FA1
| OFFEROR NAME: | = Offeror Fill-In Cells |
| SOLICITATION NO.: | = Gov't Provided Amounts; Do not change |
| PRICE MATRIX | = Formulas/Labor Categories; Do not change |
| Functional Area (FA) 1 - Large Caliber Cannon | |
| Offerors may NOT add or delete rows or categories for the FFP labor. If submitting an offer for this FA, the Government-provided hours per labor category must be used. | | | | | | | | |
| Functional Area (FA) 1 - Large Caliber Cannon | | | | | | | | |
| Solicitation Labor Category | FFP Labor | | | | | | | |
| Government Provided Hours per OP1-OP5 | Proposed Hours per OP (must equal Gov't provided or "0") | OP 1 | OP2 | OP3 | OP4 | OP5 | Total FFP |
| PROGRAM MANAGER | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TASK LEADER | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEER | 3,760 | | $0 | $0 | $0 | $0 | $0 | $0 |
| GENERAL ENGINEER | 5,640 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR ENGINEER | 3,760 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR SOFTWARE ENGINEER | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SOFTWARE ENGINEER | 3,760 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR SOFTWARE ENGINEER | 3,760 | | $0 | $0 | $0 | $0 | $0 | $0 |
| QUALITY CONTROL (QC) ENGINEER* | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEERING TECHNICIAN | 3,760 | | $0 | $0 | $0 | $0 | $0 | $0 |
| ENGINEERING TECHNICIAN | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| DRAFTSMAN | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR PROGRAM ANALYST | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SUBJECT MATTER EXPERT | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| PROGRAM ANALYST | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TECHNICAL WRITER | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 43,240 | - 0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Offerors may add rows for the CPFF labor to account for categories with both Prime and Subcontractor effort, ensuring all formulas/links and totals are updated. | | | | | | | | |
| | * Allocated hours must equal Gov't Provided hours per labor category | | | | | | |
| Solicitation Labor Category | CPFF Labor | | | | | | | |
| Government Provided Hours per OP1-OP5 | * Allocated Labor Hours per OP | OP 1 | OP2 | OP3 | OP4 | OP5 | Total CPFF |
| PROGRAM MANAGER | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TASK LEADER | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEER | 3,760 | | $0 | $0 | $0 | $0 | $0 | $0 |
| GENERAL ENGINEER | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR ENGINEER | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR SOFTWARE ENGINEER | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SOFTWARE ENGINEER | 4,700 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR SOFTWARE ENGINEER | 4,700 | | $0 | $0 | $0 | $0 | $0 | $0 |
| QUALITY CONTROL (QC) ENGINEER* | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEERING TECHNICIAN | 3,760 | | $0 | $0 | $0 | $0 | $0 | $0 |
| ENGINEERING TECHNICIAN | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| DRAFTSMAN | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR PROGRAM ANALYST | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SUBJECT MATTER EXPERT | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| PROGRAM ANALYST | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TECHNICAL WRITER | 1,880 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 54,520 | - 0 | $0 | $0 | $0 | $0 | $0 | $0 |
| 4700 | | | | | | | |
FA2
| OFFEROR NAME: | = Offeror Fill-In Cells |
| SOLICITATION NO.: | = Gov't Provided Amounts; Do not change |
| PRICE MATRIX | = Formulas/Labor Categories; Do not change |
| Functional Area 2 - Weapon Research Technical Support | |
| Offerors may NOT add or delete rows or categories for the FFP labor. If submitting an offer for this FA, the Government-provided hours per labor category must be used. | | | | | | | | |
| Functional Area 2 - Weapon Research Technical Support | | | | | | | | |
| Solicitation Labor Category | FFP Labor | | | | | | | |
| Government Provided Hours per OP1-OP5 | Proposed Hours per OP (must equal Gov't provided or "0") | OP 1 | OP2 | OP3 | OP4 | OP5 | Total FA2 |
| PROGRAM MANAGER | 5,640 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TASK LEADER | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEER | 16,920 | | $0 | $0 | $0 | $0 | $0 | $0 |
| GENERAL ENGINEER | 15,040 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR ENGINEER | 13,160 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR SOFTWARE ENGINEER | 11,280 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SOFTWARE ENGINEER | 15,040 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR SOFTWARE ENGINEER | 13,160 | | $0 | $0 | $0 | $0 | $0 | $0 |
| QUALITY CONTROL (QC) ENGINEER* | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEERING TECHNICIAN | 13,160 | | $0 | $0 | $0 | $0 | $0 | $0 |
| ENGINEERING TECHNICIAN | 13,160 | | $0 | $0 | $0 | $0 | $0 | $0 |
| DRAFTSMAN | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR PROGRAM ANALYST | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SUBJECT MATTER EXPERT | 11,280 | | $0 | $0 | $0 | $0 | $0 | $0 |
| PROGRAM ANALYST | 5,640 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TECHNICAL WRITER | 3,760 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 171,080 | - 0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Offerors may add rows for the CPFF labor to account for categories with both Prime and Subcontractor effort, ensuring all formulas/links and totals are updated. | | | | | | | | |
| | | * Allocated hours must equal Gov't Provided hours per labor category | | | | | |
| Solicitation Labor Category | CPFF Labor | | | | | | | |
| Government Provided Hours per OP1-OP5 | * Allocated Labor Hours OP1-OP5 | OP 1 | OP2 | OP3 | OP4 | OP5 | Total FA2 |
| PROGRAM MANAGER | 5,640 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TASK LEADER | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEER | 16,920 | | $0 | $0 | $0 | $0 | $0 | $0 |
| GENERAL ENGINEER | 11,280 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR ENGINEER | 11,280 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR SOFTWARE ENGINEER | 11,280 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SOFTWARE ENGINEER | 15,040 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR SOFTWARE ENGINEER | 13,160 | | $0 | $0 | $0 | $0 | $0 | $0 |
| QUALITY CONTROL (QC) ENGINEER* | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEERING TECHNICIAN | 13,160 | | $0 | $0 | $0 | $0 | $0 | $0 |
| ENGINEERING TECHNICIAN | 13,160 | | $0 | $0 | $0 | $0 | $0 | $0 |
| DRAFTSMAN | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR PROGRAM ANALYST | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SUBJECT MATTER EXPERT | 11,280 | | $0 | $0 | $0 | $0 | $0 | $0 |
| PROGRAM ANALYST | 5,640 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TECHNICAL WRITER | 3,760 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 165,440 | 0 | $0 | $0 | $0 | $0 | $0 | $0 |
| 8 | 1880 | | | | | | |
| | 11280 | | | | | | |
FA3
| OFFEROR NAME: | = Offeror Fill-In Cells |
| SOLICITATION NO.: | = Gov't Provided Amounts; Do not change |
| PRICE MATRIX | = Formulas/Labor Categories; Do not change |
| Functional Area 3 - System Testing/Diagnostic and Netcentric Support | |
| Offerors may NOT add or delete rows or categories for the FFP labor. If submitting an offer for this FA, the Government-provided hours per labor category must be used. | | | | | | | | |
| Functional Area 3 - System Testing/Diagnostic and Netcentric Support | | | | | | | | |
| Solicitation Labor Category | FFP Labor | | | | | | | |
| Government Provided Hours per OP1-OP5 | Proposed Hours (must equal Gov't provided or "0") | OP 1 | OP2 | OP3 | OP4 | OP5 | Total FA2 |
| PROGRAM MANAGER | 5,640 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TASK LEADER | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEER | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| GENERAL ENGINEER | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR ENGINEER | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR SOFTWARE ENGINEER | 11,280 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SOFTWARE ENGINEER | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR SOFTWARE ENGINEER | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| QUALITY CONTROL (QC) ENGINEER* | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEERING TECHNICIAN | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| ENGINEERING TECHNICIAN | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| DRAFTSMAN | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR PROGRAM ANALYST | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SUBJECT MATTER EXPERT | 11,280 | | $0 | $0 | $0 | $0 | $0 | $0 |
| PROGRAM ANALYST | 5,640 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TECHNICAL WRITER | 3,760 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 129,720 | - 0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Offerors may add rows for the CPFF labor to account for categories with both Prime and Subcontractor effort, ensuring all formulas/links and totals are updated. | | | | | | | | |
| | * Allocated hours must equal Gov't Provided hours per labor category | | | | | | |
| Solicitation Labor Category | CPFF Labor | | | | | | | |
| Government Provided Hours per OP1-OP5 | * Allocated Labor Hours per OP | OP 1 | OP2 | OP3 | OP4 | OP5 | Total FA1 |
| PROGRAM MANAGER | 5,640 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TASK LEADER | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEER | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| GENERAL ENGINEER | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR ENGINEER | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR SOFTWARE ENGINEER | 11,280 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SOFTWARE ENGINEER | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| JUNIOR SOFTWARE ENGINEER | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| QUALITY CONTROL (QC) ENGINEER* | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR ENGINEERING TECHNICIAN | 5,640 | | $0 | $0 | $0 | $0 | $0 | $0 |
| ENGINEERING TECHNICIAN | 5,640 | | $0 | $0 | $0 | $0 | $0 | $0 |
| DRAFTSMAN | 9,400 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SENIOR PROGRAM ANALYST | 7,520 | | $0 | $0 | $0 | $0 | $0 | $0 |
| SUBJECT MATTER EXPERT | 11,280 | | $0 | $0 | $0 | $0 | $0 | $0 |
| PROGRAM ANALYST | 5,640 | | $0 | $0 | $0 | $0 | $0 | $0 |
| TECHNICAL WRITER | 3,760 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 122,200 | - 0 | $0 | $0 | $0 | $0 | $0 | $0 |
FFP Labor Rates
| OFFEROR NAME: | = Offeror Fill-In Cells |
| SOLICITATION NO.: | = Gov't Provided Amounts; Do not change |
| PRICE MATRIX | = Formulas/Labor Categories; Do not change |
| FFP LABOR | |
| Solicitation Labor Category | FFP Fully Burdened Labor Rates | | | | |
| OP 1 | OP2 | OP3 | OP4 | OP5 |
| PROGRAM MANAGER | | | | | |
| TASK LEADER | | | | | |
| SENIOR ENGINEER | | | | | |
| GENERAL ENGINEER | | | | | |
| JUNIOR ENGINEER | | | | | |
| SENIOR SOFTWARE ENGINEER | | | | | |
| SOFTWARE ENGINEER | | | | | |
| JUNIOR SOFTWARE ENGINEER | | | | | |
| QUALITY CONTROL (QC) ENGINEER* | | | | | |
| SENIOR ENGINEERING TECHNICIAN | | | | | |
| ENGINEERING TECHNICIAN | | | | | |
| DRAFTSMAN | | | | | |
| SENIOR PROGRAM ANALYST | | | | | |
| SUBJECT MATTER EXPERT | | | | | |
| PROGRAM ANALYST | | | | | |
| TECHNICAL WRITER | | | | | |
CPFF Labor Rates
| OFFEROR NAME: | = Offeror Fill-In Cells |
| SOLICITATION NO.: | = Gov't Provided Amounts; Do not change |
| PRICE MATRIX | = Formulas/Labor Categories; Do not change |
| CPFF LABOR RATES | |
| Offerors must link or manually input the CPFF labor rates on this tab from the CPFF Labor Rate Detail tabs for both Prime (Offeror) and Subcontractor Effort. Should the input be manually, the rates on this tab must match the labor rate detail tabs. | |
| Offerors may add rows/columns to this worksheet as needed, ensuring all formulas and totals are updated. | |
| 1 - Burdened Labor Rates are prior to the Prime Offeror's fee applied (Col. M (for the Prime) or Col. AF (for Subcontractor) on the Labor Rate tabs) |
| 2 - Fixed Fee is the Prime Offeror's fee per hour applied (Col. O (for the Prime) or Col. AH (for Subcontractor) on the Labor Rate tabs) |
| Prime Offeror / Subcontractor Name | Solicitation Labor Category | Offeror / Subcontractor Labor Category | CPFF Fully Burdened Labor Rates | | | | | | | | | | | | | | |
| | | OP 1 | | | OP 2 | | | OP 3 | | | OP 4 | | | OP 5 | | |
| | | Burdened Labor Rate 1 | Prime Fixed Fee 2 | Fully Burdened Labor Rate | Burdened Labor Rate 1 | Prime Fixed Fee 2 | Fully Burdened Labor Rate | Burdened Labor Rate 1 | Prime Fixed Fee 2 | Fully Burdened Labor Rate | Burdened Labor Rate 1 | Prime Fixed Fee 2 | Fully Burdened Labor Rate | Burdened Labor Rate 1 | Prime Fixed Fee 2 | Fully Burdened Labor Rate |
| ABC Company (Offeror) | Program Manager | Program Manager | $156.00 | $7.80 | $163.80 | $142.14 | $7.11 | $149.25 | $165.53 | $8.28 | $173.81 | $170.47 | $8.52 | $178.99 | $175.58 | $8.78 | $184.36 |
| XYZ Inc. (Subcontractor) | Junior Engineer | Engineer I | $84.18 | $5.05 | $89.23 | $86.72 | $5.20 | $91.92 | $89.28 | $5.36 | $94.64 | $92.00 | $5.52 | $97.52 | $94.76 | $5.69 | $100.45 |
| PROGRAM MANAGER | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| TASK LEADER | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| SENIOR ENGINEER | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| GENERAL ENGINEER | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| JUNIOR ENGINEER | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| SENIOR SOFTWARE ENGINEER | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| SOFTWARE ENGINEER | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| JUNIOR SOFTWARE ENGINEER | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| QUALITY CONTROL (QC) ENGINEER* | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| SENIOR ENGINEERING TECHNICIAN | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| ENGINEERING TECHNICIAN | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| DRAFTSMAN | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| SENIOR PROGRAM ANALYST | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| SUBJECT MATTER EXPERT | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| PROGRAM ANALYST | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
| TECHNICAL WRITER | | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 | | | $0.00 |
Example
CPFF Labor Rate Detail OP1
| OFFEROR NAME: | 0 | = Offeror Fill-In Cells | |
| SOLICITATION NO.: | | = Gov't Provided Amounts; Do not change | |
| PRICE MATRIX | | = Formulas/Labor Categories; Do not change formulas (Unless accounting practices dictate change in formulas) | |
| CPFF LABOR RATES DETAIL - Ordering Period 1 | | | |
| | | If the Offeror is unable to obtain the required documentation from its subcontractors, the Offeror shall only input the cells highlighted in ORANGE and the subcontractor shall provide the information directly to the Government following the exact submission instructions of this RFP and the format of this schedule for all subcontractors, regardless of subcontract type |
| Offerors may add rows/columns to this worksheet as needed for subcontract effort, ensuring all formulas and totals are updated but must include at least one rate per category |
| Offerors shall propose indirect rates and adjust formulas as needed to calculate the proposed costs based on their established accounting practices. |
| Offerors/Subcontractors shall provide supporting documentation for their proposed direct labor and indirect expense rates in a separate file(s). |
| Prime Offeror / Subcontractor Name | Solicitation Labor Category | Offeror / Subcontractor Labor Category | PRIME OFFEROR OP1 Costs (Add/Remove Columns As Appropriate. Adjust Formulas, if necessary) | | | | | | | | | | | | SUBCTR Costs - OP1 (Add/Remove Columns As Appropriate. Adjust Formulas, if necessary) | | | | | | | | | | | Prime Burdens on SBCTR Labor | | | | SBCTR Fully Burdened Labor Rate + Prime Burden | PRIME Fixed Fee % applied to SBCTR | Prime Fixed Fee Dollar Per Hour on SBCTR Labor | Fully Burdened SBCTR Labor Rate (with Prime Burdens & Fee) |
| | | Direct Labor Rate | Fringe (if applicable) | | Labor Overhead | | Subtotal | G&A | | Burdened Labor Rate | Fixed Fee % | Fixed Fee per Hour | Fully Burdened Labor Rate | Direct Labor Rate | Fringe (if applicable) | | Labor Overhead | | Subtotal | G&A | | Burdened Labor Rate | SBCTR Fee per Hour | SBCTR Fully Burdened Labor Rate | Mat'l Handling, if applicable | | G&A, if applicable | | | | | |
| | | | Rate | Per Hour | Rate | Per Hour | | Rate | Per Hour | | | | | | Rate | Per Hour | Rate | Per Hour | | Rate | Per Hour | | | | Rate | Per Hour | Rate | Per Hour | | | | |
| ABC Company (Offeror) | Program Manager | Program Manager | $50.00 | 30.00% | $15.00 | 100.00% | $65.00 | $130.00 | 20.00% | $26.00 | $156.00 | 5% | $7.80 | $163.80 | | | | | | | | | | | | | | | | | | | |
| XYZ Inc. (Subcontractor) | Junior Engineer | Engineer I | | | | | | | | | | | | | $25.00 | 18.00% | $4.50 | 76.00% | $22.42 | $51.92 | 35.00% | $18.17 | $70.09 | $4.21 | $74.30 | 3.00% | $2.23 | 10.00% | $7.65 | $84.18 | 6.00% | $5.05 | $89.23 |
| PROGRAM MANAGER | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TASK LEADER | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR ENGINEER | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| GENERAL ENGINEER | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| JUNIOR ENGINEER | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR SOFTWARE ENGINEER | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SOFTWARE ENGINEER | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| JUNIOR SOFTWARE ENGINEER | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| QUALITY CONTROL (QC) ENGINEER* | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR ENGINEERING TECHNICIAN | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| ENGINEERING TECHNICIAN | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| DRAFTSMAN | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR PROGRAM ANALYST | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SUBJECT MATTER EXPERT | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| PROGRAM ANALYST | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TECHNICAL WRITER | | | 0.00% | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
CPFF Labor Rate Detail OP2
| OFFEROR NAME: | 0 | = Offeror Fill-In Cells | |
| SOLICITATION NO.: | | = Gov't Provided Amounts; Do not change | |
| PRICE MATRIX | | = Formulas/Labor Categories; Do not change formulas (Unless accounting practices dictate change in formulas) | |
| CPFF LABOR RATES DETAIL - Ordering Period 2 | | | |
| | | If the Offeror is unable to obtain the required documentation from its subcontractors, the Offeror shall only input the cells highlighted in ORANGE and the subcontractor shall provide the information directly to the Government following the exact submission instructions of this RFP and the format of this schedule for all subcontractors, regardless of subcontract type |
| Offerors may add rows/columns to this worksheet as needed for subcontract effort, ensuring all formulas and totals are updated but must include at least one rate per category |
| Offerors shall propose indirect rates and adjust formulas as needed to calculate the proposed costs based on their established accounting practices. |
| Offerors/Subcontractors shall provide supporting documentation for their proposed direct labor and indirect expense rates in a separate file(s). |
| Prime Offeror / Subcontractor Name | Solicitation Labor Category | Offeror / Subcontractor Labor Category | PRIME OFFEROR OP2 Costs (Add/Remove Columns As Appropriate. Adjust Formulas, if necessary) | | | | | | | | | | | | SUBCTR Costs - OP2 (Add/Remove Columns As Appropriate. Adjust Formulas, if necessary) | | | | | | | | | | | Prime Burdens on SBCTR Labor | | | | SBCTR Fully Burdened Labor Rate + Prime Burden | PRIME Fixed Fee % applied to SBCTR | Prime Fixed Fee Dollar Per Hour on SBCTR Labor | Fully Burdened SBCTR Labor Rate (with Prime Burdens & Fee) |
| | | Direct Labor Rate | Fringe (if applicable) | | Labor Overhead | | Subtotal | G&A | | Burdened Labor Rate | Fixed Fee % | Fixed Fee per Hour | Fully Burdened Labor Rate | Direct Labor Rate | Fringe (if applicable) | | Labor Overhead | | Subtotal | G&A | | Burdened Labor Rate | SBCTR Fee | SBCTR Fully Burdened Labor Rate | Mat'l Handling, if applicable | | G&A, if applicable | | | | | |
| | | | Rate | Per Hour | Rate | Per Hour | | Rate | Per Hour | | | | | | Rate | Per Hour | Rate | Per Hour | | Rate | Per Hour | | | | Rate | Per Hour | Rate | Per Hour | | | | |
| ABC Company (Offeror) | Program Manager | Program Manager | $51.50 | 30.00% | $15.45 | 100.00% | $66.95 | $118.45 | 20.00% | $23.69 | $142.14 | 5.00% | $7.11 | $149.25 | | | | | | | | | | | | | | | | | | | |
| XYZ Inc. (Subcontractor) | Junior Engineer | Engineer I | | | | | | | | | | | | | $25.75 | 18.00% | $4.64 | 76.00% | $23.10 | $53.49 | 35.00% | $18.72 | $72.21 | $4.33 | $76.54 | 3.00% | $2.30 | 10.00% | $7.88 | $86.72 | 6.00% | $5.20 | $91.92 |
| PROGRAM MANAGER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TASK LEADER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| GENERAL ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| JUNIOR ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| JUNIOR SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| QUALITY CONTROL (QC) ENGINEER* | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR ENGINEERING TECHNICIAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| ENGINEERING TECHNICIAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| DRAFTSMAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR PROGRAM ANALYST | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SUBJECT MATTER EXPERT | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| PROGRAM ANALYST | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TECHNICAL WRITER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
CPFF Labor Rate Detail OP3
| OFFEROR NAME: | 0 | = Offeror Fill-In Cells | |
| SOLICITATION NO.: | | = Gov't Provided Amounts; Do not change | |
| PRICE MATRIX | | = Formulas/Labor Categories; Do not change formulas (Unless accounting practices dictate change in formulas) | |
| CPFF LABOR RATES DETAIL - Ordering Period 3 | | | |
| | | If the Offeror is unable to obtain the required documentation from its subcontractors, the Offeror shall only input the cells highlighted in ORANGE and the subcontractor shall provide the information directly to the Government following the exact submission instructions of this RFP and the format of this schedule for all subcontractors, regardless of subcontract type |
| Offerors may add rows/columns to this worksheet as needed for subcontract effort, ensuring all formulas and totals are updated but must include at least one rate per category |
| Offerors shall propose indirect rates and adjust formulas as needed to calculate the proposed costs based on their established accounting practices. |
| Offerors/Subcontractors shall provide supporting documentation for their proposed direct labor and indirect expense rates in a separate file(s). |
| Prime Offeror / Subcontractor Name | Solicitation Labor Category | Offeror / Subcontractor Labor Category | PRIME OFFEROR OP3 Costs (Add/Remove Columns As Appropriate. Adjust Formulas, if necessary) | | | | | | | | | | | | SUBCTR Costs - OP3 (Add/Remove Columns As Appropriate. Adjust Formulas, if necessary) | | | | | | | | | | | Prime Burdens on SBCTR Labor | | | | SBCTR Fully Burdened Labor Rate + Prime Burden | PRIME Fixed Fee % applied to SBCTR | Prime Fixed Fee Dollar Per Hour on SBCTR Labor | Fully Burdened SBCTR Labor Rate (with Prime Burdens & Fee) |
| | | Direct Labor Rate | Fringe (if applicable) | | Labor Overhead | | Subtotal | G&A | | Burdened Labor Rate | Fixed Fee % | Fixed Fee per Hour | Fully Burdened Labor Rate | Direct Labor Rate | Fringe (if applicable) | | Labor Overhead | | Subtotal | G&A | | Burdened Labor Rate | SBCTR Fee | SBCTR Fully Burdened Labor Rate | Mat'l Handling, if applicable | | G&A, if applicable | | | | | |
| | | | Rate | Per Hour | Rate | Per Hour | | Rate | Per Hour | | | | | | Rate | Per Hour | Rate | Per Hour | | Rate | Per Hour | | | | Rate | Per Hour | Rate | Per Hour | | | | |
| ABC Company (Offeror) | Program Manager | Program Manager | $53.05 | 30.00% | $15.92 | 100.00% | $68.97 | $137.94 | 20.00% | $27.59 | $165.53 | 5.00% | $8.28 | $173.81 | | | | | | | | | | | | | | | | | | | |
| XYZ Inc. (Subcontractor) | Junior Engineer | Engineer I | | | | | | | | | | | | | $26.52 | 18.00% | $4.77 | 76.00% | $23.78 | $55.07 | 35.00% | $19.27 | $74.34 | $4.46 | $78.80 | 3.00% | $2.36 | 10.00% | $8.12 | $89.28 | 6.00% | $5.36 | $94.64 |
| PROGRAM MANAGER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TASK LEADER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| GENERAL ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| JUNIOR ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| JUNIOR SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| QUALITY CONTROL (QC) ENGINEER* | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR ENGINEERING TECHNICIAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| ENGINEERING TECHNICIAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| DRAFTSMAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR PROGRAM ANALYST | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SUBJECT MATTER EXPERT | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| PROGRAM ANALYST | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TECHNICAL WRITER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
CPFF Labor Rate Detail OP4
| OFFEROR NAME: | 0 | = Offeror Fill-In Cells | |
| SOLICITATION NO.: | | = Gov't Provided Amounts; Do not change | |
| PRICE MATRIX | | = Formulas/Labor Categories; Do not change formulas (Unless accounting practices dictate change in formulas) | |
| CPFF LABOR RATES DETAIL - Ordering Period 4 | | | |
| | | If the Offeror is unable to obtain the required documentation from its subcontractors, the Offeror shall only input the cells highlighted in ORANGE and the subcontractor shall provide the information directly to the Government following the exact submission instructions of this RFP and the format of this schedule for all subcontractors, regardless of subcontract type |
| Offerors may add rows/columns to this worksheet as needed for subcontract effort, ensuring all formulas and totals are updated but must include at least one rate per category |
| Offerors shall propose indirect rates and adjust formulas as needed to calculate the proposed costs based on their established accounting practices. |
| Offerors/Subcontractors shall provide supporting documentation for their proposed direct labor and indirect expense rates in a separate file(s). |
| Prime Offeror / Subcontractor Name | Solicitation Labor Category | Offeror / Subcontractor Labor Category | PRIME OFFEROR OP4 Costs (Add/Remove Columns As Appropriate. Adjust Formulas, if necessary) | | | | | | | | | | | | SUBCTR Costs - OP4 (Add/Remove Columns As Appropriate. Adjust Formulas, if necessary) | | | | | | | | | | | Prime Burdens on SBCTR Labor | | | | SBCTR Fully Burdened Labor Rate + Prime Burden | PRIME Fixed Fee % applied to SBCTR | Prime Fixed Fee Dollar Per Hour on SBCTR Labor | Fully Burdened SBCTR Labor Rate (with Prime Burdens & Fee) |
| | | Direct Labor Rate | Fringe (if applicable) | | Labor Overhead | | Subtotal | G&A | | Burdened Labor Rate | Fixed Fee % | Fixed Fee per Hour | Fully Burdened Labor Rate | Direct Labor Rate | Fringe (if applicable) | | Labor Overhead | | Subtotal | G&A | | Burdened Labor Rate | SBCTR Fee | SBCTR Fully Burdened Labor Rate | Mat'l Handling, if applicable | | G&A, if applicable | | | | | |
| | | | Rate | Per Hour | Rate | Per Hour | | Rate | Per Hour | | | | | | Rate | Per Hour | Rate | Per Hour | | Rate | Per Hour | | | | Rate | Per Hour | Rate | Per Hour | | | | |
| ABC Company (Offeror) | Program Manager | Program Manager | $54.64 | 30.00% | $16.39 | 100.00% | $71.03 | $142.06 | 20.00% | $28.41 | $170.47 | 5.00% | $8.52 | $178.99 | | | | | | | | | | | | | | | | | | | |
| XYZ Inc. (Subcontractor) | Junior Engineer | Engineer I | | | | | | | | | | | | | $27.32 | 18.00% | $4.92 | 76.00% | $24.50 | $56.74 | 35.00% | $19.86 | $76.60 | $4.60 | $81.20 | 3.00% | $2.44 | 10.00% | $8.36 | $92.00 | 6.00% | $5.52 | $97.52 |
| PROGRAM MANAGER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TASK LEADER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| GENERAL ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| JUNIOR ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| JUNIOR SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| QUALITY CONTROL (QC) ENGINEER* | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR ENGINEERING TECHNICIAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| ENGINEERING TECHNICIAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| DRAFTSMAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR PROGRAM ANALYST | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SUBJECT MATTER EXPERT | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| PROGRAM ANALYST | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TECHNICAL WRITER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
CPFF Labor Rate Detail OP5
| OFFEROR NAME: | 0 | = Offeror Fill-In Cells | |
| SOLICITATION NO.: | | = Gov't Provided Amounts; Do not change | |
| PRICE MATRIX | | = Formulas/Labor Categories; Do not change formulas (Unless accounting practices dictate change in formulas) | |
| CPFF LABOR RATES DETAIL - Ordering Period 5 | | | |
| | | If the Offeror is unable to obtain the required documentation from its subcontractors, the Offeror shall only input the cells highlighted in ORANGE and the subcontractor shall provide the information directly to the Government following the exact submission instructions of this RFP and the format of this schedule for all subcontractors, regardless of subcontract type |
| Offerors may add rows/columns to this worksheet as needed for subcontract effort, ensuring all formulas and totals are updated but must include at least one rate per category |
| Offerors shall propose indirect rates and adjust formulas as needed to calculate the proposed costs based on their established accounting practices. |
| Offerors/Subcontractors shall provide supporting documentation for their proposed direct labor and indirect expense rates in a separate file(s). |
| Prime Offeror / Subcontractor Name | Solicitation Labor Category | Offeror / Subcontractor Labor Category | PRIME OFFEROR OP5 Costs (Add/Remove Columns As Appropriate. Adjust Formulas, if necessary) | | | | | | | | | | | | SUBCTR Costs - OP5 (Add/Remove Columns As Appropriate. Adjust Formulas, if necessary) | | | | | | | | | | | Prime Burdens on SBCTR Labor | | | | SBCTR Fully Burdened Labor Rate + Prime Burden | PRIME Fixed Fee % applied to SBCTR | Prime Fixed Fee Dollar Per Hour on SBCTR Labor | Fully Burdened SBCTR Labor Rate (with Prime Burdens & Fee) |
| | | Direct Labor Rate | Fringe (if applicable) | | Labor Overhead | | Subtotal | G&A | | Burdened Labor Rate | Fixed Fee % | Fixed Fee per Hour | Fully Burdened Labor Rate | Direct Labor Rate | Fringe (if applicable) | | Labor Overhead | | Subtotal | G&A | | Burdened Labor Rate | SBCTR Fee | SBCTR Fully Burdened Labor Rate | Mat'l Handling, if applicable | | G&A, if applicable | | | | | |
| | | | Rate | Per Hour | Rate | Per Hour | | Rate | Per Hour | | | | | | Rate | Per Hour | Rate | Per Hour | | Rate | Per Hour | | | | Rate | Per Hour | Rate | Per Hour | | | | |
| ABC Company (Offeror) | Program Manager | Program Manager | $56.28 | 30.00% | $16.88 | 100.00% | $73.16 | $146.32 | 20.00% | $29.26 | $175.58 | 5.00% | $8.78 | $184.36 | | | | | | | | | | | | | | | | | | | |
| XYZ Inc. (Subcontractor) | Junior Engineer | Engineer I | | | | | | | | | | | | | $28.14 | 18.00% | $5.07 | 76.00% | $25.24 | $58.45 | 35.00% | $20.46 | $78.91 | $4.73 | $83.64 | 3.00% | $2.51 | 10.00% | $8.61 | $94.76 | 6.00% | $5.69 | $100.45 |
| PROGRAM MANAGER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TASK LEADER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| GENERAL ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| JUNIOR ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| JUNIOR SOFTWARE ENGINEER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| QUALITY CONTROL (QC) ENGINEER* | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR ENGINEERING TECHNICIAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| ENGINEERING TECHNICIAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| DRAFTSMAN | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SENIOR PROGRAM ANALYST | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| SUBJECT MATTER EXPERT | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| PROGRAM ANALYST | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
| TECHNICAL WRITER | | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 | | $0.00 | | $0.00 | | $0.00 | $0.00 | | $0.00 | $0.00 |
CR Travel
| OFFEROR NAME: | 0 | = Offeror Fill-In Cells |
| SOLICITATION NO.: | | = Gov't Provided Amounts; Do not change |
| PRICE MATRIX | | = Formulas; Do not change |
| CR- Travel CLINs | | |
| Note: Indirect costs applicable to Travel should be applied based upon the Offeror's established accounting practices. Additional rows may be added, if necessary | | |
| * INDIRECT RATES SHALL BE THE SAME AS PROPOSED ON THE CPFF LABOR RATE DETAIL TABS OF THIS WORKBOOK | | |
| CR Travel | Application Base | Ordering Period 1 | | Ordering Period 2 | | Ordering Period 3 | | Ordering Period 4 | | Ordering Period 5 | |
| | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total |
| Description | | | | | | | | | | |
| Government Provided Travel | | | $70,000 | | | | $70,000 | | $70,000 | | $70,000 |
| Example: G&A | Total Cost Input | 12.00% | $8,400 | 12.50% | $0 | 11.90% | $8,330 | 12.00% | $8,400 | 12.30% | $8,610 |
| | | $0 | | $0 | | $0 | | $0 | | $0 |
| Total CR Travel | | | $78,400 | | $0 | | $78,330 | | $78,400 | | $78,610 |
| Functional Area 1 | | | | | | | | | | | |
| CR (no fee) Travel | Application Base | Ordering Period 1 | | Ordering Period 2 | | Ordering Period 3 | | Ordering Period 4 | | Ordering Period 5 | |
| | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total |
| Description | | | | | | | | | | |
| Government Provided Travel | | | $104,022 | | $114,386 | | $107,369 | | $110,590 | | $113,908 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Total CR Travel | | | $104,022 | | $114,386 | | $107,369 | | $110,590 | | $113,908 |
| Functional Area 2 | | | | | | | | | | | |
| CR (no fee) Travel | Application Base | Ordering Period 1 | | Ordering Period 2 | | Ordering Period 3 | | Ordering Period 4 | | Ordering Period 5 | |
| | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total |
| Description | | | | | | | | | | |
| Government Provided Travel | | | $108,263 | | $118,754 | | $122,316 | | $125,986 | | $129,766 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Total CR Travel | | | $108,263 | | $118,754 | | $122,316 | | $125,986 | | $129,766 |
| Functional Area 3 | | | | | | | | | | | |
| CR (no fee) Travel | Application Base | Ordering Period 1 | | Ordering Period 2 | | Ordering Period 3 | | Ordering Period 4 | | Ordering Period 5 | |
| | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total |
| Description | | | | | | | | | | |
| Government Provided Travel | | | $117,905 | | $128,898 | | $132,765 | | $136,748 | | $140,851 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Total CR Travel | | | $117,905 | | $128,898 | | $132,765 | | $136,748 | | $140,851 |
SAMPLE
CR Material
| OFFEROR NAME: | 0 | = Offeror Fill-In Cells |
| SOLICITATION NO.: | | = Gov't Provided Amounts; Do not change |
| PRICE MATRIX | | = Formulas; Do not change |
| CR-Material CLINs | | |
| Note: Indirect costs applicable to Material should be applied based upon the Offeror's established accounting practices. Additional rows may be added, if necessary | | |
| * INDIRECT RATES SHALL BE THE SAME AS PROPOSED ON THE CPFF LABOR RATE DETAIL TABS OF THIS WORKBOOK | | |
| CR Material | Application Base | Ordering Period 1 | | Ordering Period 2 | | Ordering Period 3 | | Ordering Period 4 | | Ordering Period 5 | |
| | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total |
| Description | | | | | | | | | | |
| Government Provided Material | | | $500,000 | | $515,000 | | $520,000 | | $525,000 | | $575,000 |
| Example: G&A | Total Cost Input | 12.00% | $60,000 | 12.50% | $64,375 | 11.90% | $61,880 | 12.00% | $63,000 | 12.30% | $70,725 |
| | | $0 | | $0 | | $0 | | $0 | | $0 |
| Total CR Material | | | $560,000 | | $579,375 | | $581,880 | | $588,000 | | $645,725 |
| Functional Area 1 | | | | | | | | | | | |
| CR (no fee) Material | Application Base | Ordering Period 1 | | Ordering Period 2 | | Ordering Period 3 | | Ordering Period 4 | | Ordering Period 5 | |
| | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total |
| Description | | | | | | | | | | |
| Government Provided Material | | | $1,234,000 | | $1,234,000 | | $1,234,000 | | $1,234,000 | | $1,234,000 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Total CR Material | | | $1,234,000 | | $1,234,000 | | $1,234,000 | | $1,234,000 | | $1,234,000 |
| Functional Area 2 | | | | | | | | | | | |
| CR (no fee) Material | Application Base | Ordering Period 1 | | Ordering Period 2 | | Ordering Period 3 | | Ordering Period 4 | | Ordering Period 5 | |
| | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total |
| Description | | | | | | | | | | |
| Government Provided Material | | | $1,945,000 | | $1,945,000 | | $1,945,000 | | $1,945,000 | | $1,945,000 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Total CR Material | | | $1,945,000 | | $1,945,000 | | $1,945,000 | | $1,945,000 | | $1,945,000 |
| Functional Area 3 | | | | | | | | | | | |
| CR (no fee) Material | Application Base | Ordering Period 1 | | Ordering Period 2 | | Ordering Period 3 | | Ordering Period 4 | | Ordering Period 5 | |
| | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total | Indirect Rate | Total |
| Description | | | | | | | | | | |
| Government Provided Material | | | $1,695,000 | | $1,695,000 | | $1,545,000 | | $1,945,000 | | $1,945,000 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Specify Indirect Rate | | | $0 | | $0 | | $0 | | $0 | | $0 |
| Total CR Material | | | $1,695,000 | | $1,695,000 | | $1,545,000 | | $1,945,000 | | $1,945,000 |
SAMPLE
Travel Matrix CONTRACTOR NAME: = Fill-In Cells
TRAVEL Matrix for Future Task Orders
Note: Travel is reimbursed at cost. Indirect rates applicable to Travel are reimbursed at cost. No profit/fee shall be proposed.
| DESCRIPTION OF COST ELEMENTS | | | | | | | | | | | | | |
| Travel Origin/Destination | Date(s) | Duration (Days) | # of Trips | Ppl/Trip | Airfare / Ticket | Car / Day | Lodging/Day | Per Diem/Day | Airfare | Car | Hotel | M&IE | Total Estimated Cost ($) |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Total Travel Costs | | | | | | | | | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
*Add more cells if needed.