DF for Consolidation Requirements (Redacted).pdf
PDF 987 KB Posted
- Solicitation number
- W9127826RA058
About this file
This is a Determination and Findings document for a federal contract consolidation request issued by the U.S. Army Corps of Engineers, Mobile District. The procurement concerns the award of an Indefinite Delivery Indefinite Quantity (IDIQ) Single Award Task Order Contract (SATOC) for general repair and construction services at the Mississippi Area Office. The contract is being awarded as a sole-source procurement to Genesis 360 LLC, an 8(a) certified small business concern located at 8352 Bluebonnet Boulevard, Baton Rouge, Louisiana 70810, under North American Industry Classification System (NAICS) code 236220. The SATOC will have a five-year ordering period and will support Sustainment, Restoration, and Modernization (SRM) of real property facilities and systems for Federal agencies within the Mississippi Area Office Area of Responsibility, spanning the Gulf Coast from Mobile, Alabama to New Orleans, Louisiana. Two currently identified projects total approximately [redacted] in estimated value.
The determination establishes that consolidation is both necessary and justified under 15 U.S.C. § 657q and RFO 7.107-2 because the contract involves construction at two or more discrete sites within the geographic area. Market research confirmed Genesis 360 LLC's capabilities through individual marketing meetings, review of capabilities and surety statements, past performance portfolio analysis, and SBA Business Development Specialist communication. The analysis demonstrated that the consolidated SATOC approach substantially exceeds alternative contracting methods, specifically stand-alone 8(a) "C-type" contracts, by providing significant advantages in quality, acquisition cycle time, administrative costs, and responsiveness to rapid end-of-fiscal-year requirements. Cost analysis indicated the SATOC approach reduces acquisition time and administrative expenses by eliminating duplicative pre-award documentation and SBA coordination on individual projects. The determination was approved by the Chief of Contracting Office with concurrence from the Small Business Administration, indicating no adverse impact on small business concerns.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE ARMY
U.S. ARMY CORPS OF ENGINEERS, MOBILE DISTRICT
DETERMINATION AND FINDINGS
REQUEST FOR CONSOLIDATION
W9127826RA058
INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ)
SINGLE AWARD TASK ORDER CONTRACT (SATOC)
FOR GENERAL REPAIR AND CONSTRUCTION AT MISSISSIPPI AREA OFFICE
Revolutionary Federal Acquisition Regulation Overhaul (RFO) 2.101 defines consolidation or consolidated requirement as a solicitation for a single contract, a multiple-award contract, a task order, or a delivery order to satisfy- (i) Two or more requirements of the Federal agency for supplies or services that have been provided to or performed for the Federal agency under two or more separate contracts, each of which was lower in cost than the total cost of the contract for which offers are solicited; or (ii) Requirements of the Federal agency for construction projects to be performed at two or more discrete sites. RFO 7.107-1(b)(1) requires a written determination for consolidation requirements above $2 million (15 U.S.C. § 657q).
I have reviewed this requirement and associated market research and determined in accordance with 15 U.S.C. § 657q and RFO 7.107-1 that consolidation is both necessary and justified. This approval is made in accordance with the approval thresholds set forth in Army Federal Acquisition Regulation Supplement (AFARS) Appendix GG, �Consolidation.� My review resulted in the following findings:
1. Introduction: Headquarters, U.S. Army Corps of Engineers, Mobile District, proposes to award a sole-source 8(a) Firm Fixed Price (FFP) IDIQ SATOC in the amount of to Genesis 360 LLC, 8352 Bluebonnet Blvd, Baton Rouge, LA 70810. The SATOC will support repair and construction requirements of Federal agencies within the Mississippi Area Office Area of Responsibility (AOR) under North American Industry Classification System (NAICS) NAICS code 236220. This procurement constitutes consolidation of requirements per 15 U.S.C. § 657q(a)(2)(B) because it involves construction at two or more discrete sites within the Mississippi Area Office AOR. Mobile District's analysis and market research demonstrate the consolidation is both necessary and justified.
2. Description of Procurement Action:
a. Project Description:
(1) Mobile District performs studies, investigations, designs, repairs, and construction within the Mississippi Area Office AOR. Each project is assigned a Project Delivery Team (PDT) comprising District elements: technical (Engineering and Construction Divisions), contracting, legal, project management (including the Deputy for Small Business), and the end user and facilities' engineering organizations. The District's contracting responsibilities include acquisition planning; procurement actions leading to contract award with associated documentation and approvals; and administration of resulting contracts, including award and administration of individual task orders.
(2) The purpose of this acquisition is to establish a highly responsive repair and construction contracting tool supporting Federal agencies within the Mississippi Area Office AOR.
Work is generally Sustainment, Restoration, and Modernization (SRM) of real property facilities and their systems and components, but may include new construction.
This effort, with the installation's facilities maintenance program, ensures compliance with Department of War (DoW) facilities standards. The enduring nature of this requirement means the necessity for the contract is not expected to be affected by current or future budget limitations.
b. Acquisition Strategy/Procurement Summary: To meet the repair and construction requirements of Federal agencies within the Mississippi Area Office's AOR (Gulf Coast from Mobile, AL to New Orleans, LA), Mobile District intends to award an IDIQ SATOC, FFP construction contract in accordance with RFO 16.504. The Government anticipates recurring requirements but cannot predetermine the exact quantity or time period needed. The SATOC will be awarded with in available capacity and five-year ordering period to Genesis 360 LLC for repair and construction work within the Mississippi Area Office AOR. Individual task orders will be negotiated with the contractor.
Mobile District determined an 8(a) SATOC is the most effective vehicle for meeting the Mississippi Area Office's construction mission. This approach supports the Small Business Administration's (SBA) 8(a) Business Development Program for socio-economically disadvantaged concerns. The SATOC also facilitates the District's smaller repair and construction programs and positions the District to meet short-fused, end-of-fiscal-year requirements. Use of a SATOC is in the best interest of the Government with respect to timeliness, oversight, and administrative costs.
c. Applicability of Consolidation: As implemented in RFO 2.101, consolidation or consolidated requirement means a solicitation for a single contract, a multiple-award contract, a task order, or a deliver order to satisfy -- (i) Two or more requirements of the Federal agency for supplies or services that have been provided to or performed for the Federal agency under two or more separate contracts, each of which was lower in cost than the total cost of the contract for which offers are solicited; or (ii) Requirements of the Federal agency for construction projects to be performed at two or more discrete sites. The definition applies to this procurement because a SATOC will be used to perform multiple construction projects, awarded on individual task orders, at two or more discrete sites within the Mississippi Area Office�s AOR.
d. Requirements Being Consolidated: This SATOC will provide full-service repair and construction of real property facilities, systems, and components, addressing both current known and anticipated future requirements from Federal agencies within the Mississippi Area Office's AOR. Task orders will be issued within the IDIQ scope of work and will reflect each customer's timing, urgency, funding sources, and mission-specific requirements.
accordance with RFO 16.504-2. The Contracting Officer may use an indefinite-quantity contract when the Government knows what kind of supplies and services required and a certain minimum amount needed, but does not know exactly how much will be needed or when during the effective period. The Contracting Officer should use an indefinite-quantity contract only when ongoing, repeated needs are anticipated. It is anticipated that the SATOC will be used to fulfill customer requirements within the Mississippi Area Office AOR, to include any tenant organizations.
(3) In accordance with RFO 7.107-2(e), when the benefits of consolidated requirements is not quantifiable as stated at RFO 7.107-2(c)(1), the consolidation must be determined to be necessary and justified based on the anticipated benefits of being critical to the agency�s mission success and that the procurement strategy provides for maximum practicable participation by small business. The work required under the proposed solicitation involves SRM and new construction at the Mississippi Area Office. An IDIQ SATOC will provide a flexible and effective contract vehicle that can accommodate both the known and unknown repair and construction requirements of the Mississippi Area Office AOR. In accordance with RFO 19.108-7, proposed 8(a) requirements that do not exceed the competitive thresholds at RFO 19.108-7(a)(2) or meet the exceptions detailed at RFO 19.108-7(b) may be awarded on a non-competitive basis. The independent statute allows this procurement to be awarded on a sole source basis. Pursuant to the Small Business Act (15 U.S.C.
637(a)) and RFO 19.108, this requirement is authorized for a sole-source award to an 8(a) participant, exempting it from full and open competition. The acquisition strategy does not negatively impact contracting with small business concerns. Both the consolidated SATOC approach and the alternative of multiple stand-alone 8(a) sole source contracts direct the work to small business, satisfying the small business participation policy at 15 U.S.C. § 657q(b). Though it is feasible to fulfill the requirements by awarding multiple stand-alone 8(a) sole source "C" contracts, which could be awarded to multiple 8(a) contractors, the advantages of the SATOC support the intended approach.
3. Applicable Statutes/Regulations: 15 U.S.C. § 657q, RFO 7.107-2, and AFARS Appendix GG.
4. Results of Market Research:
a. To support the District's determinations on where to place projects, market research regarding 8(a) sole source contractors is performed throughout the year. The purpose of this market research is to provide the District with the necessary information regarding the capabilities and limitations of 8(a) contractors needed to perform the work required at the dollar levels anticipated. To this end, the District reviews 8(a) contractor referrals from SBA district offices in Alabama, Tennessee, Mississippi, and Florida, as well as other SBA offices. Interested 8(a) firms are scheduled for marketing meetings with the District's Small and Disadvantaged Business Office Chief, who conducts interviews to assess the 8(a) company's bonding and technical capabilities and number of employees, and determines whether the 8(a) is a proper match for prospective projects. Companies possessing the requisite capabilities are scheduled for face-to-face marketing meetings with District technical personnel, who consider whether the contractor's experience demonstrates the capability and bonding capacity to perform multiple projects simultaneously. Genesis 360 LLC was selected based on prior successful work history in Mobile District's AOR and customer satisfaction with previous and ongoing work performed within the customer's installation boundary.
b. For Mississippi Area Office, the following market research techniques were used to assess Genesis 360 LLC's capabilities:
(1) Individual marketing meetings held with Genesis 360 LLC in the last 18 months.
(2) Review and analysis of Genesis 360 LLC's Capabilities and Surety Statements.
(3) Review and analysis of Genesis 360 LLC's past performance portfolio for relevance to the projects anticipated under this SATOC.
(4) Communication with the SBA Business Development Specialist as to Genesis 360 LLC's status in the 8(a) program.
(5) Review of Genesis 360 LLC's company profile in the Small Business Search engine.
c. Following market research, it was determined that an acquisition approach using Genesis 360 LLC under the 8(a) program was appropriate. The requirement was offered to and accepted by the SBA. In its acceptance letter, the SBA affirmed that the proposed procurement would have no adverse impact on small businesses. Genesis 360 LLC is fully capable of fulfilling all requirements that will be awarded under the SATOC.
5. Alternate Contracting Approaches Considered and Rationale for Rejection: Mobile District considered stand-alone 8(a) "C-type" contracts on a project-by-project basis. The District determined that a sole-source 8(a) SATOC was the most effective approach for satisfying the repair and construction requirements for Federal customers in the Mississippi Area Office AOR. The intent of this analysis is to address alternative contracting approaches involving a lesser degree of consolidation, or no consolidation. See analysis below for the benefits of this proposed consolidated acquisition. Consistent with RFO 7.107-2(d), the justification does not rely on the reduction of administrative or personnel costs alone.
a. Alternative 1: Stand-Alone 8(a) Sole-Source �C� Type Contracts: The District considered the award of multiple stand-alone sole source contracts to 8(a) vendors to perform the work within the Mississippi Area Office AOR. While this approach could provide a lesser degree of consolidation, or no consolidation at all if individual contracts are awarded for single requirements, the benefits of the SATOC approach substantially exceed those of the stand-alone alternative for the reasons outlined below.
(1) Quality. The ability to work directly with a single contractor through a SATOC provides significant advantages compared to awarding multiple 8(a) sole-source contracts to different contractors. The District's experience is that working with a single contractor on repair and construction efforts generates greater understanding between contractor and Government, resulting in more thorough proposals and quality projects. While "C" contracts give the Government the opportunity to avail itself of a wider range of potential contractors for each project, the 8(a) vetting process described in paragraph 4, Market Research, achieves a comparable result for task orders under the proposed SATOC: a high-quality contractor suited to the requirements. Working with one contractor under the SATOC also generates a more thorough shared understanding of Government described in paragraphs (i), (ii), and (iii) of this definition. Under RFO 2.101, "separate smaller contract" means a contract that has been performed by one or more small business concerns or that was suitable for award to one or more small business concerns.
b. Applicability of RFO Bundling Definition. This acquisition does not meet the definition of bundling since the Government will procure this requirement via a sole source procurement to an 8(a) small business concern. The selected 8(a) is capable of fulfilling all requirements under the SATOC.
c. Definition of the Competition in Contracting Act (CICA) Bundling Principle. This principle, as developed by the Government Accountability Office (GAO) case law, focuses on whether the combined requirement (new, old, or otherwise) restricts competition, and whether the agency is consolidating or bundling a new requirement unnecessarily. In order to justify CICA Bundling the agency must show "a reasonable basis for why the bundling is necessary to meet the agency need." (Vantex Serv., Inc., B-290415, Aug. 8, 2002 and Outdoor Venture Corp., B-299675; B-299676, Jul. 19, 2007).
CICA requires solicitations to provide for full and open competition except where restrictions on competition are necessary to satisfy the procuring agency's needs. In such a case, restrictions on competition are allowed. Bundled procurements combining separate requirements into one contract have the potential to restrict competition by excluding firms that can provide only a portion of the bundled requirement. However, combining like and related efforts to achieve economies of scale and eliminate duplication of effort, consistent with industry practice and market research is reasonable basis for bundling requirements, though it may have the effect of restricting competition. All the acquisition approaches discussed above implicate CICA bundling, though in varying degrees.
d. Applicability of CICA Bundling Principle. Although this action constitutes CICA bundling by combining like and related repair and construction work, it is consistent with industry practice and necessary to satisfy the customers' needs. This procurement will allow the District to leverage economies of scale, streamline acquisition cycles, and eliminate duplication of efforts by establishing an 8(a) SATOC with a responsive and responsible contractor to perform individual task orders as the need arises. Additionally, the Government has independent statutory authority to proceed as proposed, fulfilling these requirements via a sole source procurement to an 8(a) small business concern.
7. Considerations, facts, and reasoning supporting the determination: All facts, considerations, and rationale supporting this determination are documented in the preceding sections. These include the rationale for consolidation, market research and small business impact analysis, alternative contracting approaches considered and rationale for rejection, and bundling analysis. These sections collectively support the determination that consolidation of these requirements is necessary and justified under RFO 7.107-2.
8. Summary: Though this sole-source 8(a) SATOC constitutes consolidation in that it combines construction at two or more discrete sites in one contract, this approach provides the best combination of timely acquisition, cost efficiency, quality, and capable prime contractor performance to execute repair and construction requirements located within the Mississippi Area Office AOR. This approach also accrues to the benefit of the District's aggressive small business goals. Stand-alone "C" contracts were considered but rejected as they would result in significantly higher administrative costs and increased acquisition cycle time. Although cost savings do not amount to 10% of the contract value, a consolidated SATOC, as opposed to using a stand-alone contract or other procurement strategies, provides qualitative benefits including a significant increase in quality and acquisition cycle. Consolidating these requirements also provides cost savings of approximately in administrative costs.
Given the increased time required to award projects and the number of projects involved, if these benefits are not leveraged, the District will not be able to fully execute the SRM requirements of the Mississippi Area Office, particularly in the fourth quarter, which constitutes the largest portion of the District's SRM construction program. The Mississippi Area Office will experience significant impacts to mission readiness, negatively affecting the ability of the Army and other tenant organizations to accomplish their mission. The consolidated approach is therefore critical to the agency's mission success, executed through the Mobile District in support of Federal customers within the Mississippi Area Office AOR. Additionally, administering one SATOC is significantly less burdensome for the District's Contracting and Construction Divisions than administering numerous "C" contracts. Moreover, the planned approach meets the intent of the statute to protect small business by awarding to an 8(a) sole source. The findings of the market research and the documentation provided herein support the conclusion that consolidation of requirements is both necessary and justified, based on sound business judgment in view of the size, complexity, and number of efforts to be executed at the Mississippi Area Office, and the consolidated approach provides advantages that substantially exceed the benefits of an approach that provides a lesser degree of consolidation.
DETERMINATION REQUEST FOR CONSOLIDATION
W9127826RA058
IDIQ SATOC FOR GENERAL REPAIR AND CONSTRUCTION
AT MISSISSIPPI AREA OFFICE
Upon the basis of the findings above and with the concurrence of the SBA, I hereby determine, pursuant to the authority of RFO 7.107-2, 15 U.S.C. § 657q, and Army Federal Acquisition Regulation Supplement Appendix GG, "Consolidation," that the proposed consolidation of two or more discrete construction projects for the Department of War and other Federal Agencies within the Mobile District is both necessary and justified.
Carl Wade Chief of Contracting Office, Contracting Division, Mobile District