DRAFT C26-015 High Pressure Air Compressor - SOWv3_Redacted.pdf
PDF 1 MB Posted
- Attached to
- High Pressure Air Compressor
- Solicitation number
- C26-015
About this file
This is a Statement of Work (SOW) for the delivery, installation, and commissioning of a High-Pressure Air Compressor (C26-015) for the 76th Consolidated Maintenance Wing (CMXG) at Tinker Air Force Base, Oklahoma. The work must be completed within 10 business days of delivery. The contractor shall provide all labor, equipment, parts, incidentals, consumables, and transportation necessary to deliver and install the compressor.
The compressor must be a Typhoon Series WP3100 or similar model with the following specifications: rated for continuous duty, minimum 110 Standard Cubic Feet per Minute (SCFM) free air supply at 750-1000 PSI pressure, configurable to regulate at 750 PSI output pressure, operating on 460 VAC 3-phase 60 Hz power, water-cooled compatible with existing chilled water systems, no larger than 60" wide by 108" long by 72" height, and weighing less than 6,000 pounds. The compressor controller must communicate via Modbus TCP, and the contractor must supply a list of Modbus registers. The unit must include a lifetime warranty. Installation requires the contractor to deliver and position the compressor in a designated location, provide and install electrical equipment per the National Electrical Code (NEC), and connect air piping in accordance with ASME B31.1. The contractor must also perform startup and commissioning, provide on-site basic training covering operation and maintenance on the same day as commissioning, and serve as a factory-authorized distributor and repair center for the compressor model supplied. Work hours are Monday through Friday, 6:00 AM to 1:00 PM, with approval required for any work outside these hours. The SOW includes extensive on-base requirements covering environmental protection, hazardous materials management, safety protocols, FOD/DOP training, housekeeping standards, visitor pass procedures, and emergency procedures compliance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DRAFT C26-015 High Pressure Air Compressor - Item Description_v3_Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
For
C26-015 High Pressure Air Compressor
PREPARED BY:
OC-ALC/OBCA
3 November 2025
DRAFT
(7) Must be a water-cooled unit that will work with existing chilled water system.
(8) Must be no larger than 60” wide by 108” long by 72” height.
(9) Must weigh less than 6,000 pounds.
(10) Dimensions and weight must be such that the installation crew can lower the machine by crane, move into place, and install the equipment at the designated site in the without having to move or disassemble any major mechanical equipment in the surrounding area.
(11) Controller must be capable of communicating via Modbus TCP.
(12) Contractor must supply a list of Modbus registers and what they are/represent.
(13) Must include lifetime warranty
(14) Contractor must deliver, move, and install the compressor in the in the location specified by the government, and provide necessary electrical and piping equipment to connect to existing electrical, air, and cooling water utilities. In accordance with the Statement of Work, Section 3.2.
(15) Contractor must provide startup and commissioning and training by a qualified technician.
3. Shipping Instructions – Compressor shall be shipped to: , Tinker AFB, 73145
3. Shipping Instructions – Compressor shall be shipped to: , Tinker AFB, 73145
3.2 Installation -- The Contractor shall be responsible for equipment delivery to and installation at at Tinker AFB, OK 73145. The contractor shall:
• Deliver, move, and install the compressor in the in the location specified by the government.
• Provide and install necessary electrical equipment needed to connect compressor to existing electrical disconnect switch on south wall per latest version of NEC.
• Provide and install necessary piping equipment to connect compressor to existing facility high pressure air system, cooling water supply and return lines, and drain lines.
All electrical and air piping work shall be performed in accordance with the latest edition of the National Electrical Code (NEC), and all applicable local amendments. Air piping shall be installed in accordance with ASME B31.1 and the manufacturer's recommendations for the air compressor model.
3.3 Startup and Commissioning – Contractor shall perform startup and commissioning of the High-Pressure Air Compressor.
3.4 Training – Contractor shall provide basic training on-site at Tinker Air Force Base on the same day as startup and commissioning. Training shall cover operation and maintenance of the compressor.
3.5 Special Qualifications - Contractor must be a distributor of parts and factory repair certified for the compressor system they provide.
4. GENERAL REQUIREMENTS
4.1 Hours of Operation – The Contractor shall perform the work required under this contract during the following days and hours: Monday through Friday, 6:00 am -1:00 pm.
If work hours are required outside the hours stated, the Contractor shall contact the Government POC for approval from the CO. Upon approval from the CO, the Government Subject Matter Expert (SME) or Government POC must be present with the Contractor.
These dates and hours exclude Federal Holidays, base closures due to inclement weather, and furlough days, as applicable.
5.0 On-Base Requirements
5.1 Environmental Protection & Safety: The Contractor shall be knowledgeable of and comply with all applicable federal, state, and local laws, regulations, instructions and requirements regarding environmental protection and occupational safety and health. The Contractor shall comply with any laws, instructions, or regulation changes during the term of this contract.
Contractors shall be compliant Tinker Air Force Base (TAFB) Supplement to Air Force Instruction (AFI) 32-7086, “Hazardous Materials Management”, Tinker AFB procedures per Tinker Air Force Base Hazardous Waste Management Plan (TAFB HWMP), and Complex procedures per Oklahoma City Air Logistics Complex (OC- ALC) Sup to AFI 32-7086, “Hazardous Material Management” and OC-ALCI 32-101 “Air Quality Record Keeping Procedure”. Publications are available digitally on e- Publishing website at www.e-publishing.af.mil for downloading or ordering.
5.1.2 Hazardous Material (HAZMAT): If no HAZMAT will be brought on base or used in performance on this contract, the Contractor shall certify “No HAZMAT will be brought on base” or “No HAZMAT Usage” by official correspondence. This certification shall be provided to the COR within ten (10) days after award. Upon COR receipt of the certification, the requirements of this section no longer apply.
Appropriate penalties for the Contractor, or administrative and disciplinary action for the later shall be assessed if found in violation of above certification.
The Contractor shall not store chemicals or hazardous material (HAZMAT) on Tinker AFB. Contractors shall be compliant with HAZMAT management procedures per Oklahoma City Air Logistics Complex (OC-ALC) Supplement to AFI 32-7086, “Hazardous Materials Management”. The Contractor shall maintain a log of all HAZMAT that is used on base. This usage log shall be provided to the COR monthly, the last business day of each month, or when the required work is completed. The COR will forward the records to the Unit Environmental Coordinator (UEC) no later than the fourth (4th) day of the following month or the first (1st) subsequent business day.
5.1.3 Safety Data Sheet (SDS) and Labeling: Upon COR receipt of the “No HAZMAT Usage” certification, the requirements of this section no longer apply.
The Contractor shall not transport, ship, or use any chemical, material or substance used in the performance of this PWS on Tinker AFB before written approval is provided by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). The Contractor shall submit to the COR, ten (10) calendar days after contract award date all Safety Data Sheets (SDSs) and a completed OC-ALC Form 152, SDS Information Sheet. The Contractor shall receive approval from the COR prior to shipping any chemical, material, or substance to Tinker AFB. A copy of the manufacturer SDS shall accompany the shipment. Contractor shall comply with the effective dates for SDS requirements IAW the Occupational Safety and Health Administrations (OSHA) Hazardous Communication Standard, Title 29, Code of Federal Regulation (CFR) Part 1910.1200. The Contractor shall ensure containers of hazardous chemicals are labeled with the following information, prior to shipping to Tinker AFB IAW OSHA Hazardous Communication Standard, Title 29, CFR Part
1910.1200 (2012): product identifier; signal word; hazard statement(s); precautionary statement(s); pictogram(s); and name, address and telephone number of the chemical manufacturer, importer, or other responsible party. The COR will forward all SDS submittals to 72 ABW/CEIE for approval. A current manufacturer SDS shall be submitted to the COR if the Contractor changes manufacturer or vendor for any chemicals that were prior approved. The Contractor shall maintain copies of manufacturer SDSs for all chemicals and SDSs shall be readily accessible at all times by Contractor personnel as well as government employees.
5.1.4 Hazardous Waste: If no HAZWASTE will be generated during performance of this contract, the Contractor shall certify “NO Hazardous Waste Generation” by official correspondence. This certification shall be provided to the COR within ten
(10) days after award. Upon COR receipt of the “No Hazardous Waste Generation” certification, the requirements of this section no longer apply. Appropriate penalties for the Contractor, or administrative and disciplinary action for the later shall be assessed if found in violation of above certification.
The Contractor shall dispose of contaminated solid waste, spent or processed chemical solutions, used rags and hazardous waste in government furnished waste containers located in the shop or area the work is being performed. The Contractor shall notify the COR if the required waste containers are not available on site.
5.1.5 Discharges: Any discharges into Tinker’s industrial waste treatment plant (IWTP) or sanitary sewer shall be approved and done IAW Tinker Industrial Wastewater Discharge Permit as instructed by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). Notice of intent documentation shall be provided to the COR within ten (10) days after award. The COR will submit the required notice of intent documentation to the UEC for 72 ABW/CEIE approval. The Contractor shall not discharge into IWTP and sanitary sewer prior to approval issued by 72 ABW/CEIE. The Contractor shall maintain records of written approval issued by 72 ABW/CEIE for discharges into IWTP and sanitary sewer.
5.1.6 Off-Site Discharges: For discharges outside of Tinker AFB, the Contractor shall ensure wastewater discharges, that may contain pollutants resulting from any contracted service, go to a state or federal permitted treatment facility such as a municipal Publicly Owned Treatment Works (POTW). The Contractor shall provide official correspondence ten (10) calendar days after contract award date to the COR from the POTW that states the POTW is permitted for all pollutants that the Contractor may discharge during the contracted service.
5.1.7 Spills: Upon occurrence of any spill that could enter the storm system or cause any harmful environment effects, the Contractor shall immediately call 911 to report the incident. When possible, the Contractor shall use a base telephone to receive help from Tinker AFB 911. If using a cell phone, the Contractor shall request Tinker AFB
911. The Contractor shall immediately report all environmental violations to the COR and UEC. The Contractor shall provide five (5) copies of a typed or written report about the incident within four (4) clock hours as follows:
One (1) copy to CO, two (2) copies to the COR, a copy for UEC and one (1) copy for record. The format of the report shall be left up to the Contractor, but the report shall contain the following information:
1.) Name and contact number of person reporting the spill 2.) Date and time of incident 3.) Location and source of spill 4.) Substance or pollutant spilled 5.) Amount spilled and rate of discharge 6.) Any damages or injuries involved 7.) Extent of area impacted 8.) Potential hazards 9.) Actions taken 10.) Organizations contacted 11.) Remarks Section - that addresses the cause of the spill (e.g. human error, equipment, etc.) and whether 911 was called and which agencies responded.
5.1.8 Environmental Training: Upon COR receipt of the “No Hazardous Waste Generation” certification, the requirements of this section no longer apply.
Contractor personnel performing duties in the service of this PWS shall have training that acquaints the person with the details of Resource Conservation Recovery Act (RCRA) regulations in 40 CFR 260 through 279; applicable State Laws and regulations; DoD, Air Force and local requirements. This training can be obtained through creditable training institutions or companies. All training shall be approved by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). RCRA training is available at http://www.natlenvtrainers.com/RCRA-hazardous-waste.htm;
http://www.skillsoft.com/catalog/detail.asp?CourseCode=esh_sah_a34_sh_enus00000 0 and http://www.lion.com/Storing-Hazardous-Waste-for-LQGs at the Contractor’s expense. Prior to obtaining training, the Contractor shall provide the name of the training institution or company and course description to the COR for approval within ten (10) calendar days after contract award date. Once written approval is received from the COR, the Contractor shall provide the environmental training certificates for employees performing duties in the service of this PWS to the COR, within thirty (30) calendar days after contract award date. In addition to the required environmental training, Contractors shall be compliant with Tinker AFB procedures per TAFB HWMP, “Hazardous Waste Management”.
5.2 Reserved
5.3 Housekeeping: The Contractor shall keep the work areas clean and neat IAW industry standards, OSHA, fire and safety standards, and this SOW.
5.4 Foreign Object Damage (FOD) and Dropped Object Prevention: Contractor personnel who work in or travel though areas near operational and production aircraft, engines, munitions, missiles, drones, space systems, support equipment, Aerospace Ground Equipment (AGE), trainers, and the Contactor personnel operating vehicles and equipment on flight lines, runways, taxiways, parking ramps, and in aircraft hangers and maintenance areas are required to receive the FOD/DOP training and to comply with AFI 36-2650, AFMC Supplement 1, paragraph 9.2., and A4.4.4. (Initial)/A4.4.5. (Refresher).
The Contractor and Contractor personnel shall acknowledge the FOD/DOP training either by viewing the Digital Versatile Disc (DVD) provided by the GPOC or the You Tube site, http://www.youtube.com/watch?v=tYcbodjFPnM.
5.4.1 The Contract Manager shall provide written certification to the GPOC for each employee within ten (10) business days after the contract award date. The certification shall have the title of the training, the name of the person who received the training, and the date of the training. The Contractor shall also ensure all new employees view the FOD/DOP training and provide written certification of training to the GPOC prior to the employees starting work in the OC-ALC shops. Every 36 Months, the Contractor and Contractor personnel shall be required to review the FOD/DOP training and to provide written certification to the GPOC.
5.5 Tool Control and Accountability: N/A (if applicable)
5.6 Privately Owned Motor Vehicles (POV): Contractor personnel shall comply with the directives pertaining to operation of POVs on Tinker AFB per AFMAN 31-116, in its
Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each Contractor and government employee.
5.12 Speak up for safety: Safety surety is an integral part of our overall goal of establishing a world class safety and health program. Our “Speak Out for Safety” initiative ensures a partnership with Contractors and government employees to further enhance safety to ensure we are looking out for all our partners and empowers all employees to actively participate in each other’s safety.
A safe workplace is everyone's business. As part of the contract team, military, civilian and Contractor personnel are empowered to Speak Out for Safety (S.O.S.) when they observe an unsafe act. Events that present imminent danger to personnel or catastrophic damage to property we empower our employees to intercede to ensure continued safe operations.
5.13 Communicating Hazards Of Workplace (CHOW): Contractor’s onsite representative communicates all hazards being introduced to the worksite by the Contractor. This is accomplished prior to commencement of work and refreshed daily during performance, IAW Contractor’s Site Safety Plan.
5.14 Emergency Procedures: The Contractor personnel shall follow the direction of the Government personnel with regard to emergency procedures, such as fire, tornado, active shooter, bomb threats, or other emergency. It is the responsibility of the Contractor to provide guidance and to establish procedures for its employees to respond to an emergency. It is the Contractor’s responsibility to account for their employees following an emergency evacuation. The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.
File details come from the government source that posted it. Updated .