DRAFT 03 Package 3 (RFP Reference Documents - Specifications).pdf
PDF 24 MB Posted
- Solicitation number
- LBNF-ND-350921-BWQ
About this file
The document provided is a draft Request for Proposals (RFP) for the Fermilab LBNF NSCF Construction - Near Detector Complex project. The RFP includes Instructions to Offerors, Drawings, Specifications, and a Sample Subcontract. The project scope involves construction services for the Near Detector Complex, including a service building, primary and secondary shafts, detector cavern, and site improvements. FRA expects to select one subcontractor to perform the work on a Firm Fixed Price (FFP) basis. The RFP specifies a mandatory pre-proposal conference on July 10, 2024, and a question submission deadline of August 8, 2024. Proposals shall be valid up to the anticipated award date, which is 7 months from the proposal due date. FRA reserves the right to reject any and all proposals and will not reimburse firms for any preparation costs.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Package 3: RFP Reference Documents (Specifications) Request for Proposal FRA RFP No. LBNF-ND-350921-BWQ Near Detector Complex Construction
REQUEST FOR PROPOSAL
FRA RFP NO. LBNF-ND-350921-BWQ
for the Construction of the
Long-Baseline Neutrino Facility (LBNF)
Near Site Conventional Facilities (NSCF)
Near Detector Complex Construction
Package No. 3 of 4:
RFP REFERENCE DOCUMENTS (SPECIFICATIONS)
Package 3: RFP Reference Documents (Specifications) Near Detector Complex Construction
THIS PAGE INTENTIONALLY LEFT BLANK
Request for Proposal FRA RFP No. LBNF-ND-350921-BWQ
TABLE OF CONTENTS
Request for Proposal (FRA RFP No. LBNF-ND-350921-BWQ) Package No. 3 of 4
• Technical Specifications
ENCLOSED FOR REFERENCE/BASIS FOR PROPOSAL – DO NOT RETURN
o NSCF Final Design - Specifications Booklet – Part 1 o NSCF Final Design - Specifications Booklet – Part 2
Technical Specifications
ENCLOSED FOR REFERENCE/BASIS FOR PROPOSAL – DO NOT RETURN
Site Preparation Package - 60% Design Report AECOM
Fermi National Accelerator Laboratory 1
303 E. Wacker Drive, Suite 1400
Chicago IL 60601
(312) 373-7700
NSCF Final Design
Issued For Solicitation
Specifications Booklet – Part 1
Long-Baseline Neutrino Facility
Near Site Conventional Facilities
Fermi Research Alliance, LLC
FRA Project Number: 6-15-12 Near Detector Complex
AECOM Project Number: 60633857
May 20, 2024
ISSUED FOR SOLICITATION
TABLE OF CONTENTS - 1
Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING DOCUMENTS GROUP
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SPECIFICATIONS GROUP
General Requirements Subgroup
DIVISION 01 - GENERAL REQUIREMENTS
01 00 10 GENERAL REQUIREMENTS
01 23 00 ALTERNATES
01 25 00 SUBSTITUTION PROCEDURES
01 26 00 CONTRACT MODIFICATION PROCEDURES
01 29 00 INVOICING PROCEDURES
01 30 00 PROJECT MANAGEMENT AND COORDINATION
01 31 00 ENVIRONMENTAL SAFETY AND HEALTH REQUIREMENTS
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION
01 32 33 PHOTOGRAPHIC DOCUMENTATION
01 32 50 INSTRUMENTATION
01 33 00 SUBMITTALS
01 41 00 QUALITY REQUIREMENTS
01 41 20 SEISMIC AND WIND REQUIREMENTS
01 42 20 REFERENCES
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 56 39 TEMPORARY TREE AND PLANT PROTECTION
01 57 15 CONSTRUCTION VIBRATION MONITORING AND CONTROL
01 60 00 PRODUCT REQUIREMENTS
01 73 00 EXECUTION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 77 00 CLOSEOUT PROCEDURES
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 39 PROJECT RECORD DOCUMENTS
01 79 00 DEMONSTRATION AND TRAINING
01 91 13 GENERAL COMMISSIONING REQUIREMENTS
Facility Construction Subgroup
DIVISION 02 - EXISTING CONDITIONS
02 01 20 PROTECTING EXISTING UNDERGROUND UTILITIES
02 01 30 CONNECTIONS TO EXISTING BURIED PIPELINES
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
TABLE OF CONTENTS - 2
Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
03 34 00 CONTROLLED LOW STRENGTH MATERIAL
03 41 00 PRECAST STRUCTURAL CONCRETE
DIVISION 04 - MASONRY
04 22 00 CONCRETE UNIT MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL FRAMING
05 31 00 STEEL DECKING
05 40 00 COLD-FORMED METAL FRAMING
05 50 00 METAL FABRICATIONS
05 51 13 METAL PAN STAIRS
05 51 16 METAL PLATE STAIRS
05 51 19 METAL GRATING STAIRS
05 51 20 MODULAR ALUMINUM RAMP
05 52 13 PIPE AND TUBE RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 16 00 SHEATHING
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 00 THERMAL INSULATION
07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 42 13.16 FORMED METAL WALL PANELS
07 42 13.19 INSULATED METAL WALL PANELS
07 54 23 THERMOPLASTIC-POLYOLEFIN (TPO) ROOFING
07 62 00 SHEET METAL FLASHING AND TRIM
07 71 00 ROOF SPECIALTIES
07 72 00 ROOF ACCESSORIES
07 81 00 APPLIED FIRE PROTECTION
07 84 00 FIRESTOPPING
07 90 05 JOINT SEALERS
DIVISION 08 - OPENINGS
08 11 13 HOLLOW METAL DOORS AND FRAMES
08 31 13 ACCESS DOORS AND FRAMES
08 33 23 OVERHEAD COILING DOORS
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 71 11 DOOR HARDWARE
08 71 11.1 DOOR HARDWARE SCHEDULE
08 80 00 GLASS AND GLAZING
08 91 19 FIXED LOUVERS
DIVISION 09 - FINISHES
09 22 16 NON-STRUCTURAL METAL FRAMING
09 29 00 GYPSUM BOARD
09 65 13 RESILLIENT BASE AND ACCESSORIES
09 90 00 PAINTING AND COATING
TABLE OF CONTENTS - 3
Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
DIVISION 10 - SPECIALTIES
10 14 23 PANEL SIGNAGE
10 44 00 FIRE PROTECTION SPECIALTIES
DIVISION 11 - EQUIPMENT
11 24 00 FALL PROTECTION
DIVISION 14 - CONVEYING EQUIPMENT
14 21 23.20 ELECTRIC RACK AND PINION ELEVATOR
Facility Services Subgroup
DIVISION 21 - FIRE SUPPRESSION
21 05 17 SLEEVES AND SLEEVE SEALS FOR PIPING
21 05 18 ESCUTCHEONS FOR FIRE-SUPPRESSION PIPING
21 05 23 GENERAL-DUTY VALVES FOR FIRE PROTECTION PIPING
21 05 53 IDENTIFICATION FOR PIPING AND EQUIPMENT
21 08 00 COMMISSIONING OF FIRE SUPRESSION
21 11 19 FIRE DEPARTMENT CONNECTIONS
21 12 00 FIRE SUPPRESSION STANDPIPES
21 13 13 WET-PIPE SPRINKLER SYSTEMS
21 13 16 DOUBLE INTERLOCK PREACTION SPRINKLER SYSTEMS
DIVISION 22 - PLUMBING
22 05 13 COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT
22 05 16 EXPANSION FITTINGS AND LOOPS FOR PLUMBING
22 05 17 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
22 05 18 ESCUTCHEONS FOR PLUMBING PIPING
22 05 19 METERS AND GAUGES FOR PLUMBING PIPING
22 05 23 GENERAL-DUTY VALVES FOR PLUMBING
22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
22 05 48 VIBRATION FOR PLUMBING PIPING AND EQUIPMENT
22 05 53 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
22 07 19 PLUMBING PIPING INSULATION
22 08 00 COMMISSIONING OF PLUMBING
22 11 16 INDUSTRIAL COLD WATER PIPING
22 11 19 INDUSTRIAL COLD WATER PIPING SPECIALTIES
22 11 23 FACILITY – NATURAL GAS PIPING
22 13 16 DRAINAGE PIPING
22 13 19 DRAINAGE PIPING SPECIALTIES
22 13 19.13 BUILDING DRAINS
22 14 29 SUMP PUMPS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 13 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
23 05 16 EXPANSION FITTINGS FOR HVAC PIPING
23 05 18 ESCUTCHEONS FOR HVAC PIPING
23 05 19 METERS AND GAGES FOR HVAC PIPING
23 05 23 VALVES FOR HVAC PIPING
23 05 29 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
TABLE OF CONTENTS - 4
Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
23 05 48 VIBRATION CONTROL FOR HVAC
23 05 53 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 13 DUCT INSULATION
23 07 16 HVAC EQUIPMENT INSULATION
23 07 19 HVAC PIPING INSULATION
23 08 00 COMMISSIONING OF HVAC
23 09 23 DIRECT DIGITAL CONTROL SYSTEM AND DEVICES FOR HVAC
23 09 93 SEQUENCE OF OPERATIONS FOR HVAC DDC
23 09 95 DATA AND CONTROL POINTS LIST
23 21 13 HYDRONIC PIPING
23 21 16 HYDRONIC PIPING SPECIALTIES
23 21 23 HYDRONIC PUMPS
23 31 13 METAL DUCTS
23 33 00 AIR DUCT ACCESSORIES
23 33 46 FLEXIBLE DUCTS
23 34 13 HVAC FANS
23 37 13 AIR DIFFUSTERS, REGISTERS AND GRILLES
23 41 00 PARTICULATE AIR FILTRATION
23 55 23.13 LOW-INTENSITY, GAS-FIRED, RADIANT HEATERS
23 57 00 HEAT EXCHANGERS FOR HVAC
23 64 26.13 AIR-COOLED ROTARY-SCREW WATER CHILLERS
23 73 13 INDOOR CUSTOM AIR-HANDLING UNITS
23 73 43 OUTDOOR CUSTOM AIR-HANDLING UNITS
23 81 23 COMPUTER ROOM AIR CONDITIONING UNITS
23 82 39 PROPELLER UNIT HEATERS
DIVISION 26 - ELECTRICAL
26 05 10 ELECTRICAL WORK – GENERAL
26 05 13 MEDIUM VOLTAGE CABLE
26 05 20 ELECTRIC WIRES AND CABLES
26 05 26 GROUNDING BONDING FOR ELECTRICAL SYSTEMS
26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
26 05 34 METAL ENCLOSED CABLE BUS SYSTEM
26 05 36 CABLE TRAYS FOR ELECTRICAL SYSTEMS
26 05 43 UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS
26 05 44 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING
26 05 53 ELECTRICAL IDENTIFICATION
26 05 70 ELECTRICAL SYSTEM STUDIES
26 05 90 ELECTRICAL CONTROLS AND MISCELLANEOUS ELECTRICAL EQUIPMENT
26 08 00 COMMISSIONING OF ELECTRICAL SYSTEMS
26 08 13 FIELD INSPECTION AND ACCEPTANCE TESTS
26 09 13 ELECTRICAL POWER MONITORING AND CONTROL
26 09 23 LIGHTING CONTROL DEVICES
26 12 19 PAD MOUNTED TRANSFORMERS
26 13 03 MEDUIM VOLTAGE PADMOUNTED SWITCHGEAR
26 13 13 MEDIUM VOLTAGE CIRCUIT BREAKER SWITCHGEAR
26 20 00 ELECTRIC MOTORS
26 22 13 LOW VOLTAGE DISTRIBUTION TRANSFORMERS
TABLE OF CONTENTS - 5
Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
26 22 14 DRY TYPE TRANSFORMERS
26 24 13 LOW VOLTAGE SWITCHBOARDS
26 24 16 PANELBOARDS
26 27 26 WIRING DEVICES
26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
26 29 13 ENCLOSED CONTROLLERS
26 29 23 VARIABLE FREQUENCY MOTOR CONTROLLERS
26 32 13 ENGINE GENERATORS
26 36 00 TRANSFER SWTICHES
26 41 13 LIGHTNING PROTECTION FOR STRUCTURES
26 43 00 SURGE PROTECTION DEVICES
26 50 00 INTERIOR LIGHTING
26 52 13 EMERGENCY AND EXIT LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 13 23 OPTICAL FIBER BACKBONE CABLING
27 13 43 COMMUNICATION SERVICES CABLING
27 53 19 DISTRIBUTED ANTENNA SYSTEM (DAS)
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 15 00 ACCESS CONTROL HARDWARE DEVICES
28 20 00 VIDEO SURVEILLANCE
28 31 00 FIRE & EMERGENCY VOICE ALARM SYSTEM
Site and Infrastructure Subgroup
DIVISION 31 - EARTHWORK
31 10 00 SITE CLEARING
31 22 00 GRADING
31 23 00 EXCAVATION AND FILL
31 23 19 DEWATERING
31 23 33 TRENCHING AND BACKFILL
31 25 13 EROSION AND SEDIMENT CONTROL
31 70 05 BLASTING
31 71 19 UNDERGROUND ROCK EXCAVATION
31 71 20 REMOVAL AND TREATMENT OF CAVERN CONSTRUCTION WATER
31 71 30 TEMPORARY SHAFT AND CAVERN VENTILATION AND UTILITIES
31 71 35 MUCK AND EXCAVATED MATERIAL DISPOSAL
31 72 13 ROCK REINFORCEMENT AND INITIAL SUPPORT
31 72 15 SHOTCRETE
31 72 17 SPRAY APPLIED WATERPROOFING MEMBRANE
31 73 19 SHAFT AND CAVERN GROUTING
31 75 05 SHAFT CONSTRUCTION
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 00 FLEXIBLE PAVING
32 15 45 GRAVEL ROADWAY
32 31 13 CHAIN LINK FENCES AND GATES
TABLE OF CONTENTS - 6
Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
32 35 16 ACOUSTICAL BARRIER WALL
32 90 00 SITE RESTORATION
DIVISION 33 - UTILITIES
33 00 00 SITE UTILITY SYSTEMS
33 40 00 STORM DRAINAGE UTILITIES
DIVISION 40 and 41 – SPECIALTIES
41 22 13.13 BRIDGE CRANES
41 22 23 MONORAIL AND HOIST SYSTEM
END OF TABLE OF CONTENTS
GENERAL REQUIREMENTS
01 00 10 - 1
May 20, 2024 Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
SECTION 01 0010 – GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 RELATED DOCUMENTS
Drawings and general provisions of the Subcontract, including General and Supplementary Conditions and other Division 01 Specification sections apply to this section.
1.2 PURPOSE
The Subcontractor is required to plan, control, and deliver the Work according to the Construction Drawings and Construction Specifications incorporated into the subcontract. The Project must possess complete, functional systems that conform to the Construction Specifications, industry standards, and regulatory requirements and must be assembled safely and in a workmanlike manner according to industry standards, requirements, and best practices. In the event of conflict, the Subcontractor shall comply with the more stringent requirement.
1.3 SUMMARY
The Subcontractor shall include all labor, materials, equipment, transportation, services, occupational exposure monitoring and supervision required to maintain project work sites that meet the ES&H requirements found in Section 01 31 00.
The Subcontractor shall utilize its knowledge and experience to anticipate, and include in the cost of the Work any work which may be required or reasonably inferred from the Construction Specifications and Construction Drawings, but are not specifically expressed herein, in order to provide a complete and fully functional facility and/or system.
1.4 REFERENCES
SECTION 01 42 20 – References.
1.5 SITE LOCATION
The Subcontractor shall confine all operations (including storage of materials) within the project area.
The project is located on the Fermi National Accelerator Laboratory (Fermilab) Site, adjacent to the city of Batavia, Illinois, within Kane County. Within Fermilab, the project is situated on the north and west side of the Main Injector Ring. Access to the site is via the Kautz Rd construction gate on Rt 56 (Butterfield Rd), along Kautz Rd north to Indian Creek Rd.
1.6 PROJECT INFORMATION
Project Identification: NSCF Beamline Complex, Project 6-15-11
Architect/Engineer: AECOM Technical Services, Inc., 303 Wacker Drive, Suite 1400, Chicago, IL 60601
FRA Commissioning Authority: Burns & McDonnell Engineering Company, Inc., 200 W. Adams St, Suite 2700, Chicago, IL 60606
Construction Manager as Advisor (CMa): As designated in Subcontract.
FRA Construction Coordinator: As designated in Subcontract.
01 00 10 - 2
May 20, 2024 Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
1.7 DESCRIPTION OF WORK
The Long-Baseline Neutrino Facilities (LBNF) Deep Underground Neutrino Experiment (DUNE) Project will provide facilities to enable a world-class program in neutrino physics that can measure fundamental physical parameters, explore physics beyond the Standard Model, and better elucidate the nature of matter and anti-matter. Specifically, the LBNF/DUNE-US Project will build a new high-intensity neutrino beam at Fermilab aimed at the LBNF Far Site, SURF, 1,300 km away; the associated DUNE Project will build neutrino detectors at Fermilab and SURF. The experiment will be optimized for precision measurement of neutrino oscillations with the goal of searching for charge parity-violation in the neutrino sector, as well as making other precision oscillation measurements. The Near Site Conventional Facilities (NSCF) provides the new service buildings, underground enclosures, utilities, roads, hardstands, and other conventional facilities features needed for operation of the LBNF Beamline and DUNE Near Detector.
This Subcontract is for the NSCF Near Detector Complex and is comprised of the following elements.
The Subcontractor’s scope of work is not limited to the general work outline described below. The Subcontractor shall perform all work required to complete the construction work in accordance with the drawings and specifications. The description and quantities listed below are general in nature and are only intended to describe the range and complexity of this scope of work. The description provided below is not to be used as the basis for establishing a cost proposal. Specific quantities and definitions of the scope of work for providing a proposal shall be based solely on estimates developed by the Offeror from the drawings, specifications, and the information obtained from examining of the project site.
Site Work Site Work includes new utilities and roads, and other site improvements necessary to accommodate the LBNF Near Detector Complex enclosures and buildings.
Near Detector Complex The Near Detector Complex is necessary to house the Near Detectors to characterize the beam of Neutrino’s as they leave Fermilab’s Batavia site and head toward the LBNF Far Detectors in South Dakota. The Near Detector Complex is a cavern approximately 200 ft underground in rock connected via a primary shaft to a service building at the surface.
1.8 MATERIALS & EQUIPMENT FURNISHED BY FRA
No materials and equipment are furnished by FRA.
1.9 SERVICES FURNISHED BY FRA
Fermilab will furnish the services as described below:
Drinking Water: Fermilab will not provide drinking water for this project.
Toilet Facilities: Fermilab will not provide toilet facilities for this project.
Utility Locates: FRA will provide locations of existing known utilities as defined in Section 01 31 00 Articles 1.12 and 3.1. The Subcontractor shall excavate electrical, fiber optics, and gas utilities, in accordance with Section 01 31 00 Article 1.12, paragraph A, 4.
Subcontractor shall coordinate access to Fermilab existing utility and building services with the FRA Construction Coordinator:
FRA will de-energize and re-energize the existing Domestic Water System (DWS), Industrial Cooling Water (ICW), Low Conductivity Water (LCW), fire protection suppression system, electrical services entering facilities, and fire detection in the building(s). These activities shall be coordinated through the FRA Construction Coordinator. The FRA Construction Coordinator shall be notified a minimum 48 hour prior to systems needing to be de-energized.
01 00 10 - 3
May 20, 2024 Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
Subcontractor shall coordinate requests for FRA permits or furnished services with the FRA Construction Coordinator.
The FRA Construction Coordinator coordinates issuance of FRA permits; reference Section 01 31 00 for additional information.
The FRA Construction Coordinator or designee processes requests for and provides disablement of existing systems. Availability and use of existing Fermilab utility services will comply with Section 01 31 00, Article 1.12, Paragraph B.
Electrical Power:
Electric power will be furnished free of charge by FRA for the Subcontractor’s use. Connections to existing power sources are the responsibility of Subcontractor.
Installation of the Subcontractor’s electrical power distribution shall include ground-fault circuit protection and shall be subject to FRA approval.
Any additional power required but not specified herein shall be furnished and paid for by the Subcontractor. If Subcontractor is unable to connect FRA-provided power sources, or requires power in addition to FRA-provided power, Subcontractor shall furnish and pay for any other power used.
1.10 ITEMS AFFECTING WORK PLANNING
Safety Representative: Subcontractor Safety Representative is required on the project. Reference Section 01 31 00, Article 1.15 for further information.
Additional Training: Additional training provided by FRA other than the Subcontractor’s orientation as specified in Section 01 31 00, Article 1.17 for further information:
Project Site Specific Radiological Worker Training is required for workers working within 30 feet of the Main Injector standoff zone and Booster Neutrino Beamline Fermilab Escort Training is required for workers that will be escorting unbadged workers, mechanics and deliveries.
Fermilab Radiological Worker, Controlled Access and LOTO II Training is required for workers accessing and/or working within 30 feet of the Main Injector standoff zone prior to and after the Main Injector Shutdown Period.
Erosion Control: Subcontractor to refer to Section 31 25 13 – EROSION AND SEDIMENT CONTROL and Section 01 31 00 Article 1.13.
Metal Recycling: Subcontractor to refer to Section 01 74 19 – CONSTRUCTION WASTE
MANAGEMENT AND DISPOSAL.
Subcontractor must obtain decision if metal is or is not acceptable for recycling by ESH&Q Radiation Safety. If found to be not acceptable, FRA Construction Coordinator will arrange for a Fermilab-provided metal recycle dumpster for the Subcontractor to locate the metal in, reference Section 01 31 00, Article 1.18, Paragraph C for additional information: coordinated with SECTION 01 74 19.
Waste Disposal: Subcontractor to refer to Section 01 74 19 – CONSTRUCTION WASTE
MANAGEMENT AND DISPOSAL.
FRA will dispose of existing regulated waste or FRA-generated regulated waste. The Subcontractor is permitted to dispose of any regulated waste that is generated during the performance of this Subcontract. However, Subcontractor is required to notify the FRA Construction Coordinator prior to the commencement of any regulated waste generation and off-site shipments of any waste materials destined for disposal.
No regulated waste is anticipated for this project.
Work Restrictions associated with Accelerator Operations:
01 00 10 - 4
May 20, 2024 Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
Construction work is prohibited within 30 feet of existing accelerator beamlines, including the Main Injector Shielding Zone Area (defined on Contract Drawings as 30’-0”) and the Booster Neutrino Beamline, during periods when the Accelerator is operational.
All work identified to occur within this zone must be executed during the Accelerator Shutdown Periods listed below.
Summer Shutdown Period, unless otherwise noted: typically July 1st through September 30th. Actual dates may vary and are scheduled each year by FRA Operations.
Long Shutdown Period, tentative dates: January 4, 2027 – April 6, 2028
1.11 ELECTRONIC PROJECT DRAWINGS
FRA may, at the Subcontractor’s request and in accordance with specifications, release electronic project drawings for use in the preparation of shop drawings by the Subcontractor or Sub-tier subcontractors or vendors. By accepting these files, the Subcontractor understands and agrees that each electronic drawing is provided in connection with the above-identified project only. The drawings as incorporated into Subcontract are and will remain the record document for the Project. Use of electronic drawings does not relieve the Subcontractor from verifying or checking the information contained within the electronic drawings. The electronic drawings may not reflect all quantities, surface areas, and volumes, and may not completely describe all Architect/Engineer elements that may have an impact on the actual construction of the Project.
These electronic drawings will be distributed to the Subcontractor utilizing FRA’s current file and media format by an FRA authorized person.
The project design drawings reflect the intent and scope of the project and general routing. The routing of utilities and building/facility services indicated on the design drawings is for providing proposal only.
The Subcontractor and/or Sub-subcontractors are expected to make a site visit prior to submitting a proposal; make allowances for all necessary adjustments for the actual system installation; to examine physical conditions which may be material to the performance of its work; and coordinate the actual routing as necessary to accommodate the existing conditions and obstructions.
1.12 PARKING AND STAGING AREA
The Subcontractor’s parking and staging area is designated in the drawings.
Parking of the Subcontractor’s and the Sub-tier subcontractors’ vehicles shall be confined to the Subcontractor’s designated construction and parking areas.
The Subcontractor shall provide and maintain temporary barricades, fences, or other means to delineate the construction limits, as required for the protection of FRA employees. Provide signage at all entrances to the construction site with the Subcontractor’s company’s name and contact information. Signage shall include: Danger Construction Area, Do Not Enter. Visitors shall sign-in with the FRA Construction Coordinator and the Subcontractor’s representative and must be made aware of the current hazards and conditions and be escorted either by the Subcontractor or the FRA Construction Coordinator.
No material shall be stored beyond the construction limits unless prior written arrangements have been made through the FRA Construction Coordinator.
1.13 SITE ACCESS AND HAULING
The Subcontractor shall use only established roadways and use such temporary roadways constructed by the Subcontractor when and as may be authorized by FRA. Where materials are transported during the course of the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicles or prescribed by any Federal, State, or local law or regulation. When it is
01 00 10 - 5
May 20, 2024 Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857 necessary to cross curbings or sidewalks, the Subcontractor shall protect them from damage. The Subcontractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
Construction equipment and deliveries to the site are restricted to the Kautz Road construction entrance.
Access to the site via other Fermilab gate entrances are restricted and must be arranged a minimum of 48 hours prior to the use of the access point through the FRA Construction Coordinator. All access into FNAL and existing FNAL must be right-in / right-out. Left turns into FNAL or out of FNAL at the Kautz Road construction entrance are strictly prohibited unless prior written authorization is provided by FRA.
Fermilab gate hours of operation Kautz Road construction entrance: 6am to 6pm Wilson Street entrance. (Alternate with written FRA approval required) Batavia Road entrance. (Alternate with written FRA approval required) Pine Street entrance. (Alternate with written FRA approval required)
Fermilab site access and hauling shall be subject to the following conditions:
Electronic communication devices, such as cell phones, texting devices, laptops, etc. must not be used while driving any motor vehicle on the Fermilab site.
All roads shall remain open to emergency traffic at all times.
All equipment and vehicles shall be confined to operating along defined construction roads and approved access routes.
No overland hauling or off-road travel shall be permitted without prior approval of the FRA Construction Coordinator.
Interruption of normal traffic patterns or temporary road closings necessitated by movement of equipment or delivery of materials or utility installations shall require 72 hours advance notice to the FRA Construction Coordinator and shall require proper barricades, signage, and flag persons to divert normal traffic safely.
Traffic on paved roads shall be restricted to rubber-tired vehicles. Where crawler-mounted equipment is required to cross paved roads or areas, the pavement shall be suitably protected from damage to the satisfaction of the FRA Construction Coordinator.
Dust, debris, mud, and litter on any Fermilab roads caused by the Subcontractor's operations shall be removed by the Subcontractor in a manner as directed by the FRA Construction Coordinator.
Illinois Rules of the Road shall apply to the Subcontractor’s use of all existing roads on the Fermilab site.
The Subcontractor shall include a construction traffic access, routing, and maintenance plan.
1.14 TRANSPORTATION OF EQUIPMENT AND MATERIALS
Transportation of equipment and materials shall be subject to the following conditions:
Transportation of equipment and materials used by the Subcontractor at the job site shall be furnished by the Subcontractor at his/her own expense.
The Subcontractor shall be responsible for minimizing any interference with local traffic, other subcontractors and Fermilab operations.
The Subcontractor shall coordinate the anticipated schedule for major material deliveries and site hauling of excavated materials with the FRA Construction Coordinator.
1.15 TEMPORARY SERVICES AND FACILITIES
Subcontractor to refer to Section 01 50 00 – TEMPORARY FACILITIES AND CONTROLS
1.16 FERMILAB CLOSURE DATES
The Fermilab site is closed for major holidays and no construction activities shall occur, unless specifically approved by the FRA Construction Coordinator, on these days:
New Year’s Day – January 1st Martin Luther King Jr. Day – 1st Monday after January 15th
01 00 10 - 6
Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
Memorial Day – Last Monday in May Juneteenth – June 19th Independence Day – July 4th Labor Day – 1st Monday in September Thanksgiving Day – 4th Thursday in November Day After Thanksgiving – Friday after Thanksgiving Christmas Eve (1/2 Day) – December 24th
Christmas Day – December 25th New Year’s Eve (1/2 Day) – December 31st
If any of these holidays occur on a weekend day, a weekday will be used for the holiday.
1.17 MATERIAL SUBSTITUTIONS
Refer to Section 01 25 00 – SUBSTITUTION PROCEDURES. In the event of conflict, the Subcontractor shall comply with the more stringent requirement.
1.18 DOCUMENTATION
For Quality Control documentation refer to Section 01 41 00 – QUALITY REQUIREMENTS, in particular sub-section 1.5.G.
Refer Section 01 78 39 – PROJECT RECORD DOCUMENTS for record document requirements.
Refer to Section 01 77 00 – CLOSEOUT PROCEDURES for Final Acceptance documentation.
1.19 SUBCONTRACTOR’S REQUESTS FOR INFORMATION (RFI)
When the Subcontractor is unable to determine from the Contract Documents the exact material, process or system to be installed; or when the items of construction are required to occupy the same space (interference); or when an item of work is described differently at two places in the Contract Documents; or when other clarification is required; Subcontractor shall request a clarification through the RFI procedure set forth herein.
Requests for Information (RFIs) shall be submitted through the web-based project management system (WBPMS) with the information found in Attachment A. Each RFI shall be given a discrete, consecutive number. Each page of the RFI and of attachments to the RFI shall bear the RFI Number and Project Number. Resubmitted RFIs with additional information shall be RFI number with a .01 prefix for the first resubmitted RFI, .02 for the second, and so on.
RFIs from Sub-tier subcontractors shall be submitted through, reviewed by, given a number, and signed by the Subcontractor prior to submittal to FRA. The Subcontractor shall keep a log of the RFIs. RFIs submitted directly by Sub-tier subcontractors will be returned unanswered to the sender and the Subcontractor. Subcontractor shall be responsible for delays resulting from the necessity to resubmit an RFI.
Subcontractor shall carefully study the Subcontract documents to assure that the requested information is not available therein.
In all cases where RFIs are issued to request clarification of coordination issues (e.g., pipe and duct routing, clearances, specific locations of work shown diagrammatically, apparent interference and similar items), the Subcontractor shall furnish all information required to analyze and/or understand the circumstances causing the RFI in order to prepare a clarification or direction as to how Subcontractor shall proceed.
RFIs shall not be used for the following purposes:
01 00 10 - 7
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
To request approval of submittals.
To request approval of substitutions.
To request changes which entail additional cost or credit.
To request different methods of performing work than those indicated on the drawings and/or specified.
In the event the Subcontractor believes that a clarification by FRA results in additional cost, Subcontractor shall not proceed with the work indicated by the RFI until authorized by FRA Procurement Specialist to proceed by an approved Change Order, or FRA Procurement Specialist denies Subcontractor’s request for a Change Order based on a belief that the work is within the established scope of the Subcontract. Subcontractor may pursue a claim for additional compensation or time to complete under the provisions of the Subcontract governing disputes, but the work, including the work that is the subject of a dispute, shall not be stopped or slowed in any way during the pendency of a dispute.
FRA will return RFIs to the Subcontractor within 15 working days of receipt. RFIs received after 12:00 noon shall be considered received on the next regular workday for the purpose of establishing the start of the response period.
1.20 SPECIFICATION AND DRAWING CONVENTIONS
Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
Imperative mood and streamlined language are generally used in the Specifications. The words “shall”, “shall be,” or “shall comply with” depending on the context, are implied where a colon (:) is used within a sentence or phrase.
Specification requirements are to be performed by Subcontractor unless specifically stated otherwise.
Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings.
Keynoting: Materials and products are identified by reference keynotes referencing Specification
Section numbers found in this Specifications.
Nomenclature:
FRA is a prime contractor to the Department of Energy; therefore, contracts entered into by FRA with industry are subcontracts. The use of the “Contractor” and “Contract” are synonymous with “Subcontractor” and “Subcontract” throughout the Drawings and Specifications for this Work and are used to refer to the General Contractor selected by FRA to perform this Work.
01 00 10 - 8
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION
3.1 NOTICE TO PROCEED
The Notice to Proceed (NTP) represents the basis of the start of the project duration. The following describes the requirements for the Notice to Proceed:
The NTP is issued by the FRA Procurement Specialist.
The issuance of the NTP establishes the start of work on the Fermilab Site.
A project kickoff meeting may be required prior to the issuance of the NTP.
3.2 PROJECT SCHEDULE
This Project Complete milestone marks the completion of the project including punch list items, clean-up, and acceptance of as-built drawings and if required, submittals.
Refer to Section 01 30 00 – PROJECT MANAGEMENT AND COORDINATION for information pertaining to progress, coordination, and construction meeting requirements.
3.3 QUALITY CONTROL AND CONTROL OF INSTALLATION
Refer to Section 01 41 00 – QUALITY REQUIREMENTS for information pertaining to Quality Control.
The Subcontractor is responsible for all activities necessary to manage, control, and document that work complies with the Subcontract documents. The Subcontractor’s responsibility includes ensuring adequate Quality Control services are provided for work accomplished on and off the site by its organization, suppliers, sub-tier contractors, technical laboratories, and consultants.
The work activities include safety, submittal management, testing and inspection, and all other functions relating to the requirement for quality construction.
3.4 ACCEPTANCE
Refer to Section 01 77 00 – CLOSEOUT PROCEDURES for general information on submittals, inspections, and closeout documents and procedures.
END OF SECTION 01-00-10
ATTACHMENT A
REQUEST FOR INFORMATION
Date:
Project Name: RFI No.:
To: Project No.:
Subject: Submitted By:
Spec.. No.: Article/Par.: Drwg. No.: Detail:
Request:
Response:
ALTERNATES
01 23 00 - 1
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
SECTION 01 23 00 - ALTERNATES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Subcontract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for alternates.
1.3 DEFINITIONS
A. Alternate: An amount proposed by Proposers and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if FRA decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.
1. Alternates described in this Section are part of the Work only if enumerated in the Subcontract.
2. The cost or credit for each alternate is the net addition to or deduction from the Subcontract Price to incorporate alternates into the Work. No other adjustments are made to the Subcontract Price.
1.4 PROCEDURES
A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.
1. Include as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of alternate.
B. Execute accepted alternates under the same conditions as other work of the Subcontract.
C. Schedule: A schedule of alternates is included at the end of this Section. Specification sections referenced in the schedule contain requirements for materials necessary to achieve the work described under each alternate.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF ALTERNATES
A. Alternate No. 1 Giese Road Improvement
1. Base Bid: Proposed roadway as defined on sheets SW-ND-122 and SW-ND-123 shall be constructed as hardstand based on SW-ND-502 detail 1.
ALTERNATES
01 23 00 - 2
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
2. Alternate: Proposed roadway as defined on sheets SW-ND-122 and SW-ND-123 shall be constructed as asphalt based on SW-ND-502 detail 2.
END OF SECTION 01-23-00
SUBSTITUTION PROCEDURES
01 25 00 - 1
May 20, 2024 Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
SECTION 01 25 00 - SUBSTITUTIONS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Subcontract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. SECTION 01 00 10: General Requirements
2. SECTION 01 23 00: Alternates
3. SECTION 01 33 00: Submittals
4. SECTION 01 60 00: Product Requirements
1.3 DEFINITIONS
A. Types of Substitution Requests:
1. Substitutions for Cause: Changes proposed by Subcontractor that are required due to changed
Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Subcontractor that are not required in order to meet other Project requirements but may offer advantage to Subcontractor.
a. Substitutions for Convenience are not permitted.
1.4 SUBMITTALS
A. Submit three (3) copies of each request for consideration, if a physical submission is applicable. Identify product or fabrication or installation method to be replaced. Include the Specification Section number and title and drawing numbers and titles. The submittal shall contain the same information pertaining to the original specified product for purposes of comparison.
B. The submittal shall explain fully the differences, if any, between the original specified product and proposed substitute product.
C. Any change to the Drawings or Specifications for related work required for proper installation of the proposed substitute product shall be indicated in the submittal.
D. If the proposed substitute product requires alterations of any kind to other equipment or construction or necessitates any engineering design changes for its proper installation, such alterations and engineering design changes shall be accomplished at no cost to FRA.
E. The substitute submittal must contain a statement detailing the cost and schedule impact of the proposed substitution.
F. FRA has sole discretion to accept or reject the proposed substitution.
01 25 00 - 2
May 20, 2024 Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
G. Substitution Requests shall:
1. Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication or installation cannot be provided.
b. Coordination information, including a list of changes or revisions needed to other parts of the Work or existing Fermilab facility that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
g. List of similar installations for completed projects with project names and addresses and names and addresses of Architect/Engineers construction contractors.
h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
i. Research reports evidencing compliance with building code in effect for Project, from ICC-
ES.
j. Detailed comparison of Subcontractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall time for performance. If specified product or method of construction cannot be provided within the specified period of performance, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
k. Cost information, including a proposal of change, if any, in the Subcontract Price.
l. Subcontractor's certification that proposed substitution complies with requirements in the
Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.
m. Subcontractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
2. If necessary, FRA may request additional information or documentation.
a. Forms of Acceptance: Change Order or through the submittal process.
b. Use product specified if no decision on use of a proposed substitution is received.
H. If FRA accepts a substitution, the FRA Procurement Specialist will issue a notice of change or Change Order, as appropriate for the situation. Subcontractor shall use product specified if no decision on use of a proposed substitution is received.
1.5 QUALITY ASSURANCE
A. Investigate and document compatibility of proposed substitution with related products and materials.
Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.6 PROCEDURES
A. Revise or adjust affected work as necessary to integrate work of the approved substitutions.
01 25 00 - 3
May 20, 2024 Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
PART 2 - PRODUCTS
2.1 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, and as stipulated above, but not later than 15 days prior to time required for preparation and review of related submittals.
1. Conditions: Subcontractor's request for substitution will be considered when the following conditions are satisfied. If the following conditions are not satisfied, request shall be returned without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Subcontract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted.
c. Requested substitution will not adversely affect Subcontractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.
f. Requested substitution has been coordinated with other portions of the Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
B. Substitutions for Convenience: Not allowed.
C. FRA has the sole discretion to accept or reject the proposed substitution.
PART 3 - EXECUTION (Not Used)
END OF SECTION 01-25-00
CONTRACT MODIFICATION PROCEDURES
01 26 00 - 1
May 20, 2024 Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
SECTION 01 26 00 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Subcontract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this section.
1.2 SUMMARY
A. Section includes administrative and procedure requirements for handling and processing Subcontract modifications. The requirements of this Section shall be in addition to and supplement change and/or modification requirements established in the Contract Documents. In the event of any conflict between this Section and any other change and/or modification requirements established in the Contract Documents, the provision granting greater rights or remedies to FRA, or imposing the greater duty, standard, responsibility or obligation on Subcontractor, as determined by FRA, shall govern.
B. Related Requirements:
1. SECTION 01 00 10: General Requirements
2. SECTION 01 25 00: Substitution Procedures.
1.3 MINOR FIELD CHANGES IN THE WORK
A. The FRA representatives that will have field change authority and the limits associated with minor changes will be relayed to the Subcontractor via the FRA Procurement Specialist.
1.4 PROPOSAL REQUESTS
A. FRA-Initiated Proposal Requests: FRA will issue a detailed description of proposed changes in the Work that may require adjustment to the Subcontract Price of the Period of Performance. If necessary, the description will include supplemental or revised Construction Drawings and Construction Specifications.
1. Work Change Proposal Requests: issued by FRA are not instructions either to stop work in progress or to execute the proposed change.
2. Within time specified in a Work Change Proposal Request or 20 days, when not otherwise specified, after receipt of a Work Change Proposal Request, submit a quotation estimating cost adjustments to the Subcontract Price and the Period of Performance necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Subcontractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Minimize the impact of the change on the Period of Performance to the extent possible.
e. Quotation Form: Use form acceptable to FRA.
CONTRACT MODIFICATION PROCEDURES
01 26 00 - 2
May 20, 2024 Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
B. Subcontractor-Initiated Proposals: If latent or changed conditions require modifications to the Subcontract, Subcontractor may initiate a request for eligible adjustment by submitting a request for equitable adjustment to FRA.
1. Include a statement outlining reasons for the change and the effect of the change on the Work.
Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Subcontract Price and the Period of Performance.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Subcontractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Minimize the impact of the change on the Period of Performance to the extent possible.
6. Comply with requirements in Section 01 25 00 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
7. Proposal Request Form: Use form acceptable to FRA.
1.5 CHANGE ORDER PROCEDURES
A. On FRA's approval of a Work Changes Proposal Request or Change Order Request, FRA will issue a Change Order in accordance with the terms of the Subcontract. Any modification in Subcontract time or price will be addressed in accordance with the terms of the Subcontract.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 01-26-00
INVOICING PROCEDURES
01 29 00 - 1
May 20, 2024 Issued for Solicitation
Fermi Research Alliance, LLC 6-15-12 Near Detector Complex
AECOM Project Number 60633857
SECTION 01 29 00 – INVOICING PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Subcontract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment. The requirements of this Section shall be in addition to and supplement payment and/or invoicing requirements established in the Contract Documents.
This is the start of the file's text. The full file is on GovTribe.