Domestic Hot Water Mixing Valve Pierre SOW.pdf
PDF 268 KB Posted
- Solicitation number
- 47PJ0024R0059
About this file
This document is a Construction Scope of Work issued by the U.S. General Services Administration, Rocky Mountain Region 8 for a project to provide and install a digital water mixing valve on the domestic hot water system at the Pierre Federal Building in South Dakota.
The key objectives are to: 1) Provide and install a factory-built whole building mixing valve assembly on the domestic hot water system to temper the hot water supply, with the ability to monitor temperatures, pressures, and recirculation pump status via the building's BAS system. 2) Ensure the mixing valve can handle high and low demands at a maximum pressure drop of not more than 10 PSI. 3) Provide shutoff valves, bypass capability, and insulation. 4) Integrate the new mixing valve with the building's BAS for monitoring purposes only. The contractor must submit a detailed Method of Procedures, safety and health program, product submittals, and complete the work within 20 calendar days after the notice to proceed is issued. The contractor is also required to follow GSA's security and badging requirements.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | Page
CONSTRUCTION SCOPE OF WORK
U.S. GENERAL SERVICES ADMINISTRATION, ROCKY MOUNTAIN REGION 8
Date: 3/12/24 Section 1: Install Domestic Hot Water Mixing Valve, Pierre, South Dakota
Section 2: Project Location, Building Name, & Building Number Federal Building/Post Office/Courthouse 225 South Pierre Street, Pierre, SD, 57501 Building Number SD0034
Section 3: Contact List Contracting Officer (CO) Name: Kristen Feickert Email: Kristen.feickert@gsa.gov Address: 115 4th Ave SE, Aberdeen, SD 57401 Phone (O): 605-252-3355 Phone (C): 605-877-1200
Property Manager Name: Justin Weyer Email: Justin.weyer@gsa.gov Address: 515 9th Street, Rapid City, SD 57701 Phone (C): 605-222-0998
Project Manager/Contracting Officer Representative (COR) Name: Chad Andrews Email: chad.andrews@gsa.gov Address: 400 S Phillips Ave., Ste.111 Sioux Falls, SD 57104 Phone (C): 605-518-0733
Section 4: Project Background & Project Description The General Services Administration, Region 8, is initiating a project to provide and install a digital water mixing valve on the domestic hot water system at the Pierre Federal Building. Focus of the project is to provide the capability to operate the water heaters at higher temperatures to prevent the growth of Legionella and temper the domestic hot water supply to assure consistent safe hot water temperature to prevent scalding at the point of use with connection of the digital water mixing valve to the building’s BAS system for monitoring.
Section 5: Project Objectives The contractor shall provide labor, materials, equipment and supervision necessary to perform:
1) Contractor to provide and install factory built whole building mixing valve assembly on the domestic hot water systems to temper hot water supply.
a. Contractor is responsible for determining the size based on building demand and piping configuration.
i. International Plumbing Code Section 613 Temperature Control Devices and Valves 613.1 Temperature actuated mixing valves. Temperature actuated mixing valves, which are installed to reduce water temperatures to defined limits, shall comply with ASSE 1017. Such valves shall be installed at the hot water source.
ii. Contractor required to provide calculation documentation used to determine size.
1. GSA will provide a total number of fixtures and types to be served by the new mixing valve. See attached list.
b. Contractor is responsible for programming the new domestic hot water mixing valve and setting the leaving temperature as specified by GSA.
2) New mixing valve assembly will have the following capability
a. Handle high and low demands at a maximum pressure drop of not more than 10 PSI.
2 | Page
b. New valve assembly to have entering hot water, cold water and leaving water Temperature sensors
c. New valve assembly to have entering and leaving Pressure sensors
d. New valve assembly to have thermal disinfection cycle capability.
e. New valve assembly to have recirculating pump, controlled by new valve controller
f. New valve assembly to have BACnet capability
3) New valve assembly piping must be Type L copper with lead free solder joints. Press fitting systems may be used between ½" to 2" where approved by code and with proper approvals and certifications but must not be used in concealed locations.
4) Provide shutoff valves to isolate the entire assembly and drains to allow for repair. Provide a means of bypass of the new domestic hot water mixing valve from water heaters to system piping.
i. Valves must be lead free and have lead free solder joints. Press fitting systems may be used between ½" to 2" where approved by code and with proper approvals and certifications but must not be used in concealed locations.
5) Insulate all piping unless otherwise specified by the manufacturer.
i. Insulation shall be 1” thick fiberglass pipe insulation on pipes up to 2” and 1.5” thick on pipes larger than 2”.
6) Building Automation System Requirements.
a. Points to be added to the BAS graphics entering hot water, cold water, and leaving water temperatures, entering and leaving pressure, recirculating pump status.
b. Tie new points to existing BAS network and program, provide graphics showing new points, provide histories on all new points and provide out of range alarm on the leaving hot water temperature point (adjustable limit) and pump status alarm. Link all alarms to existing critical email alarm.
i. BAS will not control unit, it will be used for monitoring purposes only
ii. Follow GSA Division 25 Spec, object naming template, Data Normalization standard for point naming, and
Niagara graphical standard.
7) Any water service interruptions will need to take place outside of normal hours of operation for the Building.
8) Contractor to field verify all site conditions.
Section 6: Proposal Pricing & Site Walk
1) Pre-proposal Site Visit Meeting:
a) The site visit shall consist of a meeting to review construction requirements followed by a walk-thru of the project site.
The meeting shall be attended by the contractor and GSA project personnel, and appropriate sub-contractors.
b) Review existing conditions of the project area including any field verification.
c) Review the solicitation/evaluation requirements.
2) Cost Proposal Requirements:
a) When submitting a proposal, provide a cost breakdown for each task into the following categories: Materials, equipment, labor hours, subcontractor's quotes, overhead, profit, and bond. Pricing shall be broken down by Construction Specification Institute (CSI) divisions.
Section 7: Period of Performance Once notice to proceed has been issued, the contractor has 20 calendar days to complete the project. The contractor must also promptly begin the badging process at the time of award. Please allow a minimum of 30 days to complete the badging process. Extensions will be granted for unforeseen conditions and other factors outside of the contractor’s control at the Contracting Officer’s discretion.
Section 8: Universal Scope Requirements
● ALL of the requirements in this section are MANDATORY
● See the attached Universal Scope Requirements document for the full details outlining each item
● Failure to comply with any and all of the requirements will result in the project not being accepted as complete
SAFETY & HEALTH
A. Safety and Health Program D. Fire & Life Safety E. Accessibility (ABAAS)
3 | Page
ENERGY, SUSTAINABILITY & ENVIRONMENTAL
G. Sustainable Purchasing
BUILDING SYSTEMS INTEGRATION
N. Commissioning (Cx) O. GSA IT Network P. Building Automation Systems (BAS) S. National Computerized Maintenance Management System (NCMMS)
DESIGN ELEMENTS
X. Mechanical Design & Fuel Storage
Section 9: Submittals
1) Contractor shall submit a Method of Procedures (MOP) to the GSA Delivery Project Manager (PM) for approval prior to commencement of work. At a minimum, the MOP shall include:
a) Brief narrative describing method of accomplishment, construction techniques, etc
b) Project schedule (to include critical path, major milestones, long lead time items, mob & de-mob, inspection dates, substantial completion, and occupancy dates)
c) Service/Utility Outages (if necessary)
d) Any building infrastructure/BAS equipment that may be impacted
2) Pre-alteration assessment report
3) Manufacturer's specifications, instructions and material specification sheets in original form
4) Submittal register/ log for all products specified to establish a standard of quality to include. Submittal register response by the government shall be (14) calendar days or less.
5) If product samples are not submitted in a timely fashion, any delays caused by the contractor will not warrant a time extension.
After completion of all work, the Contractor shall submit to the project manager the manufacturer's specifications, instructions and material specification sheets in original form. Additionally, the Contractor shall submit all inventory changes (removals, additions, upgrades, etc., and new condition codes) to the COR.
6) Submittal response by the government shall be (14) calendar days or less.
SUBMITTAL DUE DATE
1. Performance/Experience References With Proposal
2. Alternative payment protection Within 14 calendar days after Award
3. Insurance Certificate Within 14 calendar days after Award
4. Security Clearances Forms Within 14 calendar days after Award
5. Standard Form(s) 1413 Within 14 calendar days after Award
6. Method of Procedures (MOP) Within 14 calendar days after Award
7. Safety and Health Program (see USR) Within 28 calendar days after Award
8. Payrolls Weekly after construction start date
MATERIAL SUBMITTALS DUE DATE
9. Sizing Documentation Within 28 calendar days after Award
10. BAS point Naming Template Within 28 calendar days after Award
11. Digital water mixing valve Within 28 calendar days after Award
4 | Page
12. Recirculating pump Within 28 calendar days after Award
13. Valves Within 28 calendar days after Award
14. Pipe Within 28 calendar days after Award
15. Insulations Within 28 calendar days after Award
Section 10: General Requirements
1) Contractor Use of the Premises
a) During the period of the project, the contractor will have access to the site only during business hours of 7:00 am and 5:00
pm. No on-site work shall be performed outside these hours or on holidays unless otherwise directed by the Contracting Officer. The contractor will need to coordinate with the Contracting Officer to arrange access to the parking lot. The contractor shall make every effort to cause a minimum of damage to parking lots, any other paved areas, any items that need to be moved during the course of the project, and any areas not included in this scope of work. Any damage caused will be repaired at the contractor’s expense.
b) Any water service interruptions will need to take place outside of normal hours of operation for the Building.
2) Progress Meetings
Progress meetings are not required for this project. The project manager and building team representative shall make daily inspections of the work progress.
3) Equipment The contractor shall provide all equipment associated with the entire project, operate in a safe manner and adhere to all OSHA and GSA standards.
4) Equipment and Material Storage The contractor shall provide and store all equipment, the materials specified above, and any other materials required completing the project. The materials are required to be kept clean and dry throughout the duration of the project.
Contractor to coordinate with building manager for location of storage sheds.
5) Sanitary Facilities Provide and maintain temporary toilet facilities in accordance with State Health Department and GSA requirements.
6) Electricity, Water, and Gas GSA will pay for electricity, water, and gas during the course of this project. The contractor is responsible for making connections to the existing systems. Temporary electrical work shall meet the requirements of NFPA 70-1996 (NEC), Article
305. When temporary connections are removed, restore existing utility services to their original condition.
7) Contractor’s Field Office The contractor may provide an office for their own use. Size, location, and construction shall be subject to approval.
8) Fire Watch Contractor shall be responsible for providing fire watch if required per attached GSA fire watch guidelines.
9) Fire Alarm Impairment and Hot Work When a fire suppression or alarm system impairment is required, contractor shall provide written outage request to GSA for approval in advance of impairing any systems. Contractor shall be responsible for having a GSA approved NICET certified fire alarm contractor perform all system impairments. During fire alarm/suppression impairments or hot work procedures, contractor shall provide a fire watch per the GSA Regional Fire Watch Guidelines.
10) Protection of Public The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. The contractor shall illuminate barricades and obstructions at night and maintain safe building access and egress for tenants.
11) Housekeeping The project site shall be kept in a neat, orderly, and safe condition at all times. The contractor shall provide enough containers for collecting construction debris and construction materials to be recycled. The contractor shall wet down dry materials and rubbish to prevent blowing dust and keep volatile wastes in covered containers.
12) Transportation and Deliveries The contractor shall arrange deliveries of materials in accordance with construction schedules; coordinate with COR to avoid conflict with other tenants and other work conditions at the site. Contractor must make GSA PM & CO aware of any lead times that may affect the project schedule.
5 | Page
13) Cleaning Before scheduling the final inspection, the Contractor shall accomplish six items: (1) Remove all tools, equipment, surplus material, and rubbish; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Remove grease, dirt, stains, foreign materials, and labels from finished surfaces; (4) Thoroughly clean building interiors; (5) Pickup all construction debris from the site; and (6) At time of final inspection, project shall be thoroughly cleaned and ready for use.
14) Disruptive Work All painting, staining, or other activity which may cause noxious or undesirable fumes and/ or any noisy work that may be disruptive to the tenants/ public must be performed after normal working hours. The use of paint or stain that does not generate odors is preferred and may be required if the space will be occupied the following day with prior written approval from GSA.
Section 11: Badging & Security
1) Contractor is responsible to follow GSA’s security and badging requirements as detailed in the Badging & Security Requirements (Vendor Fitness Determination Training Manual).
2) US Access shared enrollment centers can be found at fedidcard.gov. Travel distances to the nearest center should be accounted for during the badging process.
Section 12: Payments
1) Information regarding payment requests and payment is in the solicitation/ contract. Please contact the CO if you have any questions regarding payments.
Section 13: Substantial Completion & Final Inspection
1) When project, or designated portion of project is complete, request a final inspection. Upon receipt of request that project is substantially complete, the Contracting Officer will proceed with the inspection within ten days of receipt of request or will advise the contractor of items that prevent the project from being designated substantially complete.
2) Field training for Operations and Maintenance (O&M) personnel shall be provided at completion of project.
3) The contractor shall provide O&M manuals. The O&M manuals shall contain the following:
o Executed Warranties (at project completion) o Maintenance and operation manuals
Section 14: Attachments
1) Universal Scope requirements
2) Specification Division 25
3) GSA R8 Object Naming Submittal Template
4) GSA R8 Data Normalization for Building Automation Systems
5) GSA R8 Device Schedule Template
6) GSA R8 Graphics Standard for Niagara N4
7) Water Source Checklist/Fixture Count http://fedidcard.gov/
| The General Services Administration, Region 8, is initiating a project to provide and install a digital water mixing valve on the domestic hot water system at the Pierre Federal Building. Focus of the project is to provide the capability to operate th... |
| SAFETY & HEALTH |
| 1) Contractor Use of the Premises |
| a) During the period of the project, the contractor will have access to the site only during business hours of 7:00 am and 5:00 pm. No on-site work shall be performed outside these hours or on holidays unless otherwise directed by the Contracting Off... |
| 2) Progress Meetings |
| 3) Equipment |
| 4) Equipment and Material Storage |
| 5) Sanitary Facilities |
| 6) Electricity, Water, and Gas |
| 7) Contractor’s Field Office |
| 8) Fire Watch |
| 10) Protection of Public |
| 11) Housekeeping |
| 12) Transportation and Deliveries |
| 13) Cleaning |
| 14) Disruptive Work |