Dotson Creek Road Landslide_Revision Final_BID SCHEDULE.pdf
PDF 111 KB Posted
- Attached to
- Dotson Creek Road Landslide
- Solicitation number
- 70250
- Issued by
- Washington County, Virginia
About this file
This document is a Bid Schedule for the Dotson Creek Road Landslide project in Wise County, Virginia, which is being undertaken by the Commonwealth of Virginia Department of Energy Abandoned Mined Land Repurposing Program. The project involves the reclamation of a landslide under VA Route 645, including excavation, drainage infrastructure installation, riprap and aggregate placement, and revegetation. The project is estimated to have a duration of 45 calendar days from the Notice to Proceed. A mandatory pre-bid conference will be held on July 2, 2024, and sealed bids are due by July 16, 2024. The contract will be awarded to the lowest responsive and responsible bidder based on the total bid price.
The Bid Schedule includes 27 line items for various materials, labor, and services required for the project, such as mobilization, site preparation, riprap, pipe installation, and revegetation. The IFB indicates that set-aside priority will be given to DSBSD-certified micro and small businesses if their bids are deemed fair and reasonable. The contractor must comply with federal requirements such as the Buy America, Buy American Act, Davis-Bacon Act, and other regulations for federally assisted funding. The estimated contract value is not provided in the document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item No. SPEC No. Item Name Approx.
Quantity Units Unit Price Total Price
1. 1. Mobilization - 5% Limit N/A Job N/A
2. 2. Site Preparation N/A Job N/A
3. 3.B.i VDOT Class I Riprap 4080 Ton
4. 3.B.ii VDOT Class A1 Riprap 12300 Ton
5. 3.B.iii VDOT Gabion Stone 85 Ton
6. 3.B.iv VDOT No. 1 Stone 2000 Ton
7. 3.B.v VDOT No. 57 Stone 580 Ton
8. 3.B.vi VDOT No. 21B Stone 320 Ton
9. 3.B.vii VDOT No. 26 Stone 40 Ton
10. 4. Silt Fence 1100 Linear Feet
11. 5. Straw Bale Barrier 50 Linear Feet
12. 6. Excavation 7600 Cubic Yard
13. 7. Riprap Buttress N/A Job N/A
14. 8. Erosion Control Blanket 1600 Square Yard
15. 9. Riprap Backfill N/A Job N/A
16. 10. Hydraulic Hammer 50 Hour
17. 11.B.iii(a) 12"φ HDPE Pipe 50 Linear Feet
18. 11.B.iii(b) 18"φ HDPE Pipe 30 Linear Feet
19. 11.B.iii(c) 36"φ HDPE Pipe 60 Linear Feet
20. 12. Pre-Cast Endwall 2 Each
21. 13. Underdrain 80 Linear Feet
22. 14. Stone-lined Ditch 340 Linear Feet
23. 15.B.ii Asphalt Concrete - Surface Mix 160 Ton
24. 15.B.iii Asphalt Concrete - Base Mix 180 Ton
25. 16. Surveys N/A Job N/A
26. 17. Revegetation 3.8 Acre
27. 18. Traffic Control N/A Job N/A
(Signature) (Title)
"The Total Bid Price will be utilized for determining the amount of bid, to establish a contract award value, and to determine the performance and payment bond amounts for the successful Bidder. Each Bidder must submit a bid bond for all bids of $100,000 or more. Payment will be made on actual units used and verified in the field. Correct pricing is extremely important and price should be double checked before submitting a bid. In the case of errors in the extension of prices, the unit price shall govern."
(Firm) (Date)
BID SCHEDULE FOR DOTSON CREEK ROAD LANDSLIDE PROJECT
Total Base Bid (Items 2 - 27)
Total Bid Price (Items 1 - 27)
Bid Schedule
File details come from the government source that posted it. Updated .