This is Addendum No. 2 issued by the Michigan Department of Natural Resources (DNR) Marketing and Outreach Division for the Rose Lake Shooting Range Warehouse Metal Roof Replacement project (Bid Number RFP 210000000752). The bid opening date is set for Wednesday, February 10, 2021, at 12:00 Noon EST, and this addendum was issued on Thursday, February 4, 2021.

The addendum approves two additional equal materials for the project: the Firestone UnaClad UC-14 system product line and the Medallion-Lok Panel system manufactured by McElroy Metal, Inc. of Shreveport, LA. Bidders must acknowledge this addendum by signing and returning a scanned copy along with their bid submission.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of Natural Resources

DNR Marketing and Outreach Division

Rose Lake Shooting Range Warehouse Metal Roof Replacement

Bid Number: RFP 210000000752 - ADDENDUM No. 2

BID OPENING DATE: WEDNESDAY, FEBRUARY 10, 2021 at 12:00 Noon, EST

DATE BID ADDENDUM #2 ISSUED: Thursday, February 4, 2021

TO: ALL BIDDERS

SUBJECT: This Addendum No. 2 is issued to approve additional equal materials.

Item #1: The Firestone UnaClad UC-14 system product line is an approved equal material.

Item #2: The Medallion-Lok Panel system as manufactured by McElroy Metal, Inc. of Shreveport, LA is an approval equal material for this project.

Acknowledgment: A signed and scanned copy of this Addendum No. 2 shall be returned along with the bidder’s signed bid.

_________________________________Patrick Avendt, Buyer
(Firm Name)DNR Procurement Section
(517) 388-6265
avendtp@michigan.gov

(Bidder's Signature and Title)

(Date)

DNR Rose Lake Shooting Range Warehouse Metal Roof Replacement, Addendum #2 Page 1 of 1 image1.wmf

File details come from the government source that posted it. Updated .