This is a Specification Verification and Delivery Sheet for a Colorado Parks and Wildlife (CPW) procurement related to the Harvey Gap Parking Lot Improvements project (DQ1 2026-0366). The project requires the furnishing and delivery of Class 6 Road Base and Pit Run aggregates to Harvey Gap State Park in Silt, Colorado. CPW estimates requiring approximately 2,200 to 3,400 tons of Pit Run and 1,000 to 2,000 tons of Class 6 Road Base, with exact quantities dependent on bid prices and delivery costs. All trucking and delivery services must be provided by the vendor on an as-needed basis with multiple deliveries due to limited on-site storage capacity. Materials must be delivered within two weeks of Purchase Order issuance, with the delivery window spanning approximately April 6, 2026 through June 30, 2026, and initial delivery required by April 13, 2026. CPW reserves the right to conduct material inspections at the bidder's quarry prior to award, with the Project Manager contacting the low bidder to schedule inspection at least five working days after bid closure.
The Class 6 Road Base must conform to AASHTO M 147 specifications and meet CDOT Section 703.03 grading requirements for crushed stone, crushed slag, crushed gravel, or natural gravel, with liquid limits not exceeding 30 and plasticity index not exceeding 6. Pit Run must consist of non-organic mineral aggregates with a maximum particle size of six inches, liquid limit not exceeding 35, and plasticity index not exceeding 6. Bidders are required to submit a Certified Sieve Analysis and AASHTO T 89 and T 90 test results if available. Quantities shall be measured by the ton at the delivery site using certified scales, and certified weight tickets must accompany all payment applications with supplier name, date, material description, and loaded weight. CPW will award to the low bidder meeting all material specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DQ1 2026-0366 - Pricing Sheet.xlsx | XLSX spreadsheet | |
| POTermsConditions.pdf | ||
| Bid Solicitation DQ1 2026-0366.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Spec Verification & Delivery DQ1 2026-0366 Bid - Specification Verification and Delivery Sheet
Commodity To Furnish and Deliver Class 6 Road Base and Pit Run Required Vendor Specifications Does your bid item meet these specifications?
| (Y/N) | If no, describe your item: | |
| Quantity | It is required that exact tonnage purchased will depend on bid prices for material including delivery, but CPW estimates it to be approximately 2,200-3,400 tons of Pit Run and 1,000-2,000 tons of Class 6 Road Base | |
| Trucking | It is required that all trucking of road base and pit run will be provided by the vendor. The materials will be delivered on an "as-needed" basis with multiple deliveries since storage space on site is limited. | |
| Type of Road Base | Class 6 road base is required. CPW will award to low bidder who can provide the Class 6 road base. | |
| Type of Pit Run | Pit Run is required. CPW will award to low bidder who can provide the Pit Run. | |
| Measure and Payment | It is required that quantities shall be measured by the ton, delivered to the project site. All weights shall be measured on a certified scale. Copies of certified weight tickets shall be submitted to the Project Manager with the payment application. | |
| It is required that weight tickets shall have the following information at a minimum: 1. Supplier's Name and Date 2. Material Description 3. Weight of Material Loaded | ||
| Road Base Material Specification | It is required that aggregates for base courses shall be crushed stone, crushed slag, crushed gravel or natural gravel conforming to AASHTO M 147 except that the requirements for the ratio of minus No. 200 sieve fraction to the minus No. 40 sieve fraction shall not apply. Aggregates for base material shall meet the grading requirements of the following table and shall also be for material identification. | |
| The liquid limit shall not be greater than 30 and the plasticity index shall not exceed 6 when the aggregate is tested in accordance with AASHTO T 89 and AASHTO T 90, respectively. The grading requirements of the material, CDOT Section 703.03, Aggregate Base Course, are shown in the table below. |
| Pit Run Material Specification | It is required that aggregates for pit run should be non-organic mineral aggregates and shall have a maximum particle size of 6 inches. |
| It is required that the liquid limit shall not be greater than 35 and the plasticity index shall not exceed 6. | |
| Submittal Requirements for Class 6 | It is required to provide the following information with your bid: 1. Certified Sieve Analysis 2. AASHTO T 89 Test Results, if available. AASHTO T 90, if available |
| Material Inspection | Class 6 Road Base and Pit Run material shall be evaluated at the bidder's quarry, if requested by CPW, prior to the award of the bid by a Colorado Parks and Wildlife Project Manager. The PM will contact the low bidder to schedule an inspection date no less than five working days after the bid closes. |
| Material Delivery Dates | Class 6 Road Base and Pit Run are required to be delivered within 2 weeks, once the Purchase Order has been issued by CPW. The 12-week window for delivery will be approximately between April 6, 2026 and June 30, 2026. |
| Delivery Location | Must be able to deliver to Colorado Parks and Wildlife Harvey Gap State Park located at 39 36'33.7"N 107 39'24.3"W (Google Maps Link: https://www.google.com/maps/place/2757+Co+Rd+237,+Silt,+CO+81652/@39.6093262,-107.6591525,871m/data=!3m2!1e3!4b1!4m6!3m5!1s0x87416abb4ec711fd:0x17405d9fe375e29a!8m2!3d39.6093262!4d-107.6565776!16s%2Fg%2F11fscj9q7z?entry=ttu&g_ep=EgoyMDI2MDMxMS4wIKXMDSoASAFQAw%3D%3D). The exact Road Base and Pit Run placement location within the delivery window will be specified by the CPW Project Manager. |
| Delivery | Delivery Information | Vendor Response (Y/N) |
| Delivery Address | Are you able to deliver to - |
Colorado Parks and Wildlife Harvey Gap State Park 2757 Co Rd 237, Silt, CO 81652 Delivery Date Delivery is required on or before 04/13/2026. Are you able to deliver by then?