Facility_Panning_Report_(Volume_2).pdf
PDF 5 MB Posted
- Attached to
- Operation of the San Jose Job Corps Center
- Solicitation number
- DOLJ14SA00009
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_4.pdf | ||
| Amendment_4.pdf | ||
| Amendment_3.pdf | ||
| Utilities_(2013).xlsx | XLSX spreadsheet | |
| MOU_for_Head_Start.pdf | ||
| Amendment_2.pdf | ||
| Pre-proposal_Conference_Sign-in_Sheet.pdf | ||
| Amendment_1.pdf | ||
| Utilities.docx | DOCX document | |
| Facility_Panning_Report.pdf | ||
| Inventory_Estimate.docx | DOCX document | |
| Solicitation.docx | DOCX document | |
| Master_Property_Report.pdf | ||
| Regional_Career_Pathways_Plan.doc | DOC document | |
| National_Staff_Compensation_Table.pdf | ||
| Property_Summary_Report.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
San JoseSan Jose
Job Corps Center San Jose, CA
Facility Planning ReportFacility Planning Report Volume II
Supporting Data
Fi lFinal November 2012
Department of Labor/ Office of Job Corps
22San Jose Job Corps Center
San JoseSan Jose
Job Corps Center San Jose, CA
Facility Planning ReportFacility Planning Report Volume II
Supporting Data
Fi lFinal November 2012
View of the green court
33 San Jose Job Corps Center
CONTENTS
SAN JOSE JOB CORPS CENTER
FACILITY PLANNING REPORT
VOLUME I - Planning Strategy
• Existing Site Plan
• Center Statistics
INTRODUCTION
• Purpose
• Report Contents
EXECUTIVE SUMMARY
A. EXISTING CONDITIONS
• Background
• General Site Conditions
• General Building Conditions
• Preventive Maintenance
• Ownership
• Facility Assessment by Function
• Energy
• Environmental Issues
• Sustainability
• Accessibility Standards
• Health and Life Safety Issues
• Summary of Defi ciencies
B. RECOMMENDATIONS
• Status of the Previous (PY09) Plan
• Signifi cant Issues
• PY 12 Plan Overview
• National Projects
• Regional Projects
• Proposed Site Plan
• Implementation Plan
• Summary of National Projects
• Project Data Sheets
C. PLANNING ANALYSIS
• Purpose
• Planning Objectives and Assumptions
• Space Utilization Analysis
• Federal Real Property Asset Management
• Mission Dependency Site Plan
• Defi ciency Analysis
• Facility Condition Summary Report
• Building Condition by Function
• Building Condition Site Plan
VOLUME II - Supporting Data
• Vicinity Map
• Location Map
• Existing Site Plan
D. DESCRIPTIONS
• Buildings and Structures
• Space Utilization By Function
• NSF by Building
• Energy Management Report
• Environmental Management
Asbestos Report Radon Report
• Site Descriptions
• Building Descriptions
E. DEFICIENCIES
F. CORRESPONDENCE AND REPORTS
• Center Review Brief
• Survey Brief
• RA and Student Facility Feedback Questionnaire
• Life Safety Defi ciencies Transmittal and List
• O & M Defi ciency List
• Active Warranty Report
• FRPC Performance Measures Matrix
44San Jose Job Corps Center
55 San Jose Job Corps Center
66San Jose Job Corps Center
77 San Jose Job Corps Center
D Descriptions
BUILDINGS AND STRUCTURES
00902 SAN JOSE 11/28/2012
1Page: of Date:
A - WELCOME CENTER
B - GYMNASIUM/RECREATION
D - MATERIAL HANDLING
E - EDUCATION
F - DINING/CULINARY ARTS
G - EDUCATION
H - ADMIN/MEDICAL/DENTAL
J - CHILD CARE CENTER
L-1 - FEMALE DORMITORY
L-2 - MALE DORMITORY
L-3 - FEMALE DORMITORY
M - RECREATION/GROUP LIFE
N - VOCATION/WAREHOUSE
P - CAREER TRANSITION
Q - ICL
TCU SATELLITE - SAN JOSE
C - GREENHOUSE
T1 - PAINT STORAGE
T2 - LANDSCAPE STORAGE
T3 - STORAGE SHELTER
T5 - TOY STORAGE
T6 - HOUSING CONTAINER
Name GSF
12,500
6,735
11,295 6,735
10,385 3,475
23,670 30,350 11,740 7,230
12,250 1,440
5,150
Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active
StatusType
Building Building Building Building Building Building Building Building Building Building Building Building Building Building Building Building Structure Structure Structure Structure Structure Structure
Use Group Built Flrs Const
Business Assembly Business Business Assembly Business Business Business Residential Residential Residential Assembly Education Business Business Business Business Storage Storage Storage Storage Storage
Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good
ConditionAsset Number
0090200019 0090200040 0090200044 0090200020 0090200021 0090200022 0090200023 0090200024 0090200025 0090200026 0090200027 0090200028 0090200029 0090200042 0090208038 0090200041 0090200043 0090200045 0090200046 0090208039 0090208036 0090208037
16 144,975
6 1,584
22 146,559
Buildings
Structures
Total
GSF
GSF
GSF
Summary
08/22/2012
Space Utilization By Function 00902 San Jose Page: 1 of Date:
HOUSING
EDUCATION
FOOD SERVICE
SUGGESTED
NSF/
ENROLLEE
SUGGESTED
TOTAL
NSF
ACTUAL
TOTAL
NSF
TYPE OF SPACE
SUB TOTAL
SUB TOTAL
SUB TOTAL
Resident Men Resident Women Total Residents
Residents 355 Non Residents 110
465Total Students
(355)
(440)
(465)
DIFFERENCE
35,500
20,760
8,370
50,285
27,492
7,960
Lounge Other Shower/Toilet Sleeping Storage
Academic (440) Non-Academic
30 -- Business Office Technologies 20 -- Culinary Arts + 24 -- Facilities Maint. and Const. + 30 -- Landscaping + 24 -- Material Handler
88 -- OCT
24 -- Retail Sales + 92 -- TCU Transportation
Vocational Theory (98)
Dining (2 Servings) Food Preparation Food Storage
7,840 4,990 4,960
30,220 2,275
6,904 7,857
1,700 1,670 2,280
1,060 4,065
3,800 2,270 1,890
3,550
4,260 25,560
2,130
4,400 4,400
1,200 1,200 1,800 1,500 1,560
2,760
3,720 2,790 1,860
4,290
4,660
2,504 3,457
-1,030 -874
1,305
-180
-520
Vocations
14,785
6,732
-410
08/22/2012
Space Utilization By Function 00902 San Jose Page: 2 of Date:
RECREATION
MEDICAL/DENTAL
ADMINISTRATION
STORAGE/SUPPORT
SUGGESTED
NSF/
ENROLLEE
SUGGESTED
TOTAL
NSF
ACTUAL
TOTAL
NSF
TYPE OF SPACE
SUB TOTAL
SUB TOTAL
SUB TOTAL
SUB TOTAL
TOTAL 230.86 107,350 112,047
(465)
(465)
(465)
(465)
DIFFERENCE
144,975
0.77
TOTAL GSF
NET TO GROSS RATIO
19,400
4,720
9,300
9,300
14,825
2,640
6,145
2,700
Gymnasium Learning Resource Center/Library Miscellaneous Recreation Non-Resident Lounge Recreation Room Student Store Weight Room
Medical Only Medical/Dental
Administration Child Development Center (0)
Operations & Maintenance Warehouse
4.39 5.76
7,950
1,540
2,100
1,800
1,510 1,130
3,535 2,610
1,290 1,410
2,040 2,680
9,300
3,720 5,580
-530 -1,550
-5,765
-2,430 -4,170
RESIDENT
NON-RESIDENT
(355)
(110) 15
50 17,750 1,650
-4,575
-2,080
-3,155
-6,600
4,697
Net Square Footage By Building Date: 11/28/2012 Page: 1
Center: SAN JOSE (00902) of 4
HOUSING
Sleeping
Lounge
Storage
Shower/Toilet
Other
Function Suggested
NSF
10,810 14,005
5,405
1,755 3,285 2,800
1,880 2,140
2,500
1,810
L-1 - FEMALE DORMITORY
L-2 - MALE DORMITORY
L-3 - FEMALE DORMITORY
L-3 - FEMALE DORMITORY
L-1 - FEMALE DORMITORY
L-2 - MALE DORMITORY
L-1 - FEMALE DORMITORY
L-2 - MALE DORMITORY
L-3 - FEMALE DORMITORY
L-1 - FEMALE DORMITORY
L-2 - MALE DORMITORY
L-3 - FEMALE DORMITORY
L-2 - MALE DORMITORY
L-3 - FEMALE DORMITORY
L-1 - FEMALE DORMITORY
M - RECREATION/GROUP LIFE
Bldg Name Actual NSF Difference
30,220
7,840
2,275
4,960
4,990
Sub Total: 50,285
25,560
3,550
2,130
4,260
35,500
4,660
4,290
4,990
( 355
14,785
Page: 2
Center: SAN JOSE (00902) of 4
EDUCATION
Academic
Vocational Theory (98)
Culinary Arts
Retail Sales
Facilities Maint. and Const.
Landscaping
Non-Academic
TCU Transportation
Material Handler
Business Office Technologies
Function Suggested
NSF
1,670
1,060
2,280
1,840
1,330
1,200
4,065
1,700
G - EDUCATION
M - RECREATION/GROUP LIFE
E - EDUCATION
E - EDUCATION
N - VOCATION/WAREHOUSE
E - EDUCATION
E - EDUCATION
G - EDUCATION
G - EDUCATION
E - EDUCATION
N - VOCATION/WAREHOUSE
F - DINING/CULINARY ARTS
F - DINING/CULINARY ARTS
N - VOCATION/WAREHOUSE
N - VOCATION/WAREHOUSE
N - VOCATION/WAREHOUSE
G - EDUCATION
E - EDUCATION
N - VOCATION/WAREHOUSE
P - CAREER TRANSITION
E - EDUCATION
G - EDUCATION
E - EDUCATION
Q - ICL
H - ADMIN/MEDICAL/DENTAL
TCU SATELLITE - SAN JOSE
D - MATERIAL HANDLING
N - VOCATION/WAREHOUSE
Bldg Name Actual NSF Difference
6,904
1,670
1,060
2,280
7,857
4,065
1,700
Sub Total: 27,492
4,400
1,200
1,800
1,500
4,400
2,760
1,560
1,200
20,760
2,504
-180
-1,030
3,457
1,305
-874
( 440
6,732
Page: 3
Center: SAN JOSE (00902) of 4
FOOD SERVICE
RECREATION
MEDICAL/DENTAL
Dining (2 Servings)
Food Preparation
Food Storage
Gymnasium
Weight Room
Student Store
Miscellaneous Recreation
Recreation Room
Non-Resident Lounge
Learning Resource Center/Library
Medical/Dental
Medical Only
Function Suggested
NSF
3,800
2,270
1,890
7,950
1,000
2,100
1,130
1,510
F - DINING/CULINARY ARTS
F - DINING/CULINARY ARTS
F - DINING/CULINARY ARTS
B - GYMNASIUM/RECREATION
B - GYMNASIUM/RECREATION
M - RECREATION/GROUP LIFE
M - RECREATION/GROUP LIFE
M - RECREATION/GROUP LIFE
B - GYMNASIUM/RECREATION
M - RECREATION/GROUP LIFE
H - ADMIN/MEDICAL/DENTAL
M - RECREATION/GROUP LIFE
H - ADMIN/MEDICAL/DENTAL
H - ADMIN/MEDICAL/DENTAL
Bldg Name Actual NSF Difference
3,800
2,270
1,890
7,950
1,800
1,540
2,100
1,130
1,510
Sub Total:
Sub Total:
Sub Total:
7,960
14,825
2,640
3,720
2,790
1,860
2,680
2,040
8,370
19,400
4,720
-520
-1,550
-530
-410
-4,575
-2,080
Page: 4
Center: SAN JOSE (00902) of 4
ADMINISTRATION
STORAGE/SUPPORT
Administration
Child Development Center
Warehouse
Operations & Maintenance
Function Suggested
NSF
2,675
2,610
1,410
1,290
A - WELCOME CENTER
G - EDUCATION
H - ADMIN/MEDICAL/DENTAL
J - CHILD CARE CENTER
N - VOCATION/WAREHOUSE
N - VOCATION/WAREHOUSE
Bldg Name Actual NSF Difference
3,535
2,610
1,410
1,290
Sub Total:
Sub Total:
6,145
2,700
9,300
5,580
3,720
9,300
9,300
-5,765
2,610
-4,170
-2,430
-3,155
-6,600
Energy Management Report Center: SAN JOSE (00902)
Page: 1 Date: 11/28/2012 of 3
CENTER ENERGY DATA
Yes
ENERGY CONSUMPTION ASSESSMENT
-14% 83,748
60,390 73,646
ENERGY USE BY FUEL TYPE
Energy Audit :
Date of Audit :
Status of Energy Conservation Measure Recommendations :
Electric Company :
Percent Change since Baseline Year :
Natural Gas Company :
Property Status :
6/27/05 Implemented Pacific Gas & Electric Pacific Gas and Electric
Combination of Owned & Leased
1,699,468 5,799=
Total 11,910
MBtu
MBtu
Total $297,741 MBtu/ $24.999
BTU/GSF
BTU/GSF
BTU/GSF
Electricity
Natural Gas kWh
5,927 MCF = 6,111 MBtu
$253,985 $0.149= kWhElectricity
Natural Gas $43,756 = $7.382 MCF
ENERGY COST BY FUEL TYPE
COMMENTS
2/01 - Gas consumption will increase as several inoperative boilers have been repaired
WATER CONSUMPTION ASSESSMENT
Percent Reduction Since Baseline Year:
1,000 Gallons
1,000 Gallons
FY 2011 Energy Goal:
Further Reduction in Energy Usage is needed to meet Energy Reduction Goals.
FY 2011 Energy Consumption:
Note: The Federal Government has set a goal of 3% Energy Consumption Reduction per year in EO 13423.
9,743 8,964 9,750
Further Reduction in Water Usage is needed to meet Water Reduction Goals.
Note: The Federal Government has set a goal of 2% Water Consumption Reduction per year in EO 13423.
FY 2011 Goal:
FY 2011 Water Consumption:
1,000 Gallons
FY 2003 Energy Baseline:
FY 2007 Baseline:
Page: 2 of 3
Implementing some of the below recommendations can save you 10% to 25% off your annual energy bill without negatively impacting comfort or productivity.
1. Your staff and students are the key to savings. Educate the students and staff on the why of energy saving - costs and environmental impacts. Encouraging them to actively participate in energy reduction is also important. Post reminders at exit doors and bulletin boards about energy conservation. Simple tips include:
a. Turn it down (lights, heating & cooling),
b. Turn it off (lights, computers, other equipment),
c. Keep it tight (close doors and windows, use window blinds)
2. Operations and Maintenance: Educate the O&M staff on the why of energy saving -costs and environmental impacts. Simple tips include:
a. Make sure that the Operations and Maintenance staff is properly trained for the equipment they operate.
b. Tune and clean HVAC: Perform seasonal cleanups on air conditioners, boilers and furnaces, and regularly clean cooling coils and drain pans. Get rooftop or outdoor condenser coils cleaned and maintain an appropriate filter changing schedule.
c. Check (or ask your HVAC contractor to check) your outside air dampers or economizers to verify proper ventilation. Make sure economizer controls function properly. Make sure automatic dampers close during unoccupied periods.
d. Restore automatic control: When troubleshooting a system, take time to figure out and repair the automatic controls. Today's quick fix is tomorrow's bad idea.
e. Reasonable set points: Try 68°F in the heating season and 75°F in the cooling season.
f. Schedule HVAC equipment and lighting: (weekdays, weekends, holidays, off-season). Make sure equipment runs only when it is needed and the buildings are occupied. When buildings are vacant (i.e. dormitories during the day with students in class), make sure all the lights in the building are off.
g. Seasonal (resets, schedules, and shutoffs): As the seasons change, adjust set points and schedules to match the system's response to the weather.
h. Lighting: Invest in an inexpensive light level meter to measure the foot-candles in spaces to determine whether or not they are over lit and lamps can be safely removed. Where four-lamp fixtures are in use, two lamps can usually be removed from every fixture or every other fixture. After lamps are removed, disconnect ballasts. Contact the Energy team at PBDewberry for suggested light levels for individual space types. Cleaning fixtures regularly increases light levels.
i. Utilize power management features for all computers and monitors to shut them off when idle for more than 15 minutes.
Page: 3 of 3
j. Have your vending machine suppliers turn off or remove light tubes from the advertising lighting in the machine. This will save about $50 per year per vending machine.
k. Save water with low flow sink aerators (0.5gpm) and low flow shower heads (1.5gpm - 2.0gpm). This will also reduce water heating energy consumption.
l. Set your water heater to 120°F. Verify by measuring at the tap. Never go below 115°F.
m. For water heaters installed in unconditioned spaces, add insulation blankets making sure that access covers, electric connection areas, and pressure relief valves are left uncovered.
n. Caulk and fill cracks around doors and windows to reduce costly air leaks.
o. When replacing broken glass, use high transmittance, low heat gain windows.
p. Make sure automatic door closers are functioning properly to avoid drafts.
3. Buy energy efficient, buy EnergyStar (www.energystar.gov).
a. Buy EnergyStar appliances and equipment.
b. Replace burned out lightbulbs with EnergyStar labeled compact fluorescent lightbulbs (CFLs).
c. Replace broken thermostats with EnergyStar labeled programmable products.
d. Replace broken exit signs with EnergyStar LED exit signs.
Environmental Management Report
Page: 1 Date: 11/28/2012 of 1
SOLID & HAZARDOUS WASTE MANAGEMENT (RCRA)
Commercial Waste Service
HAZARDOUS MATERIALS STORAGE (EPCRA)
Yes Bldg. F Patio, Bldg. T-1, Bldg. T-2
Propane gas (2 1-gal Tanks), oil-based Paint (10 gals), paint thinner (3 gals), gasoline (5 gals)
Yes
PETROLEUM UNDERGROUND STORAGE TANKS (RCRA)
N/A0
PETROLEUM ABOVEGROUND STORAGE TANKS (CWA)
ASBESTOS AND PCB MANAGEMENT (TSCA)
AIR POLLUTION CONTROL (CAA)
N/A None
Attainment
Solid Waste Disposal :
Hazardous Waste Generator :
Hazardous Waste ID :
Generator Classification :
Hazadous Materials Storage :
Hazardous Materials ID :
HazMat Storage Area :
HazMat Spill Response Plan :
Number of Regulated USTs :
Number of Un-regulated USTs :
Local Hazardous Use Permit :
LEPC Notification :
EPA Generator ID Number :
Hazardous Waste Disposal :
RCRA Compliance
ID LocationFuel Type Capacity
Number of ASTs :
Asbestos Survey Date :
Asbestos Type :
Asbestos Coordinator :
Coordinator Training Date:
Custodial/Maintenance Training :
AHERA Regulated :
Management Plan Approval :
PCB Transformer Testing :
PCB Transformers :
PCB-Contaminated Transformers :
Transformers Labelled :
Regional Air Quality :
Permitted Air Pollution Source :
Source Description :
Stevens Creek Disposal Yes Oil-based paint (1gal/month),organic solvent (1gal/ month), x-ray developer (2 gal/
Conditionally Exempt Small Quantity Generator
CAL000120837
Commercial Hazardous Waste Disposal Service
ECO Solutions & Integrated Environmental Systems
No No
Overfill Leak Corrosion
SPCC Plan Required : SPCC Plan Completed :
N/A N/A
07/13/1990 Friable/Non-Friable Benjamin Mundwyler 03/01/2001 Yes No
No No
ID Fuel Type Capacity Location Overfill
Prevention Secondary ContainmentTank Status
Tank Status Prevention/Detection
Asbestos-Containing Materials Inventory
Date: 11/28/2012Center : San Jose (00902) Page: 1 of 1
Plumbing (Bldg) Floor Finishes Floor Finishes
Plumbing (Bldg) Floor Finishes Floor Finishes
Plumbing (Bldg)
Plumbing (Bldg)
Bldg System
Bldg System
Bldg System
Bldg System
Pipe fitting insulation Mastic beneath 9x9 floor tile 9x9 Vinyl floor tile
Pipe fitting insulation 9x9 Beige vinyl floor tile Mastic beneath 9x9 floor tile
Pipe fitting insulation
Pipe fitting insulation
Category Description
Category Description
Category Description
Category Description
Ea.
Sq. Ft.
Sq. Ft.
Ea.
Sq. Ft.
Sq. Ft.
Ea.
Ea.
Location
Location
Location
Location
Unit
Unit
Unit
Unit
Quantity
Quantity
Quantity
Quantity
Classroom & Mech rm Throughout building Throughout building
Classroom & Mech rm Throughout building Throughout building
Above ceiling
Nursery & Mech. room
Building :
Building :
Building :
Building :
E - EDUCATION
G - EDUCATION
H - ADMIN/MEDICAL/DENTAL
J - CHILD CARE CENTER
Radon
Page: 1 of 1
A - WELCOME CENTER
B - GYMNASIUM/RECREATION
D - MATERIAL HANDLING
E - EDUCATION
F - DINING/CULINARY ARTS
G - EDUCATION
H - ADMIN/MEDICAL/DENTAL
J - CHILD CARE CENTER
L-1 - FEMALE DORMITORY
L-2 - MALE DORMITORY
L-3 - FEMALE DORMITORY
M - RECREATION/GROUP LIFE
N - VOCATION/WAREHOUSE
P - CAREER TRANSITION
Q - ICL
TCU SATELLITE - SAN JOSE
Bldg Name
06/06/1990
06/06/1990
06/06/1990
06/06/1990
06/06/1990
Test Date
No
No
N/A
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
No
No
Radon Testing
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
Test Result
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
Mitigation Mitigation Date
RADON EXPLANATORY NOTES
The US Environmental Protection Agency (EPA) has established a radon action level of 4.0 picoCuries per liter (pCi/L). Occupied buildings with radon concentrations less than 4.0 pCi/L do not require radon mitigation; un-occupied buildings, or those buildings which are occupied only infrequently for brief periods of time, also do not require radon mitigation. Occupied buildings with radon concentrations greater than
4.0 pCi/L require radon mitigation and verification of radon reductions as soon as possible, with priority given to dormitories and student recreation buildings. Occupied buildings with radon concentrations greater than 20.0 pCi/L should be considered significant radon exposure hazards, and priority for mitigation should be given to buildings with these highly elevated radon concentrations.
Radon mitigation techniques include: (1) adjustment of the building HVAC system to create a positive pressure within the building; (2) sealing of foundation wall cracks, penetrations, or other openings;
(3) sealing crawlspace openings and sump pits; (4) installing an active subslab depressurization (ASD) system.
Site Description
SAN JOSE
Aerial View of San Jose JCCAerial View of San Jose JCC
Page: 1 Date: 11/30/2012 of 4
Comments:
Paving Type for Roads & Parking
There are bike racks at the entrance to the center.
Paving Type for Sidewalks
Asphalt Concrete
Comments:
Topography Buildings and Structures
Center is fully enclosed by fencing.
ROADS, PARKING & SIDEWALKS
Water Source Water Authority Service Meter On-Site Treatment Plant
1. Water System
Treatment Type Storage Type Storage Capacity(Gallons)
NoMasterCity of San JosePublic Water Authority
None 0None
There is a site master meter for all buildings except for Gymnasium/Recreation Building B, which has a dedicated water meter.
Comments:
Fire Hydrants On-Site Water Supply Storage Capacity
(Gallons) Pressure Source FD Response Time (Minutes)
Yes 0 5None Municipal
Sewage Treatment Flow
Center
Publicly Owned Treatment Works
Center
Gravity
Maintenance ResponsibilityOwnership
Number of Deficiencies = 1SITE FEATURES
UTILITIES
3. Sanitary Sewer System/ Sewage Treatment Plant
2. Fire Protection System
Buildings Structures16 6Flat
Surrounding
Outdoor Recreation
Residential
Basketball None
North side of the property
West, south and east sides
Wrought Iron
CMU
Location Type
Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
Separate Loop
No
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
System Capacity Adequate System Condition
Yes Good
Ownership
Roads & Parking Adequate Roads & Parking Condition Sidewalks Adequate Sidewalk Condition Yes Good Yes Good
Number of Deficiencies = 1
Fencing
Other Features
Page: 2 Date: 11/30/2012 of 4
Pacific Gas and Electric
Comments:
Electric Company PCB Trans.
Transformer Mounting Transformer Ownership
Systems Ownership Maintenance Responsibility
Pacific Gas & Electric
The primary underground service is delivered to the center from the last power pole on East Hills Drive and Gunn Court at the center main entrance. The service entrance equipment, located behind Building H, consists of a pad-mounted utility-owned transformer and a 1,600A, 480/277V, 3-phase, 4 wire, center-owned main switchboard with a built-in meter. An 800A switch in the main switchboard feeds distribution switchboard MDP-1 located in Building H main computer room. Switchboard MDP-1 in turn, provides services to Buildings E, G, H, L-2 and N. A second 800A switch in the main switchboard feeds distribution switchboard MDP-2 located in Building F electrical room.
Switchboard MDP-2 provides services to Buildings F, L-1, L-3 and M. Gymnasium/Recreation Building B is served by a 225A switch in the main switchboard. A 45 kVA, 480V:120/208V, pad-mounted transformer located next to the main switchboard provides service to Welcome Center Building A. The 480/277V services are further stepped down to 120/208V via pad-mounted transformers located inside the respective buildings.
Pad Utility
Utility Utility
No
12.47 kV, 3-Phase, 3 Wire
480/277V & 208/120V, 3-Phase, 4 WireUnderground
Overhead & UndergroundPrimary Service
Secondary Service
Distribution Characteristics
5. Fuel Distribution System
4. Storm Water System
Drain Type On-Site Storm Water Management
Underground Retention Pond
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center Yes GoodCenter
Gas Company Metering
Master
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
7. Electrical (Service)
Transformer Maint Resp
Utility
System Capacity Adequate System Condition
Yes Good
Generator
None
8. Electrical (Site Lighting)
Roadways Parking Walkways Building Outdoor Sports
Mounting
Control
Pole Pole Pole Building Pole
Photocell Photocell Photocell, Time Clock Photocell, Time Clock Photocell, Time Clock
System Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
ATS MTS
No No
6. Central Plant: None
Metering Master
Page: 3 Date: 11/30/2012 of 4
ACCESSIBILITY
Yes
NoNoNoNo
Nationally Registered Site
Site Eligible for National Register
Located in Historic District
Archaeological Significance
Comments:
Telephone Company
On-site Line Owner
AT&T provides telephone service. The data network and IP service are provided and maintained by Job Corps Data Center. The center has digital voice over IP. The center is provided with 5 T1 lines, which enter the main data closet located in Building H. The fire alarm control/annunciator panels (FACP) in most buildings on center are monitored by the center's annunciator panel located in Welcome Center Building A. This site graphic annunciator panel provides building location fire alarm monitor points center wide. Gymnasium/Recreation Building B fire alarm panel is connected to the main FACP in Welcome Center Building A. Buildings C and D fire alarm devices are also connected to the main FACP. The fire alarm panel in Child Care Center Building J is connected to the FACP in Building B. An electric gate operator with a card reader is installed at the campus main entrance to the south and rear entrance to the north. The main gate can be remotely controlled from the Welcome Center Building A. Door alarms are installed at the dormitory exit doors. Satellite dish TV is provided in the dormitory, administration, and recreation buildings. The center's warning system is controlled from Admin/Medical/Dental Building H and several speakers are located throughout the center.
AT&T
Maint. Responsibility
Center Center
Electrical Gate Operators, Card Readers, Door Alarms
Earthquake Risk
High Low LowLow LowUniform Low
LightningEarthquake Def. Authority Flooding Tornado Hurricane Forest
Fire
Number of Deficiencies = 1
Accessible Parking: Accessible Slope:
Yes
Curb Cuts:
Yes
Ramps:
N/AYes
Site Accessible Route:
GENERAL SITE CONDITION
Rating X Good Fair Poor
HISTORIC PRESERVATION
9. Electrical (Communication/Alarm/Security)
NATURAL HAZARDS
The site condition is not impacting the functional use of the facilities.
The site condition IS impacting the functional use of the facilities.
The site condition IS SIGNIFICANTLY impacting the functional use of the facilities.
Yes
Stand-Alone
VOIP
System Capacity Adequate System Condition
GoodYes
Number of Deficiencies = 7
STORAGE TANKS: None
Fire Alarm Security
Page: 4 Date: 11/30/2012 of 4
SATELLITE SITE DESCRIPTION
Location:
Description:
Ownership Maintenance Responsibility
Downtown San Jose
The second floor of 95 S. Market Building Stateside property is leased for classrooms.
Lessor Lessor
Rating The site condition is not impacting the functional use of the facilities.
The site condition IS impacting the functional use of the facilities.
The site condition IS SIGNIFICANTLY impacting the functional use of the facilities.
Good Fair Poor
X
SATELLITE SITE CONDITION
Building Descriptions and Utilities
BUILDING A WELCOME CENTERBUILDING A - WELCOME CENTER
Building Descriptions
Page: 1 of 76
Building: A - WELCOME CENTER
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Wood Wood
Stucco
Wall Roof Batt Batt
Metal Unit - Metal Frame
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Business 100 80 1 Owned 1993 Unevaluated
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
N/A
Yes
N/A
N/A
N/A
Yes
N/A
N/A
N/A
N/A
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Insulation4.
Exterior Doors5.
Material
The estimated remaining roof life is based on visual observation during the March 2012 Facility Survey.
Drainage Year Life
Remaining Type Area Served
Rolled Asphalt Surface Run-off 1993 4 Flat Entire Building
Comments:
3. Roof
Entire Building
Area Served
Page: 2 of 76
Building: A - WELCOME CENTER
INTERIOR FINISH
Concrete
Drywall
None
Natural Entire Building
Ventilation Area Served
VERTICAL CIRCULATION
None
Fixed - Aluminum Frame; Double Glazing; Single Hung - Aluminum Frame; Double Glazing;
Sliding - Aluminum Frame; Double Glazing;
Gypsum Board
Exhaust Ventilation
Windows6.
Floors1.
Interior Walls2.
3.
Interior Doors4.
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
HVAC
Heat1.
None None None None Natural None Entire Building
Ventilation2.
Ceilings
Page: 3 of 76
Building: A - WELCOME CENTER
None None None
None
None
None None ABC Type Fire Extinguisher
Comments: Service is brought from a 45 kVA, 480V:120/208V pad-mounted transformer outside to a 100A MCB panel located inside the building.
None None None None No
Hot Water Cold Water Water Heater Water Treatment HW Storage Tank
Grease InterceptorWaste / Vent Interior Storm
Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices
Packaged Direct
Expansion (Air Cooled)
Window Unit None Electric Mechanical None Entire Building
Compact Fluorescent
Comments: There are three recessed compact fluorescent light fixtures, located at the canopy above the security window and controlled by the on/off switch inside the building.
Main Branch Panel 120/208V, 3-Phase, 4 Wire Branch Panel Only Receptacles, Switches
Sprinkler System Stand Pipe System Fire Suppression
PLUMBING
System Type
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Water Distribution1.
Sanitary Distribution2.
Fixtures3.
Fuel Distribution4.
FIRE PROTECTION
ELECTRICAL SERVICES
Exterior Lighting1.
3. Air Conditioning
LIGHTING
Page: 4 of 76
Building: A - WELCOME CENTER
FIRE ALARM
Comments: The main fire alarm control/annunciator panel (FACP), an Edwards System Technology model EST-3, is located in this building. This panel only monitors and controls the FACP in Gymnasium/Recreation Building B, and fire alarm devices in Buildings C and D. A site graphic annunciator panel provides building location fire alarm monitor points center wide. Buildings E, F, G, H, M, L-1, L-2, L-3 and N are monitored by this annunciator panel.
Comments: There are total three operational security cameras monitored by the color monitor located inside the building. One building-mounted bullet camera is located on the west building exterior wall, one camera is pole-mounted at the front parking lot and one camera is located inside the building. There is a motorized gate at the main entrance to the center controlled from Building A. Building A is provided with an intercom system with the intercom device and card reader both located at the main entrance to the center.
Central Annunciator Panel Control/Annunciator Panel
Connected to Main System Closed Circuit TV None None
Telephone Security Public Address Television
Comments: The recorded footcandle level includes natural light contribution.
Compact Fluorescent65Offices 50
Area Recommended Level
Recorded Level Light Type
None None
Emergency Exit
GENERAL BUILDING CONDITION
Rating X Good
Fair Poor
Interior Lighting2.
Emergency /Exit Lighting3.
COMMUNICATION
The facility condition is not impacting the functional use of the facility.
The facility condition IS impacting the functional use of the facility.
The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.
Electric Water Gas N/A N/ANo
BUILDING UTILITY METERING
Structure: Good Exterior: Good Interior: Good Mechanical: Good Electrical: Good
BUILDING B GYMNASIUM/RECREATIONBUILDING B - GYMNASIUM/RECREATION
Page: 5 of 76
Building: B - GYMNASIUM/RECREATION
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Loadbearing Masonry Steel
CMU Masonry Stucco
Wall Roof Batt/Rigid Rigid
Metal Unit - Metal Frame
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Assembly 12,500 9,820 1 Owned 2003 Unevaluated
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
N/A
Yes
Yes
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Insulation4.
Exterior Doors5.
Material Drainage Year Life
Remaining Type Area Served
Built-up Roofing Interior Roof Drains 2003 11 Flat Entire Building
3. Roof
Page: 6 of 76
Building: B - GYMNASIUM/RECREATION
Comments: There are skylights in the gymasium.
INTERIOR FINISH
Ceramic Tile Rubber Vinyl Tile Wood
Comments: The gymnasium floor is a synthetic athletic flooring.
CMU Ceramic Tile Drywall FRP Gym Wall Padding
Comments: The gymnasium has exposed metal roof deck.
Wood Unit - Metal Frame
VERTICAL CIRCULATION
Concrete Stairs Metal Ladder Ramp
Comments: There are metal ladders to the roof in the storage room and office. The exterior ladder is from the lower roof to the high gymnasium roof surface. Ramp and stairs are from the gymnasium to the stage.
Fixed - Aluminum Frame; Double Glazing; Fixed - Metal Frame; Single Glazing;
Skylight - Aluminum Frame; Double Glazing;
Acoustical Tile Exposed Structure Gypsum Board
Number of Deficiencies = 1
Windows6.
Floors1.
Interior Walls2.
3.
Interior Doors4.
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Two packaged rooftop units (Carrier #48HJE006) serve the lobby, office, and weight/aerobics room.
Two packaged rooftop units (Carrier #48HJZ414, 184 MBH output, built 10/2002) serve the gymnasium.
Comments:
Comments:
HVAC
Heat1.
Gas-Fired Packaged
Gas-Fired Packaged
Single Duct
Single Duct
None
None
Electronic
Electric
Mechanical
Mechanical
None
None
Recreation Area
Gymnasium
Page: 7 of 76
Building: B - GYMNASIUM/RECREATION
Mechanical
Mechanical
Restroom
Janitor's Closet
Domestic hot water heater (AO Smith #FGR40248E, 40 gallon, 38 MBH input) is located in the janitor's closet.
Comments:
Cast Iron/PVC None Cast Iron
Electric Water Cooler Hose Bibb Lavatory Mop Sink Urinal Water Closet (Flush Valve)
Gas (Natural)
Wet None ABC Type Fire Extinguisher
Ventilation Area Served
Copper Copper Gas-Fired None No
Hot Water Cold Water Water Heater Water Treatment HW Storage Tank
Grease InterceptorWaste / Vent Interior Storm
Packaged Direct
Expansion (Air Source)
Packaged Direct
Expansion (Air Source)
Single Duct
Single Duct
None
None
Electric
Electric
Mechanical
Mechanical
None
Economizer
Recreation Area
Gymnasium
Sprinkler System Stand Pipe System Fire Suppression
PLUMBING
Exhaust Ventilation
Two packaged rooftop units (Carrier #48HJE006, 5 ton) serve the lobby, office, and weight/aerobics room.
Two packaged rooftop units (Carrier #48HJZ414, 184 12-1/2 ton, built 10/2002) serve the gymnasium;
one is equipped with economizer mode operation including power exhaust.
Comments:
Comments:
Ventilation2.
System Type
Number of Deficiencies = 1
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Water Distribution1.
Sanitary Distribution2.
Fixtures3.
Fuel Distribution4.
FIRE PROTECTION
Page: 8 of 76
Building: B - GYMNASIUM/RECREATION
Comments: Service is brought from a 225A switch in the main switchboard located behind Building H. Service terminates in a 225A panel (by IEM, model PIU, 14 kA) with a 200A MCB located in the gymnasium electrical room. A 30 kVA transformer (by Cutler-Hammer, V48M28T30K, C-series) provides the 120/208V, 3-phase, 4 wire system for the building. The transformer serves a 100A MCB panel providing for 120/208V loads.
FIRE ALARM
Comments: The fire alarm control/annunciator panel is an Edwards Systems Technology model EST-3 located in the electrical room. This panel also monitors a fire alarm panel in Child Care Center Building J. The fire alarm panel in this building is connected to the main fire alarm control/annunciator panel in Building A. Beam detectors are provided in the gymnasium.
Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices
Audible Alarm Beam Detector Control/Annunciator Panel Duct Smoke Detector Exterior Audio/ Visual Device Flow Switch Heat Detector Manual Pull Station Smoke Damper Smoke Detector Tamper Switch Visual Alarm
Comments: Recorded footcandle levels include natural light contribution. There are 12 skylights in the gymnasium.
Lighting in the gymnasium is provided by high pressure sodium light fixtures.
Comments: Combination exit sign emergency light fixtures are utilized in the gymnasium. Selected linear fluorescent light fixtures with battery backup are also provided.
High Intensity Discharge (HID)
Comments: Exterior building-mounted and surrounding area pole-mounted light fixtures are controlled by lighting control panel (by Intelligent Lighting Control) with an integral time clock and a photocell.
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
High Intensity Discharge (HID)
T8 - Fluorescent
Offices
Recreation
Lounges
Corridors & Stairs
Storage Rooms
Toilets
Equipment Rooms (Elec/Mech)
Gymnasium
Storage Rooms
Area Recommended Level
Recorded Level Light Type
Battery Backup Battery Backup
Main Distribution Panel 277/480V, 3-Phase, 4 Wire Panelboard Receptacles, GFCI, Switches
Emergency Exit
Number of Deficiencies = 1
ELECTRICAL SERVICES Number of Deficiencies = 1
Exterior Lighting1.
Interior Lighting2.
Emergency /Exit Lighting3. Number of Deficiencies = 1
Page: 9 of 76
Building: B - GYMNASIUM/RECREATION
Comments: The building is connected to the center's telephone and LAN system. Roof-mounted paging horn speakers (model SC-630, VNS2084) are connected to the warning system controlled from Admin/Medical/Dental Building H.
Connected to Main System None Connected to Main System Satellite Dish
Telephone Security Public Address Television
GENERAL BUILDING CONDITION
Rating X Good
Fair Poor
COMMUNICATION
The facility condition is not impacting the functional use of the facility.
The facility condition IS impacting the functional use of the facility.
The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.
Electric Water Gas Yes NoNo
BUILDING D MATERIAL HANDLINGBUILDING D - MATERIAL HANDLING
Page: 10 of 76
Building: D - MATERIAL HANDLING
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Loadbearing Masonry Wood
CMU Masonry Stucco
Wall Roof Batt Batt
Metal Overhead - Metal Frame Metal Unit - Metal Frame
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Business 960 686 1 Owned 1999 Unevaluated
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
N/A
Yes
N/A
Yes
N/A
Yes
N/A
N/A
N/A
Yes
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Insulation4.
Exterior Doors5.
Material Drainage Year Life
Remaining Type Area Served
Asphalt Shingles Gutters and Downspouts 1999 7 Gable Entire Building
Number of Deficiencies = 13. Roof
Page: 11 of 76
Building: D - MATERIAL HANDLING
Comments: There are skylights in the classroom.
INTERIOR FINISH
Concrete
Chain link Drywall
Metal Unit - Metal Frame
Mechanical Entire Building
Comments: This is provided by a sidewall propellar fan.
Ventilation Area Served
VERTICAL CIRCULATION
None
Fixed - Aluminum Frame; Double Glazing; Fixed - Aluminum Frame; Single Glazing;
Skylights - Aluminum Frame; Double Glazing;
Split Direct Expansion (Air
Source)
Single Duct Refrigerant Electronic Natural None Entire Building
Gypsum Board
Exhaust Ventilation
Cooling is provided to the furnace/DX coil (Carrier, with a condensate pump) by a condensing unit (Carrier, 2-1/2 ton).
Comments:
Windows6.
Floors1.
Interior Walls2.
3.
Interior Doors4.
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
The horizontal furnace (Carrier #58DLX070, 70 MBH, built 5/2006) is hung above the storage area.Comments:
HVAC
Heat1.
Gas-Fired Furnace
Single Duct None Electric Natural None Entire Building
Ventilation2.
System Type
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Page: 12 of 76
Building: D - MATERIAL HANDLING
None None None
Portable Bottled Water Cooler
Gas (Natural)
None None ABC Type Fire Extinguisher
Comments: Service is sub fed from a 200A disconnect switch fused at 150A located in Building L-1 and terminates in a 100A MCB main panel in Building D. The main panel feeds a 100A MLO secondary panel controlled by the emergency shut off switch. Since the building use changed from a shop to a classroom, the emergency shut off switch is not in use.
None None None None No
Hot Water Cold Water Water Heater Water Treatment HW Storage Tank
Grease InterceptorWaste / Vent Interior Storm
Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices
Comments: Recorded footcandle levels include natural light contribution. There are six skylights in the large classroom.
High Intensity Discharge (HID)
Comments: Exterior building-mounted light fixtures are controlled by a photocell.
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
Classrooms
Offices
Storage Rooms
Area Recommended Level
Recorded Level Light Type
Main Panelboard 120/208V, 3-Phase, 4 Wire Panelboard Receptacles, GFCI, Switches
Sprinkler System Stand Pipe System Fire Suppression
PLUMBING
Water Distribution1.
Sanitary Distribution2.
Fixtures3.
Fuel Distribution4.
FIRE PROTECTION
ELECTRICAL SERVICES Number of Deficiencies = 1
Exterior Lighting1.
Interior Lighting2.
Page: 13 of 76
Building: D - MATERIAL HANDLING
FIRE ALARM
Comments: The fire alarm control/annunciator panel is a DSC model MAXSYS PC 4020CF located in the electrical closet. This panel reports to the fire alarm panel in Building B.
Comments: The building is connected to the center's telephone and LAN system. There is a local security keypad with a motion sensor in this building.
Audible Alarm Manual Pull Station Smoke Detector Visual Alarm
Connected to Main System Motion Detector None TV with VCR
Telephone Security Public Address Television
Battery Backup Battery Backup
Emergency Exit
GENERAL BUILDING CONDITION
Rating
Comments:
X Good Fair Poor
The building lacks toilet facilities.
Emergency /Exit Lighting3.
COMMUNICATION
The facility condition is not impacting the functional use of the facility.
The facility condition IS impacting the functional use of the facility.
The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.
Electric Water Gas N/A NoNo
BUILDING UTILITY METERING
Structure: Good Exterior: Good Interior: Fair Mechanical: Good Electrical: Good
This building has been recommended for demolition in the Long Range Development Plan.
DEMOLITION RECOMMENDATION
BUILDING E EDUCATIONBUILDING E - EDUCATION
Page: 14 of 76
Building: E - EDUCATION
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Wood Wood
There is a covered walkway at the west side of the building.
Ceramic Tile Metal Siding Stucco
Wall Roof Batt Batt
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Business 6,735 5,520 1 Owned 1964 Unevaluated
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
N/A
Yes
Yes
Yes
N/A
Yes
N/A
N/A
Yes
Yes
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Insulation4.
Material
The roof was repaired and patched in 2008 to prolong its life expectancy. The estimated remaining roof life is based on visual observation during the March 2012 Facility Survey.
The roof was repaired and patched in 2008 to prolong its life expectancy. Roof life is estimated based on visual observation and condition of the roof during the March 2012 Facility Survey.
Drainage Year Life
Remaining Type Area Served
Rolled Asphalt
Rolled Asphalt
Scuppers and Downspouts
Surface Run-off
Flat
Flat
Entire Building
Covered Walkway
Number of Deficiencies = 1
Comments:
Comments:
3. Roof
Entire Building
Comments:
Page: 15 of 76
Building: E - EDUCATION
INTERIOR FINISH
Carpet Ceramic Tile Concrete Epoxy Vinyl Tile
Ceramic Tile Drywall
Accordion - Metal Frame Wood Unit - Metal Frame
VERTICAL CIRCULATION
None
Metal Unit - Metal Frame
Double Hung - Aluminum Frame; Double Glazing; Fixed - Aluminum Frame; Single Glazing;
Hopper - Aluminum Frame; Single Glazing; Sliding - Aluminum Frame; Double Glazing;
Acoustical Tile Gypsum Board
Number of Deficiencies = 1
Exterior Doors5.
Windows6.
Floors1. Asbestos: Yes
Interior Walls2.
3.
Interior Doors4.
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Each space in the building is served by a packaged rooftop unit built in the summer of 1993. Two similar units (York #D4CG048N06246ECA, 62 MBH output) serve the GED classroom and Career Exploration room. Eight other units (York #D2GA024N03206B, 32 MBH output) serve the balance of the rooms.
Comments:
HVAC
Heat1.
Gas-Fired Packaged
Single Duct None Electric Mechanical None Entire Building
Page: 16 of 76
Building: E - EDUCATION
Mechanical
Mechanical
Restroom
Mechanical Equipment Room
The domestic hot water heater (10 gallon) is located in the janitor's closet.Comments:
Cast Iron None None
Fixed Emergency Eyewash Hose Bibb Lavatory Service Sink Urinal Water Closet (Flush Valve)
Gas (Natural)
None None ABC Type Fire Extinguisher
Ventilation Area Served
Copper Copper Electric None No
Hot Water Cold Water Water Heater Water Treatment HW Storage Tank
Grease InterceptorWaste / Vent Interior Storm
Packaged Direct
Expansion (Air Source)
Single Duct None Electric Mechanical None Entire Building
Sprinkler System Stand Pipe System Fire Suppression
PLUMBING
Exhaust Ventilation
Each space in the building is served by a packaged rooftop unit built in the summer of 1993. Two similar units (York #D4CG048N06246ECA, 4 ton) serve the GED classroom and Career Exploration room. Eight other units (York #D2GA024N03206B, 2 ton) serve the balance of the rooms.
Comments:
Ventilation2.
System Type
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Water Distribution1.
Sanitary Distribution2.
Fixtures3.
Fuel Distribution4.
Page: 17 of 76
Building: E - EDUCATION
Comments: Service is brought from a 175A breaker in switchboard MDP-1 located in Building H. Service terminates in three enclosed circuit breakers, two 20A serving two 4 ton RTU units and a 175A CB serving a 112.5 kVA step down transformer (by Square D, imp. 4.2%). The transformer provides the 120/208V, 3-phase, 4 wire system for the entire building and serves several 120/208V panels: 200A MCB panel LE serving HVAC loads, 225A MLO panel D1 serving lighting loads, 225A MLO panel CMPE and a 125A MLO computer panel, both serving receptacles and computer loads. Panel CMPE is protected by a transient voltage surge suppression (by Leviton). Switchboard MDP-1 also provides services to Buildings G, H, L-2 and N.
FIRE ALARM
Comments: The fire alarm control/annunciator panel is an Edwards Systems Technology model LSS1 located in the electrical room. The remote annunciator panel, pull station and A/V devices are installed on the building exterior.
Comments: The building is connected to the center's telephone and LAN system. The classrooms are equipped with TV/VCR and computer work stations.
Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices
Control/Annunciator Panel Exterior Audible Alarm Exterior Manual Pull Station Exterior Visual Alarm Heat Detector Remote Annunciator Panel
Connected to Main System None None TV with VCR
Telephone Security Public Address Television
Comments: Recorded footcandle levels include natural light contribution.
High Intensity Discharge (HID)
Comments: Exterior building-mounted light fixtures are controlled by a time clock.
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
Offices
Classrooms
Toilets
Equipment Rooms (Elec/Mech)
Area Recommended Level
Recorded Level Light Type
Selected Lighting w/ Battery Battery Backup
Main Circuit Breaker 277/480V, 3-Phase, 4 Wire Panelboard Receptacles, GFCI, Switches
Emergency Exit
ELECTRICAL SERVICES Number of Deficiencies = 2
Exterior Lighting1.
Interior Lighting2.
Emergency /Exit Lighting3.
COMMUNICATION
Electric Water Gas No NoNo
Page: 18 of 76
Building: E - EDUCATION
GENERAL BUILDING CONDITION
Rating X Good
Fair Poor
The facility condition is not impacting the functional use of the facility.
The facility condition IS impacting the functional use of the facility.
The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.
BUILDING F DINING/CULINARY ARTSBUILDING F - DINING/CULINARY ARTS
Page: 19 of 76
Building: F - DINING/CULINARY ARTS
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Wood Wood
Brick Masonry Metal Siding Stucco
Wall Roof Batt Batt
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Assembly 11,295 10,030 1 Owned 1964 Unevaluated
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
N/A
Yes
Yes
Yes
Yes
Yes
N/A
N/A
Yes
Yes
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Insulation4.
Material Drainage Year Life
Remaining Type Area Served
Rolled Asphalt
Metal
Interior Roof Drains
Gutters and Downspouts
Flat
Shed
Kitchen
Dining Hall
Number of Deficiencies = 13. Roof
Page: 20 of 76
Building: F - DINING/CULINARY ARTS
INTERIOR FINISH
Ceramic Tile Concrete Epoxy Quarry Tile Vinyl Tile Wood
Ceramic Tile Drywall Stainless Steel
Metal Unit - Metal Frame Wood Unit - Metal Frame
VERTICAL CIRCULATION
None
Metal Unit - Metal Frame Storefront - Metal Frame
Fixed - Aluminum Frame; Double Glazing;
Acoustical Tile Gypsum Board
Number of Deficiencies = 1
Number of Deficiencies = 1
Exterior Doors5.
Windows6.
Floors1.
Interior Walls2.
3. Number of Deficiencies = 1
Interior Doors4.
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
A rooftop unit (York #D2CG240N24046ECB, 237 MBH output) serves dining hall. The main food storage, culinary arts dining room, and culinary arts classroom are served by two rooftop units (York #D2CG240N24046ECB and #D2GA030N03206C, both 32 MBH output). All units were built in 8/1993.
Rooftop makeup air units serve the main kitchen (Reznor #CRGBL10502, 105 MBH input, 11,000 CFM, 20 HP) and culinary arts kitchen (Reznor #HCRGB4002J, 400 MBH input, 6000 CFM, 5 HP).
Comments:
Comments:
HVAC
Heat1.
Gas-Fired Packaged
Gas-Fired Furnace
Single Duct
Makeup Air Unit
None
None
Electric
Electric
Mechanical
Mechanical
None
None
Dining Hall
Page: 21 of 76
Building: F - DINING/CULINARY ARTS
Mechanical
Mechanical
Mechanical
Restroom
Kitchen
Dishwashers
Comments: All exhaust fans are roof-mounted.
Domestic water is heated by two water heaters (Lochinvar #PPN0750, 750 MBH input) and stored in two tanks (Lochinvar #RJA200, 200 gallon). The dishwasher is equipped with an electric booster water heater (Hatco #C36, 36 kW)
Comments:
Cast Iron Outdoor Cast Iron
Emergency Eye Wash Hose Bibb Lavatory Sink Urinal Water Closet (Flush Valve) Water Closet (Tank)
Gas (Natural)
Ventilation Area Served
Copper Copper Gas-Fired Water Softener Yes
Hot Water Cold Water Water Heater Water Treatment HW Storage Tank
Grease InterceptorWaste / Vent Interior Storm
Packaged Direct
Expansion (Air Source)
Evaporative Cooler
Single Duct
Makeup Air Unit
None
None
Electric
Electric
Mechanical
Mechanical
Economizer
None
Entire Building
Kitchen
PLUMBING
Exhaust Ventilation
A rooftop unit (York #D2CG240N24046ECB, 20 ton, economizer) serves dining hall. The main food storage, culinary arts dining room, and culinary arts classroom are served by two rooftop units (York #D2CG240N24046ECB, 2 ton and #D2GA030N03206C, 2-1/2 ton). All units were built in 8/1993.
Rooftop makeup air units with evaporative coolers mounted on their intake serve the main kitchen (Reznor #CRGBL10502, 11,000 CFM, 20 HP) and culinary arts kitchen (Reznor #HCRGB4002J, 6000
CFM, 5 HP).
Comments:
Comments:
Ventilation2.
System Type
Number of Deficiencies = 2
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Water Distribution1.
Sanitary Distribution2.
Fixtures3. Number of Deficiencies = 1
Fuel Distribution4.
Page: 22 of 76
Building: F - DINING/CULINARY ARTS
None None ABC Type Fire Extinguisher, K Type Fire Extinguisher, Wet Chemical
Comments: Service is brought from an 800A switch in the main switchboard located behind Building H. Service terminates in 800A, 480/277V, 3-phase, 4 wire distribution switchboard MDP-2 located in Building F electrical room. A 400A CB in the switchboard serves a 400A MLO, 277/480V distribution panel providing for the building. The panel serves a 100A MLO and two 225A MLO, 277/480V secondary panels providing for the HVAC loads and a 150 kVA step down transformer. The 150 kVA transformer provides the 120/208V, 3-phase, 4 wire system for the building and serves a 600A MLO, 120/208V distribution panel (DP). The 600A DP provides for one 100A MLO (from a 80A CB) and three 225A MLO panels (from (3) 225A CB) in this building and a 150A panel (from a 150A CB) in Building J.