DO_50_Kelly_Island_Final_Drawings_20221102.pdf
PDF 7 MB Posted
- Attached to
- GAOA - KELLY ISLAND WATER SYSTEM REPLACEMENT
- Solicitation number
- 140L2623R0007
About this file
This package includes plans and specifications for the Kelly Island Water System Replacement project. The project involves replacing the existing water system at Kelly Island, located in Ririe, Idaho, to bring it up to current standards. Work includes demolishing portions of the existing well house and water distribution system, upgrading the pump house, installing a new reverse osmosis water treatment system, installing approximately 2,000 linear feet of new water lines, installing new hydrants and valves, constructing a new concrete pad, and installing a prefabricated shade shelter. Bidders must follow the requirements and specifications in the documents, which cover civil site work, plumbing, and structural plans. The solicitation number for this project is 140L2623R0007. The agency is the Department of the Interior Bureau of Land Management Idaho Region. Bids are due by November 30, 2022.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT
LOCATION
PROJECT
LOCATION
PROJECT
LOCATION
INDEX OF DRAWINGS
PROJECT LOCATION
DESIGNERS
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
KELLY ISLAND WATER SYSTEM REPLACEMENT
GENERAL
G001 COVER SHEET
CIVIL
C001 CIVIL NOTES & LEGEND
C101 EXISTING CONDITIONS
C102 DEMOLITION PLAN
C103 SITE IMPROVEMENT PLAN
C104 CAMP HOST SITE PLAN
C501 DETAILS
C502 DETAILS
PLUMBING
P001 GENERAL NOTES AND LEGEND
PD101 PUMP HOUSE DEMOLITION PLAN
P101 PUMP HOUSE PLAN
P102 PUMP HOUSE P&ID
P501 PLUMBING DETAILS
P601 PLUMBING SCHEDULE
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE
YOU DIG, GRADE, OR EXCAVATE FOR THE
MARKING OF UNDERGROUND MEMBER
UTILITIES
PROJECT VICINITY - RIRIE, IDAHO SITE ACCESS - 43°37'26.08"N, 111°39'46.75"W
GENERAL NOTES
1. ALL CONSTRUCTION WORK SHALL BE DONE IN ACCORDANCE WITH THE CURRENT VERSION OF THE IDAHO STANDARDS FOR PUBLIC WORKS CONSTRUCTION (ISPWC), AND THE REQUIREMENTS FOR THE CONTRACT DOCUMENTS. THE MORE STRINGENT OF ANY OF
THESE STANDARDS SHALL BE THE CONTROLLING STANDARDS OR SPECIFICATIONS.
2. ALL CONTRACTORS, AND SUBCONTRACTORS SHALL ATTEND A PRE-CONSTRUCTION CONFERENCE WITH THE GOVERNMENT PRIOR
TO START OF WORK.
3. ALL CONTRACTORS WORKING WITHIN THE PROJECT BOUNDARIES ARE RESPONSIBLE FOR COMPLIANCE WITH ALL APPLICABLE SAFETY LAWS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL BARRICADES, SAFETY DEVICES, AND CONTROL OF TRAFFIC
WITHIN AND AROUND THE CONSTRUCTION AREA.
4. WHEN DISCREPANCIES OCCUR BETWEEN THE PLANS, SPECIFICATIONS, AND/OR FIELD CONDITIONS, THE CONTRACTOR SHALL
IMMEDIATELY NOTIFY THE GOVERNMENT.
5. THE LOCATIONS OF EXISTING UTILITIES SHOWN ARE APPROXIMATE. THE CONTRACTOR SHALL DETERMINE THE EXACT LOCATION OF ALL EXISTING UTILITIES BEFORE COMMENCING WORK. CALL IDAHO DIGLINE AT 811 A MINIMUM OF 48 HOURS PRIOR TO EXCAVATING TO REQUEST LOCATIONS OF UNDERGROUND UTILITIES. UTILITY LOCATION AND VERIFICATION SHALL BE AN ONGOING PROCESS. WHERE CONFLICTING UTILITIES MAY BE PRESENT, THE CONTRACTOR SHALL VERIFY LOCATION AHEAD OF TRENCHING OPERATIONS, AND IMMEDIATELY NOTIFY THE GOVERNMENT OF ANY POTENTIAL CONFLICTS AS APPLICABLE.
6. CONTRACTORS SHALL NOTIFY THE GOVERNMENT WHEN MATERIALS ARE ON SITE OR INSPECTION OF THE WORK IS REQUIRED. NO
WORK MAY BEGIN ON ANY PROJECT WITHOUT TWENTY-FOUR (24) HOUR PRIOR NOTICE.
7. ALL MATERIAL FURNISHED ON OR FOR THE PROJECT MUST MEET THE MINIMUM REQUIREMENTS OF THE GOVERNMENT.
8. WORK SUBJECT TO APPROVAL BY THE GOVERNMENT MUST BE APPROVED PRIOR TO (A) BACKFILLING; (B) PLACING OF AGGREGATE
BASE; AND (C) PLACING OF CONCRETE.
9. RETAIN AND PROTECT ALL FEATURES NOT DESIGNATED TO BE MODIFIED OR CONSTRUCTED.
10. ALL EXISTING FEATURES WHICH ARE BEING JOINED OR MATCHED IN CONNECTION WITH THIS PROJECT, SHALL BE JOINED OR
MATCHED IN A MANNER SATISFACTORY TO THE GOVERNMENT INCLUDING NECESSARY SAW CUTTING, REMOVAL, REPLACEMENT, AND CAPPING.
11. SITE SHALL BE CLEANED AND RESTORED TO ORIGINAL OR BETTER CONDITION UPON COMPLETION OF WORK.
12. CONTRACTOR SHALL ENSURE THAT ALL SIDEWALKS, RAMPS, ACCESSIBLE PARKING SPACES, AND OTHER PEDESTRIAN ACCESS
ITEMS COMPLY WITH THE ARCHITECTURAL BARRIERS ACT (ABA) REQUIREMENTS.
13. TEMPORARY SHORING, BRACING, FORMING, SCAFFOLDING, ETC. ARE THE SOLE RESPONSIBILITY OF THE CONTRACTOR OR
SUBCONTRACTORS AND HAVE NOT BEEN CONSIDERED BY THE DESIGNER.
14. PROVIDE 14 DAYS NOTICE PRIOR TO START OF CONSTRUCTION FOR GOVERNMENT STAFF PLANNING PURPOSES.
CONCRETE NOTES:
1. CONCRETE STRENGTH TO BE A MINIMUM F'C=4,000PSI IN 28 DAYS.
2. SLUMP 4” MAXIMUM, AGGREGATE 3/4” MAXIMUM, AIR CONTENT 6 + 1.5.
3. CONCRETE SHALL BE TO THE STRENGTH AND SLUMP SPECIFIED AND CONSIST OF: AASHTO M 85 OR ASTM C-150 TYPE I OR II
CEMENT, U.N.O. AGGREGATE SHALL CONFORM TO ASTM C-33.
4. CALCIUM CHLORIDE OR ADMIXTURES CONTAINING CALCIUM CHLORIDE SHALL NOT BE USED.
5. FORMS SHALL BE SECURED TO PREVENT MOVEMENT OR SETTLEMENT AND SHALL BE CLEAN AND FREE OF HARDENED CONCRETE, DIRT, DISTORTION, AND RUST.
6. THE BOTTOMS OF FOOTING EXCAVATIONS SHALL BE LEVEL, CLEAN AND FREE OF LOOSE MATERIAL. OVER EXCAVATED FOOTINGS
SHALL BE FILLED WITH APPROVED FILL MATERIAL.
7. REMOVE ALL DEBRIS FROM FORMS BEFORE CASTING ANY CONCRETE.
8. SPECIFICATIONS FOR MIXING, PLACING, AND FINISHING SHALL BE AS PER SPECIFICATIONS AND ACI-302.
9. REINFORCING, DOWELS, BOLTS, ANCHORS, SLEEVES, ETC., TO BE EMBEDDED IN CONCRETE SHALL BE SECURELY POSITIONED
BEFORE PLACING CONCRETE.
10. CONSOLIDATE CONCRETE PLACED IN FORMS BY MECHANICAL VIBRATING EQUIPMENT SUPPLEMENTED BY HAND-SPADING, RODDING OR TAMPING. USE EQUIPMENT AND PROCEDURES FOR CONSOLIDATION OF CONCRETE IN ACCORDANCE WITH THE RECOMMENDED PRACTICES OF ACI 309 TO SUIT THE TYPE OF CONCRETE AND PROJECT CONDITIONS. CONCRETE SHALL NOT BE DROPPED THROUGH REINFORCING STEEL (AS IN WALLS) SO AS TO CAUSE SEGREGATION OF AGGREGATES. IN SUCH CASES HOPPERS AND CHUTES OF VARIABLE LENGTHS SHALL BE USED SO THAT THE FREE UNCONFINED FALL OF CONCRETE SHALL NOT
EXCEED 6 FEET.
11. WATER TO CEMENT RATIO SHALL NOT EXCEED 0.45.
REINFORCING STEEL NOTES:
1. CONCRETE CLEAR COVERAGE TO REINFORCING STEEL SHALL CONFORM TO THE FOLLOWING MINIMUMS, U.N.O.
A. CONCRETE CAST AGAINST AND PERMANENTLY EXPOSED TO EARTH 3”
B. CONCRETE EXPOSED TO EARTH OR WEATHER 2”
C. CONCRETE NOT EXPOSED TO WEATHER OR IN CONTACT WITH GROUND 1-1/2”
3. SPLICES IN CONTINUOUS REINFORCEMENT SHALL BE LAPPED U.N.O. IN NO CASE SHALL SPLICES BE LESS THAN 40 BAR DIAMETERS.
SPLICES IN ADJACENT BARS SHALL NOT BE LESS THAN 5' APART. SPLICE CONTINUOUS BARS IN SOIL-BEARING GRADE BEAMS AS
FOLLOWS: TOP BARS AT CENTERLINE OF SUPPORT; BOTTOM BARS AT MID-SPAN.
4. ALL HOOKS SHALL BE STANDARD HOOKS UNLESS OTHERWISE SHOWN OR NOTED.
W
LEGEND
EXISTING GRAVEL ROADWAY
PROPOSED GRAVEL ROADWAY
EXISTING GRAVEL ROADWAY
EXISTING CONCRETE
PROPOSED CONCRETE
EXISTING COMMUNICATION LINE
EXISTING POWER LINE
EXISTING MAJOR CONTOURS
EXISTING MINOR CONTOURS
PROPOSED MAJOR CONTOURS
PROPOSED MINOR CONTOURS
EXISTING IRRIGATION LINE
PROPOSED WATER LINE
EXISTING WATER LINE
LOCAL SURVEY CONTROL POINT
EXISTING IRRIGATION SPRINKLER
EXISTING IRRIGATION VALVE
EXISTING WELL
EXISTING POWER POLE
EXISTING LIGHT POLE
EXISTING ACCESSIBLE VAULT TOILET
EXISTING SEWER HOOKUP
EXISTING HYDRANT
PROPOSED HYDRANT
PROPOSED GATE VALVE
EXISTING TREE
EXISTING PLANT
DEMOLITION
ABBREVIATIONS
EDGE OF GRAVEL
EDGE OF CONCRETE
BUILDING CORNER
EG
EC
BC
13293
CONSTRUCTION NOTES:
1. ALL EQUIPMENT SHALL BE CLEANED AND INSPECTED PRIOR TO USE ON THE PROJECT SO AS TO PREVENT THE TRANSPORT AND
SPREAD OF NOXIOUS WEEDS AS WELL AS TO PREVENT SPILLS OR LEAKS OF EQUIPMENT FLUID.
2. SERVICE AND REFUEL EQUIPMENT IN DESIGNATED AREAS ONLY.
3. DISTURBANCES IN STAGING AREAS SHALL BE KEPT TO A MINIMUM, AND SHALL BE RESTORED TO EXISTING CONDITIONS AFTER
CONSTRUCTION ACTIVITIES.
4. STRIP AND STOCKPILE TOPSOIL/GRAVEL FOR REUSE AFTER COMPLETION OF CONSTRUCTION ACTIVITIES.
5. PROVIDE BEST MANAGEMENT PRACTICES FOR STORMWATER CONTROLS PRIOR TO AND DURING CONSTRUCTION. THIS PLAN SHALL
BE IN ACCORDANCE WITH THE LOCAL AUTHORITY, INCLUDING ALL REQUIRED PERMITS AND APPROVALS, PRIOR TO CONSTRUCTION.
CIVIL NOTES:
1. AT COMPLETION OF PROJECT STOCKPILE AREAS SHALL BE REMOVED AND RESTORED TO EXISTING CONDITION UNLESS SPECIFIED
OTHERWISE BY GOVERNMENT.
2. ALL AREAS DISTURBED DURING CONSTRUCTION SHALL BE REHABILITATED TO THE ORIGINAL CONTOURS AND RESTORED TO THE
ORIGINAL CONDITION TO THE GREATEST EXTENT POSSIBLE.
3. AT A MINIMUM, THE MATERIALS USED FOR A POTABLE WATER SYSTEM MUST MEET NSF STANDARD 61, AND APPLICABLE AWWA
STANDARDS.
3.1. THE MINIMUM DEPTH OF PIPE COVER MUST BE 36".
3.2. POTABLE AND NON POTABLE UTILITY MAINS, LATERAL OR UNDOCUMENTED CONDUIT MUST MAINTAIN HORIZONTAL AND
VERTICAL SEPARATION REQUIREMENTS, IN ACCORDANCE WITH THE MINIMUM REQUIREMENTS OUTLINED IN THE ISPWC.
3.3. NEWLY INSTALLED WATER MAINS AND SERVICE LINES MUST BE HYDROSTATICALLY TESTED IN ACCORDANCE WITH THE MOST
RECENT AWWA, IDWR, AND IDEQ STANDARD.
3.4. NEWLY INSTALLED WATER MAINS MUST BE FLUSHED, STERILIZED AND SAMPLED FOR CONTAMINATES, IN ACCORDANCE WITH
THE MOST RECENT AWWA, IDWR, AND IDEQ STANDARD.
3.5. THE CONTRACTOR IS RESPONSIBLE FOR:
3.5.1. OBTAINING APPLICABLE LICENSES, PERMITS, BONDS, OR OTHER REQUIRED ADMINISTRATIVE REQUIREMENTS, AT THE
CONTRACTOR'S EXPENSE.
COM
W
E
R C
McKay Andersen
Digitally signed by McKay Andersen Date: 2022.11.03 11:42:22 -06'00'
W
W
WW
WWW
E E
E
W
W
W
W
COUNTY ROAD
s
W
W
W
STUMP
CO
M
CO
M
CO
M
COM
COM
COM
COM
E
E
SNAKE RIVER
W
W
W
W
W
W
13293
EXISTING ACCESSIBLE
VAULT TOILET
EXISTING ACCESSIBLE
VAULT TOILET
EXISTING 3000
GALLON SANITARY SEWER VAULT
EXISTING SANITARY SEWER
HOOKUP
EXISTING POTABLE
WATER HOOKUP
EXISTING POTABLE
WATER LINE (TYP)
EXISTING COMMUNICATIONS
LINE
SURVEY NOTES:
1. EXISTING FEATURES: EXISTING ROADWAYS, UTILITIES,
STRUCTURES, AND OTHER FEATURES ARE SHOWN USING A
COMBINATION OF DRAWINGS AND SURVEY PROVIDED BY THE
GOVERNMENT AND FIELD OBSERVATIONS.
2. VERIFICATION: APPROXIMATE SIZE, CONDITION, AND LOCATION
OF EXISTING FEATURES SHALL BE VERIFIED PRIOR TO
CONSTRUCTION.
EXISTING PRECAST
CONCRETE WELL HOUSE
EXISTING POTABLE
WATER WELL
EXISTING DRINKING
FOUNTAIN
EXISTING YARD
HYDRANT (TYP)
EXISTING
SIDEWALK
EXISTING IRRIGATION
WATER LINE (TYP)
McKay Andersen
Digitally signed by McKay Andersen
11:43:45 -06'00'
W
WW
WWW
E E
E
W
W
W
W
COUNTY ROAD
s
W
W
W
STUMP
CO
M
CO
M
CO
M
COM
COM
COM
COM
E
E
SNAKE RIVER
W
W
W
W
W
W
13293
REMOVE ALL EXISTING
PIPING WEST OF THE
MAIN ROADWAY
DEMOLISH EXISTING
WATER FOUNTAIN
RETAIN AND PROTECT
EXISTING SEWER VAULT
RETAIN AND PROTECT
EXISTING SEWER
HOOKUP
REPLACE POTABLE WATER
HOOKUP AND PIPING FROM
WELL HOUSE WITH NEW
RETAIN AND PROTECT EXISTING
PRECAST CONCRETE PUMP
HOUSE SEE P101 FOR PUMP
HOUSE UPGRADES
RETAIN AND PROTECT
EXISTING WELL
RETAIN AND PROTECT EXISTING
COMMUNICATION LINES
REMOVE EXISTING
PIPING TO MAKE WAY
FOR NEW
DEMOLISH YARD HYDRANT
FOUNTAIN (TYP-5 PLACES)
RETAIN AND PROTECT EXISTING
PRECAST CONCRETE
ELECTRICAL SHELTER
RETAIN AND PROTECT EXISTING
IRRIGATION LINES
McKay Anderse n
Digitally signed by McKay Andersen
11:44:45 -06'00'
E
E
COUNTY ROAD
s
STUMP
CO
M
CO
M
CO
M
COM
COM
COM
COM
E
E
SNAKE RIVER
W
W W
W W
W
WW
W
W
W
W
W
W
W
W
W
W
W W
W
W
W W
W
W
W
W
W
W
W
W
W W
W
W W
W
W
W
W
13293
NOTES:
1. APPROXIMATE LOCATION OF SHADE STRUCTURE IS SHOWN ON
THE PLANS. THE FINAL LOCATION WILL BE DETERMINED BY THE
GOVERNMENT.
2. INSTALL NEW WATER LINES JUST TO THE SIDE OF THE ROAD
AND OUT OF THE VEGETATION. DO THIS EXCEPT WHERE
SHOWN OTHERWISE ON THE PLANS.
3. HYDROSEED ALL DISRUPTED AREAS OUTSIDE OF ROADS,
PARKING AND CONCRETE PADS.
KEY NOTES:
1. PROVIDE AND INSTALL NEW 2" HDPE DR 11 WATER PIPE TO CAMP
SITES PER PLANS AND TRENCH PER DETAIL 1/C501. SEE NOTE 2.
2. PROVIDE AND INSTALL NEW HYDRANT PER DETAIL 2/C501 (TYP).
3. UPGRADE EXISTING PUMP HOUSE SEE SHEET P101.
4. MAINTAIN A MINIMUM OF 10 FT HORIZONTAL SEPARATION
BETWEEN SEWER AND NEW WATER LINES.
5. PROVIDE AND INSTALL 16 FT BY 40 FT CONCRETE PAD PER DETAIL
3/C501.
6. PROVIDE AND INSTALL SHADE STRUCTURE ON CONCRETE PAD
PER SHEET C502. SEE NOTE 1.
7. CROSS EXISTING WATERLINE PER DETAIL 5/C501.
8. PROVIDE AND INSTALL ANSI/AWWA C509 2" RESILIENT SEATED
GATE VALVE PER ISPWC SD406 (TYP).
SEE SHEET C104
PLACE HYDRANT NEAR THE GROUP
SHADE SHELTER AS DIRECTED BY
GOVERNMENT
2 8
McKay Andersen
Digitally signed by McKay Andersen
11:46:13 -06'00'
EEE
E
E
E E
E E
E E
E E
E E s E
E E
E
CO
M
CO
M
CO
M
CO
M
CO
M
CO
M
CO
M
CO
M
COM
WWWWWW
W W
W W
W W
W W
W W
W W
W W
W W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W W W
W W
W
W
W
W
W
W
W
W
W W
W W
W
W
W
W
W
W W
W W
13293
NOTES:
1. PLACE NEW ~16 FT BY ~45 FT CONCRETE PAD 5 FT NORTH OF
EXISTING RV PAD.
KEY NOTES:
1. UPGRADE EXISTING PUMP HOUSE SEE SHEET P101.
2. MAINTAIN A MINIMUM OF 10 FT HORIZONTAL SEPARATION
BETWEEN SEWER AND NEW WATER LINES.
3. RETAIN AND PROTECT EXISTING SEWAGE VAULT SERVICE AND
HOOKUP.
4. PROVIDE AND INSTALL 16 FT WIDE CONCRETE PAD PER DETAIL
3/C501. SEE NOTE 1. MATCH ELEVATION OF EXISTING PAD
5. CROSS WATERLINE FROM WELL PER DETAIL 5/C501.
6. RETAIN AND PROTECT EXISTING COMMUNICATION SERVICE AND
HOOKUP
7. RETAIN AND PROTECT EXISTING ELECTRICAL SERVICE AND
HOOKUP.
8. RETAIN AND PROTECT EXISTING RV PAD.
9. PROVIDE AND INSTALL NEW 2" HDPE DR 11 WATER PIPE FROM
WELL HOUSE TO CAMP SITES PER PLANS TRENCH PER DETAIL
1/C501.
10. PROVIDE AND INSTALL NEW HYDRANT PER DETAIL 2/C501.
11. PROVIDE AND INSTALL NEW 2" HDPE DR 11 WATER PIPE FROM
WELL PITLESS ADAPTER TO WELL HOUSE. TRENCH PER DETAIL
1/C501.
12. PROVIDE AND INSTALL NEW 1" HDPE DR 11 WATER PIPE FROM
WELL HOUSE TO CAMP SITES PER PLANS TRENCH PER DETAIL
1/C501.
25' MIN.
EXISTING
WELL
0'
21'
McKay Andersen
Digitally signed by McKay Andersen
11:47:00 -06'00'
SCALE:4 TYPICAL SLAB JOINTS
NTS
FIRST POUR SECOND POUR
1/2" DIA x 18" DOWEL @ 18" O.C.
1/8" SAWCUT OR
TOOLED JOINT
EXPANSION JOINT
MATERIAL
1/2" JOINT
3/8" SEALANT
NOTE:
CONSTRUCTION JOINTS & CONTROL JOINT FOR ALL FLATWORK SHALL DIVIDE SLAB INTO AREAS NOT
EXCEEDING 225 SQFT WITHOUT REENTRANT CORNERS AND WITH LENGTH TO WIDTH RATIOS NOT
EXCEEDING 1 1/2 TO 1. CONTRACTOR SHALL SUBMIT LAYOUT PLAN SHOWING PROPOSED CONTROL AND CONSTRUCTION JOINT LOCATIONS. JOINT SPACING SHALL NOT EXCEED 20 FEET IN EITHER DIRECTION.
CONTRACTOR SHALL HAVE CONTROL JOINTS IN SIDEWALKS EVERY 5 FEET AND EXPANSION JOINTS
EVERY 50 FEET MINIMUM.
CONSTRUCTION JOINT CONTROL JOINT
EXPANSION JOINT
SCALE:1 TYPICAL WET UTILITY TRENCH
NTS
MATCH ADJACENT
SURFACE TREATMENT
SIZE OF UTILITY
MAY VARY
SUITABLE SOIL
BACKFILL
WIDTH AS NEEDED
2xØ MIN
PIPE ZONE BEDDING
COURSE
1/2Ø MIN
TYP
NOTE: BACKFILL MATERIALS COMPACTION
- 95% STD PROCTOR UNDER SLABS AND ROADS
- 90% STANDARD PROCTOR MIN ALL OTHER AREAS
PIPE ZONE MATERIAL TO
SURROUND PIPE 3" MIN
DEPTH 3' MIN
UTILITY MARKING TAPE
12 AWG TRACING WIRE
13293
TRENCH PIPE PER DETAIL 1
SHEET C501
WOODFORD MODEL S3 YARD
HYDRANT OR APPROVED EQUAL
6' DIAMETER
BACKFLOW RESERVOIR OF
FROST FREE YARD HYDRANT
GROUND LEVEL
5% MAX SLOPE (TYP)
12" DIA BY 40" LONG
HDPE PIPE 15° SKEW
FILL PIPE WITH LOOSE
DRAINAGE COURSE GRAVEL
1" MINUS
CRUSHED
AGGREGATE
SURROUNDING
YARD HYDRANT
4 OZ/SY NONWOVEN GEOTEXTILE FABRIC PER AASHTO
M288.06 CLASS II FOR FINES GREATER THAN 50%.
LAP ENDS MINIMUM OF 1 FOOT INTO AROUND PIPE.
36"
1" FEMALE THREAD
36" MIN BURY
FROST LINE
SE
E
N O
TE
SCALE:2 TYPICAL HYDRANT DETAIL
NTS
SCALE:5 TYPICAL WATER LINE CROSSING
NTS
NOTE:
INSTALL POTABLE WATER LINE CROSSING WITH A MINIMUM OF
6 INCH CLEARANCE BETWEEN PIPES.
SCALE:3 TYPICAL THICKENED EDGE CONCRETE SLAB
NTS
FIRM NATIVE SOILS OR
ENGINEERED COMPACTED FILL
IMPROVED GRAVEL
SURFACE WHERE OCCURS
6" CRUSHED AGGREGATE
BASE COURSE
6" CONCRETE REINFORCED WITH #4 BARS
@ 18" O.C. EACH WAY
THICKENED EDGE SLAB
6"
NOTE:
INSTALL CONSTRUCTION JOINTS & CONTROL JOINTS PER
DETAIL 4 SHEET 501.
NOTE:
1. PER MANUFACTURERS RECOMMENDATION.
GROUND SURFACE
POTABLE LINE
POTABLE LINE
VA
R
IE
S
6" MIN
McKay Andersen
Digitally signed by McKay Andersen
11:48:12 -06'00'
PAVILION STRUCTURE SECTION2
5'4'3'2'0 1'1' 6' 7'
PAVILION STRUCTURE SECTIONA
5'4'3'2'0 1'1' 6' 7'
PAVILION STRUCTURE PLAN VIEW1
5'4'3'2'0 1'1' 6' 7'
C502
6" MIN CONCRETE
SLAB WITH #4 BARS
@ 18" O.C. EACH WAY
6" MIN OF 3 4" CRUSHED
AGGREGATE
SLOPE PAD TO DRAIN,
2% MAX SLOPE IN ALL
DIRECTIONS
20' X 40' GABLE SHELTER RCP
SHELTER MODEL TS-G2040-04
OR APPROVED EQUAL
17'18'-6" 18'-6"
8'
STANDING SEAM METAL
ROOF SHEETING
40'
20'
A C502
RIDGE
STRUCTURAL NOTES:
1. RCP (OR APPROVED EQUAL) GABLE SHELTER STEEL COLOR TO BE APPROVED BY
THE GOVERNMENT.
2. RCP (OR APPROVED EQUAL) METAL ROOF SHEETING COLOR TO BE APPROVED BY
THE GOVERNMENT.
FINAL BUILD AND FOUNDATION DESIGN NOTES:
1. ALL COLUMN SIZES AND LOADS REPRESENTED IN THIS FOUNDATION PLAN WERE
ASSUMED. ACTUAL SIZES, LAYOUT, AND LOADING SHALL BE PROVIDED BY THE
CONTRACTOR-PROVIDED PRE-ENGINEERED SHELTER DESIGNER.
2. ALL RELEVANT LOADS AND LOAD COMBINATIONS PER ASCE 7 SHALL BE CHECKED
FOR MOST CRITICAL.
3. THE FINAL FOUNDATION DESIGN SHALL BE BY THE CONTRACTOR-PROVIDED
FOUNDATION ENGINEER WITH THE ACTUAL SIZES, LAYOUT, AND LOADS PROVIDED
BY THE CONTRACTOR-PROVIDED PRE-ENGINEERED SHELTER DESIGNER.
4. COLUMNS BASE PLATES AND ANCHOR BOLT REQUIREMENTS SHALL BE PROVIDED
BY THE CONTRACTOR-PROVIDED PRE-ENGINEERED SHELTER DESIGNER.
5. THE CONTRACTOR IS RESPONSIBLE FOR FINAL FOUNDATION AND DESIGN AND
SHALL COORDINATE ALL APPROVALS WITH THE GOVERNMENT.
PAVILION FOUNDATION DESIGN DRAWINGS ON SHEET C502
ARE FOR REFERENCE ONLY.
SCALE: NTS
PAVILION SHELTER FOOTING DETAIL (TYP)3
STEEL POSTS (TYP)
6" MIN CONCRETE SLAB WITH #4
BARS @ 18" O.C. EACH WAY MIN
(30) #4 VERTICAL REINFORCEMENT
BARS EVENLY SPACED
#3 REINFORCEMENT
HOOPS @ 8" O.C.
FIRM NATIVE SOIL OR ENGINEERED
COMPACTED FILL
#3 REINFORCEMENT HOOPS @ 8" O.C.
(30) #4 VERTICAL REINFORCEMENT
BARS EVENLY SPACED
ANCHOR BOLTS PER
PRE-ENGINEERED METAL BUILDING
MANUFACTURERS SPECIFICATION
6" MIN OF 3/4" CRUSHED
AGGREGATE
Ø3'-6" CONCRETE FOOTING
Ø3'-6"
3" MIN3" MIN
5'-3" MIN
EMBEDMENT
13293 McKay Andersen
Digitally signed by McKay Andersen
11:49:03 -06'00'
AV
DOMESTIC COLD WATER
DOMESTIC HOT WATER
DOMESTIC HOT WATER RECIRC.
NON POTABLE COLD WATER
SANITARY SEWER
VENT
FLOOR CLEAN OUT
WALL CLEAN OUT
CONDENSATE DRAIN
ROOF DRAIN
OVERFLOW DRAIN
CONDENSATE RETURN
SLOPE DOWN IN DIRECTION OF FLOW
DCW
HWC
NPCW
DHW
SS
VT
FCO
WCO
CD
CR
RD
OD
S=.XXX
DE
X
ISOLATION VALVE
BALL VALVE
BUTTERFLY VALVE
GLOBE VALVE
GAS SHUT-OFF COCK
CHECK VALVE
Y-TYPE STRAINER
WATER OUTLET (TYPE INDICATED)
BACKFLOW PREVENTER (TYPE INDICATED)
SLEEVE (PIPE) THRU WALL OR FLOOR
FLEX CONNECTOR (TYPE INDICATED)
HOSE END DRAIN VALVE
PRESSURE REDUCING VALVE
TEMP. & PRESSURE RELIEF VALVE
AUTOMATIC AIR VENT
DIELECTRIC UNION
UNION
(AUTOMATIC) BALANCING VALVE
DIAL/GAUGE THERMOMETER
PRESSURE GAUGE
PIPE ANCHOR
SOLENOID VALVE
PLUG VALVE
VALVE IN RISER
INLINE PUMP
TEE DOWN
ELBOW UP
ELBOW DOWN
PIPE CAP
PIPE DRAIN & CAP
NEW PIPING
CENTRIFUGAL PUMP
LINE SIZE CHANGE
TURBINE WATER METER
T-TYPE STRAINER
ALTITUDE VALVE
SUMP PUMP
HOSE BIBB
DRAIN
INSTRUMENT WIRE
AIR/VACUUM VALVE
INSTRUMENT
REPLACE "XX" WITH THE FOLLOWING
WBG - WATER BOARD GAGE
LE - LEVEL ELEMENT
LT - LEVEL TRANSMITTER
LD - LEVEL DISPLAY
P - ANALOG PRESSURE GAUGE
PG - PRESSURE GAUGE, DIGITAL
WM - WATER METER TRANSMITTER
PS - PRESSURE SWITCH
LS - LEVEL SWITCH
BREAK LINE
XX
REVISION NUMBER
DETAIL BUBBLE
SECTION CUT
P102
SHEET NO. - WHERE SECTION
IS SHOWN
SECTION LETTER
SHEET NO. - WHERE DETAIL
IS SHOWN
DETAIL NUMBER
-PUMPS AND INSTRUMENTS- -VALVES AND GAGES- - ABBREVIATIONS -
NORTH ARROW
EQUIPMENT TAG
KEY NOTE
(NOTE: NOT ALL SYMBOLS OR ABBREVIATIONS SHOWN ARE USED ON THESE DRAWINGS)PLUMBING LEGEND
EF-1
HATCHING INDICATES
ITEM(S) TO BE
REMOVED
SAFETY RELIEF VALVE
A P102
UNDERGROUND PIPING, XXX= SYSTEM
DESIGNATOR
GAS REGULATOR
COMPRESSED AIRCA
S
Hb
XXX
TEE UP
NATURAL GASNG
LIMIT OF DEMOLITION (SHADED AND HATCHED)
CONNECT NEW (SHADED) TO EXISTING
PRESSURE REGULATOR
WATER HAMMER ARRESTOR
ANGLE VALVE / STOP
DIAPHRAGM VALVE
TEST PLUG (PETE'S PLUG)
QUICK CONNECT COUPLING
FLEX CONNECTION
FLOOR OR WALL PENETRATION (ISO VIEW)
FLANGED CONNECTION
BFP
FLEXPIPE
FLOOR DRAIN
FLOOR SINK
AAV AIR ADMITTANCE VALVE
AB.C. ABOVE CEILING
ACP AIR COMPRESSOR
AFF ABOVE FINISHED FLOOR
AV ACID VENT
AW ACID WASTE
BFF BELOW FINISHED FLOOR
BFP BACK FLOW PREVENTER
BG BELOW GRADE
BOP BOTTOM OF PIPE
BP BOOSTER PUMP
CA COMPRESSED AIR
CD CONDENSATE DRAIN
C.I.N.H CAST IRON NO HUB
CL CENTERLINE
CO CLEANOUT
CON CONCENTRIC
CONT. CONTINUED
CKV CHECK VALVE
CPVC CHLORINATED POLYVINYL CHLORIDE
CW COLD WATER
CX CONNECT TO EXISTING
(D) PIPE DROP
DCW DOMESTIC COLD WATER
DF DRINKING FOUNTAIN
DHW DOMESTIC HOT WATER
DN PIPE DROP TO NEXT LEVEL
DTL DETAIL
(E) EXISTING
ECC ECCENTRIC
EEW EMERGENCY EYE WASH
ESW EMERGENCY SAFETY SHOWER
ET EXPANSION TANK
F FIRE SERVICE
FCO FLOOR CLEANOUT
FD FLOOR DRAIN
FFHB FROST FREE HOSE BIBB
FIL FILTER
FND FOUNDATION DRAIN
FM FLOW METER
F.R.R. FEMALE RESTROOM
FS FLOOR SINK
GCO GRADE CLEANOUT
HB HOSE BIB
HW HOT WATER
HWC HOT WATER CIRCULATION
HWR HOT WATER RETURN
HWS HOT WATER SUPPLY
IDW INDIRECT WASTE
IRR INVERT ELEVATION IRRIGATION
LAV LAVATORY
LPG LIQUEFIED PETROLEUM GAS
LWCO LOW WATER CUTOFF
MAX MAXIMUM
MIN MINIMUM
M.R.R. MALE RESTROOM
MSB MOP SINK BASIN
NG NATURAL GAS
NIC NOT IN CONTRACT
NO NORMALLY OPEN (VALVE)
NC NORMALLY CLOSED (VALVE)
NTS NOT TO SCALE
OD OVERFLOW DRAIN
OH OVER HEAD
OFL OVERFLOW RAIN LEADER
(P) PUMP
PCV PRESSURE CONTROL VALVE
PEX CROSS LINKED POLYETHYLENE
(R) PIPE RISE
RD ROOF DRAIN
RP RECIRCULATION PUMP
R.R. REST ROOM
PVC POLYVINYL CHLORIDE
RIO ROUGH-IN ONLY
RW RECIRCULATED WATER
RWL RAIN WATER LEADER
(S) SINK
SHT SHEET
SCW SOFT COLD WATER
SOC SHUT OFF COCK (GAS)
SOV SHUT OFF VALVE
S.S. SANITARY SEWER
ST SAMPLE TAP
STR STRAINER
TYP TYPICAL
TPL TRAP PRIMER LINE
(U) URINAL
UG UNDERGROUND
UP PIPE RISE TO NEXT LEVEL
U.S. UNDER SLAB
US UTILITY SINK
UTR UP THRU ROOF
VA VALVE
VT VENT
VTR VENT THRU ROOF
(W) WASTE
WC WATER CLOSET
WCO WALL CLEANOUT
WHA WATER HAMMER ARRESTOR
WH WATER HEATER
WM WATER METER
WSR WATER SOFTENER
T
DESCRIPTION SYMBOL DESCRIPTIONSYMBOL
-PIPE LINEWORK-
DESCRIPTIONSYMBOL
-DRAINS-
DESCRIPTIONSYMBOL
-GRAPHIC SYMBOLS-
DESCRIPTIONSYMBOL
(N) NEW
1. COORDINATE PLUMBING FIXTURES AND RELATED PIPING WITH ALL OTHER
TRADES AS REQUIRED.
2. CONTRACTOR TO PROTECT AND MAINTAIN EXISTING UTILITIES AS INDICATED.
REFERENCE, PLUMBING, ELECTRICAL DRAWINGS. FIELD LOCATE
UNDERGROUND LINES, MARK, AND PROTECT AS NECESSARY. COORDINATE
PROTECTION AND ANY AND ALL TEMPORARY DISRUPTIONS OF SERVICE WITH
GOVERNMENT AS NECESSARY. PROVIDE ANY REQUIRED SHORING AND
STRUCTURAL SUPPORTS OF PIPING AND CONDUITS AS REQUIRED.
SCHEDULE WORK AND ANY REQUIRED INSPECTIONS TO MINIMIZE
DISRUPTION OF SERVICE AS NECESSARY.
3. LOCATE WATER PIPING IN HEATED AREAS ONLY. DO NOT LOCATE PIPING IN
NON-INSULATED ATTIC, CEILING OR WALL SPACES. DO NOT LOCATE WATER
PIPING IN ANY EXTERIOR WALL.
4. COORDINATE WITH ALL OTHER TRADES INCLUDING MECHANICAL FOR
EQUIPMENT, FIXTURES AND RELATED PIPING.
5. REFER TO PLUMBING FIXTURE SCHEDULE FOR CONNECTION SIZES. FIELD
VERIFY FOR TRANSITIONS REQUIRED FOR CONNECTING TO EXISTING PIPING.
GENERAL NOTES:
Juan L Rodriguez
Digitally signed by Juan L Rodriguez DN: CN=Juan L Rodriguez, dnQualifier=A01410C0000017D390FBB550001FB2C, O=CIRI DEVELOPMENT CORPORATION DBA
NORTH WIND GROUP, C=US
Location: NorthWind, Knoxville TN Reason: I am approving this document Contact Info: 7863518681 Date: 2022.11.07 08:57:02-05'00'
1. RETAIN AND CAP 2" RISER FROM WELL FOR FUTURE USE.
2. DEMOLISH COLD WATER LINE.
3. REMOVE PRESSURE TANK.
4. REMOVE PUMP AND PIPING UP TO THE 500 GALLON
STORAGE TANK.
5. RETAIN CAP AND PROTECT 500 GALLON STORAGE TANK
FOR FUTURE USE.
6. REMOVE PIPING ASSOCIATED WITH THE EXISTING WATER
FILTRATION SYSTEM.
7. REMOVE DRAIN LINE PIPING TO SUMP.
8. RETAIN AND PROTECT SUMP FOR FUTURE USE.
9. RETAIN AND CAP 2" RISER TO CAMPGROUND.
10. RETAIN AND PROTECT ALL OTHER UTILITIES INCLUDING
ELECTRICAL AND SANITARY SEWER.
11. RETAIN AND PROTECT EXISTING WELL HOUSE.
12. REMOVE ALL PIPING AND EQUIPMENT ASSOCIATED WITH
THE IRRIGATION SYSTEM.
DEMOLITION KEY NOTES:
SCALE:1 PUMP HOUSE DEMOLITION PLAN
NTS
Juan L Rodriguez
Digitally signed by Juan L Rodriguez DN: CN=Juan L Rodriguez, dnQualifier=A01410C0000017D390FBB550001FB2C, O=CIRI DEVELOPMENT CORPORATION DBA
NORTH WIND GROUP, C=US
Location: NorthWind, Knoxville TN Reason: I am approving this document
Date: 2022.11.07 08:58:09-05'00'
SCALE:1 PUMP HOUSE PLAN
NTS
1. 2" RISER FROM WELL (EXISTING PVC RISER).
2. 1" PVC PIPE WITH SOCKET CONNECTIONS.
3. PRESSURE RELIEF VALVE, ROUTE TO SUMP. SET TO 75 PSI.
4. ISOLATION VALVE IN THE OPEN POSITION DURING NORMAL
OPERATION.
5. TEE WITH SMOOTH NOSE SAMPLE TAP (NO CONNECTION
ALLOWED) AND PRESSURE GAUGE.
6. FLOWMETER (FM-1).
7. FILTER (FIL-1). FIELD ROUTE 1/2" BACKWASH LINE TO SUMP
ALONG GROUND. AUTOMATIC ISOLATION VALVE INSTALLED.
8. FLEX PIPE FOR TREATMENT SYSTEM. FIELD ROUTE.
9. BACK WASH LINE.
10. PRESSURE GAUGE. INSTALL SO AS TO BE ACCESSIBLE AND
READABLE.
11. HOSE BIB WITH BACKFLOW FOR SYSTEM DRAIN INSTALLED
NEAR GROUND LEVEL.
12. CHEMICAL CONTAINMENT PAD. 29.9" X 54.6" X 16.8". SEE DETAIL
2 / P-502
13. 2" LINE.
14. VERTICAL CHECK VALVE, PRESSURE GAUGE AND TEE (SHOWN
IN DETAIL DRAWINGS).
15. DRAIN LINE. ISOLATION TO REMAIN CLOSED DURING NORMAL
OPERATION.
16. INLET TO THE 500 GALLON STORAGE TANK. MATCH EXISTING
CONDITIONS.
17. OUTLET FROM THE 500 GALLON STORAGE TANK. OUTLET IS AT
GROUND LEVEL.
18. 500 GALLON STORAGE TANK (EXISTING).
19. EXPANSION TANK (ET-1). 211 GALLON, 2" NPTF CONNECTION.
CONNECT PRESSURE SWITCH TO PUMP P-1. SET CUT IN
PRESSURE TO 40 PSI AND CUT OUT PRESSURE TO 55 PSI.
20. PUMP (P-1). PROVIDE WITH AN AUTOMATIC SHUTOFF FOR LOW
PRESSURE ON THE INTAKE SIDE (LESS THAN 5 PSI) AND TO
CUT OFF TO AVOID EXCESSIVE TANK DRAW DOWN.
21. FILTRATION SYSTEM. SEE SCHEDULE AND P & ID FOR DETAILS.
22. REDUCER.
23. 2" SUCTION LINE AT GROUND LEVEL.
24. 2" DISCHARGE LINE. RISE TO LEVEL SUFFICIENT TO AVOID PIPE
WORK ON THE GROUND AND ALLOW FOR MANEUVERING
AROUND FOR MAINTENANCE.
25. 2" TANK DRAIN LINE. ROUTE ALONG GROUND.
26. 1" WELL DISCHARGE LINE. ROUTE AT GROUND LEVEL. VALVE
NORMALLY CLOSED.
27. 2" RISER TO CAMPGROUND AND TEE OFF TO 1" RISER TO
CAMP HOST SITE SERVICE (EXISTING).
28. SUMP PIT WITH COVER (EXISTING). MODIFY LID TO ACCEPT
THE VARIOUS WASTE LINES BEING ROUTED TO IT.
29. SUMP EXIT TO DRAIN FIELD (EXISTING).
30. UNION.
31. ELECTRICAL PANEL WITH 36" X 30" MIN. CLEARANCE IN FRONT.
QUALIFIED ELECTRICIAN TO VERIFY THAT THE PANEL HAS
SUFFICIENT CAPACITY FOR THE RE-DESIGNED SYSTEM.
32. EYEWASH STATION. PROVIDE HONEYWELL TWO (2) 32 OZ
BOTTLES ITEM # 32-000462-0000-H5 OR SIMILAR.
33. STORAGE TANK OVERFLOW, ROUTE TO SUMP.
34. RISE ALL NEW PIPING DISCHARGING TO THE SUMP A MINIMUM
OF 12" ABOVE SUMP PIT TO ALLOW FOR AN AIR GAP.
35. EXPANSION TANK (ET-2). 34 GALLON, 1 1/4" NPTF CONNECTION.
CONNECT PRESSURE SWITCH TO WELL PUMP. CUT IN AT 40
PSI AND CUT OUT AT 60 PSI.
36. SOLENOID VALVE. CONNECT TO LEVEL SWITCH INSIDE
STORAGE TANK. SET CUT IN AT 9" LEVEL DIFFERENTIAL FROM
THE TOP OF THE FULL TANK. (APPROX. 50 GALLONS). SEE
SCHEDULE FOR DETAILS.
37. REVERSE OSMOSIS SKID.
38. DOUBLE CHECK BACKFLOW PREVENTER, BFP-1.
39. UV LIGHT INSTALLED IN WATER STORAGE TANK. SEE
SCHEDULE FOR DETAILS. FOLLOW MANUFACTURERS
INSTRUCTIONS FOR PROPER INSTALLATION AND
DISINFECTION.
P501
TYP
KEY NOTES: GENERAL NOTES:
1. SECURE LINES RUN ALONG GROUND TO
PREVENT MOVEMENT.
2. ALL LINES AND FITTINGS ARE TO BE
SCHEDULE 40 PVC.
3. FOLLOW SPECIFICATION 220529 FOR
PIPING SUPPORT.
4. PIPING IS SHOWN DIAGRAMMATICAL.
EXACT DIMENSIONS AND LOCATIONS TO BE
MADE IN THE FIELD FOR FINAL FIT UP WITH
MINIMIZED BENDS AND FITTINGS. FIELD
VERIFY DIMENSIONS FOR EQUIPMENT
LOCATIONS TO ALLOW ACCESS FOR
OPERATIONS AND MAINTENANCE. ANY
DIMENSIONS SHOWN ARE FOR REFERENCE
ONLY
5. SEE SHEET P601 FOR SCHEDULE.
TYP
SCALE:2 VERTICAL RUN
NTS
TYP
P101
P501
2'-11"
12" MIN
Juan L Rodriguez
Digitally signed by Juan L Rodriguez DN: CN=Juan L Rodriguez, dnQualifier=A01410C0000017D390FBB550001FB2C, O=CIRI DEVELOPMENT CORPORATION DBA
NORTH WIND GROUP, C=US
Location: NorthWind, Knoxville TN Reason: I am approving this document
Date: 2022.11.07 08:59:00-05'00'
PS
LS
P
P
P
PS
BF
P
Hb
S
S
500 GALLON
STORAGE TANK
(EXISTING)
ST-1
2" LINE
FROM WELL
(8 GPM MAX FLOW)
DISCHARGE TO SUMP
PROVIDE
AIR GAP (TYP)
PRESSURE TANK 40 / 55
PRE-CHARGE TO 38 PSIG
2" LINE TO CAMPGROUND
SCALE:1 PUMP HOUSE P & ID
NTS
CONNECT TO
SOLENOID VALVE. SET TO ACTIVATE
WHEN TANK EMPTIES 9" FROM THE
TOP (APPROXIMATELY 50 GALLONS)
CONNECT
PRESSURE
SWITCH TO
PUMP P-1
PUMP HOUSE WALL
PUMP HOUSE WALL
PRESSURE
RELIEF VALVE. SET TO
75 PSI.
2" X 1"
HB-1
FIL-1 FM-1
2" X 1"
2" X 1 1/4"
P-1
ET-1
2" LINE
2" LINE
1" LINE1" LINE
1" LINE
1" LINE
1/2" LINE
2" LINE
CONNECT
PRESSURE
SWITCH TO
WELL PUMP
PRESSURE TANK 40 / 60
PRE-CHARGE TO 38 PSIG
ET-2
ST-1
FLOW NARRATIVE
1. A PRESSURE SWITCH AT THE EXPANSION TANK (ET-2) CONTROLS THE WELL PUMP. THE PRESSURE SWITCH IS SET TO CUT IN AT 40 PSI AND CUT OUT AT 60 PSI.
2. WATER ENTERS THE PUMP HOUSE IN THE WEST CORNER OF THE BUILDING PASSING THE PRESSURE TANK (ET-2) AND A BRANCH LINE TO THE SUMP. THE VALVE ON THE BRANCH LINE IS
NORMALLY CLOSED.
3. WATER THEN PASSES BY A SMOOTH NOSE SAMPLE TAP AND CONTINUES TO FLOW THROUGH THE FLOWMETER AND INTO THE FILTRATION SYSTEM. THE SYSTEM CONSISTS OF A 60 MICRON FILTER WITH AUTOMATIC BACKWASH, REMOVING THE LARGER DIRT AND DEBRIS BEFORE PASSING THROUGH THE PURIFICATION SYSTEM. THE WATER THEN PASSES THROUGH PRECHLORINCATION SYSTEM AND ONTO A MULTIMEDIA FILTRATION UNIT TO FURTHER REMOVE SMALLER PARTICLES. AN ACTIVATED CARBON FILTER IS THEN USED TO ENSURE THE WATER HAS NO ODORS, DISCOLORATION OR RESIDUAL CHLORINE. LASTLY THE WATER PASSES THROUGH AN ANTI SCALANT DOSING SYSTEM IN PREPARATION FOR THE REVERSE OSMOSIS PROCESS.
4. THE REVERSE OSMOSIS SYSTEM IS CAPABLE OF TREATING 6000 GALLONS OF HIGH TDS (TOTAL DISSOLVED SOLIDS) PER DAY OR AROUND 4 GPM. AS THE WATER PASSES THROUGH, ALL IMPURITIES ARE REMOVED AND THE WATER THEN FLOWS THROUGH A CALCITE FILTER TO INCREASE THE WATER pH LEVELS BEFORE ENTERINGTHE 500 GALLON STORAGE TANK.
5. FLOW INTO THE STORAGE TANK IS CONTROLLED BY A SOLENOID VALVE THAT IS CONNECTED TO A LEVEL SWITCH INSIDE THE TANK. THE LEVEL SWITCH IS SET TO OPEN THE SOLENOID WHEN WATER LEVEL FALLS BELOW 9" FROM THE TOP OF THE TANK (ABOUT 50 GALLONS OF WATER). THIS WILL THEN CAUSE THE PRESSURE IN THE SYSTEM TO DROP, TURNING ON THE WELL PUMP.
THE WELL PUMP OPERATES AT A MAX FLOWRATE OF 8 GPM ALTHOUGH THE REVERSE OSMOSIS SYSTEM IS CAPABLE OF MAINTAINING A 4 GPM FLOWRATE. THE WATER IN THE STORAGE TANK
REMAINS CLEAN BY THE USE OF AN ULTRAVIOLET DISINFECTION SYSTEM LOCATED INSIDE.
6. WHEN WATER IS NEEDED, PUMP P-1 AND PRESSURE TANK ET-1 REGULATE THE PRESSURE AND FLOW IN THE WATER LINE TO THE CAMPGROUND. WHEN WATER IS BEING CALLED FOR, A PRESSURE SWITCH AT ET-1 SET TO CUT IN AT 40 PSI AND CUT OUT AT 55 PSI TURNS ON THE PUMP TO BRING WATER FROM THE STORAGE TANK TO THE SYSTEM.
7. THERE IS ONE LOCATION FOR WATER SAMPLING AND VARIOUS LOCATIONS FOR PRESSURE GAUGES TO VERIFY THAT THE SYSTEM IS PROPERLY PRESSURIZED.
8. THE SUMP RECEIVES THE DISCHARGE OF THE FIL-1 FILTER BACKWASH, THE WELL PUMP DISCHARGE LINE, THE PURIFICATION SYSTEM BACKWASH, THE RO SYSTEM DISCHARGE AND THE
STORAGE TANK DRAIN LINE.
NC
NC
1" LINE
MMF-1TCF-1ADS-1 PDS-1
ROS-1
CAF-1
PRESSURE
RELIEF VALVE.
SET TO 75 PSI.
SOV-1
Juan L Rodriguez
Digitally signed by Juan L Rodriguez DN: CN=Juan L Rodriguez, dnQualifier=A01410C0000017D390FBB550001FB2C, O=CIRI DEVELOPMENT CORPORATION DBA
NORTH WIND GROUP, C=US
Location: NorthWind, Knoxville TN Reason: I am approving this document
Date: 2022.11.07 09:00:05-05'00'
GENERAL NOTES:
1. SUPPORT AND INSTALL EQUIPMENT PER
MANUFACTURERS WRITTEN INSTRUCTIONS OR
OTHERWISE PER SPECIFICATION 220529
2. DIMENSIONS SHOWN ARE FOR REFERENCE ONLY
UNLESS NOTED. FIELD VERIFY DIMENSIONAL
ACCURACY.
SCALE: NTS
PUMP DETAIL1
P501
CHECK VALVE
2" X 1"
2" X 1 1/4"
PUMP (P-1)
CONCRETE ANCHORS INSTALLED
INTO THE FLOOR
VIBRATION
ISOLATION
PAD (V-1)
2" INLET
2" OUTLET
2'-11"
SCALE: NTS
CHEMICAL FEED CONTAINMENT SYSTEM2
P501
CHEMICAL FEED LINE
DOSING PUMP
AND CONTROLLER
35 GALLON
CHEMICAL
STORAGE TANK
CHEMICAL
FILL CAP
PRIMARY
CONTAINMENT
MIN 40 GAL.
SECONDARY
CONTAINMENT
MIN 53 GAL.
1'-6"
PRESSURE RELIEF VALVE
ROUTE TO SUMP AND
PROVIDE AIR GAP
PROVIDE WITH LID
AND VENTING
Juan L Rodriguez
Digitally signed by Juan L Rodriguez DN: CN=Juan L Rodriguez, dnQualifier=A01410C0000017D390FBB550001FB2C, O=CIRI DEVELOPMENT CORPORATION DBA
NORTH WIND GROUP, C=US
Location: NorthWind, Knoxville TN Reason: I am approving this document
Date: 2022.11.07 09:01:01-05'00'
EQUIPMENT SCHEDULE
TAG DESCRIPTION CONN. SIZE QTY
ADS-1 ANTI-SCALANT DOSING SYSTEM, ADJUSTABLE METERING PUMP, POLYETHYLENE SOLUTION TANK, MANUAL, 220V/1PH/60HZ. PURE AQUA MODEL CDS-36-G-15. PROVIDE WITH 5 GAL OF ANTI SCALANT. CONNECT POWER INTO REVERSE OSMOSIS CONTROL PANEL. 1/4" 1
BFP-1 DOUBLE CHECK BACKFLOW PREVENTER. 1" LEAD FREE CAST COPPER SILICON ALLOY. ASSE 1015, AWWA C510. WATTS MODEL # LF007M1QT 1" 1
CAF-1 12" FRP TANK CALCITE FILTER COMPLETE WITH MEDIA, 2510 FLECK VALVE 1" 1
ET-1 WELL X-TROL MODEL NUMBER WX-452C. 211 GALLON 30" DIAM X 91" HEIGHT. 38 PSI PRECHARGE. CUT IN 40 PSI. CUT OUT 55 PSI 2" 1
ET-2 WELL X-TROL MODEL NUMBER WX-205D. 34 GALLON 22" DIAM X 30" HEIGHT. 38 PSI PRECHARGE. CUT IN 40 PSI. CUT OUT 60 PSI 1 1/4" 1
FIL-1 RUSCO SPINDOWN SEDIMENT FILTER. PROVIDE WITH MOTORIZED STAINLESS STEEL VALVE WITH TIMER (CLEAN WATER SYSTEMS PART # V3002950). 110V
AC. DRAIN VALVE IS 1/2" OUTLET. PROVIDE 60 MICRON MESH. THREADED CONNECTION 1" 1
FM-1 DIGITAL FLOW METER, BADGERMETER E-SERIES ULTRASONIC, PROVIDE TOTALIZING AND INSTANTANEOUS FLOW MEASURMENTS, .4 TO 55 GPM, 20 YEAR
NON REPLACEABLE BATTERY 1" 1
HB-1 HOSE BIB, LEGEND VALVE AND FITTING MODEL # R-671NL. PROVIDE WITH VACUUM BREAKER MODEL # T-553NL 3/4" 1
MMF-1 8" FRP TANK MULTIMEDIA FILTER COMPLETE WITH MEDIA, 5812 FLECK VALVE, 1" PIPE SIZE, 220V/1PH/60HZ. PUREAQUA MODEL 56F8075MM. 3/4" / 1" 1
PDS-1 PRECHLORINATION DOSING SYSTEM, ADJUSTABLE METERING PUMP, POLYETHYLENE SOLUTION TANK, MANUAL, 220V/1PH/60HZ. PUREAQUA MODEL
CDS-36-G-15. CONNECT POWER INTO THE REVERSE OSMOSIS CONTROL PANEL 1/4" 1
ROS-1 REVERSE OSMOSIS SYSTEM TO PRODUCE 6000 GPD AT MAXIMUM 5000 PPM FEED WATER TDS, 220V/1PH/60HZ. PURE AQUA MODEL BW-6.0K-440 1" 1
ST-1 SMOOTH NOSE SAMPLE TAP. LEGEND VALVE AND FITTING MODEL # R-671NL. 1/2" MODEL HAS A NON THREADED SWEAT OUTLET 1/2" 1
SOV-1 SOLENOID VALVE. 2 WAY 2 POSITION NORMALLY CLOSED. 120V 15VA POWER. NSF RATED, SLOW CLOSE OPERATION. 1" FNPT CONNECTION. AUTOMATION DIRECT P/N 21WN6K1E250-10T5-A. PROVIDE WITH FLOAT SWITCH, MANUFACTURER: SJE-RHOMBUS P/N SJE PUMPMASTER WPS 1" 1
TCF-1 10" FRP TANK CARBON FILTER COMPLETE WITH MEDIA, 5812 FLECK VALVE, 1" PIPE SIZE, 220V/1PH/60HZ. 3/4" / 1" 1
UV-1 TANK MASTER UV LIGHT. 120 V / .115 kW. MODEL TMH064 25-8564A6 OR SIMILAR. 62.6875" INSERTION DEPTH 1" 1
V-1 MASON INDUSTRIES VIBRATION ISOLATION PAD. MODEL BBNR -- 1
NOTES
1. ALTERNATIVE EQUAL FIXTURES MAY BE SUBMITTED FOR CONSIDERATION DURING CONSTRUCTION SUBMITTAL PROCESS. ALTERNATIVE FIXTURES WILL REQUIRE CONSTRUCTION MANAGER AND SUBMITTAL
APPROVAL PRIOR TO BEING PROCURED.
2. MANUFACTURER'S SERIES SHOWN INDICATE BASIC FIXTURE TYPES REQUIRED FOR THIS PROJECT. VERIFY WITH MANUFACTURER TO INCLUDE ALL ACCESSORIES REQUIRED FOR ACTUAL INSTALLATION.
3. PROVIDE SUFFICIENT UV INSTALLED AS PER MANUFACTURER TO REACH ALL SECTIONS OF THE TANK AND TREAT 100% OF THE WATER.
PUMP SCHEDULE
TAG MANUFACTURER MODEL DESCRIPTION MECHANICAL SEAL ELECTRICAL MOTOR IMPELLER SUCTION DISCHARGE QTY
P-1 BELL AND GOSSETT E-3530 SERIES #
AM1 1 G 1 B 2 END SUCTION PUMP
ROTARY: CARBON.
STATIONARY:SILICON CARBIDE.
ELASTOMER: EPR. METAL PARTS: 316L
115 V, 1 PH, 60 Hz 2 HP ODP 5-3/4" 1-1/4" NPT 1" NPT 1
Juan L Rodriguez
Digitally signed by Juan L Rodriguez DN: CN=Juan L Rodriguez, dnQualifier=A01410C0000017D390FBB550001FB2C, O=CIRI DEVELOPMENT CORPORATION DBA
NORTH WIND GROUP, C=US
Location: NorthWind, Knoxville TN Reason: I am approving this document
Date: 2022.11.07 09:02:13-05'00'
File details come from the government source that posted it. Updated .