Agency Minimum Technical Requirements

View the file

Other files

File Type Posted
Updated_NCATS_RLP_R100_Draft.pdf PDF
NIH_Agency_Minimum_Technical_Requirements_Updated.pdf PDF
Global_Lease_L100.pdf PDF
Global_Lease_L100_10_2016.docx DOCX document
GSA_Form_3517B.pdf PDF
2018-0530_NIH_NCATS_POR_BOOK_FINAL.pdf PDF
GSA_Form_1364.pdf PDF
GSA_Form_1217.pdf PDF
GSA_Form_12000.pdf PDF
GSA_Form_3516.pdf PDF
NCATS_RLP_1.25.2019.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NATIONAL INSTITUTES OF HEALTH

AGENCY MINIMUM TECHNICAL REQUIREMENTS

The following Agency Minimum Technical Requirements (AMTR) are an integral part of the Request for Lease Proposal (RLP) and the Lease and, unless otherwise provided herein, are to be provided by the Lessor at its sole cost and expense. In the event of a conflict between the RLP, the Lease, and the AMTR, the more stringent requirements shall govern.

1. Program of Requirements (POR): The attached POR dated 05/30/2018 is to be considered integral to this RLP and Lease. The offered space shall allow for all the requirements of the POR to be satisfied. The POR contains information necessary to respond to Paragraph 2.01(B) of the RLP. The POR lists the various space requirements and associated infrastructure and building systems requirements. In the case of any conflicts between the Lease and the POR, the more stringent requirements will prevail. As set forth in detail in the POR, and without limitation thereof, the offered building must meet the following base building conditions at the Lessor's sole cost and expense:

• A minimum of 17,000 ABOA SF of offered space capable of accommodating the NCATS Laboratory, Laboratory Support, Office and Office Support, and Building Support space requirements as set forth in the attached POR.

• Space must be able to accommodate BSL-2 Laboratory. Building space previously used for office space shall not be used for BSL-2 laboratory space

Except as otherwise specifically stated herein or elsewhere in the Lease and its attachments, to the extent that the POR requires building shell elements that are more costly than the building shell elements described in the Lease, the resulting increase in the cost of providing such building shell elements shall be paid for by the Government.

2. Laboratory corridor widths shall be a minimum of 6’-0” with a minimum ceiling height of

9’-0”.

• Water lines, drainpipes, reheat coils, valves, electric service connections, and other utilities servicing labs shall be accessible above corridors outside the lab space.

• Fire alarms, fire extinguishers, and telephones shall be recessed, installed high enough, or shielded by protective guards to prevent damage from the movement of large equipment or carts.

• No unused equipment or consumable materials shall be planned for storage in the corridors. The corridor corners should be rounded. Wall and corners should have physical protection with guardrails as required in the NIH DRM.

3. Roof Rights: As part of the rental consideration, the Government shall have unrestricted roof rights and must be able to accommodate security and communications equipment on the roof.

Installation of such equipment shall be coordinated with Lessor and installed in a manner that does not invalidate the terms of any of Lessor’s roof warranties. Any antennas or satellite dishes shall not adversely affect the structural integrity of the building and shall be installed in a manner so as to minimize any adverse aesthetic concerns. In the event the roof shall require maintenance, repair, or replacement, the Lessor will advise the Government prior to roof repairs.

In no event shall the Lessor be responsible for personal property of the Government placed on the roof top pursuant to this Paragraph.

4. Access to Data: Upon request by the Government, the Lessor shall, at its sole cost and expense, provide the Government with reasonable access to data that the Government may be required to collect and report under applicable statutes, regulations, and executive orders relating to the environment, sustainability, and energy efficiency, including but not limited to data regarding energy and water usage and solid waste and hazardous material generation and disposal.

5. Option Regarding Utilities: The Government reserves the right to become directly responsible for the costs of one or more utilities which are listed in Section I of the Offeror’s GSA Form 1217, which right may be exercised by the Government at any time after lease award but prior to lease commencement. To the extent the Government chooses to become directly responsible for one or more utilities, such cost as shown on the Form 1217 shall be removed from the operating costs base and there shall be a corresponding downward adjustment in the rental rate.

6. Option Regarding Operating Services: The Government reserves the right to become directly responsible for one or more of the operating costs which are listed in Section I of the Offeror’s GSA Form 1217 (the “Optional Operating Costs”), which right may be exercised by the Government at any time, and from time to time, upon not less than ninety (90) days’ notice to Lessor. To the extent the Government chooses to become directly responsible for an Optional Operating Cost, such cost shall be removed from the operating costs base and there shall be a corresponding downward adjustment in the rental rate. The basis for negotiating the adjustment to the rent and operating costs base shall be the greater of (i) the amount shown for such cost on the Form 1217, including a proportionate share of any accrued annual operating costs adjustments, or (ii) actual historical operating costs information for the prior 12 months, all of which the Lessor shall provide to the Government. Any adjustment pursuant to this clause shall take effect on the first day of the first full month of the Government’s direct payment of any such Optional Operating Cost. If the Government has elected to become directly responsible for a particular Optional Operating Cost and wishes to initiate any contest or challenge with the applicable utility or service provider, the Lessor agrees to cooperate with the Government in any such contest or challenge. In addition, the Lessor shall provide the Government, at no additional charge, with all training manuals, instruction, orientation, and transition services necessary to ensure continuity of services during any such transition of direct responsibility to the Government.

Provided that the Lessor has cooperated as required above in performing transition services, and provided that the Lessor has disclosed all known aspects of the equipment’s prior maintenance, performance and condition, including replacement schedules, the Government shall assume the responsibility for the repair and replacement of any equipment which is damaged as a result of the Government’s failure to properly operate or maintain such equipment. However, the Lessor shall retain responsibility for regularly scheduled capital repairs and replacements which would have been required due to normal use and considering normal equipment life.

7. Preventive Maintenance for Government-Owned Equipment: Upon request of the

Government and at the Government’s cost, the Lessor shall provide preventive maintenance services on all Government-owned equipment, including but not limited to supplemental HVAC units, UPS units, and backup power generators, serving the leased space as an additional cost billed directly to and paid by the Government outside of the annual rent and the operating cost base. This preventive maintenance service will include inspection, cleaning, filter replacement, any other manufacturer-recommended preventive maintenance, and such other maintenance as the Government may specify from time to time. Repairs, parts, major component replacement or any full unit replacement not covered by the preventive maintenance service agreements will be charged to the Government in addition to the above preventive maintenance services. The allowable cost of the preventive maintenance and any other repairs, parts or replacements covered by this paragraph shall be determined in the same manner as pricing for tenant improvements is determined under Lease Clause 4.04 and shall not include any Lessor markup.

Notwithstanding the foregoing, the Government’s obligation to pay for such work shall be subject to availability of funding. Accordingly, the Lessor shall not proceed with any such work until it has requested and obtained from the Government evidence that funding is available for the applicable fiscal year or other relevant period.

8. Electricity for LAN Rooms and Data Rooms: Electricity for LAN Rooms and Data Rooms shall be separately metered or sub-metered at Lessor’s sole expense. The electrical consumption for such rooms will be paid by the Lessor and invoiced separately to the Government without additional markups or Lessor fees. The Lessor invoice will include backup documentation to include paid utility invoice, separate meter reading, and consumption cost based on the utility market rate. The Government will reimburse electrical usage cost per the Prompt Payment Act.

9. CIT: Dedicated telecom rooms (TR) sized 10ft x 15ft shall be provided for every 10,000 SF of occupied space. TR spaces shall be sized to accommodate both current and future requirements. Emergency power will feed rack mounted UPS network switches. Provide a grounding bar attached to the main building ground in each telecom room. The telecom grounding bar will ground all telecom equipment in the closet. All telecom rooms will require card reader access. Telecom rooms shall be stacked to the extent possible and shall not be located below rooms with wet plumbing. Telecom rooms will be adequately cooled by HVAC. Sprinkler heads in data closets shall have guards and shall not be located directly above the telecom equipment. No audio/visual devices shall be installed in any telecom room. Utilities that are not associated with the telecom equipment shall not be routed through telecom rooms. All wall shall extend slab to slab and provided with a 1 hour fi re rating. Provide a minimum of 36" of clearance on the front and back of all equipment on racks and fi re rated plywood. Grounding and bonding for the electrical room shall meet requirements of NEC and BiSCI. Provide a minimum of 4-4" conduits between vertically stacked TRs. Basket type cable tray for TEL/LAN shall be run above the ceiling along the main hallway perimeter back to the telecom room. Provide a minimum 6” clearance on all sides of the cable tray to allow for access to cables. From the cable tray, cables shall be run in conduit to final device locations. Th e farthest cable run shall be 250ft measured along the cable tray route or 230ft for systems furniture. Wireless access points shall be located throughout the space to provide full wireless coverage.