for review and acceptance for proposed changes. At a minimum, the QCP must include and answer the following to be acceptable:
(a) A chart showing the organizational structure and lines of authority, the names, qualifications, duties, responsibilities, and classification of each member of the Contractor's Quality Control Team;
(b) How the Contractor will monitor work to ensure performance complies with all deliverables (etc. timelines, deadlines, and goals);
(c) How the Contractor will monitor work to ensure performance complies with all specifications and requirements of the contract, including the contract’s clauses;
(d) How the Contractor will monitor and ensure staff qualifications remain current and valid including Department of Defense (DoD) Contractor Personnel Office (DOCPER) processes/approvals throughout contract performance;
(e) How the Contractor will ensure all keys issued will remain controlled items
(Paragraph 1.7 Key Control);
(f) How the Contractor will inventory and track maintenance of all Government Provided Equipment / Materials;
(g) How the Contractor will identify, investigate, and correct any non-conforming performance and prevent similar deficiencies in the future; and
(h) How the Contractor will file and save all Quality Control related documents for the life of the contract plus 5 years.
1.5.1.1 An Analysis of Quality Control and Timeliness of Submittals (i.e. deliverables) shall be provided to the COR within thirty (30) days upon completion of each option period or Task Order.
1.5.1.2 Reserved
1.5.2 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).
1.5.3 Recognized Holidays: The following provides information on recognized holidays for the purpose of the PWS. If submittal of any documentation (e.g. deliverables, submittals, etc.)
deadlines fall on a holiday, the closest work day prior to the holiday will apply as the deadline for submittal.
1.5.3.1 U.S. Holidays: Work shall not be performed on U.S. federally recognized holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer.
When a U.S. holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively.
New Year’s Day January 1st M. L. King Memorial Day 3rd Monday in Jan Presidents Day 3rd Monday in February Memorial Day last Monday in May Juneteenth June 19th Independence Day July 4th
Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veteran’s Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th
1.5.3.2 Reserved
1.5.4 Operating Hours: The Government facility office hours, facility operating hours, and the Contractor support hour requirements often coincide, however, they may differ. Please refer to the following.
1.5.4.1 Government Facility Office Hours: The Government facility office hours are 0700 – 1530, Monday through Friday, except U.S. Holidays identified in paragraph 1.5.3.1 above or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.
1.5.4.2 Government Facility Operating Hours: The Government facility operating hours occur twenty-four (24) hours a day / seven (7) days a week. The Government facility is open for operations during the recognized U.S. Holidays identified in paragraph 1.5.3.1 above. The
Government facility may close due to local or national emergencies, administrative closings, or similar Government directed facility closings and will be communicated by the COR. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
The Government facility operating hours occur between the hours of 0700 – 1530, Monday through Friday.
1.5.4.3 Contractor Support Hours: The Contractor shall provide support between the hours of 0700 – 1530, Monday through Friday. The Contractor shall maintain an adequate workforce at all times, for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce is essential.
1.5.5 Training Holidays: Reserved
1.5.6 Place of Performance: The work to be performed under this contract will be performed at Tobyhanna Army Depot (TYAD), 11 Hap Arnold Blvd., Coolbaugh Township, PA 18466.
1.6 Security Requirements: Contractor personnel performing work under this contract must have a completed background check prior to start of any work to be performed and must maintain the level of security required for the life of the contract.
See the separately attached pdf titled “Security Requirements Insert for All SOWs and PWSs Updated 20251001” for the current TYAD Security Requirements. See Part 6, “Applicable Publications”, Section 6.1.13.
1.7 Key Control: Reserved
1.8 Post Award Conference/Periodic Progress Meetings: The Contractor shall attend any post award conference convened by the contracting activity or contract administration office in accordance with FAR Subpart 42.5. The Contracting Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.8.1 The Contractor shall attend, participate in, and furnish input to scheduled and unscheduled meetings, conferences, and briefings that relate to the functions and services herein as required by the Government to provide effective communication and impart necessary information. The Contract Manager or designated representative shall attend meetings as requested by the Government. Meeting attendees shall at times include Contractor managerial, supervisory, and other personnel knowledgeable of the subject matter.
Meetings may start or end outside of regular duty hours.
1.9 Contracting Officer’s Representative (COR): Refer to Part 2 of this PWS for the definition of a COR. As determined by the Contracting Officer, a COR will be appointed and identified by letter of designation, a copy of which will be provided to the Contractor by the Contracting Officer. The designation letter states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is not authorized to obligate the Government. If the work is not written in the contract, the COR is not authorized to request new work. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract, perform inspections necessary in connection with contract performance, maintain written and oral communications with the Contractor concerning technical aspects of the contract, issue written interpretations of technical requirements, including Government drawings, designs, specifications, monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies, coordinate availability of Government property, and coordinate site entry of Contractor personnel.
1.10 Key Personnel: The following personnel are considered key personnel by the Government:
1. David Hudak, Contracting Officer Representative (COR).
The Contractor shall provide a Program/Contract Manager who shall be responsible for the performance of the work. The name of this person and an Alternate Program/Contract Manager, who shall act for the Contractor when the Program/Contract Manager is absent, along with a Curriculum Vitae (CV) for each of these individuals, shall be provided in writing to the Contracting Officer no later than five (5) days after contract award. Deliverable D.02
1.11 Identification of Contractor Employees: All Contractor
personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties must identify themselves, to include proper marking of signature blocks in correspondence, to avoid creating an impression in the minds of members of the public that they are Government officials. The
Contractor shall ensure that all documents or reports, produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.
1.12.1 If applicable, Contractor workspace (staging site, on-site office, desk or work area, etc.) shall contain a sign signifying the space is occupied by Contractor employee(s) to ensure that Government employees and the public know that they are not Government employees.
The proposed sign shall be submitted to the Contracting Officer via the COR for review and acceptance as requested after contract award. Workspace sign location shall be coordinated with the COR. Contractor employees shall identify themselves by name and company affiliation when answering the telephone, presenting briefings, conducting or attending meetings, and seminars. All Contractor correspondence (written, facsimile, and email display) shall include their company name. Requirements for Contractor vehicles is addressed under Part 4 paragraph
1.12.2 Contractor Identification Badges: Reserved
1.13 Contractor Travel: Reserved
1.14 Other Direct Costs (ODCs): Reserved
1.15 Data Rights: The Government has unlimited rights to all documents and materials produced under this contract. All documents and materials, to include the source codes of software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership and copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.16 Non-Disclosure Requirements: Performance under this contract may require the Contractor to access data and information proprietary to a Government agency, another Government Contractor, or of such nature that its dissemination or use other than as specified in this work statement would be adverse to the interests of the Government or others. The Contractor and Contractor personnel, shall not divulge or release data or information developed, or obtained under performance of this PWS, except to authorized Government personnel or upon written approval of the Contracting Officer. The Contractor shall not use, disclose, or reproduce proprietary data, which bears a restrictive legend, other than as specified in this PWS. All documentation showing individual names or other personal information shall be controlled and protected under the provisions of the Privacy Act of 1974, Public Law 93-579, 5 United States Code (U.S.C.) Section 552a.
1.17 Protection of Government and Contract Information: Per Public Use Notice of Limitations stated by Defense imagery Management operations Center and contained at www.dimoc.mil/resources/limitations/ , the Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any hard copy or digital marketing tools to include its company website.
http://www.dimoc.mil/resources/limitations/
1.18 Non-Disclosure Statements: Resserved
1.19 Organizational Conflict of Interest (OCI): Reserved
1.20 Phase In /Phase Out Period: Reserved
1.21 Safety: See the separately attached pdf titled “SERVICE OR EQUIPMENT INSTALLATION Over $250K CONTRACTOR SAFETY STANDARD JUNE 2024” for the current TYAD Safety Requirements. See Part 6, “Applicable Publications”, Section 6.1.14 .
1.21.1 Host Nation Safety Laws and Regulations: Reserved
1.21.1.1 In addition to other requirements for accident prevention specified in the contract, the Contractor shall comply with all Federal and State requirements governing safety and health protection on construction sites and other applicable occupational safety codes., the Contractor shall coordinate all work at the site, including development of plans and providing advance notices.
The Contractor shall indicate its plan for compliance considering conditions of the work described by the design, technical proposal, operational activities of the Government or others in the area of the work, identification of the coordinator, and implementation of all other accident prevention provisions of the contract. For the compliance with host nation laws and regulations, the Contractor shall comply with the non-exclusive list of duties described in this paragraph. If the Contractor determines that additional activities are required to fully comply, the Contractor shall ensure that compliance with the laws is complete. The duties include:
(a) Conditions of construction and operational activities to be considered include but are not limited to:
(i) For all construction activities meeting the following criteria: the work is scheduled to last longer than 30 working days and more than 20 workers are occupied simultaneously, or the volume of work is scheduled to exceed 500 person days, or the work presents particular tasks, e.g. excavations deeper than 5 meters, falls from a height of greater than 7 meters, exposures to hazardous chemical or biological substances, work at less than 5 meters from high voltage lines, underground earth works or tunnels, danger of drowning, diving, use of compressed air, work with ionizing radiation, explosives, or work involving assembly or dismantling of heavy prefabricated components (10 tons or greater).
(i) Maintenance of tools and equipment.
(ii) Provisions for the storage and disposal of materials and waste, particular hazardous materials and substances.
(iii) Modifying performance periods for such work, taking into consideration the site conditions.
(iv) Organizing cooperation between different employers and Contractors without employees.
(v) Interaction between work at the site and other operational activities in the area, on which or near which the first identified work will be performed, and taking into consideration the instructions and advice of the coordinator as well as safety and health plans
1.21.1.2 Reserved
1.21.1.3 Reserved
1.22 Environmental Compliance: The following provides information on Environmental Compliance.
See the separately attached pdf titled “Standard NEPA Specifications for Projects_9 Jun 25” for the current TYAD Environmental Requirements. See Part 6, “Applicable Publications”, Section 6.1.16 .
1.22.1 Environmental Compliance Plan and Program: Reserved
“Current Environmental Policy (Garrison policy Number 22) is available at the Garrison website: http://www.wiesbaden.army.mil/policies/22EnvironmentalManagementSystem.pdf
“Current Prohibited Refuse Disposal Practices Policy (Garrison policy Number 27) is available at the Garrison website:
http://www.wiesbaden.army.mil/policies/27Prohibited_Refuse_Disposal_Practices.pdf
1.23 Required Training: The following provides information on training requirements.
1.23.1 Anti-Terrorism (AT) Level I Training: All Contractor employees, including subcontractor employees, who are employed under the contract, shall complete AT Level I Training within twenty (20) days (Deliverable # A.014) after contract start date or effective date of incorporation of this requirement into the contract, whichever applies, or twenty (20) days after employment of new personnel. Contractor personnel travelling overseas shall complete area of responsibility (AOR) specific AT awareness training for U.S. based Contractor employees and associated subcontractor employees. The Contractor shall submit certificates of completion (Deliverable # A.014) for each affected Contractor employee and subcontractor employee to the COR (or to the Contracting Officer, if a COR is not assigned) within twenty
(20) days after completion of this training by all employees and subcontractor personnel. AT Level I awareness training is available at https://jkodirect.jten.mil. Contractor personnel shall complete refresher training (Deliverable # A.014) every twelve (12) months except AOR specific AT Level I training which shall be completed as required by local AT policies
If training cannot be conducted on the website, the Contractor shall coordinate with the COR who will contact the local AT Officer at their assigned location for classroom training.
Contractor personnel completing training in the classroom will receive a certificate or the training attendance roster signed by the AT Officer. Verification of the training shall be provided to the COR within twenty (20) days after completion of the training (Deliverable # A.014 http://www.wiesbaden.army.mil/policies/22EnvironmentalManagementSystem.pdf http://www.wiesbaden.army.mil/policies/27Prohibited_Refuse_Disposal_Practices.pdf https://jkodirect.jten.mil/
1.23.2 OPSEC Training: All Contractor employees, including subcontractors, shall complete Level I OPSEC training within twenty (20) days of employment under this PWS (Deliverable # A.015). Verification of the training shall be provided to the COR within twenty (20) days after completion of the training (Deliverable # A.015). OPSEC Level I training is available at http://www.cdse.edu/catalog/elearning/GS130.html. Contractor personnel must complete refresher training every 12 months (Deliverable # A.015). Verification of the training shall be provided to the COR within twenty (20) days after completion of the training (Deliverable # A.015).
If training cannot be conducted on the website, the Contractor shall coordinate with the COR, who will contact the local OPSEC Officer at their assigned location for classroom training.
Contractor personnel completing training in the classroom will receive a certificate or the training attendance roster signed by the OPSEC Officer. Verification of the training shall be provided to the COR within twenty (20) days after completion of the training (Deliverable # A.015).
1.23.3 iWATCH Training: iWATCH Training: The Contractor and all associated subcontractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within twenty (20) days after the contract is awarded and within twenty (20) days after new employees commence contract performance, with the results reported to the COR within twenty (20) days after the contract is awarded and within twenty (20) days after new employees commence contract performance (Deliverable # A.016). Verification of the training shall be provided to the COR within twenty (20) days after completion of the training (Deliverable # A.016). Training slides can be found on the Army OneSource we site:
http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx.
1.23.4 Information Assurance (IA) Training Reserved
1.23.4.2 Reserved
1.23.4.3 Reserved
1.23.5 Personally Identifiable Information (PII): Reserved
1.24 Authorization to Perform Services in Germany Reserved
1.24.1 Reserved
1.24.2 Reserved
1.24.3 Reserved
http://www.cdse.edu/catalog/elearning/GS130.html http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx
1.25 Notice to Proceed: the notice to proceed will be provided as indicated below.
X☐The effective date of contract will constitute the date of notice to proceed ☐A notice to proceed letter will be issued ☐The date of the letter transmitting the contract will constitute the date of the notice to proceed
1.26 Electromagnetic Compatibility Directive: Reserved
1.27 Government Property and Services: Reserved
1.28 Conventional Forces Europe (CFE) Treaty Verification Inspection: Reserved
PART 2
DEFINITIONS & ACRONYMS
2. Definitions and Acronyms
2.1 Definitions: Although not inclusive of every term used within this PWS, the following provides a list of definitions used throughout this PWS and commonly used in the acquisition field.
Contracting Officer – means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
Contracting Officer's Representative (COR) – As defined in DFARS 202.101, means an individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. DoD Instruction (DoDI) 5000.72, Part II Definitions states the following when defining a COR: “Defined in subpart 202.101 of Reference (f). Any individual delegated responsibilities pursuant to subpart 1.602-2 of Reference (e), regardless of local terminology, must be certified in accordance with this instruction. For example, local terminology can be COR, Contracting Officer’s technical representative, technical point of contact, technical representative, alternate COR, administrative COR, assistant COR, line item manager, task order manager, quality assurance personnel, quality assurance evaluator, or COR management.” In addition, Army Regulation 70-13, Chapter 2, paragraph 2-2g, states, in part, the following when providing other surveillance support personnel to assist the COR when needed, “…These other surveillance support personnel may serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR requirements and have been appointed by the Contracting Officer as alternate CORs.”
Contractor – means a supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
Contractor-acquired Property - means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract and to which the Government has title.
Day – means, unless otherwise specified, a calendar day.
Defective Service – means a service output that does not meet the standard of performance associated with the Performance Work Statement.
Deliverable – means anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.
Government-furnished Property – As reflected in FAR 52.245-1, Government-furnished Property “means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract
Government Property - means all property owned or leased by the Government. Government property includes both Government-furnished and Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.
Property Administrator - means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.
High Level Objective (HLO) – means a key overarching result-based objective for a project necessary to achieve the project’s vision. HLOs are similar to Level 2 in a Work Breakdown Structure. Each HLO may contain several statements to flesh out the areas necessary to meet the objective.
Physical Security – means that part of security concerned with physical measures designed to safeguard personnel; to prevent unauthorized access to equipment, installations, material, and documents; and to safeguard against espionage, sabotage, damage, and theft.
Quality Assurance – (or Government contract quality assurance) means the various functions, including, inspection, performed by the Government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.
Quality Assurance Surveillance Plan (QASP) – means the key Government-developed surveillance process document, and is applied to Performance-Based Service Contracting (PBSC). The QASP is used for managing Contractor performance assessment by ensuring that systematic quality assurance methods validate that Contractor quality control efforts are timely, effective, and are delivering the results specified in the contract or task order. The QASP directly corresponds to the performance objectives and standards (i.e., quality, quantity, timeliness) specified in the Performance Work Statement (PWS). It provides specific details on how the Government will survey, observe, test, sample, evaluate, and document Contractor performance results to determine if the Contractor has met the required standards for each objective in the PWS. The QASP, with very few if any exceptions, is an internal to Government document.
Quality Control – means all necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
Statement – means the specific results-based activities required to satisfy HLOs. A statement contains a result, the context of the statement, and the required action(s). Statements focus on “what” is to be accomplished; however they are not prescriptive in describing “how” the outcome is to be achieved. Each HLO may have several statements to flesh out the areas necessary to meet the objective. Statements are similar to Level 3 in a Work Breakdown Structure.
Subcontractor – means one that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.
Work Day - The number of hours per day the Contractor provides services in accordance with the contract.
Work Week - Monday through Friday, unless otherwise specified.
2.2 Acronyms: Although not inclusive of every term used within this PWS, or that may be included in an acquisition, the following provides a list of acronyms commonly used in the acquisition field.
ACOR Alternate Contracting Officer's Representative AE Army in Europe AFARS Army Federal Acquisition Regulation Supplement AHA Activity Hazard Analysis AOR Area of Responsibility AR Army Regulation AT Anti-terrorism ATCTS Army Training Certification Tracking System CAC Common Access Card CCE Contracting Center of Excellence CFE Conventional Forces Europe CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer’s Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DoD Department of Defense FAR Federal Acquisition Regulation FRG Federal Republic of Germany GFP Government Furnished Property HLO High Level Objective HIPAA Health Insurance Portability and Accountability Act of 1996 IA Information Awareness IAC Installation Access Control IACO Installation Access Control Office ID Identification IGCE Independent Government Cost Estimate
IT Information Technology JTR Joint Travel Regulation JPAS Joint Personnel Adjudication System KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs OPSEC Operations Security PA Property Administrator PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program RA Requiring Activity RCO Regional Contracting Office SIGE Safety and Health Protection Plan TE Technical Exhibit USAG United States Army Garrison USAREUR United States Army Europe UOM Unit of Measure
PART 3
GOVERNMENT PROPERTY (GP) AND SERVICES
3. Government Property and Services
3.1 Services: Reserved
3.2 Facilities: During the servicing period the contractor shall have limited use of the premises for the performance of their operations, including use of the site. The contractor’s use of the premises is confined to those areas where work is to be performed.
3.3 Utilities: All utilities in the facility will be available for the contractor’s use in performance of tasks outlined in this PWS. The Contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount to accomplish cleaning vehicles and equipment.
3.4 Equipment: Reserved
3.5 Special Tooling and Test Equipment: Reserved
3.6 Materials: Reserved
3.7 Training: The Government will provide the following training: AT Level 1, iWATCH Army and OPSEC.
3.8 Common Access Cards (CAC): Reserved
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. Contractor Furnished Property and Services
4.1 General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS.
4.2 Secret Facility Clearance: Reserved
4.3 Materials: The Contractor shall furnish all materials and supplies necessary to meet the requirements under this PWS.
4.4 Vehicles and Equipment: The Contractor shall furnish all necessary vehicles and equipment to perform the work described in this PWS.
4.5 Background Checks: The Contractor shall provide Background Checks in accordance with this PWS and as determined by the Government.
PART 5
SPECIFIC TASKS
5.1 Basic Services: The Contractor shall provide services for and furnish all labor, tools, materials, equipment and transportation necessary to assess and repair the overhead doors, dock equipment and their closely associated components at Tobyhanna Army Depot (TYAD) as required by the contract and described herein.
5.1.1 Pre-Existing Manufacturers: TYAD currently has the following manufacturer’s overhead doors on the installation but are not limited to: Raynor, Cornell, Cloplay, C.H.I. and Wayne Dalton.
5.1.2 Approximate Quantities (Overhead Doors): TYAD has approximately five hundred
(500) overhead doors, one hundred fifty (150) roll up doors, eighty (80) sliding doors, forty (40) high speed doors and one (1) bi-fold hangar door.
5.1.3 Approximate Quantities (Dock Equipment): TYAD has approximately ninety five (95) pieces of dock equipment consisting of dock locks, dock levelers, dock shelters, dock bumpers, etc.
5.2. Tasks:
5.2.1 Assessments with Proposals: The contractor will be notified by the COR via email that their services are needed to provide an assessment for inoperable equipment. The contractor has five (5) business days to respond on site in person at TYAD. Upon arrival and departure of each visit, the contractor shall contact the COR. Upon completion of the assessment, the contractor shall provide a detailed proposal for repair within one week of the date of the assessment. The proposal for repair shall include all pertinent information which includes but is not limited to: dates and times, contractor personnel name(s), location(s), and all costs associated with returning equipment to its proper operating status. The costs associated in the proposal shall be broken down to include: travel, labor, parts and anything else necessary to complete the task(s). All repairs must have prior approval from the COR before the commencement of any work shall begin. Repairs shall be scheduled with the COR at minimum forty-eight (48) hours in advance. Deliverable D.03
5.2.2 Repair Work: The Contractor shall perform all repairs, with prior COR approval, on overhead doors, dock equipment and closely associated components throughout Tobyhanna Army Depot (TYAD) in compliance with manufacturer’s recommendations, applicable laws, regulations, rules, ordinances, codes, etc. If conflicts do arise, the more stringent of the two shall be followed. The Contracting Officer’s Representative (COR) shall be the Authority Having Jurisdiction (AHJ).
5.3 Quarterly Status Report: The Contractor shall provide a quarterly status report to the Contracting Officer’s Representative (COR). This report shall contain the following information for the preceding quarter:
• Parts and Materials Consumed: A detailed list of all parts and materials used for repairs and maintenance during the reporting period.
• Associated Costs: The costs associated with each part and material listed.
• Labor Hours: A summary of the total labor hours expended on all tasks, broken down by repair or service order.
The first report shall be submitted at the end of the first full quarter after the contract award, and quarterly thereafter. Deliverable D.04
PART 6 APPLICABLE PUBLICATIONS
6. Applicable Publications (Current Editions): The following publications, manuals, regulations, etc. are mentioned in this PWS and are listed below.
6.1.1 Department Of Defense Contract Security Classification Specification (DD Form 254)
6.1.2 Department of Defense Security Agreement (DD Form 441)
6.1.3 National Industrial Security Program Operating Manual (DoD 5220.22-M)
6.1.4 Installation Access Control (AE Reg 190-16)
6.1.5 The Army Physical Security Program (AR 190-13)
6.1.6 Contractor Identification (AE Reg 27-715)
6.1.7 U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1)
6.1.8 Information Assurance Workforce Improvement Program (DoD 8570-M)
6.1.9 Information Assurance Training Certification and Workforce Management Directive (DoDD 8570.01)
6.1.10 Information Assurance (AR 25-2)
6.1.11 Electromagnetic Compatibility Directive (2004/108/EC)
6.1.12 Policies and Procedures for Property Accountability (AR 735-5)
6.1.13 Security_Requirements_Insert_for_All_SOWs_and_PWSs_Updated_20260225
6.1.14 SERVICE OR EQUIPMENT INSTALLATION Over $250K CONTRACTOR SAFETY STANDARD JUNE 2024.pdf
6.1.15 Standard NEPA Specifications for Projects_9 Jun 25.pdf
PART 7
ATTACHMENT AND TECHNICAL EXHIBIT LISTING
7. Attachment and Technical Exhibit List
7.1 Technical Exhibit A - Performance Requirements Summary
7.2 Technical Exhibit B – Deliverables Schedule
TECHNICAL EXHIBIT A
Performance Requirements Summary (PRS)
PERFORMANCE
OBJECTIVE
STANDARD PERFORMANCE
THRESHOLD
ACCEPTABLE
QUALITY
LEVELS (AQLs)
METHOD OF
SURVEILLANCE
PRS#1 - PWS para (5.2.1)
Assessments: Assess inoperable overhead doors, dock equipment and their closely associated components in order to provide a proposal for repair.
The assessment request will come from the COR and the contractor shall respond on site in person within five
(5) business days.
100% Compliance
Zero deviation from the standard
100% Inspection
PRS#2 - PWS para (5.2.2)
Repair Work: The contractor shall repair the necessary equipment in order to return it to its safe and proper operating condition.
The COR will approve a proposal for repair work prior to the commencement of any repair work.
100% Compliance
Zero deviation from the standard
100% Inspection
TECHNICAL EXHIBIT B
DELIVERABLES SCHEDULE
Deliverable Frequency # of Copies Medium/Format Submit To D.01: Quality Control Plan (QCP) Para 1.5.1
Once within 30 days after contract award and no later than 7 days prior to any anticipated changes.
One copy submitted to
COR.
Electronic delivery via email using Microsoft Office Word, Power Point or PDF
Contracting Officer’s Representati ve (COR):
david.t.huda k.civ@army.
mil
D.02 Key Personnel Para 1.10
Contractor Key personnel list with qualifications within five
(5) days after contract award or during the post-award meeting.
One copy submitted to
COR
Electronic delivery via email using Microsoft Office Word or PDF
Contracting Officer’s Representati ve (COR):
david.t.huda k.civ@army.
mil
D.03 Proposals for Repair
Required no later than one week from when the assessment was performed.
One copy submitted to
COR
Electronic delivery via email using Microsoft Office Word, Power Point or PDF
Contracting Officer’s Representati ve (COR):
david.t.huda k.civ@army.
mil
D.04 Quarterly Status Report Para 5.3
Quarterly One copy submitted to
COR
Electronic delivery via email using Microsoft Word or PDF
Contracting Officer’s Representati ve (COR):
david.t.huda k.civ@army.
mil
| 1.5 General Information: |
| 1.12.2 Contractor Identification Badges: Reserved |
| 1.19 Organizational Conflict of Interest (OCI): Reserved |
| 1.22.1 Environmental Compliance Plan and Program: Reserved |
| 1.23.4 Information Assurance (IA) Training Reserved |
| 1.23.5 Personally Identifiable Information (PII): Reserved |
| PART 2 DEFINITIONS & ACRONYMS |
| 2. Definitions and Acronyms |
| PART 3 |
| 3. Government Property and Services |
| 3.5 Special Tooling and Test Equipment: Reserved |
| PART 4 |
| 4. Contractor Furnished Property and Services |
| PART 5 SPECIFIC TASKS |
| 5.2. Tasks: |
| 5.3 Quarterly Status Report: The Contractor shall provide a quarterly status report to the Contracting Officer’s Representative (COR). This report shall contain the following information for the preceding quarter: |
| Parts and Materials Consumed: A detailed list of all parts and materials used for repairs and maintenance during the reporting period. |
| Associated Costs: The costs associated with each part and material listed. |
| Labor Hours: A summary of the total labor hours expended on all tasks, broken down by repair or service order. |
| The first report shall be submitted at the end of the first full quarter after the contract award, and quarterly thereafter. Deliverable D.04 |
| PART 7 |
| 7. Attachment and Technical Exhibit List |
TECHNICAL EXHIBIT A