DHS Uniforms III Acquisition Schedule Major Milestones.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
DHS/CBP Uniform III Follow-on Contract - GOVERNMENT RESPONSE TO QUESTIONS
Solicitation number
70B01C25R00000001-V2
Issued by

About this file

This is an acquisition schedule spreadsheet outlining major milestones for the DHS Uniforms III procurement, accompanied by a special notice responding to questions about the RFI. The schedule indicates an RFI release date of 7/26/24, with responses due 9/1/24, followed by site visits to the First Article Closet (1/15/25) and academies in Glynco, GA and Artesia, NM (11/21/25). The solicitation is planned for release on 9/15/25, with proposals due 1/15/26 and contract award by 8/31/26.

The timeline includes post-award milestones for first article samples (COTS items due 60 days after award, non-COTS items due 120 days after award), with government approval required by 1/31/27. A phased transition is planned beginning 2/1/27, including quartermaster services, bulk purchases, and component allowances, with a staggered 12-month transition period for TSA (April 2027) and CBP (January 2028). The procurement is being conducted by DHS Customs and Border Protection for uniform items and services supporting multiple DHS components.

View the file

Other files

File Type Posted
UniformOrderingDataForVendors_1.24.2025 totals.xlsx XLSX spreadsheet
RFI QA Response.xlsx XLSX spreadsheet
FY2024 DHS Country of Origin.xlsx XLSX spreadsheet
Compiled Uniform Vendor Interview Notes -Final.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 DHS Uniforms III Acquisition and Transition Schedule

Action ItemEstimated Completion DateActual Completion DateResponsible PartyNotes
RFI Released4/30/247/26/24Contracting Officer
RFI Received7/1/249/1/24Contracting Officer
RFI Matrix11/30/24OngoingUMC/CO
First Article Closet Site visit1/30/251/15/25UMC
RFI and FAC Q&A Released2/7/25UMC/CO
Solicitation Released9/15/25Contracting Officer
Academy Site Visits (Glynco, GA & Artesia, NM11/21/25
Proposal Received1/15/26Contracting Officer
Contract Award8/31/26Contracting Officer
COTS First Article Samples10/31/26Vendor60 days post award
Non-COTS First Article Samples12/31/26Vendor120 days post award
Government ApprovalNLT 1/31/27Government30 days after receipt of FAS
Transition of Services (Quartermaster)2/1/27Vendor
Transition of Bulk Purchases2/1/27CO/Vendor
Transition of Allowances (TSA April - CBP Jan 28)2/1/2027-1/31/28CO/VendorStaggered Transition 12 mos