Statement of Work (SOW)

Project Title: Toilets Waste Line Removal and Replacement

Location: Building TNG-1, Fort Gordon, GA

1.0 Scope of Work

The Contractor shall remove all existing drain lines serving the Toilets in the male and female latrines of Building TNG-1. Dispose all debris and install new 4-inch piping with proper slope / pitch per plumbing code from the Toilets groups to the clean-out sweep located just outside the building. The Contractor shall reconnect all disturb sink and urinal lines. All Toilets, urinals, and sinks must be fully operational upon completion. The Contractor shall furnish all labor, materials, equipment, and supervision necessary to complete the work in accordance with applicable codes and standards.

2.0 Project Requirements

2.1 Demolition and Removal

Removal of all existing Toilets waste piping serving both male and female latrines.

Disconnect piping only as required to avoid damage to finished surfaces.

All removed materials shall be disposed of in accordance with federal, state, and local regulations.

2.2 Installation of New Piping

The Contractor shall install new 4-inch sanitary piping in accordance with plumbing code, including slope / pitch, support, and alignment requirements.

2.2.1 Fixture Reconnection

The following fixtures shall be reconnected only if temporarily disconnected:

Fixture Type Quantity Location

Toilets 8 total (4 female, 4 male) Latrines

Sinks 5 total (2 female, 3 male) Latrines

Urinals 3 Men�s latrine

Floor Drains 2 total (1 per side) Latrines

Janitor/Mud Room Clean-outs 2 total Utility rooms

All reconnections shall be watertight and code-compliant.

All Toilets must flush properly and drain without obstruction.

2.2.2 Toilets Waste Line Installation

Install new 4-inch piping from each Toilets group to the exterior clean-out sweep.

Ensure proper slope / pitch per plumbing code.

Provide all required hangers, supports, and fittings. Support all piping using all-thread rod and steel pipe clamps

Ensure all piping is installed to maintain proper flow and prevent blockages.

2.3 Testing and Verification

Test all toilets, urinals and sinks for proper flushing and drainage.

Verify no leaks, blockages, or improper slope conditions.

Provide final inspection to the Government for acceptance.

3.0 General Requirements

Contractor shall comply with all OSHA, federal, state, and local safety regulations.

Contractor shall coordinate all inspections with the Government.

Contractor shall maintain a clean and safe worksite at all times.

Work shall be performed during approved working hours unless otherwise authorized.

Contractor shall protect all existing finishes, utilities, and building components from damage.

4.0 Deliverables

Demolition and installation completion report

As-built sketch showing new piping layout

Inspection and testing documentation

5.0 Final Acceptance

The Government will perform a final inspection. The project will be accepted once all Toilets flush properly, all reconnections are verified, and all work meets code and contract requirements.