This is a General Requirements and Covenants document (Division I) issued by the City of Bridgeport, Connecticut, Department of Public Purchases, in conjunction with the State of Connecticut, Department of Transportation, for the Rehabilitation of the Access Ramp of Margaret E. Morton Government Center located at 999 Broad Street, Bridgeport, Connecticut. The project involves structural repairs to the roof parking ramp steel framing. Electronic bid submissions are required through the City's e-Procurement Portal (OpenGov) and must be received by 2:00 pm on Tuesday, March 24, 2026. The deadline for submitting written questions regarding the bid is 4:00 pm on Wednesday, March 11, 2026, with all answers published as addenda on the procurement portal. Bidders are required to create a free account with OpenGov Procurement to submit their bids and monitor the portal for any issued addendums.

The contract incorporates the latest revision of the State of Connecticut Standard Specification for Roads, Bridges, and Incidental Construction (Form 819) as of September 3, 2025. A limited hazardous materials site investigation identified the presence of lead paint on the steel framing below the threshold for lead-based paint classification, as well as non-asbestos fireproofing material. The contractor is solely responsible for implementing appropriate health and safety protocols to address potential exposure to these site-specific hazards, including air monitoring, engineering controls, personal protective equipment, decontamination procedures, and personnel training. All steel and metal generated during work activities must be segregated and recycled at a scrap metal recycling facility, which is exempt from USEPA RCRA and Connecticut Department of Energy and Environmental Protection hazardous waste regulations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL REQUIREMENTS AND COVENANTS

DIVISION I - GENERAL REQUIREMENTS AND COVENANTS

NOTICE TO CONTRACTOR

SPECIAL PROVISIONS – TECHNICAL SPECIFICATIONS

DIVISION I GENERAL REQUIREMENTS AND COVENANTS

SECTION

NOTICE TO CONTRACTOR – USE OF FORM 819

NOTICE TO CONTRACTOR – HAZARDOUS MATERIALS INVESTIGATIONS

GENERAL

NOTICE TO CONTRACTOR - STATE OF CONNECTICUT, DEPARTMENT OF

TRANSPORTATION, STANDARD SPECIFICATION FOR ROADS, BRIDGES AND

INCIDENTAL CONSTRUCTION, FORM 819

The latest revision of the “State of Connecticut Standard Specification for Roads, Bridges, and incidental Construction (Form 819) are herein made part of this contract (Including Standard Details). Any references to 818, Article, or related nomenclature shall be meant to reference Form 819 as amended.

Rev. Date 09/03/25

GENERAL

NOTICE TO CONTRACTOR – HAZARDOUS MATERIALS INVESTIGATIONS

A limited hazardous materials site investigation has been conducted at 999 Broad Street, Bridgeport, CT for structural repairs to the Roof Parking Ramp steel framing. The scope of inspection was limited to the representative components projected for impact.

The results of the investigation indicated the presence of lead in the paint on the steel framing. The results indicated that the percentage of lead was below the minimum for the paint to be considered “Lead-Based Paint”.

All steel and metal generated from work tasks (painted or not) shall be segregated and recycled as scrap metal at a scrap metal recycling facility. The recycling of scrap metal (regardless of lead paint concentration) is exempt from USEPA RCRA and CTDEEP Hazardous Waste Regulation.

Suspect asbestos fireproofing material coating the existing steel framing was sampled and determined to be a non-asbestos containing material.

The Contractor is hereby notified that these hazardous materials requiring special management or disposal procedures will be encountered during various construction activities conducted within the project limits. The Contractor will be required to implement appropriate health and safety measures for all construction activities impacting these materials. These measures shall include, but are not limited to, air monitoring, engineering controls, personal protective equipment and decontamination, equipment decontamination and personnel training. WORKER HEALTH

AND SAFETY PROTOCOLS WHICH ADDRESS POTENTIAL AND/OR ACTUAL RISK OF

EXPOSURE TO SITE SPECIFIC HAZARDS ARE SOLELY THE RESPONSIBILITY OF

THE CONTRACTOR.