Draft Price Schedule for Initial Delivery Order.pdf

PDF 998 KB Posted

Attached to
Soo Area Office Equipment Rental
Solicitation number
W911XK20Q0010
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item Equipment Type Equipment Description Requirements Quantity Unit of Issue Week(s) Weekly Rate Month(s) Monthly Rate Total Period of Performance

1 Crane IC 250 Carry Deck Industrial Crane

4x4;

with all weather enclosed cab, door, and heat; with 2 and 4 part line blocks; with sufficient wire rope to lower lowest point of hook on 4 part line block at least 60' below grade with boom fully retracted and horizontal; with swing away jib

2 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 BASE

2 Loader Compact Track loader with general purpose bucket

With general purpose bucket; With lifting points;

Minimum operating capacity 2300 lb, 50% tipping load 2 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 BASE

3 Loader

Multi Terrain Compact Track Loader with general purpose bucket and snow plow blade

With general purpose bucket and snow plow blade; With lifting points; Minimum operating capacity 2300 lb, 50% tipping load 1 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 BASE

4 Hydronic Heater Ground Heater with hose

Diesel; Minimum 140,000 btu/hr input; Minimum 1000' hose; with fork pockets;

with lift points; Minimum run time at 100% 60 hours Diesel; Minimum 140,000 btu/hr input; Minimum 1000' hose; with fork pockets;

with lift points; Minimum run time at 100% 60 hours

1 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 BASE

5 Welder Towable 500a diesel

500 Amp Diesel; towable;

300' stinger and ground cable each;

Welding stinger and air arc gouging assembly

1 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 BASE

6 Air Compressor Towable 75 cfm at 90 psi 2 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 BASE

7 AWP 60-1 60' Boom Lift Minimum platform height 60’, 4WD, diesel, maximum weight 28,000 lb, equipped for lifting by crane 2 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 BASE

8 Small Ground Level Office 8'x20' Ground level office Single wide (8’ x 20’) with electric heat and lifting lugs/capability. 4 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 BASE

9 Telehandler High capacity Telehandler with rated capacity of 16,755lb, maximum lift height of 31’ 8” and Artic package. 2 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 BASE

10 Ice crusher /breaker 4' wide attachment for snow and ice removal

Mechanical type, road-profiling, ice-breaking, snow removal equipment, meant for ice and snow removal on sidewalks. The attachment shall comply with the following specifications:

a. For use on sidewalks and other narrow roadways where highly compacted snow and ice may accumulate.

b. Has a moveable plow blade that can push the pulverized ice/snow to either side of the pathway

c. Be compatible with Bobcat Toolcat Model 5600T

d. Working Width mm/ft: 250/3.94

e. 4 sets of double wheels

f. Wheel diameter (mm/in): 250/9.84

g. Number of Shovels: 1

h. Discharge direction shall be available on both the left and right

i. System Dimensions (mm/ft): 1100/3.6 x 1230/4 x 480/1.57

j. Contour ability (mm): 100

k. Has a universal adapter plate so the type of couplers used with these small tractors can be bolted direction to the adapter plate.

1 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 BASE

11 Telescopic Crawler Crane 120TN Telescopic Crawler Crane

120 TN Crane shall be able to start and operate at temperatures as low as -20 degrees F. Auxiliary boom nose, inserts, jibs, and extensions not required but will be accepted if they are with the machine.

Shall have a working radius of 8 feet up to 115 feet on the main boom.

Main boom only required to be supplied; auxiliary boom nose, inserts, jibs, and extensions not required but will be accepted if they are with the machine. 1 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 BASEDRAFT

12 Scaffold system

Heated, enclosed tube and clamp scaffold system, delivered, set up and removed; including engineering and submittals for government approval

Naturas Gas Heated, enclosed tube and clamp scaffold system, delivered, set up and removed; including engineering and submittals for government approval. 1 Each -$ 6 -$ -$

02 OCT 2020 TO 25

MAR 2021 BASE

13 Hydronic Heater Ground Heater with hose

Diesel; Minimum 140,000 btu/hr input; Minimum 1000' hose; with fork pockets;

with lift points; Minimum run time at 100% 60 hours Diesel; Minimum 140,000 btu/hr input; Minimum 1000' hose; with fork pockets;

with lift points; Minimum run time at 100% 60 hours

1 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 OPTION

14 Crane IC 200-2 Carry Deck Industrial Crane

4x4;

with all weather enclosed cab, door, and heat; with 2 and 4 part line blocks; with sufficient wire rope to lower lowest point of hook on 4 part line block at least 60' below grade with boom fully retracted and horizontal; with swing away jib

1 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 OPTION

15 Crane IC 250 Carry Deck Industrial Crane

4x4;

with all weather enclosed cab, door, and heat; with 2 and 4 part line blocks; with sufficient wire rope to lower lowest point of hook on 4 part line block at least 60' below grade with boom fully retracted and horizontal; with swing away jib

1 Each Diesel 3.5 keep warm

14 DEC 2020 TO 25

MAR 2021 OPTION

16 Mini Compact Track Loader Mini Eco-Friendly Compact Track Loader Electric 1 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 OPTION

17 Concrete Buggy Concrete Buggy for transport of construction materials Electric or Propane 2 Each -$ 3.5 -$ -$

14 DEC 2020 TO 25

MAR 2021 OPTION

18 Dry Prime Trailer Mounted Pump

Dry prime pump with 8" connection. Pump up to 4500 GPM with up to 200 ft. of head capabilities. Trash Flow 8" dry prime pump trailer mounted

8inch, 150 pound ANSI B 16.5 Suction and Discharge Connection. 4500 GPM maximum capacity and capable of handling up to 3 inch solids. 1 Each -$ 3 -$ -$

04 JAN 2021 TO 25

MAR 2021 OPTION

19 Hydraulic Pump

12" Hydraulic pump and critically silenced diesel HPU, piping and appurtenances

Hydraulic pump and critically silenced diesel HPU; Pump with lifting eye and frame;

Hydraulic hose sufficient to place pump 150' from HPU 12" 150# flange discharge

1 Each -$ 3 -$ -$

04 JAN 2021 TO 25

MAR 2021 OPTION

Hydraulic Pump Piping Appurtenances

Hydraulic Pump Piping Appurtenances

Quantity 50 12" SDR 17 Polyethylene pipe 10' length with 150 lb flanges Quantity 6 12" SDR 17 Polyethylene pipe 5' length with 150 lb flanges Quantity 6 12" SDR 17 Polyethylene pipe 3' length with 150 lb flanges Quantity 6 12" SDR 17 Polyethylene pipe 1' length with 150 lb flanges Quantity 10 12" SDR 17 Polyethylene 90 degree elbows with 150 lb flanges Quantity 6 12" SDR 17 Polyethylene 45 degree elbows with 150 lb flanges Gaskets and bolts for 100 of the above flange connections.

1 Each -$ 3 -$ -$

04 JAN 2021 TO 25

MAR 2021 OPTION

21 Abrasive Blast Machine Abrasive Blast Machine for high production blasting

160 CuFT Blasting system with 1600cfm Air system/trailer mounted 1 Each -$ 5.5 -$ -$

01 NOV 2020 TO 15

APR 2021 OPTION

22 Abrasive Blast Machine Abrasive Blast Machine for high production blasting

161 CuFT Blasting system with 1600cfm Air system/trailer mounted 1 Each -$ 3.5 -$ -$

04 JAN 2021 TO 15

APR 2021 OPTION

22 Ventilation Fan Shrouded 6900 CFM Pneumatic Ventilation Fan Shrouded 6900 CFM Pneumatic Ventilation Fan 2 Each -$ 5.5 -$ -$

01 NOV 2020 TO 15

APR 2021 OPTION

23 Ventilation Fan Shrouded 6900 CFM Pneumatic Ventilation Fan Shrouded 6900 CFM Pneumatic Ventilation Fan 2 Each -$ 3.5 -$ -$

04 JAN 2021 TO 15

APR 2021 OPTION

sssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssSSSSSSSSSSSSSSSSSs sssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssss BASE TOTAL

DRAFT

24 Vacuum Recovery System High Capacity vac recovery system

6" vacuum hose, conveying capacity of 8 ton/hr vacuum system, powered by compressed air, auto reverse pulse cleaning 1 Each -$ 5.5 -$ -$

01 NOV 2020 TO 15

APR 2021 OPTION

25 Vacuum Recovery System High Capacity vac recovery system

6" vacuum hose, conveying capacity of 8 ton/hr vacuum system, powered by compressed air, auto reverse pulse cleaning 1 Each -$ 3.5 -$ -$

04 JAN 2021 TO 15

APR 2021 OPTION

26 Vacuum Interceptor Vacuum Interceptor 55 cft vacuum interceptor, capable of abrasive waste seperation and disposal handling 1 Each -$ 3.5 -$ -$

04 JAN 2021 TO 15

APR 2021 OPTION

27 Vacuum Interceptor Vacuum Interceptor 55 cft vacuum interceptor, capable of abrasive waste seperation and disposal handling 1 Each -$ 5.5 -$ -$

01 NOV 2020 TO 15

APR 2021 OPTION

28 Vacuum Hose Vacuum Hose 100' Length of 4" Hose 1 Each -$ 3.5 -$ -$

04 JAN 2021 TO 15

APR 2021 OPTION

29 Vacuum Hose Vacuum Hose 100' Length of 4" Hose 1 Each -$ 5.5 -$ -$

01 NOV 2020 TO 15

APR 2021 OPTION

30 Vacuum Hose Vacuum Hose 15' Length of 6" Hose 1 Each -$ 3.5 -$ -$

04 JAN 2021 TO 15

APR 2021 OPTION

31 Vacuum Hose Vacuum Hose 15' Length of 6" Hose 1 Each -$ 5.5 -$ -$

01 NOV 2020 TO 15

APR 2021

32 Air Hose 3" Air Hose 50' Lenth of 3" Air Hose with 3" Boss Fittings 4 Each -$ 3.5 -$ -$

04 JAN 2021 TO 15

APR 2021 OPTION

33 Air Hose 3" Air Hose 50' Lenth of 3" Air Hose with 3" Boss Fittings 4 Each -$ 5.5 -$ -$

01 NOV 2020 TO 15

APR 2021 OPTION

34 Air Compressor Towable Air Compressor Diesel, 1800 CFM Towable Air Compressor 1 Each -$ 3.5 -$ -$

04 JAN 2021 TO 15

APR 2021 OPTION

35 Air Compressor Towable Air Compressor Diesel, 1800 CFM Towable Air Compressor 1 Each -$ 5.5 -$ -$

01 NOV 2020 TO 15

APR 2021 OPTION

1 1 -$ 1 -$ -$

36 Delivery and Pick-up Tractor Trailer W/ Lowboy or flatbed

Equipment delivery and pick-up will be priced on a round trip basis (Equipment from point of origin, delivered to SAO, Picked up at SAO, and returned to the point of origin) 1 Job 1 -$ 1 -$ -$

37 Delivery and Pick-up Rollback or flatbed truck with or without trailer

Equipment delivery and pick-up will be priced on a round trip basis (Equipment from point of origin, delivered to SAO, Picked up at SAO, and returned to the point of origin) 1 Job 1 -$ 1 -$ -$ sssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssSSSSSSSSSSSSSSSSSs sssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssss OPTIONS TOTAL sssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssSSSSSSSSSSSSSSSssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssss DELIVERY AND PICK-UP TOTAL sssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssSSSSSSSSSSSSSSSSSs sssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssssss BASE PLUS ALL OPTIONS TOTAL

Options may be exercised within 120 days after award

DRAFT

File details come from the government source that posted it. Updated .