16-ETA-OJC-ANAT-0030 3724
PROJECT TITLE: BUILDING 1 – INTERIOR REPLACEMENT OF MAIN WATER LINE at the ONEONTA
JOB CORPS CENTER, ONEONTA, NEW YORK
The work involves services for the replacement of two main water lines both supplying water to various portions of Building 1 (Main Building) at the Oneonta Job Corps Center in Oneonta, New York. The work includes, but is not limited to, miscellaneous site improvements in the form of demolition of the existing water line, demolition of unused HVAC equipment, installation of two new water lines and associated accessories from the entrance of the building to and including each branch line to where it extends thru to the first floor. Both water lines are connected in the main section of the building on the basement level. Each branch will have its own isolation valve.
Oneonta Job Corps Center 21 Homer Folks Avenue
Oneonta, NY 13820
- This requirement has been set-aside for a competitive Service Disabled Veteran Owned Small Business (SDVOSB)
- The estimated Construction Cost is between $500,000 and $1,000,000
- Please Reference Section C for the Statement of Work.
- Contractor shall submit one copy of the proposal via email to ramso.bryan@dol.gov by the solicitation due date. Paper copy submittals are not required for this solicitation. Include the solicitation number in the subject line of the email.
- Please see Section L for further offeror instructions.
X
1. SOLICITATION NO. 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
A. NAME B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12B.)
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 4-85) STANDARD FORM 1442
Prescribed by GSA YFAR (48 CFR) 52.236-1(d) NSN 7540-01-155-3212
SOLICITATION, OFFER
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION, OFFER
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL: Bryan Ramso, Contract Specialist (202) 693-3618
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____10______ calendar days and complete it within ___201___ calendar days after receiving award, notice to proceed. This performance period is X mandatory, negotiable. (See _____________________________.)
YES NO
A. Sealed offers in original and __One (1)__copies to perform the work required are due at the place specified in Item 8 by _2:00 PM EST__ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference
D. Offers providing less than ___120 ______ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NOTICE: SET-ASIDE for Service Disabled Veteran Owned Small Business Competitive
DOL-ETA-17-R-00009
11-16-2016 1 of 93
U.S. Department of Labor, ETA/OCM SEE SECTION L Division of Job Corps Procurement 200 Constitution Avenue, NW Room N-4643 Washington DC 20210
52.211-10
X Ten (10) Days
12/20/2016 mailto:ramso.bryan@dol.gov
See Block 7
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO.
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within 90 calendar days after the date offers are due.
CLIN 0001 ………………………………………………………………………………………….….$ _______________
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20B. SIGNATURE 20C. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c) ( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation, is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work, requisitions identified award consummates the contract. which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER
TO SIGN
30B. SIGNATURE 30C. DATE 31B. UNITED STATES OF AMERICA
BY
OFFER
AWARD
STANDARD FORM 1442(REV. 4-85)BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14)
(Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) MARIA J. PIZARRO Contracting Officer
Division of Job Corps Procurement
(Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
ETA
U.S. Department of Labor ETA Payment Office 200 Constitution Avenue NW, Suite N-4702 Washington, DC 20210
DOL-ETA-17-R-00009
Table of Contents
PART I - THE SCHEDULE ............................................................................................................................... A-1
SECTION A - SOLICITATION/CONTRACT FORM .................................................................................... A-1
SF 1442 SOLICITATION, OFFER, AND AWARDNOTICE: Total SET-ASIDE (Construction, Alteration, or Repair) ................................................................................................................................... A-1
SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS .................................................................. B-1
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK ......................................... C-1
[For this Solicitation, there are NO clauses in this Section] ................................. C-Error! Bookmark not defined.
SECTION D - PACKAGING AND MARKING ............................................................................................... D-1
SECTION E - INSPECTION AND ACCEPTANCE ....................................................................................... E-1
E.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE .................................. E-1 E.2 INSPECTION AND ACCEPTANCE ............................................................................................................ E-1
SECTION F - DELIVERIES OR PERFORMANCE ....................................................................................... F-1
F.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE ................................... F-1
F.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
ALTERNATE I (APR 1984) ........................................................................................................................ F-1 F.3 52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEPT 2000) .................................................. F-1 F.4 PERIOD OF PERFORMANCE ..................................................................................................................... F-2 F.5 PLACE OF PERFORMANCE ........................................................................................................................ F-2
SECTION G - CONTRACT ADMINISTRATION DATA .............................................................................. G-1
G.1 PRE-CONSTRUCTION CONFERENCE ..................................................................................................... G-1 G.2 PERIODIC PROJECT MEETINGS .............................................................................................................. G-1 G.3 SUBCONTRACTS ........................................................................................................................................ G-1 G.4 SHOP DRAWINGS ....................................................................................................................................... G-1 G.5 OPERATIONS, STORAGE AREAS AND SECURITY .............................................................................. G-2 G.6 PROJECT SAFETY ....................................................................................................................................... G-3 G.7 DISPOSAL OF REFUSE ............................................................................................................................... G-3 G.8 SCHEDULE OF PROGRESS ........................................................................................................................ G-3 G.9 PAYMENTS TO CONTRACTOR ................................................................................................................ G-4 G.10 METHOD OF PAYMENT .......................................................................................................................... G-4 G.11 FURNISHING INFORMATION AND RECORDS .................................................................................... G-4 G.12 WORKERS’ COMPENSATION LAWS .................................................................................................... G-5 G.13 REQUIRED INSURANCE .......................................................................................................................... G-5 G.14 EQUITABLE ADJUSTMENTS .................................................................................................................. G-6 G.15 WEATHER DELAYS (EXCUSABLE DELAY) ........................................................................................ G-8 G.16 TEST RESULTS .......................................................................................................................................... G-8 G.17 SUBSTANTIAL COMPLETION ................................................................................................................ G-8 G.18 CONTRACT CLOSEOUT .......................................................................................................................... G-9 G.19 PRECEDENCE OF PLANS, SPECIFICATIONS, AND CLAUSES ......................................................... G-9 G.20 INVOICE PREPARATION AND SUBMISSION .................................................................................... G-10
SECTION H - SPECIAL CONTRACT REQUIREMENTS ........................................................................... H-1
H.1 COMMENCEMENT OF WORK .................................................................................................................. H-1 H.2 SUBCONTRACTING RESPONSIBILITIES ............................................................................................... H-1 H.3 ENVIRONMENTAL COMPLIANCE .......................................................................................................... H-1 H.4 INSTALLATION RULES AND REGULATIONS ...................................................................................... H-1 H.5 SPECIAL UTILITY PROVISION ................................................................................................................ H-1 H.6 DESIGNATION OF GOVERNMENT INSPECTOR ................................................................................... H-1 H.7 ACCOUNTING AND AUDITING SERVICES ........................................................................................... H-1 H.8 SUBMISSION OF CORRESPONDENCE .................................................................................................... H-2 H.9 OTHER CONTRACTORS ............................................................................................................................ H-2 H.10 DISPOSITION OF MATERIAL ................................................................................................................. H-2 H.11 HAZARDOUS OCCUPATION ORDERS .................................................................................................. H-2 H.12 DATA COLLECTION FOR THE DEPARTMENT OF LABOR ............................................................... H-2 H.13 RIGHTS AND OBLIGATIONS .................................................................................................................. H-3 H.14 INITIATION OF LIQUIDATED DAMAGES ............................................................................................ H-3 H.15 MODIFICATIONS AND CHANGE ORDERS .......................................................................................... H-3 H.16 PERMITS ..................................................................................................................................................... H-4
PART II - CONTRACT CLAUSES ................................................................................................................... I-5
SECTION I - CONTRACT CLAUSES ............................................................................................................ I-5
I.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE .....................................I-5 I.2 INFORMATION REGARDING RESPONSIBILTY OF MATTERS (FEB 2012) ..........................................I-4
I.3 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRCT
AWARDS (JUL 2013) ...................................................................................................................................I-5 I.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013) ...........I-7
I.5 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS
ACT (DEC 2010) (DEVIATION) ..................................................................................................................I-8 I.6 52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (AUG 2013) ....................................................I-9
I.7 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND
CONSTRUCTION CONTRACTS (SEPT 2013) ........................................................................................I-12
I.8 52.223-3 HAZARDOUS MATERIAL IDENTIFICAITON AND MATERIAL
SAFETY DATA (JAN 1997) .......................................................................................................................I-12 I.9 52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (MAY 2014) ................................I-13
I.10 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT CONSTRUCTION
MATERIALS (MAY 2014) ........................................................................................................................I-16 I.11 52.227-4 PATENT INDEMNITY—CONSTRUCTION CONTRACTS (DEC 2007) ALT I (DEC 2007).I-16 I.12 52.228-15 PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION (OCT 2010) ....................I-17 I.13 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (MAY 2014) .........................I-18 I.14 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) ........................I-23 I.15 52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994) .................................................................I-24 I.16 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) ..................................................I-25
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS .................................... J-1
SECTION J - LIST OF ATTACHMENTS ........................................................................................................ J-1
J.1 WAGE DETERMINATION ............................................................................................................................ J-1 J.1 JCH 814 ............................................................................................................................................................ J-1
SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF
OFFERORS OR RESPONDENTS ........................................................................................................... K-1
K.1 NOTICE LISTING SOLICITATION PROVISIONS INCORPORATED BY REFERENCE ..................... K-1 K.2 52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985) ......................... K-1 K.3 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2012) ................................. K-2 K.4 52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS (APR 2010) ......................... K-4 K.5 52.219-1 SMALL BUSINESS PROGRAM REPRESENTATIONS (APR 2012) ........................................ K-5 K.6 52.219-22 SMALL DISADVANTAGED BUSINESS STATUS (OCT 1999) ............................................. K-8 K.7 SIGNATURE BLOCK ................................................................................................................................ K-10
SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS ........................................................................................................................................ L-1
L.1 NOTICE LISTING SOLICITATION PROVISIONS INCORPORATED BY REFERENCE ...................... L-1
L.2 52.215-20 REQUIREMENTS FORCERTIFIED COSTOR PRICING DATA AND DATA
OTHER THAN CERTIFIED COST OR PRICING DATA (OCT 2010) ................................................ L-1 L.3 52.216-1 TYPE OF CONTRACT (APR 1984) ............................................................................................. L-2
L.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) ................................................. L-2 L.5 52.233-2 SERVICE OF PROTEST (SEP 2006) ............................................................................................. L-3 L.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE 1 (FEB 1995) .............................. L-4 L.7 52.236-28 PREPARATION OF PROPOSALS—CONSTRUCTION (OCT 1997) ...................................... L-4 L.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE ........................................ L-4 L.9 52.252-3 ALTERATIONS IN SOLICITATIONS (APR1984) ....................................................................... L-5 L.10 GENERAL PROPOSAL PREPARATION INSTRUCTIONS ................................................................... L-5
SECTION M – EVALUATION FACTORS FOR AWARD ........................................................................... M-1
DOL-ETA-17-R-00009 Section B Supplies or Services and Price/Costs
B-1
PART I - THE SCHEDULE
SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS
PRICE/COST SCHEDULE
CLIN SUPPLIES/
SERVICES
QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 LS --------- $
Firm Fixed Price
The Contractor shall provide all supervision, personnel, equipment, transportation, material, and other items and services necessary to perform the Construction Services for the Building 1 – Interior Replacement of the Main Water Line at the Oneonta Job Corps Center.
TOTAL $
B.2 DELIVERABLE - RELEASABLE COPIES - FREEDOM OF INFORMATION ACT
The Freedom of Information Act (FOIA) permits withholding information under several exemptions, including Exemption 4 which protects "trade secrets and commercial or financial information obtained from a person [that is] privileged or confidential," 5 U.S.C. 552(b) (4). Within five business days of contract award, the contractor shall provide a statement that the contract is available for full disclosure under the FOIA or provide a scanned PDF of the redacted copy of the contract identifying the specific potions the contractor believes are covered by the particular exemption requested. Any redactions must be fully supported under the FOIA. In the event the Government notifies the contractor that it does not agree with a proposed redaction, the contractor shall have five business days to submit additional information to support the requested redaction. For subcontracts, within 5 business days of the contractor's award of any subcontract over $500,000 the contractor shall provide the Government a scanned PDF copy of the subcontract with a statement that the copy is either available for full disclosure, or identifying the specific portions believed to be covered by the particular exemption requested.
Redactions should be limited to those protections provided under the FOIA. Following the procedures above, the Government has the right to notify the contractor of any disagreement with proposed redaction or exemption requests.
DOL-ETA-17-R-00009 Section C Description/Specifications
C-1
CONSTRUCTION SCOPE OF WORK
FOR
3724 – BUILDING 1 – INTERIOR REPLACEMENT OF MAIN WATER LINE
AT THE
ONEONTA JOB CORPS CENTER
ONEONTA, NEW YORK
U.S. DEPARTMENT OF LABOR
PREPARED BY:
PROJECT NO. 3724
July 2016 CSOW
C-2
TABLE OF CONTENTS
I. GENERAL ......................................................................... C-Error! Bookmark not defined.
II. SPECIFIC REQUIREMENTS/INSTRUCTIONS ............. C-Error! Bookmark not defined.
A. LEGALLY MANDATED STANDARDS C-ERROR! BOOKMARK NOT DEFINED.
1. Code of Federal Regulations .................................... C-Error! Bookmark not defined.
2. National and State Building Codes .......................... C-Error! Bookmark not defined.
3. Permits and Licenses................................................ C-Error! Bookmark not defined.
B. JOB CORPS GUIDELINES ...................... C-ERROR! BOOKMARK NOT DEFINED.
1. JCH-814: Planning, Design, and Construction Administration Guidelines ... C-Error!
Bookmark not defined.
C. OTHER STANDARDS.................................................................................................. C-5
1. Suistainability and Green Building Requirements .................................................... C-5
2. Energy Conservation ................................................................................................. C-6
3. Environmentaly Preferable Products ........................................................................ C-6
4. Existing Facility Investigative Survey ...................................................................... C-6
D. SPECIFIC INSTRUCTIONS .......................................................................................... C-6
1. Center Operation ....................................................................................................... C-6
2. Contractor Responsibilites ........................................................................................ C-7
3. Site Visit.................................................................................................................... C-7
4. Submittal Requirements ........................................... C-Error! Bookmark not defined.
5. Web-Based Project Management System ................................................................. C-8
6. Construction Drawings ............................................ C-Error! Bookmark not defined.
7. Work Scheduling ..................................................... C-Error! Bookmark not defined.
8. Site Visits – Construction Observation – Construction Progress Meetings ............. C-9
9. Availability of Existing Documents.......................................................................... C-9
E. SCHEDULE AND DELAYS .................... C-ERROR! BOOKMARK NOT DEFINED.
III. USE OF THE SITE .......................................................... C-Error! Bookmark not defined.0 IV. EXENT OF WORK .......................................................... C-Error! Bookmark not defined.0
A. IMPROVEMENTS AND UTILITIES ...... C-ERROR! BOOKMARK NOT DEFINED.
1. Objectives ............................................................................................................... C-10
2. Utilites ..................................................................................................................... C-10
3. Investigation ............................................................................................................ C-10
B. GENERAL REQUIREMENTS .................................................................................... C-11
1. Architectural ........................................................................................................... C-11
2. Structural ................................................................................................................. C-11
3. Mechanical/Plumbing ............................................................................................. C-11
4. Electrical ................................................................................................................. C-12
5. Warranties ............................................................................................................... C-12
V. ACCEPTANCE OF WORK ............................................................................................. C-13 A. SUBSTANTIAL COMPLETION ................................................................................ C-13
B. FINAL INSPECTION ................................................................................................... C-14
C-3
VI. CONSTRUCTION REQRIREMENTS/SPECIFIC INSTRUCTIONS Error! Bookmark not defined.14
1. Quality Requirements ............................................................................................. C-14
2. Temporary Facilities ............................................................................................... C-14
3. Utility Connections ................................................................................................. C-15
4. Warranties ............................................................................................................... C-15
5. Incindental Cutting and Pitching ............................................................................ C-15
6. Clean and Safe Area................................................................................................ C-15
7. Storage Materials .................................................................................................... C-15
8. Laydown Area ......................................................................................................... C-16
9. Coordination of Work ............................................................................................. C-16
VII. SKETCHES ....................................................................................................................... C-17 A. LOCATION MAP ........................................................................................................ C-17 B. VICINITY MAP ........................................................................................................... C-18 C. SITE PLAN ................................................................................................................... C-19
VII. PROJECT SCHEDULE .................................................................................................... C-20
C-4
CONSTRUCTION SCOPE OF WORK
3724 – BUILDING 1 – INTERIOR REPLACEMENT OF MAIN WATER LINE
ONEONTA JOB CORPS CENTER
ONEONTA, NEW YORK
I. GENERAL
The work involves services for the replacement of two main water lines both supplying water to various portions of Building 1 (Main Building) at the Oneonta Job Corps Center in Oneonta, New York. The work includes, but is not limited to, miscellaneous site improvements in the form of demolition of the existing water line, demolition of unused HVAC equipment, installation of two new water lines and associated accessories from the entrance of the building to and including each branch line to where it extends thru to the first floor. Both water lines are connected in the main section of the building on the basement level. Each branch will have its own isolation valve. The extent of work is described in Parts IV & V of this scope of work (SOW).
II. SPECIFIC REQUIREMENTS/ INSTRUCTIONS
A. LEGALLY MANDATED STANDARDS
The Contractor shall conform to:
1. Code of Federal Regulations
a) Safety and Health………………………………………..OSHA CFR Part 1926.62
Because the building was constructed around 1936, work may disturb painted wall surfaces, the Contractor is to provide the services of an independent industrial hygiene consultant to conduct representative paint sampling as necessary to determine the lead content of painted surfaces affected by the renovation. If lead paint is identified on surfaces to be disturbed by renovation activities, the Contractor shall include the following information in the project documents:
• The locations and concentrations of lead-containing paint in areas affected by the renovation
• A requirement of the Contractor to comply with the OSHA Lead Standard for Construction
Industry (29 CFR 1926.62), and other environmental or occupational safety and health regulations as applicable
• A statement prohibiting scraping or sanding of lead painted surfaces. Where removal or demolition of lead painted building components is required, these building components will be removed intact wherever possible
• A requirement that all construction debris will be disposed of in accordance with applicable solid and hazardous waste regulations. It is anticipated that lead-painted building components will be disposed as normal construction debris
b) Life Safety Code………………………………………………………NFPA-101
The Contractor’s responsibility for safety related requirements extends to all impacted areas and access ways affected by the work.
C-5
2. National and State Building Codes
The Contractor shall conform to all applicable construction codes, ordinances, and regulations including the national building code used in the local area, laws and local ordinances. Deviations and interpretations will be subject to the approval of the CO.
3. Permits and Licenses
The Oneonta Job Corps Center is a leased facility.
The Contractor shall research, and be responsible for obtaining and paying for, all regulatory, permitting and licensing requirements in accordance with JCH-814, 2013 Section 1.7. No drawings or specifications will be submitted for building permits unless express notification in writing is received from the Contracting Officer (CO).
B. JOB CORPS GUIDELINES
1. JCH-814: Planning, Design, and Construction Administration Guidelines for Architects and
Engineers
Job Corps publication JCH-814, September 2013 "Planning, Design, and Construction Administration Guidelines for Architects and Engineers," is a companion document to this scope of work. It presents the Contractor additional requirements not specifically stated in the scope of work. Where conflicts occur between the requirements of the contract and JCH-814, 2013, the requirements of the contract will take precedence.
C. OTHER STANDARDS
1. Sustainability and Green Building Requirements
The Department of Labor (DOL) and the Office of Job Corps are committed to the practice of implementing sustainable design and construction best practices into all Job Corps projects, including projects of limited scope.
The project will use methodologies, materials, systems and components that will minimize negative environmental impacts, increase energy efficiency and make use of renewable energy technologies.
Within budget constraints, the project will embody best current sustainable design and building practices. The project team is to propose the highest possible implementation of these strategies for consideration by DOL, the Regional DOL office, and the Job Corps Center.
To the extent possible, the Center and the Center’s Contractors are to reference, use, and procure materials, components, equipment and services noted in the attached “Green Sheet” or JOB CORPS SUSTAINABILITY GUIDELINES FOR PROJECTS OF LIMITED
SCOPE OF WORK V.2.26.2015.
The Contractor shall verify construction phase sustainability measures as detailed in the Green Sheet and provide noted submittals substantiating compliance. Any specifications or proposals will include requirements to provide documentation and comply with the Green Sheet as far as practicable.
C-6
2. Energy Conservation
The Contractor shall evaluate options for the use of energy and water conservation measures. The Contractor shall follow guidelines provided in the Green Sheet for the procurement and installation of Energy Star HVAC equipment, low flow water fixtures, the use of testing, energy efficient lighting, use of controls, sensors, weatherization, and other energy efficient measures.
3. Environmentally Preferable Products
The Contractor shall evaluate options for the use of environmentally preferable products/materials and apply standards as noted in the Green Sheet.
4. Existing Facility Investigative Survey
If the work is to be performed on an existing building for which plans are not available, the Contractor shall perform an investigative survey to determine if there are hidden conditions or elements which will impact the work. Demolition may be required to expose suspected unknown elements. The survey’s objectives will include, but not be limited to, the following:
a) Determine whether multiple ceilings exist.
b) Determine the extent of any hidden structural elements. The design and spacing of hidden structural elements will be investigated.
c) Locate any hidden mechanical or electrical components, the presence of which would impact the proposed design.
Any openings in the exposed finishes created to perform the investigative survey will be sealed and restored to its original condition in all areas where there are occupants. Any opening hidden by the exposed finish¸ such as a drop-in ceiling, will be sealed back to the original finish level.
Care must be taken to avoid disruption of suspected or known ACM.
The investigative survey will be submitted for the record 14 calendar days before start of construction and will include appropriate photographic and/or video records to illustrate its findings and existing conditions.
D. SPECIFIC INSTRUCTIONS
1. Center Operation
Building 1 (Main Building) is a mixed use facility that includes dorms, classrooms and administrative office areas. This building is critical to the operation of the Center. The Center will remain in full operation throughout the construction phase. The Contractor shall, as part of this contract, coordinate with DOL’s Engineering Support Contractor (ESC) and develop a project phasing plan that will minimize disruption of Center operations during construction. The Contractor shall develop and maintain proper scheduling and phasing of the construction work as required ensuring the Center continues to operate in a normal fashion during construction. Water service will remain in full operation including all wings and branches throughout the duration of this contract. Coordination of any short duration outages will be the sole responsibility of the Contractor. Any short duration
C-7 outages must be planned one calendar week in advance with the Center staff and the Engineering Support Contractor (ESC). The Contractor shall submit one week in advance of each proposed outage a detailed plan in writing for each outage including durations for approval. A detailed schedule of construction will be provided to the Contracting Officer Representative (COR) thru the ESC for approval at the Pre-construction Meeting.
2. Contractor Responsibilities
The Contractor shall ensure the security of operations and storage areas to preclude all breaches of security including, but not limited to, vandalism and/or theft that can impact the timely and successful completion of the work. While existing Center operations will be continuing during the course of the project, the Contractor shall not rely on any aspect of the Center’s security to guard aspects of his operations. At no time during this construction duration, up to and including the acceptance of the Substantial Completion walk-through, will the CO accept requests for additional security measures.
The DOL shall not be held to have incurred any liability for loss of, and/or damage to, materials, tools, and equipment of the Contractor by contract or otherwise. The DOL shall not in any way be liable or responsible for damage or loss to work due to trespass or theft.
The specified construction materials must be of quality that is consistent with the intended use of the facility, and reflect local availability and construction skills. Newly developed materials and methods should be considered and discussed with DOL for inclusion in the project.
Although this scope of work may identify specific elements of construction, it is the Contractor’s responsibility to provide any and all elements which are incidental to provide a fully complete and functional facility.
The Contractor is required to provide twenty (20) high quality photographs in digital and paper format to document the completed facility. Submission of the requisite photo record will follow remediation of the Substantial Completion Punch List, and will be included in the project’s Closeout documents.
The Contractor and all persons employed under the contract:
a) Shall observe all security regulations in effect at the Center;
b) Shall not be permitted to use the food service facilities at the Center;
c) Shall not fraternize with the students or staff of the Center;
d) Shall not consume or transport any alcoholic beverages or drugs on the Center; and shall not transport any firearms on the Center.
Persons violating the above shall be subject to disciplinary actions as set forth by the Center.
3. Site Visit
A Pre-Bid meeting and site visit will be held at the Oneonta Job Corps Center. Participants will include representatives from DOL and its ESC.
This meeting is intended to familiarize the Contractor with the objectives of the project, the Center Programmatic Requirements and other inputs and constraints stemming from Center operations. The Contractor’s responsibilities and lines of communication will also be discussed. Project data, budget, schedule, etc., will be further defined or clarified, as appropriate and if necessary.
C-8
The Contractor may utilize this opportunity to gather as much information as possible to aid in the preparation of a Bid to the CO.
4. Submittal Requirements
The Contractor shall, at a minimum, submit the following for approval before commencing construction:
• Schedule, Critical Path Method (CPM) in Microsoft Project or Primavera P6, with electronic files
• Safety Plan
• Construction Site Plan
• Quality Plan
• Construction Phasing and Layout Plan
• Shop drawings including a piping plan layout indicating hangar details, structural connections, bills of materials and valve connections and sizes.
• Lead and Asbestos Abatement Plan
• Installers Qualifications
• Material submittals will include but not be limited to:
i. Water Pipe, Pipe Insulation
ii. Pipe Hangers and Supports (including shop drawings),
iii. Water meter & Backflow preventer with strainers (including shop drawings)
iv. Freeze Protection Equipment (Unit Heaters) (including controls, wiring and shop drawings)
v. Louvers and Motorized Dampers (including shop drawings).
The Contractor shall, at a minimum, submit the following before requesting Substantial Completion:
• As-built drawings
• Warranties
• O&M Manuals
• Consent of Surety
• Records of Training
• Records of Waste Disposal
• Water Test Reports
• Final punch list with request for certification that the project is substantially complete.
5. Web-Based Project Management System
The DOL shall provide, and requires the Contractor to use, the secure online construction management system Submittal Exchange©, to expedite submittal information and management exchanges between members of the Contractor’s team, the ESC, the DOL and other designated project stakeholders.
C-9
The system offers an extensive user automatic information exchange, and electronic closeout documentation for the entire project. The program service provides a comprehensive online system for exchanging, reviewing, and archiving construction communications as well as product manufacturer training for users. The use of Submittal Exchange© is a reimbursable cost, therefore the Contractor is required to include it in its Schedule of Values.
6. Construction Drawings
a. Construction drawings of the buildings involved are not available. The Contractor is required to familiarize him/herself with the existing conditions affecting the work through site verification (See Part II, Section C, Paragraph 4). The Contractor is responsible for verification of all dimensions, layout, and conditions in and around the construction area involved. The Contractor shall inform the Contracting Officer immediately of any unforeseen conditions which may affect the work.
7. Work Scheduling
a. For work scheduling, the Contractor shall provide a sequenced CPM construction schedule to the CO for approval no later than 10 calendar days after he receives a Notice to Proceed (NTP). The CPM schedule will indicate the areas and the periods of time the Contractor requires them vacant in order to perform the work. As the work progresses, the Contractor shall submit an updated CPM schedule on a monthly basis for approval by the CO, as part of the Contractor’s monthly invoices. The CPM schedule will capture the shut down and the sequencing of installation of the new main water line.
8. Site Visits - Construction Observation – Construction Progress Meetings
The Contractor shall prepare a monthly construction progress report. The report will include an updated CPM schedule, a minimum of 10 electronic photos of all aspects of the project and a list of open issues with the responsible person and target date for resolution identified. The ESC representative will visit the site at least once a month. During this visit, the Contractor’s payment application will be quantified and verified by the CO’s representative.
Once construction commences, in coordination with DOL, the Contractor shall organize, prepare agenda, and conduct weekly construction progress meetings, record and prepare meeting minutes, and distribute to team members and attendees within 3 days after the meeting. These weekly progress meetings will include representatives from the Contractor, the ESC, DOL and others as determined by DOL. Meetings will be held at the construction site in conjunction with ESC site visits and/or attended by conference call. The ESC will provide the teleconference platform.
9. Availability of Existing Documents
Site verification of the existing conditions is required. Existing Construction Documents are not available. The Contractor will be responsible for verification of all the dimensions and existing system types and conditions.
E. SCHEDULE AND DELAYS
The Contractor shall immediately notify the CO of any expected delays in the acquisition of materials which may delay the completion of the project. Should this impact the approved CPM construction
C-10 schedule the Contractor shall adjust the schedule and resubmit it for the CO’s approval. No extensions in time will be granted unless the modified schedule is approved by the CO.
III. USE OF THE SITE
The Contractor shall access the site using the main campus entrance access road from the east off West Avenue. Unless otherwise approved by the Department of Labor, the lay-down area will be located on the flat area south and to the west of Building F. Contractor is responsible for restoration of the laydown area to its current condition after completion of the project.
IV. EXTENT OF WORK
A. IMPROVEMENTS AND UTILITIES
1. Objectives
The Contractor shall provide all labor, materials and equipment required to remove and re-install both domestic main water lines. The existing water line is comprised of various sizes of galvanized steel pipe primarily 6 inch. At or near the entrance to the building, the Contractor shall install a new shut-off valve. Immediately following the valve, the Contractor shall install a new house meter and backflow preventer/strainer. Branches will be replaced up to penetrations into walls and ceilings that will remain accessible. Where the main water line passes thru rated walls or thru floors, the Contractor shall provide fire-stop caulking. Each new water line will include adequate isolation valves to isolate the wings and individual branches. The Contractor shall comply with the relevant sections of JCH-814.
The Contractor shall ensure that the domestic water service will stay in operation throughout the duration of this project. The Contractor shall phase the work to avoid or minimize interruptions to the functions of the facility.
2. Utilities
In compliance with the Energy Policy Act of 2005, each (for this project only the water meter is applicable) utility will be provided with “owner’s meters” at the point of entry into each building served. The meters will be used by the Center for tracking energy use and will be pulse emitting type, 20 hertz maximum with dry contact, KYZ pulse output. All “owner’s” meters will be connected to a central monitoring/reporting device with an Ethernet RJ45 female connection port. Provide Ethernet cabling to the connection port to monitor the signals from the meters. Each water meter monitoring device will be installed in the Center Director’s office suite. Provide 120v dedicated receptacles as necessary to power all metering equipment.
3. Investigation
It is the Contractor’s responsibility to thoroughly investigate the site prior to submitting a bid.
B. GENERAL REQUIREMENTS
1. Architectural
C-11
a) In the progression of the Work, if any architectural finishes are disturbed, it is the responsibility of the Contractor to replace or repair the finishes to their original condition. Original conditions will be as captured in the Existing Facility Investigative Survey (see section II/C/4 herein).
b) It is anticipated that the Contractor may need to disturb walls in the sub-basement or basement levels. Each wall will be completely closed and fire caulked up to the insulation, and sleeved.
2. Structural
a) Provide shop drawings illustrating the support of the new water supply pipe and freeze protection heaters. Provide calculations and shop drawings for support hangars.
b) Provide seismic bracing in accordance with all applicable codes (federal, state and local).
3. Mechanical/Plumbing
a) The Contractor shall closely follow the requirements of the JCH-814, September 2013 Chapter 5 as pertains to Plumbing and Mechanical Design Criteria.
b) The Contractor is responsible for the replacement of the existing domestic water service. The water service is comprised of two water mains.
1) The first water main enters the building in the sub-basement of B-wing where there is an existing water meter that is non-functional. The first main feeds various restrooms on several floors above in B-wing as it goes thru several crawl spaces. It then travels up to C-Wing basement level where it connects to the other main. At the point of entry, it is a 6-inch galvanized pipe. This new water main will maintain 6-inch pipe size throughout.
2) The second water main enters the building at the basement floor corridor on the northwest side. There is a 6-inch valve which will be replaced with a new gate type valve of the same size and a house meter, backflow preventer and strainer. The line tees off to feed the kitchen (above) and continues down the hall southward, then travels down to the basement level where it tees off to feed wings E and F in opposite directions. It also continues down the main hallway in C-wing on the basement level where it ties into the other main. This new water main will maintain 6-inch pipe size throughout.
c) The existing water line is approximately 650 linear feet of up to 6-inch water piping located inside of the building. The work includes installation of new hangers, insulation, demolition and disposal of old pipe. Provide seismic bracing as required by applicable code. The Contractor is responsible for field verifying all quantities. New water piping routing must in no instance limit the use of the existing spaces and will be installed in a manner that resembles the current installation as closely as possible.
d) The shop drawings will include means to isolate individual wings without compromising service to the remainder of the building or other wings.
e) The Contractor shall provide two (2) new 6-inch water meters, full size backflow preventer and strainers. The water meters will be flanged with 6-inch isolation valves on either side of the meter, backflow and strainer assembly. See section IV/A/2. for water meter requirements.
f) The new water line will be fully insulated through each penetration with a minimum of 1.5-inch insulation to include all joints, elbows and hangers.
C-12
g) Prior to placing it into service, the Contractor shall be responsible for…