This file is a site analysis document related to the County of Solano's Request for Information (RFI) regarding affordable housing development on the former Dixon Corporation Yard property located at 580 North First Street in Dixon, California. The County seeks qualified developers and development teams to provide market feedback on the feasibility and interest in developing affordable housing, potentially including complementary mixed-use elements on the County-owned site. The RFI is intended for market research and planning purposes, and responses should not exceed 15 pages, excluding optional supporting materials. The County has not established a timeline for responses or subsequent solicitations; rather, the information gathered will be evaluated by the Solano County Board of Supervisors to inform decisions regarding the site's development approach, the type and scale of feasible affordable housing, developer interest levels, financing strategies, and the County's potential participation and site control requirements.
The RFI process carries no obligation for the County to proceed with a formal solicitation, dispose of the property, commit funding, or award any contract, lease, or agreement. Participation in this RFI does not confer competitive advantages in any subsequent solicitation process. Respondents are not required to provide formal development proposals, designs, or pricing commitments; rather, they should focus on demonstrating relevant experience and capability to develop affordable housing projects. Responses will be used by the County for planning purposes and are subject to California public records requirements. No pricing terms, set-asides, or specific funding sources are identified in this RFI stage, as the process is exploratory and designed to inform the County's future solicitation strategy.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OCTOBER 2025
PRESENTED BY:
THURMOND CONSULTING, LLC.
PREPARED FOR:
SOLANO COUNTY
DIXON CORPORATION YARD
SITE ANALYSIS REPORT
Executive Summary
Background and Project Context
Site Utilities and Infrastructure
Regulatory Framework and Approvals
Site Mobility and Accessibility
Physical Site Conditions
Site Expansion Opportunity
02 03
05 06
TABLE OF
CONTENTS
Market Conditions and Demand
Building Types and Construction Methods
Project Costs and Financing
Development Challenges and Risk Factors
Recommendations and Next Steps
10 11 12
Conclusion
2121 Natomas Crossing Drive Sacramento, CA 95834
Dixon Corporation Yard Redevelopment Analysis
Executive Summary
The County's 1.3-acre Corporation Yard site (“CorpYard”) in Dixon presents an opportunity to address critical housing needs while potentially incorporating community-serving commercial uses. The site is flat, environmentally suitable, has good utility access, sits in a walkable location near downtown Dixon, and offers excellent highway connectivity. The parcel contains no major environmental hazards, sits above flood elevations, and has adequate subsurface soil conditions for conventional foundations.
The site can accommodate up to 24 residential units, most likely as two or three-story walkup apartments or rowhouses, with the option to include a small commercial component (up to 2,000 square feet). The location works particularly well for farmworker housing, given the County's agricultural economy and demonstrated need for affordable housing near employment centers.
The site analysis seeks to assess the site’s physical and environmental conditions, determine its regulatory parameters, mobility and access capabilities, financial and market feasibility, and potential for meeting social needs in the County, building types, and costs.
The primary challenge is securing adequate funding for design, construction, and long-term operations. Current construction costs, prevailing wage requirements for publicly funded projects, and volatile material prices compound the funding challenge. However, the relatively small scale may improve competitiveness for state farmworker housing programs and other targeted funding sources.
Background and Project Context
The CorpYard site, located on 580 North First Street, currently houses County General Services staff with one primary structure for office and storage. The site sits on State Road 113 between Dixon's downtown commercial area to the south and industrial areas near the I-80 interchange to the north.
In May 2024, PlaceWorks drafted a preliminary financial feasibility assessment for affordable housing. Town Green produced two conceptual plans for modular workforce housing. Thurmond Consulting submitted a comprehensive proposal in June 2024, leading to the current analysis managed through First Carbon Solutions. The project gained momentum when California's Agricultural Secretary toured farmworker housing with on-site childcare, prompting deeper consideration for agricultural worker housing.
While affordable housing remains the primary focus based on County staff recommendations and Board direction, this analysis also explores non-residential uses and market feasibility to provide the Board with comprehensive information before making final decisions.
Physical Site Conditions
The 1.3-acre property is rectangular and relatively flat with less than three percent slope. The site has been previously graded for industrial and commercial uses. The topographical survey describes the slopes and the attached Site Mapping Data1. A 0.17-acre out parcel on the east side, owned by the Solano Mosquito Abatement District, is currently leased to a commercial tenant until 2026.
Recent environmental investigations by First Carbon Solutions identified soil conditions through boring logs from Cameron Cole LLC 2. The preliminary subsurface investigations suggest adequate soil composition and compaction for building foundations in Seismic Zone 33. The site shows no evidence of a high water table or perimeter water intrusion issues. FEMA Flood Insurance Maps indicate the site lies within an area of minimal flood hazard, eliminating the need for flood-related design modifications. A National Flood Hazard Layer FIRMette map describes the flood areas in spatial relation to the site4. Earthquake Fault Special Study Zone maps show no active faults crossing the property.
The site benefits from mature trees along its perimeter, particularly along North First Street, providing natural shade and buffering from traffic noise. Proximity to Union Pacific railroad tracks means frequent train service and associated noise, requiring interior building sound attenuation measures, including upgraded windows and insulation.
Summary:
● Flat topography with suitable soil conditions and no major obstacles
● Located above flood zones with no unusual seismic risks
● Mature trees provide natural buffering and should be preserved
● The main site-specific issue is railroad and traffic noise mitigation
● Standard geotechnical and engineering studies are required before design
4 National Flood Hazard Map
3 Preliminary Site Subsurface Conditions
2 Soil Boring Logs
1 Site Area Maps attached https://drive.google.com/file/d/1K-8GyLlJ2NCHVISVTSdnl0ZW76HGLAcq/view?usp=drive_link https://drive.google.com/file/d/1lExY0-F6dBWe5NP--sTUIdsl3nEGd79z/view?usp=drive_link https://drive.google.com/file/d/1lExY0-F6dBWe5NP--sTUIdsl3nEGd79z/view?usp=drive_link https://drive.google.com/file/d/1k0TLhDOHDK1GGLQMekyCCGzPELEjWt0P/view?usp=drive_link https://drive.google.com/file/d/1BbI4U3LpvxjArH83hginKjcRfhwedZF-/view?usp=drive_link
Site Utilities5 and Infrastructure
Water Supply: The City of Dixon owns and operates the municipal water system, delivering approximately one million gallons daily for residential, fire suppression, and industrial uses. The site requires water for habitation and fire protection. Modern fire codes require fire sprinkler systems in multifamily buildings over two stories. Engineering analysis based on the building program will determine the adequacy of existing water infrastructure, though surrounding parcels suggest capacity will be adequate with possible minor on-site improvements.
Sanitary Sewer: The City owns and operates the municipal sewer collection system and Wastewater Treatment Facility. The site can connect via a sewer lateral to the six-inch line on East F Street (most cost-effective) or through the ten-inch main in North First Street (requires opening a busy street). Sewer capacity is rarely a limiting factor for small residential developments. The attached Utility Maps include the sanitary sewer diagrams from the City of Dixon.6
Storm Drainage: A stormwater inlet near the northwest corner connects to the city's stormwater infrastructure. Increasing on-site permeability through green areas, landscaped courtyards, permeable paving, and bioswales can significantly reduce stormwater volumes. Modern developments often include on-site detention or retention to manage peak flows.
Electrical Power: PG&E provides service via underground and overhead lines along East F Street. California's building code requires photovoltaic solar systems for new residential construction, which must be sized to meet the project's estimated annual electricity usage. Solar panels will substantially decrease utility costs for future tenants—a significant quality of life benefit for families on tight budgets. The attached map shows PG&E underground service in Solano County.7
Communications: Multiple providers (AT&T, Astound, Earthlink) serve the area with fiber internet service. Business class internet ranges from approximately $650 per month for 100 megabits per second to $1,400 per month for 500 megabits per second.
Summary:
● All essential utilities are available through the existing infrastructure
● Engineering studies must confirm capacity, but the preliminary assessment is positive
● Solar panels required per state code, adds upfront cost but creates long-term savings
● No major infrastructure gaps identified
7 PG&E Solano Underground Service Map 6 Site Utilities Maps
5 Site Utilities Detailed https://drive.google.com/file/d/13tj3lRn0gfYIcy2FInHDs-RTCCA2723K/view?usp=drive_link https://drive.google.com/file/d/1lbebNQmbtsJYX5ynpNmpvvQv9pzPlitj/view?usp=drive_link https://drive.google.com/file/d/1QQ3d3ip9A6T7XmRTyq8hcTbH_ZigMSak/view?usp=drive_link https://drive.google.com/file/d/1QQ3d3ip9A6T7XmRTyq8hcTbH_ZigMSak/view?usp=drive_link
Site Mobility and Accessibility
Mobility and accessibility8 describe the ability of individuals to move freely and easily within their environment, in this case the site, particularly in relation to transportation options. The CorpYard's location on North First Street (State Road 113) provides exceptional regional connectivity. SR 113 connects Dixon to I-80 approximately one mile north, providing direct highway access to Sacramento, the East Bay, Napa, and the Central Valley. Within Dixon, the site sits at the edge of downtown, with main retail and service businesses roughly one quarter mile south.
The Walk Score methodology rates the Corp Yard site a 75 or "Very Walkable", meaning most errands can be accomplished on foot9. The site’s proximity to Downtown, with shaded sidewalks and lower travel speeds along North First St., provides an incentive for the eventual occupants and visitors to walk and bike to neighboring stores and amenities. The 2008 Safe Routes to School program includes a safe rail crossing, improving access to Anderson Elementary School and nearby residential neighborhoods.
Public transit availability near the site remains limited. No fixed route bus service operates along North First Street within one mile. Dixon operates Dixon Readi-Ride, a dial-a-ride transit system providing curb-to-curb service within city limits. Limited transit service means most residents will need vehicle access for commuting to work, particularly agricultural workers whose job sites are spread across the county.
Roughly 13,000 motor vehicles use North First Street daily. The site has two current access points: one along North First Street and one along East F Street. If the County acquires the Mosquito Abatement parcel, a third access point becomes possible. On-street parking along East F Street could provide up to twelve standard spaces on the north side of the site, with additional spaces on the opposite (north) side of East F Street, with signage and permission.
Summary:
● Excellent highway access and walkability to downtown services
● Limited public transit—most residents will need vehicles for work
● Plan for twelve parking spaces with the possibility of additional parking
● Location in a walkable community incentivizes active transportation
9 Site Walk Score 8 Site Mobility and Access Detailed https://drive.google.com/file/d/1ri31ALYVC6Pdd1pVeSHKQAX-LQ6M6etQ/view?usp=drive_link https://drive.google.com/file/d/192YST016elg4D1kDe7Ai5Yd3kDrSC2J4/view?usp=drive_link https://drive.google.com/file/d/192YST016elg4D1kDe7Ai5Yd3kDrSC2J4/view?usp=drive_link
Site Expansion Opportunity
The 0.17-acre parcel at the northeast corner, currently owned by the Solano Mosquito Abatement District10, operates under a commercial lease11 through 2026. Acquiring it would create a full rectangular development parcel with better circulation and more efficient building layouts. Adding this parcel could allow additional housing units and improve internal site circulation. The District's board may consider selling at fair market value when the lease expires, though they may choose to renew the lease. The County has indicated it currently has no plans to purchase this parcel. However, the parcel isn't essential for project success. The 1.3-acre site alone provides sufficient area for a viable development.
Summary:
● The adjacent parcel could add additional units if available in 2026
● Not necessary for long-term project success
● Proceed with existing site; revisit expansion when lease expires
Regulatory Framework and Approvals
The County-owned site12 will require planning approval and building permits through the County's Resource Management Department. The County maintains land use jurisdiction13 despite the site's location within the Dixon city limits. The Corp Yard site in the City of Dixon, lies outside the County’s 2008 General Plan boundary14, as shown on the County’s updated map.
The City of Dixon’s General Plan updated in 2021, contains three relevant land use references and maps, attached in the addendum. Current zoning allows ten dwelling units per acre (up to 13 units on 1.3 acres). However, the County can approve higher densities through its discretionary approval process. For affordable or farmworker housing, state density bonus laws may allow additional units beyond base zoning, plus concessions like reduced parking or setback requirements.
Once the Board approves a direction, the County will issue a Request for Qualifications (“RFQ”) for an architect and engineer team to develop architectural and construction phasing plans. The approval process will likely include CEQA environmental review, though the project may qualify for streamlining under recent housing legislation. Once construction documents are complete and funding secured, the County will issue a separate RFP to contractors. Building and zoning approvals should be relatively straightforward given the flat topography, project type, and lack of environmental constraints.
14 Solano General Plan 13 Jurisdiction Context Data 12 Dixon RCD Map 11 SMAD Site Aerial 10 Site Expansion Detailed https://drive.google.com/file/d/1kbOrpHU8vgHzT5rAsuG0l8D_wUvIYStD/view?usp=drive_link https://drive.google.com/file/d/1kbOrpHU8vgHzT5rAsuG0l8D_wUvIYStD/view?usp=drive_link https://drive.google.com/file/d/1T1wkyE1tPwre_AWJDVapApjwwEjcQVnN/view?usp=drive_link https://drive.google.com/file/d/1BbI4U3LpvxjArH83hginKjcRfhwedZF-/view?usp=drive_link https://drive.google.com/file/d/1J4EVvWt_TOmG-m0Ft4qsm4om0jZ4zL7v/view?usp=drive_link https://drive.google.com/file/d/1Vz2iIdBdXarbnc46_aRbqY_o1wX_XHT1/view?usp=drive_link
Summary:
● County controls the entire approval process; no City approvals required
● Current zoning allows 10+ units per acre; the County can approve a higher density
● Budget 6 to 9 months for design and approvals, 12 to 13 months for construction
● The density bonus law may allow additional units for affordable housing
Market Conditions and Demand
Residential Market15: Despite California's overall housing deficit, Dixon's current housing market shows relatively modest demand. According to CoStar, only one new apartment development has been completed in Dixon since 2020. Vacaville and Davis have successfully built three-story multifamily walkups—a building type offering optimal balance between construction cost efficiency and land utilization.
Demographics and Housing Needs: Solano County's 2023 median household income is $99,994, with a median property value of $589,600 and a homeownership rate of 63.2%.
Approximately 20.7% of the population experiences severe housing problems. Many agricultural workers earn below 80% of the area's median income. A family earning $60,000 (60% AMI) could afford monthly housing costs under $1,500, but market-rate apartments typically rent for $1,800 to $2,500 per month. This income rent gap creates the fundamental need for subsidized affordable housing.
Commercial Potential: The site's corner location provides excellent visibility for retail or food service businesses. However, Dixon's commercial market isn't robust enough to support standalone commercial development. Any commercial use makes most sense as part of a mixed-use project. Options include a small café, farmer’s market, ghost kitchens, daycare/preschool, or business incubator space. Uses should visibly activate the site, provide clear community benefit, leverage Dixon's agricultural strengths, and have viable long-term operations.
Summary:
● Clear need for affordable housing for agricultural workers earning below 80% median income
● Site works best as primarily residential (up to 24 units)
● Commercial uses should be small-scale (2,000 SF or less) and community-serving
● Consider a café, a farmer’s market, or childcare rather than standard retail
15 Residential Market Data https://drive.google.com/file/d/1CYWgh46Fb53oi6Pr8q75c5EGMstqNM--/view?usp=drive_link
Building Types16 and Construction Methods
Wood Frame Construction: Type V Construction represents the most cost-effective building system for residential development. Type VB (fire-protected wood frames) accommodates multifamily buildings up to three stories with fire sprinklers. Wood frame provides excellent earthquake resistance due to wood's ductile nature, is familiar to local contractors, and accommodates modifications easily.
Modular and Prefabricated Construction: Factory-manufactured housing, fully modular or panelized, offers significant cost and schedule advantages. Modular construction can reduce costs by 30 to 50% compared to stick-built methods through factory efficiency, reduced weather delays, compressed schedules (6 to 9 months versus 12 to 15 months), and lower labor costs where prevailing wage applies only to on-site work. The tradeoff is less design flexibility, which aligns well with affordable housing, where simple, efficient designs reduce both construction and operating costs.
Commercial Buildings: For commercial components, Insulated Metal Panels (IMPs) work well for building envelopes. Pre-engineered steel buildings offer another option, installing quickly with large column-free interior spaces. A simple farm stand structure could cost as little as $125 per square foot.
Site Design: The site layout should include meaningful open space—a green commons or landscaped plaza providing shade and creating an inviting environment. Preserving mature perimeter trees buffers activities from North First Street. 17 For multifamily residential, common open space serves important social functions—children's play areas, picnic spaces, community gardens, or gathering spots.
Summary:
● Three-story walkup apartments offer the best balance of density and cost
● Modular construction can reduce costs by 30 to 50% and accelerate the schedule
● Particularly valuable for projects with prevailing wage requirements
● Include meaningful green space and preserve existing mature trees
Development Program and Capacity18
The 1.3-acre site can accommodate approximately 20,000 square feet of building area, possibly including up to 2,000 square feet of commercial or community space.
18 Building Uses Detailed 17 Corp Yard House Plan 16 Building Types and Systems Detailed https://drive.google.com/file/d/13k1VYV_cKwfHun8O7XYula42PBinrUpH/view?usp=drive_link https://drive.google.com/file/d/1VGzs5pg9LUkZDdkeedw1WBEWYgXprSxG/view?usp=drive_link https://drive.google.com/file/d/1VGzs5pg9LUkZDdkeedw1WBEWYgXprSxG/view?usp=drive_link https://drive.google.com/file/d/1VGzs5pg9LUkZDdkeedw1WBEWYgXprSxG/view?usp=drive_link https://drive.google.com/file/d/1ZHk3TiywG6OlkaCyxUWhz2hdsbgq9zLq/view?usp=drive_link
Residential Options: Two or three-story walkup apartments with 12 to 20 units (maximizes density and cost effectiveness). Townhomes or rowhouses with 8 to 12 units (more privacy and family-friendly). Duplex or fourplex buildings with 6 to 10 units (smaller building scales, neighborhood feel). For farmworker housing, unit sizes should emphasize two-bedroom (750 to 850 SF) and three-bedroom (950 to 1,200 SF) units to reflect larger household sizes. Kitchen and bathroom design should reflect cultural preferences with larger kitchens, durable finishes, and adequate storage.
Mixed Use Development: If pursuing mixed use, limit commercial to approximately 2,000 square feet. This could accommodate a small café (800 to 1,200 SF), childcare facility (1,500 to 2,000 SF), or commercial kitchen (1,000 to 1,500 SF). Locate commercial space at the northwest corner (North First Street and East F Street intersection) for maximum visibility.
Summary:
● Site accommodates 15 to 25 residential units, depending on configuration
● Three-story walkups yield the highest density (18 to 25 units)
● If including commercial space, limit to 2,000 SF at North First/East F corner
● Parking consumes a significant area—plan for 30 to 40 spaces
Project Costs and Financing19
Site Improvements: Estimate $500,000 to $750,000 for demolition, grading, utility connections, paving, landscaping, and site lighting. Required utility upgrades could add $100,000 to $300,000.
Building Construction: Three-story walk-up apartments cost $350 to $450 per square foot stick-built, or $245 to $315 modular (30 to 50% savings). For a 15,000 square foot building (18 to 20 units): stick built $6.25M to $8.75M, modular $5.2M to $6M.
Indirect Costs: Typically 25 to 35% of total project costs, including architecture/engineering (8 to 12% of construction costs), permits and impact fees ($15,000 to $30,000 per unit), environmental review ($50,000 to $100,000), legal/administrative ($75,000 to $150,000), developer overhead (8 to 15%), construction financing (3 to 5%), and contingency (10 to 15%).
Total Project Cost: For a 24-unit multifamily project: modular construction, approximately $8M ($333,000 per unit), stick-built, approximately $10.2M ($425,000 per unit). Adding 2,000 SF commercial space adds $500,000 to $750,000.
Financing Sources: State programs include Joe Serna Jr. Farmworker Housing Grant Program, Multifamily Housing Program, PLHA, CDBG, and the Multifamily Finance Super
19 Estimated Construction Cost Detailed https://drive.google.com/file/d/1ir1bcwCq6RrftsFGqPStYfo2PbA2tZyr/view?usp=drive_link
NOFA. Federal programs include USDA Rural Development Section 514/516 Farm Labor Housing loans and grants. County resources could provide gap financing. County land value represents significant equity.
Operating Costs: It’s worth considering what level of local operational support exists within the County of Solano. The project could use additional sources of income, including but not limited to CalAIM, VASH vouchers, Section 8 vouchers, or Project-Based Vouchers. Any structural deficit requires either a long-term operating subsidy, some market-rate units to subsidize affordable units, a financially strong entity to absorb deficits, or rents set higher than truly affordable levels.
Summary:
● Total costs range from $8M (modular) to $10.2M (stick built) for 24 units
● Modular construction offers substantial savings, critical for feasibility
● Funding requires layering multiple sources—state, federal, and County resources
● Plan for ongoing operating subsidies or financially strong ownership
● Start funding conversation immediately, it's the critical path
Development Challenges and Risk Factors
Funding and Financing: Securing adequate funding represents the single largest challenge.
Affordable housing development typically requires 3 to 5 funding applications over 12 to 24 months. Funding programs operate on annual cycles with intense competition. Some programs require experienced affordable housing developers as applicants, so the County may need to partner with a qualified developer organization. Thurmond Consulting can provide its development experience toward the project as needed.
Construction Cost Volatility: Materials prices have fluctuated 20 to 40%, with labor shortages and supply chain disruptions. Projects taking 2 to 3 years from concept to construction may face costs 15 to 25% higher than initial estimates. Risk reduction strategies include securing firm contractor pricing before finalizing financing, using modular construction to lock in factory prices, maintaining robust contingencies (10 to 15%), and moving quickly through design and permitting.
Prevailing Wage Requirements: Most state and federal affordable housing funding requires prevailing wage compliance, paying workers state-determined hourly rates typically 20 to 30% above standard wages. Factory-built construction provides the best strategy for managing these costs since factory workers typically aren't subject to these requirements.
Timeline: Realistic timeline from Board direction to occupied buildings: funding applications 12 to 24 months, design and engineering 6 to 9 months, approvals and permits 6 to 9 months
(overlaps with design), construction bidding 2 to 3 months, construction 12 to 13 months (stick-built) or 6 to 9 months (modular).
Long Term Operations: Property management, maintenance, tenant relations, compliance with funding requirements, and financial management require professional expertise. The County must decide early whether to self-manage or contract with an experienced affordable housing property management firm. For farmworker housing specifically, consider partnerships with agricultural employers or farmworker service organizations.
Summary:
● Funding is critical; start immediately with multiple parallel strategies
● Cost volatility requires robust contingencies and quick execution
● Prevailing wage requirements favor modular construction
● Plan for 3 to 4 years from today to occupancy
● Secure experienced partner for development, operations, or both
Recommendations and Next Steps
1. Board Decision: Decide between affordable housing only, mixed-use with a commercial component, or another direction. Recommendation: Proceed with affordable farmworker housing as the primary use.
2. Pursue Funding Immediately: Begin funding applications for state farmworker housing programs and USDA Rural Development programs now. Assign a dedicated staff member or consultant to coordinate funding efforts across multiple programs simultaneously.
3. Organize RFQ process: Establish a process that enables qualified architectural and general contractors to submit their credentials and remain in a holding pool until funding sources are identified and secured, allowing interested parties to engage early without committing the County before funds are confirmed.
4. Commission Engineering Studies (as needed): Complete geotechnical analysis, utility capacity studies, and traffic analysis early. These studies cost $75,000 to $125,000 total but provide critical information and eliminate major uncertainties.
5. Pursue Modular Construction: Given cost pressures and prevailing wage requirements, strongly favor factory-built construction. Issue RFP for architect/engineer teams with modular housing experience.
6. Engage Community and Stakeholders: Talk with agricultural employers about housing needs and potential partnerships. Engage farmworker service organizations. Conduct community meetings with Dixon residents and businesses.
7. Monitor Adjacent Parcel: Track Mosquito Abatement District lease expiration (2026) and be prepared to negotiate purchase if the Board decides expansion would improve the project. Don't delay the primary project waiting for this parcel.
8. Develop Realistic Budget and Timeline: Prepare a detailed budget with adequate contingencies (10 to 15%) and a realistic timeline (3 to 4 years to occupancy). Secure Board commitment to multi-year project timeline and funding requirements.
Conclusion
The Dixon Corporation Yard site offers the County a genuine opportunity to address critical farmworker housing needs while activating an underutilized public asset in an excellent location.
The site presents no major obstacles—it's flat, environmentally suitable, has utility access, and offers good connectivity to downtown Dixon and regional highways.
The project's greatest asset is its scale: small enough to be manageable, large enough to make a difference. A 15 to 25 unit development won't solve the County's entire affordable housing challenge, but it can provide quality homes for farmworker families while demonstrating the County's commitment to workforce housing. With realistic expectations, adequate funding, experienced partners, and thoughtful design, this project can deliver meaningful community benefit while establishing a model for future County affordable housing efforts.
Appendix
The following appendix provides a complete list of all supplemental materials, data sources, and reference documents linked throughout this report. These attachments offer additional detail and supporting documentation for the findings, analyses, and recommendations presented in the main sections. Each item has been organized for ease of reference and corresponds to the hyperlinks or references noted within the report body.
https://drive.google.com/drive/folders/1A6D0EyhO1W7xgZ2Ia4o-7zxlV6hziUEC?usp=drive_link https://drive.google.com/drive/folders/1A6D0EyhO1W7xgZ2Ia4o-7zxlV6hziUEC?usp=drive_link
THANK YOU
thurmondconsultingllc.com brian@thurmondconsultingllc.com
| Pages from V4_Dixon Corp Yard Final Analysis.pdf |
| Dixon Corporation Yard Redevelopment Analysis (Final) (2).pdf |
| Dixon Corporation Yard Redevelopment Analysis |
| Executive Summary |
| Background and Project Context |
| Physical Site Conditions |
Site Utilities5 and Infrastructure
Site Mobility and Accessibility
| Site Expansion Opportunity |
| Regulatory Framework and Approvals |
| Market Conditions and Demand |
| Building Types16 and Construction Methods |
| Development Program and Capacity18 |
| Project Costs and Financing19 |
| Development Challenges and Risk Factors |
| Recommendations and Next Steps |
| Conclusion |
| Appendix |