Fence Questions.docx

DOCX document 16 KB Posted

Attached to
Fencing Federal contract opportunity
Solicitation number
DJBP05191200018
Issued by
Department of Justice Bureau of Prisons Federal Correctional Complex Pollock

About this file

Conf. Questions

View the file

Other files for this federal contract opportunity

Other files attached to Fencing, newest first.
File Type Posted
Fence Conf.pdf PDF
RFQP05191200018 Wage Rates.PDF PDF
RFQP05191200018 SOW.PDF PDF
RFQP05191200018.PDF PDF
Cover Letter.PDF PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FCC Pollock Pre-Bid Conference Questions Solicitation RFQP05191200018 – Fencing

1. Do sliding gates need to be constructed as depicted in the drawing (drawings A-2, A-3, A-4)?

Answer: No. They need to comply with specifications as outlined in section 2.4 CHAIN LINK GATES of the FBOP TECHNICAL DESIGN GUIDELINES, page 02820-4 to 02820-5.

2. Can aluminum tie wire be used?

Answer: No. As stated in section 2.5 MISCELLANEOUS MATERIALS (A), tie wires shall be produced from a 9 gauge steel cores wire with aluminum coating…. Aluminum wire shall not be used.

3. Is the contractor responsible for locating utility lines?

Answer: Yes. As stated in Statement of Work, Part 3 – INSTALLATION.

4. Drawing part c/A-4 of A-4 depicts (gate assembly) 3” steel pipe for frame support and 2 ½” steel pipe for vertical and horizontal brace support. Are those pipe sizes required?

Answer: After further review of the guidelines, a smaller dimension pipe shall be used. A 2 3/8” pipe shall be used for frame support and 1 7/8” shall be used for vertical and horizontal brace support.

5. Drawings call for a 2” Schedule 40 Intermediate Rail (typ. Throughout Top and Bottom Rail). Is that required? (Reference A-3, B/A-1 and A-2 A/A-1) Answer: After further review of the guidelines, a small dimension pipe shall be used. A 1 5/8” Schedule 40 Intermediate (Horizontal) Rail shall be used.

At this time, no other technical requirements have changed. Due to the changes made, solicitation due date has been extended until July 10, 2012, no later than 3:00 p.m.