Downey-Frankel_WM_Ext_-_Equipment_Warranties_and_Spare_Parts.pdf
PDF 127 KB Posted
- Solicitation number
- Y23-795
- Issued by
- Orange County, Orlando City, Florida
About this file
This document is a List of Equipment, Warranties, and Spare Parts from the Orange County Utilities Division for the Lake Downey & Frankel Street Water Main Extension project, dated 4-11-23. The document details warranty periods for specific equipment categories, specifically covering all major and minor equipment and gate valves, each with a 1-year warranty period. Both equipment sections (01740 and 15111) list "None Specified" for spare parts.
The associated state and local contract opportunity involves a water main extension project in Orange County, Florida, with a total estimated project cost of $1,149,585.00. The bid submission deadline is set for Thursday, August 31, 2023, at 4:00 pm EST, with electronic submissions required through the ProcureNow OpenGov e-Procurement Platform. Potential bidders must create a free account on the platform and are prohibited from hand-delivering, mailing, faxing, or emailing offers. Technical support is available through chat, email, and phone, and questions regarding the solicitation must be submitted by Wednesday, August 9, 2023, at 5:00 pm EST through the platform's question and answer module.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ORANGE COUNTY UTILITIES DIVISION
List of Equipment, Warranties, and Spare Parts
Project: Lake Downey & Frankel Street WM Extension Date: 4‐11‐23
Section Equipment Warranty Period (years) Spare Parts 01740 All major and minor equipment 1-year None Specified 15111 Gate Valves 1‐year None Specified
| ORANGE COUNTY UTILITIES DIVISION |
| List of Equipment, Warranties, and Spare Parts |