AMENDMENT 0003

to Invitation for Bids (IFB)

Solicitation No. DOL099RB20779 Phase 4 Vocational Complex Potomac Job Corps Center

Washington, DC

Date of Issue: 10/20/09

Notice: Failure to acknowledge this Amendment in Block 19 of the Standard Form (SF) 1442, “Solicitation, Offer and Award” as a part of your bid will result in your bid being considered as non-responsive, and not subject to an award.

As a result of the Pre-bid Conference held at the Potomac Job Corps Center on September 24, 2009, the following comments, questions and answers, attachments and revised full size sheets are provided, and are hereby incorporated into the above solicitation:

A. Contractual Matters:

1. Please confirm how PEPCo related work and relocation of existing light poles is to be handled in the bid.

Response: Specification Section (16010,3.2,B,2) is changed to read as follows: The Contractor is responsible for coordinating all work required by PEPCo in order to meet the project schedule. The Contractor shall pay the cost for PEPCo, and will be reimbursed in accordance with the Change Clause (52.243-4) of the contract.

2. Please confirm how other utility work is to be handled in the bid.

Response: As stated within the response to Question # 1, the contractor will be reimbursed for all appropriate related utility work and relocation of existing utilities.

3. At the pre-bid conference it was mentioned that this property is leased from the DC government. Is this a tax-exempt project? Is this project exempt from DC material sales tax?

Response: No. This is not a tax-exempt project. Nor is this project exempt from DC material sales tax. The bidder’s price must include all appropriate taxes.

4. What is the not to exceed amount or percentage of bid for the bid bond required?

Response: Pursuant to FAR 28.101-2 Solicitation Provision or Contract Clause, the bid guarantee amount shall be 20 percent of the bid price but shall not exceed $3 million. When the penal sum is expressed as a percentage, a maximum dollar limitation may be stated.

5. The sample Pay Request that was issued with the Sample Forms lists Retention at 10%.

Please confirm the retention requirement.

Response: The Contracting Officer reserves the right to withhold 10% of the contract amount when a contractor falls behind schedule. Once satisfactory progress is demonstrated, the retainage will be release.

6. Will award be based on the lowest bid or best value?

Response: Lowest bid

7. In Solicitation section L.7 BID SUBMISSION REQUIREMENTS, (b) BIDDER’S QUALIFICATIONS: All bidders must submit a list of at least five references within the last five years for work comparable in nature. At the end it says “This information must be received before award can be made.” Please clarify do we need to submit this information with the bid? Can we submit this information after bid opening or before award?

Response: According to the IFB Amendment 0002 dated 10/1/09, Sub-section L.7 BID SUBMISSION REQUIREMENTS, (b) BIDDER’S QUALIFICATIONS:

Along with submission of a bid, all bidders must submit a list of at least five (5) references within the last five (5) years for work comparable in nature.

8. As per amendment #1 section L.7 BID SUBMISSION REQUIREMENTS: “Bid Opening.

One (1) copy of a bid shall be furnished to the following location on Thursday, October 22, 2009 at 2:00 PM EDT: 2101 Wilson Boulevard, #200, Arlington, VA and bid can also submitted to 200 Constitution Ave, NW, Washington DC. Do we need to submit this bid both location on October 22, 2009 before 2:00 PM? Or Can we submit this bid to any one location on October 22, 2009?

Response: The new date for the Bid Opening is Thursday, 11/5/09 at 2:00 PM EDT.

According to the IFB Amendment 0003, bids can either be furnished at the time of the Bid Opening or submitted in advance by mail delivery or overnight carrier service. All bids must be in no later than Thursday, 11/5/09 at 2:00 PM EDT.

One (1) copy of a bid will be furnished during the bid opening to the following location on Thursday, November 5, 2009 at 2:00 PM EDT:

PBDewberry Koht’aene/AMES Construction JV 2101 Wilson Boulevard, Suite 200 Arlington, VA 22201

ATTN: MARIA J. PIZARRO, CPCM CFCM

Division Chief, Contracting Officer Solicitation No: DOL099RB20779

OR Bids may be submitted in advance by mail delivery or overnight carrier service to:

U.S. DEPARTMENT OF LABOR/BOC/OPS

ARRA Division for A-E & Construction Services 200 Constitution Avenue, NW Room N4308 Washington, DC 20210 ATTN: Miriam J. Holst, Contracts Specialist (Marked) SEALED Bid–DO NOT OPEN Solicitation No: DOL099RB20779 Bid Due Date: Thursday, 11/5/2009 Time: 2:00 PM EDT

B. Technical Matters:

1. Graphic scale is 1” = 20’-0” on drawing A1.02 which doesn’t match with the drawing.

Please provide actual graphic scale for drawing A1.02.

Response: The graphic scale for drawing A1.02 is incorrect. The correct drawing scale is 1” = 16’–0”

2. Please provide the graphic scale for drawing C8.2 and C8.3

Response: The graphic scale for drawings C8.2 and C8.3 is 1” = 20’-0”

3. 8” CMU wall is shown on Drawing 5/A1.03 and 6/A1.03. Same wall on drawing 3/S4.03 and 4/S4.03 is shown 12”. Please clarify which one is correct 8” or 12”.

Response: Change note on details 3, 5, & 6 on sheet A1.03 to read “REINFORCED CMU– REF STRUCTURAL”. CMU retaining wall is 12” per structural drawings.

4. B6 type of wall is shown on drawing A3.30 but no details are given on drawing A8.2.30 for this wall. Please provide wall details for B6 type wall.

Response: B6 wall type note is incorrect. The correct wall type is B1.

5. There is no detail given for drawing 5/A10.32. Please provide drawing details for 5/A10.32

Response: Detail 5/A10.32 is referenced from exterior elevations sheet A6.32 note

4.3. See details 2, 3, 4, 5 on A6.32.

6. Please clarify work access restrictions/rules for the construction tradesmen working at the site. Will the contractor be allowed to work weekends?

Response: Construction will be allowed Monday to Friday 6 AM–6 PM.

7. What specific permits will be provided by the DOL and what permits will be the responsibility of the contractor?

Response: The contractor is required to obtain all permits required by DCRA, with the exception of the Building Permit and the Raze Permit, which will be provided by the owner.

8. Can 3rd party inspection services be utilized on this contract?

Response: No.

9. Does the contract require a separate Quality Control Manager, or can this function be performed by the qualified superintendent, as we are already required to utilize an independent testing agency for required aspects of the project?

Response: The Superintendent and the Quality Control Manager cannot be the same person.

10. It appears that some portion of the Black Iron perimeter fencing has been installed and/or is being installed. How are we to quantify our portion of this work?

Response: For bidding purposes, 48’ of 10’ tall black iron fence is to be salvaged for the Owner.

11. Is fire sprinkler system required for this project? If yes please provide the specifications and drawings for fire sprinkler system because I am unable to find any drawings and specification for fire sprinkler.

Response: Per sheet G1.31, there is no automatic sprinkler system.

12. Geotechnical reportpage #10 says “This report is information purpose only and should not be considered part of the contract documents. Should the data contained in this report not be adequate for the contractor’s purpose, the contractor may make their own investigations, tests and analyses prior to bidding. Drawing S1.01 DESIGN NOTES IV– F. “A geotechnical engineering report for this project has been prepared by Geo Concepts Engineering Inc. This report shall become a part of the contract documents.” Please clarify do we need to consider geotechnical report as a part of contract? Do we need to include price for design build rammed aggregate piers?

Response: See Specification Section (02475) Short Aggregate Piers

Structural Design Note (S1.01, Design notes IV, F) is changed as follows: “A geotechnical engineering report for this project has been prepared by Geo Concepts Engineering Inc., Project No 21079.01, dated June 9, 2009. Excerpts from this report are provided on Sheet S1.02 & S1.03, and become part of the contract documents.”

See Specification Section (01420, 1.02, A, 2): The Geotechnical Engineering Report is a reference document, and as such, is “provided for informational purposes only and should not be considered part of the Contract Documents.”

13. The soil borings and reports are from a different area than the actual construction site. In fact, they are from an entirely different elevation. Are we to assume soil conditions from these reports are to be used and referenced for this construction site?

Response: Included with the Reference Documents are:

Appendix A. “Geotechnical Engineering Report, Phase 4 Vocational Complex, Potomac Job Corps Center,” dated June 9, 2009. This document provides the boring locations and soil conditions specific to the Vocational Complex site.

Appendix B. “Conductivity Test Report,” dated June 14, 2002. This document provides conductivity tests for the geothermal wells. Although located outside the Vocational Complex construction area, we do not expect the conductivity for the 350’ deep geothermal wells to vary significantly.

14. The geotechnical boring logs for the geothermal installation show a layer of fill comprising the first 5-7 feet. The Structural drawings call for shallow spread footings under structural piers, and a slab on grade. Will a unit cost for excavation to suitable bearing and consolidated fill to support the slab be added to bid requirements? If not, how should this potential unknown cost issue be addressed uniformly by all bidders?

Response: For bidding purposes, the contractor is to provide a separate bid line item for the cost to replace 2,400 cubic yards of unsuitable soil with compacted fill.

15. The Geotechnical Report mentions the possibility of undercutting of the subgrade at the buildings and pavements. Please confirm that if undercutting is required, it will be addressed via a contact change order. If not, please provide an estimated quantity of undercutting that will be required.

Response: See previous response.

16. Specification Section 02229 "Rock Removal" provides the procedures for removal of rock. The Geotechnical Report does not mention the presence of any rock. Please confirm that if rock is encountered on this project, it will be addressed via a contract change order. If not, please provide an estimated quantity of rock blasting that will be required.

Response: If rock, as defined in Section 02229, is encountered, it is to be handled as an unforeseen condition.

17. Does the center have available as-built site utility drawings from previous and most recent projects on the center?

Response: Previous Phase work that will impact Phase 4 was updated in drawing C3.2. As-builts for previous phase work can be made available by PJCC should the need arise.

18. Is this a LEEDS certified project?

Response: This project is not pursuing a LEED rating. The project does however utilize green building principals as part of its design and construction as outlined in individual specifications (e.g., Low VOC paints, etc.). LEED templates are not required but the contractor must provide proof of compliance with specification requirement.

19. I have looked through allthe specs and drawings, but I can’t locate any information on the communications cabling requirements.

Response: IT/TelCom/Security wiring is by owner. See electrical drawings and specifications for cabling infrastructure (conduit, boxes, etc…). with revision as noted below.

See attachment#4 (ESK-1) for Revision to E0.31 Electrical symbols list.

20. In Specification Section 15995- Mechanical and Plumbing Systems Commissioning, Section 4.1, A, it is unclear who will pay for the Commissioning Authority. The summary also makes reference to Section 01810 that is not included. Please clarify if and how this cost is to be included in the bid.

Response: Delete Specification Section 15995.

21. Delete Specification Section 02870 - Site, Street and Mall Furnishings.

22. Specification 08710–Door hardware: Section 3.05, HW Set #02:

Delete “STOREROOM LOCK”. Replace with:

“1 EA, PANIC HARDWARE, 9927NL-OP, 626, VON”

23. Specification 09510–Acoustical Ceilings:

Section (1.08, A, 1, a, 1) is changed to read as follows:

“ Acoustical ceiling panels shall be manufactured with not less than 32% recycled material.”

Section (2.03, A, 6, c) is changed to read as follows:

“ USG Interiors – Touchstone #5896”

24. Specification 02821–Fences and Gates:

Section 3.02, A, 3: is changed to read as follows:

“Provide continuous top rails. Provide bottom rail if fence is greater than 8’-0”.”

Section 3.02, C, 1: is changed to read as follows:

“Install fence with a top rail and bottom tension wire. Install bottom rail if fence is greater than 8’-0”.”

25. Sheet C3.1. Description of Lumber Storage Bldg. is changed to read as follows:

“One story;CMU bearing walls with wood frame w/ plywood siding; Wood frame asphalt shingle roof.”

Descriptions are for building identification purposes only. Contractors are to field verify existing conditions.

26. Sheet C3.1. Revise description of Bldg #51: Carpentry Shop is changed to read as follows:

“One story w/ mezannine;CMU bearing walls with plaster siding; Wood frame asphalt shingle roof; Wood framed entry.”

Descriptions are for building identification purposes only. Contractors are to field verify existing conditions.

Replace photo of Bldg #51 Carpentry Shop with the photo below:

27.The 50’ Chain link rolling gate is deleted and changed to a 30’ Chain link cantilever slide gate. Delete drawing details for Rolling Gate on C9.1, 5/A1.04, and 6/A1.04.

Add Specification Section 02825–Chain-link Cantilever Slide Gates.

See attachment #1 and revised sheet A1.02 for revised plan and details.

28. Specification 11220–Sliding Gate Operator:

Section 2.03, B, 2: is added to read as follows:

“Control to be Siren activated for fire emergency vehicle access” Section 2.03, C: is changed to read as follows:

“Provide obstruction sensors at front and back, and 2 loop detectors in pavement” Section 2.04, A is deleted.

29. The site retaining wall adjacent to Ninos Drive has been revised.

See Attachment #3 and revised details A1.02, 5/A1.03, 8/A1.03 (on revised sheets) for revised plan and details.

30. Provide additional light fixture type G to be mounted to underside of high roof eave with concealed conduit in roof assembly. (12) Fixtures total:

Building A: Provide 8 type G fixtures connect to 20 amp 1 pole circuit breaker via 20 amp contactor and photocell.

Building B: provide 2 type G fixtures and connect to 20 amp circuit breaker via photocell.

Building C: provide 2 type G fixtures and connect to 20 amp circuit breaker via photocell.

See attachment #2 (ESK-2 & ASK-1) for fixture type G and locations.

31. See revised sheet A1.04 for revisions to chain link fence at Storage bins. (Note that revisions are not shown on the revised civil C4.1)

32. Add signage Type 4 per revisions on sheet A8.4.30.

33. Drawing changes to full sheets include, but are not limited to:

(See clouded changes on sheets for complete scope of drawings revisions)

• Remove trees.

• Mill and overlay of existing asphalt road.

• Modify existing sanitary and storm, adding 2 new structures, at north end of site.

• Delete one PEPco power pole and relocate one PEPco pole.

• Revisedproposed relocation of Washington Gas line at north end of site.

Attachments to Amendment 0003:

Attachment#1: Specification Section 02820 Chain-link Cantilever Slide Gates & Cantilever Slide Gate details (6 pages)

Attachment#2: ESK-2 Light fixture G & ASK-1 Fixture G locations (2 pages) Attachment#3: SSK-1 Site retaining Wall at Ninos Drive (1 page) Attachment#4: ESK-1 Electrical Symbols list (1 page)

Revised full size drawings sheets to Amendment 0003:

(Provided as a separate pdf file):

The following drawing sheets indicate clouded revisions and clarifications. These sheets are replacement sheets and supercede any previous sheets with the same sheet number. They include one new sheet G1.32.

C3.2, C4.1, C7.1, C7.2, G1.32, A1.02, A1.03, A1.04, A8.4.30, E1.31

END OF AMENDMENT 0003