DRAFT - Follow-On AWSM MA IDIQ - CONUS - Attachment 0003 - Zone 1 Pricing Attachment.xlsx

XLSX spreadsheet 44 KB Posted

Attached to
Follow-On Army Watercraft Sustainment Maintenance (AWSM) Program - DRAFT Solicitation - ZONE 1 - CONUS
Solicitation number
W912CH-25-R-0001
Issued by

About this file

This is a draft pricing template spreadsheet for Zone 1 (CONUS) of the Army Watercraft Sustainment Maintenance (AWSM) Multiple Award IDIQ contract, solicitation number W912CH-25-R-L001. The template requires offerors to input fully burdened labor rates (FBLR) for 17 labor categories including supervisors, machinists, welders, electricians, and other trades across 6 ordering years (5 full years plus 6-month option).

The spreadsheet includes government-provided estimates for material and Other Direct Costs (ODCs) totaling approximately $48.3M across all years, with individual yearly estimates ranging from $3M to $13.5M. Labor hours are pre-populated for each category and year, totaling approximately 528,511 hours in Year 1, with similar levels in most subsequent years. Offerors must propose ceiling rates for indirect costs and profit, as well as escalation factors for labor rates in future ordering years. The template calculates total proposed price based on labor rates, material/ODC costs, and proposed indirect and profit rates.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GFPM Cover

Army Watercraft Sustainment Maintenance (AWSM)

GOVERNMENT FORMAT PRICING MODEL

(GFPM)

SOLICITATION NO. W912CH-25-R-L001

ZONE 1 - CONUS

Offeror:

Cage:

DRAFT

Instructions to Offerors

Solicitation Number: W912CH-24-R-L001 (CONUS)
Attachment: 0003 - Zone 1 Pricing Attachment

INSTRUCTION TO OFFERORS

GFPM COVER:
Cells that require inputs are highlighted in Yellow
Each offeror is required to input its legal business entity name and Cage Code
INSTRUCTION TO OFFERORS:
*No Offeror inputs are required on this tab
Each Offeror is required to read the Instruction to Offerors
SUMMARY:
*No Offeror inputs are required on this tab
Do not adjust formulas or otherwise manipulate any of the non yellow cells
This Tab calculates the Total Proposed Price
Hours & Ceiling Rates:
*No Offeror inputs are required on this tab
Do not adjust formulas or otherwise manipulate any cells
This tab applies the Ceiling Fully Burdened Labor Rates proposed by the offeror against the Government provided labor hours to calculate the labor costs for the Total Proposed Price
These ceiling FBLRs will be incorporated into the contract as ceiling rates for use on future TO’s containing Over and Above CLINS.
Labor Rate Input:
Cells that require inputs are highlighted in Yellow
Do not adjust formulas or otherwise manipulate any of the non yellow cells
Each offeror is required to input its ceiling FBLR less profit for each labor category.
The ceiling FBLR less profit is inclusive of all direct labor, subcontract labor, indirect cost, labor uplifts (as applicable).
Each offeror is required to input its proposed profit ceiling rate.
Each offeror is required to input its proposed escalation rates
Ordering Years 2-6 will calculate the Ceiling FBLR based on a calculation of the previous ordering year Ceiling FBLR and the proposed escalation factor.
The escalation factor is intended to capture costs associated with increases in wages and industry inflation

If the offer has determined that labor costs in future periods will decrease the offeror may input 0% or a negative percentage.

Mat+ODC:
Cells that require inputs are highlighted in Yellow
Do not adjust formulas or otherwise manipulate any of the non yellow cells
For evaluation purposes only, the Government has provided an estimated cost for direct material and ODCs
Each Offeror is required to input proposed ceilings for Indirect Cost and Profit rates
The proposed indirect ceiling cost rate will be applied to the Government provided material estimate which calculates total indirect costs by year.
The proposed profit ceiling rate will be applied to both, the Government provided material estimate and the proposed indirect cost dollars to calculate total profit by year.

DRAFT

Summary

Solicitation Number: W912CH-24-R-L001 (CONUS)
Attachment: 0003 - Zone 1 Pricing Attachment
Summary - Total Proposed Price

Offeror: 0

Ordering YearFully Burdened Labor CostFully Burdened Material/ODCsTotal
Ordering Year 1$ - 0$ 13,530,735.69$ 13,530,735.69
Ordering Year 2$ - 0$ 11,268,452.96$ 11,268,452.96
Ordering Year 3$ - 0$ 4,435,851.40$ 4,435,851.40
Ordering Year 4$ - 0$ 8,021,648.90$ 8,021,648.90
Ordering Year 5$ - 0$ 7,977,683.60$ 7,977,683.60
Ordering Year 6 (6 Month Option)$ - 0$ 3,045,325.21$ 3,045,325.21

Zone 1 Total Proposed Price $ 48,279,697.76

Hours & Ceiling Rates

Solicitation Number: W912CH-24-R-L001 (CONUS)
Attachment: 0003 - Zone 1 Pricing Attachment
Zone 1 Labor Costs
Offeror:0
Labor CategoryLabor HoursFBLRExtended Price
Supervisor5,969.00$ - 0$ - 0
Outside Machinist24,869.00$ - 0$ - 0
Inside Machinist24,869.00$ - 0$ - 0
Pipefitter22,383.00$ - 0$ - 0
Shipfitter19,896.00$ - 0$ - 0
Welder27,130.00$ - 0$ - 0
Blaster/Painter83,934.00$ - 0$ - 0
General Laborer154,362.00$ - 0$ - 0
Electrician23,561.00$ - 0$ - 0
Shipboard Electronics Technician5,117.00$ - 0$ - 0
HVAC Technician2,984.00$ - 0$ - 0
Hydraulics Technician31,211.00$ - 0$ - 0
Carpenter3,220.00$ - 0$ - 0
Dockmaster11,821.00$ - 0$ - 0
Rigger30,536.00$ - 0$ - 0
Firewatch25,508.00$ - 0$ - 0
Production Support31,141.00$ - 0$ - 0
Total Ordering Year 1528,511.00- 0
Labor CategoryLabor HoursFBLRExtended Price
Supervisor5,906.00$ - 0$ - 0
Outside Machinist24,606.00$ - 0$ - 0
Inside Machinist24,606.00$ - 0$ - 0
Pipefitter22,146.00$ - 0$ - 0
Shipfitter19,685.00$ - 0$ - 0
Welder26,843.00$ - 0$ - 0
Blaster/Painter83,046.00$ - 0$ - 0
General Laborer152,729.00$ - 0$ - 0
Electrician23,311.00$ - 0$ - 0
Shipboard Electronics Technician5,063.00$ - 0$ - 0
HVAC Technician2,953.00$ - 0$ - 0
Hydraulics Technician35,433.00$ - 0$ - 0
Carpenter5,715.00$ - 0$ - 0
Dockmaster11,696.00$ - 0$ - 0
Rigger30,212.00$ - 0$ - 0
Firewatch25,238.05$ - 0$ - 0
Production Support30,811.00$ - 0$ - 0
Total Ordering Year 2529,999.05- 0
Labor CategoryLabor HoursFBLRExtended Price
Supervisor4,400.00$ - 0$ - 0
Outside Machinist18,334.00$ - 0$ - 0
Inside Machinist18,334.00$ - 0$ - 0
Pipefitter16,501.00$ - 0$ - 0
Shipfitter14,667.00$ - 0$ - 0
Welder20,001.00$ - 0$ - 0
Blaster/Painter61,877.00$ - 0$ - 0
General Laborer113,798.00$ - 0$ - 0
Electrician17,369.00$ - 0$ - 0
Shipboard Electronics Technician3,773.00$ - 0$ - 0
HVAC Technician2,200.00$ - 0$ - 0
Hydraulics Technician26,401.00$ - 0$ - 0
Carpenter4,258.00$ - 0$ - 0
Dockmaster8,714.00$ - 0$ - 0
Rigger22,511.00$ - 0$ - 0
Firewatch18,804.75$ - 0$ - 0
Production Support22,957.00$ - 0$ - 0
Total Ordering Year 3394,899.75- 0
Labor CategoryLabor HoursFBLRExtended Price
Supervisor6,327.00$ - 0$ - 0
Outside Machinist26,363.00$ - 0$ - 0
Inside Machinist26,363.00$ - 0$ - 0
Pipefitter23,727.00$ - 0$ - 0
Shipfitter21,091.00$ - 0$ - 0
Welder28,760.00$ - 0$ - 0
Blaster/Painter88,976.00$ - 0$ - 0
General Laborer163,635.00$ - 0$ - 0
Electrician24,976.00$ - 0$ - 0
Shipboard Electronics Technician5,425.00$ - 0$ - 0
HVAC Technician3,164.00$ - 0$ - 0
Hydraulics Technician37,963.00$ - 0$ - 0
Carpenter5,276.00$ - 0$ - 0
Dockmaster12,321.00$ - 0$ - 0
Rigger32,370.00$ - 0$ - 0
Firewatch27,040.00$ - 0$ - 0
Production Support33,011.00$ - 0$ - 0
Total Ordering Year 4566,788.00- 0
Labor CategoryLabor HoursFBLRExtended Price
Supervisor5,969.00$ - 0$ - 0
Outside Machinist24,869.00$ - 0$ - 0
Inside Machinist24,869.00$ - 0$ - 0
Pipefitter22,383.00$ - 0$ - 0
Shipfitter19,896.00$ - 0$ - 0
Welder27,130.00$ - 0$ - 0
Blaster/Painter83,934.00$ - 0$ - 0
General Laborer154,362.00$ - 0$ - 0
Electrician23,561.00$ - 0$ - 0
Shipboard Electronics Technician5,117.00$ - 0$ - 0
HVAC Technician2,984.00$ - 0$ - 0
Hydraulics Technician31,211.00$ - 0$ - 0
Carpenter3,220.00$ - 0$ - 0
Dockmaster11,821.00$ - 0$ - 0
Rigger30,536.00$ - 0$ - 0
Firewatch25,508.00$ - 0$ - 0
Production Support31,141.00$ - 0$ - 0
Total Ordering Year 5528,511.00- 0
Labor CategoryLabor HoursFBLRExtended Price
Supervisor3,016.60$ - 0$ - 0
Outside Machinist12,568.80$ - 0$ - 0
Inside Machinist12,568.80$ - 0$ - 0
Pipefitter11,312.10$ - 0$ - 0
Shipfitter10,055.20$ - 0$ - 0
Welder13,711.50$ - 0$ - 0
Blaster/Painter42,419.90$ - 0$ - 0
General Laborer78,014.00$ - 0$ - 0
Electrician11,907.00$ - 0$ - 0
Shipboard Electronics Technician2,586.00$ - 0$ - 0
HVAC Technician1,508.30$ - 0$ - 0
Hydraulics Technician18,099.20$ - 0$ - 0
Carpenter2,919.20$ - 0$ - 0
Dockmaster5,974.20$ - 0$ - 0
Rigger15,432.50$ - 0$ - 0
Firewatch12,891.50$ - 0$ - 0
Production Support15,738.30$ - 0$ - 0
Total Ordering Year 6 (6 Month Option)270,723.10- 0

Labor Rate Input

Solicitation Number: W912CH-24-R-L001 (CONUS)
Attachment: 0003 - Zone 1 Pricing Attachment
Fully Burdened Labor Rates (FBLR)
Offeror:0
Profit Ceiling Rate
Labor CategoryEscalation
OY 1OY 1OY 2OY 3OY 4OY 5OY 6 (6 Month Option)
FBLR Less ProfitFBLRFBLRFBLRFBLRFBLRFBLR
Supervisor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Outside Machinist$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Inside Machinist$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Pipefitter$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Shipfitter$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Welder$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Blaster/Painter$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
General Laborer$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Electrician$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Shipboard Electronics Technician$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
HVAC Technician$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Hydraulics Technician$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Carpenter$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Dockmaster$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Rigger$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Firewatch$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Production Support$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

DRAFT

Mat + ODC

Solicitation Number: W912CH-24-R-L001 (CONUS)
Attachment: 0003 - Zone 1 Pricing Attachment
Zone 1 Fully Burdened Material & ODC
Offeror:0
Material & Other Direct Costs (ODC)OY 1OY 2OY 3OY 4OY 5OY 6 (6 Month Option)
Government Provided
Material/ODC Cost EstimateGovernment Provided
Material/ODC Cost EstimateGovernment Provided
Material/ODC Cost EstimateGovernment Provided
Material/ODC Cost EstimateGovernment Provided
Material/ODC Cost EstimateGovernment Provided

Material/ODC Cost Estimate $ 13,530,735.69 $ 11,268,452.96 $ 4,435,851.40 $ 8,021,648.90 $ 7,977,683.60 $ 3,045,325.21

Indirect Cost $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0

Profit$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Material Cost by Year$ 13,530,735.69$ 11,268,452.96$ 4,435,851.40$ 8,021,648.90$ 7,977,683.60$ 3,045,325.21
Indirect Ceiling Rate
Profit Ceiling Rate

File details come from the government source that posted it. Updated .