Statement of Work (SOW)
Project Title: Toilets Waste Line Removal and Replacement
Location: Building TNG-1, Fort Gordon, GA
1.0 Scope of Work
The Contractor shall remove all existing drain lines serving the Toilets in the male and female latrines of Building TNG-1. Dispose all debris and install new 4-inch piping with proper slope / pitch per plumbing code from the Toilets groups to the clean-out sweep located just outside the building. The Contractor shall reconnect all disturb sink and urinal lines. All Toilets, urinals, and sinks must be fully operational upon completion. The Contractor shall furnish all labor, materials, equipment, and supervision necessary to complete the work in accordance with applicable codes and standards.
2.0 Project Requirements
2.1 Demolition and Removal
Removal of all existing Toilets waste piping serving both male and female latrines.
Disconnect piping only as required to avoid damage to finished surfaces.
All removed materials shall be disposed of in accordance with federal, state, and local regulations.
2.2 Installation of New Piping
The Contractor shall install new 4-inch sanitary piping in accordance with plumbing code, including slope / pitch, support, and alignment requirements.
2.2.1 Fixture Reconnection
The following fixtures shall be reconnected only if temporarily disconnected:
Fixture Type Quantity Location
Toilets 8 total (4 female, 4 male) Latrines
Sinks 5 total (2 female, 3 male) Latrines
Urinals 3 Men�s latrine
Floor Drains 2 total (1 per side) Latrines
Janitor/Mud Room Clean-outs 2 total Utility rooms
All reconnections shall be watertight and code-compliant.
All Toilets must flush properly and drain without obstruction.
2.2.2 Toilets Waste Line Installation
Install new 4-inch piping from each Toilets group to the exterior clean-out sweep.
Ensure proper slope / pitch per plumbing code.
Provide all required hangers, supports, and fittings. Support all piping using all-thread rod and steel pipe clamps
Ensure all piping is installed to maintain proper flow and prevent blockages.
2.3 Testing and Verification
Test all toilets, urinals and sinks for proper flushing and drainage.
Verify no leaks, blockages, or improper slope conditions.
Provide final inspection to the Government for acceptance.
3.0 General Requirements
Contractor shall comply with all OSHA, federal, state, and local safety regulations.
Contractor shall coordinate all inspections with the Government.
Contractor shall maintain a clean and safe worksite at all times.
Work shall be performed during approved working hours unless otherwise authorized.
Contractor shall protect all existing finishes, utilities, and building components from damage.
4.0 Deliverables
Demolition and installation completion report
As-built sketch showing new piping layout
Inspection and testing documentation
5.0 Final Acceptance
The Government will perform a final inspection. The project will be accepted once all Toilets flush properly, all reconnections are verified, and all work meets code and contract requirements.