This is an industry day presentation for the Fort Devens Collective Training Barracks Design-Bid-Build construction project hosted by the U.S. Army Corps of Engineers, Louisville District on April 15, 2026. The project involves constructing a 300-bed open-bay Collective Training Enlisted Barracks at Devens Reserve Forces Training Area in Massachusetts, comprising approximately 46,000 square feet with open bay sleeping rooms, storage, team rooms, laundry, restrooms, and showers. The scope includes information systems, fire protection, alarm systems, Intrusion Detection Systems, Energy Monitoring Control Systems, site development, utilities, lighting, paving, sidewalks, curbs, gutters, storm drainage, landscaping, signage, sustainability measures, cybersecurity measures, antiterrorism force protection, and physical security measures. The project requires demolition of two adjacent buildings. The solicitation number is W912QR26RA051, to be issued in April 2026 with proposal closure in May 2026, evaluation in May/June 2026, and contract award in June 2026.
This is an unrestricted, full and open competition using a single-phase Design-Bid-Build approach with a "Best Value Trade-off" evaluation methodology. Proposals will be evaluated on past performance (most important), management plan, and schedule narrative, with all technical factors combined considered approximately equal to price. A Small Business Participation Plan is a rated evaluation factor for all offerors; large businesses must also submit a Subcontracting Plan. Proposals must be submitted through the PIEE Solicitation Module by the deadline with no late submissions accepted. All solicitation documents, amendments, and the interested vendors list will be posted to SAM.gov. Offerors must submit questions through the ProjNet system only, and an optional site visit will be provided. Key contacts include Ryan King (Contracting Specialist), Jesse Scharlow (Contracting Officer), Crystal Harbin (Deputy for Small Business), and Courtney Luckett (Small Business Professional) of the Louisville District.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| INDUSTRY DAY Sign In Sheet.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDUSTRY DAY FORUM
Devens RFTA COLLECTIVE TRAINING barracks Army Reserves: army reserve center
DATE: 15 APR 2026
TIME: 1000 ET
LOCATION:
31 Quebec Street Devens, MA 43015
Tony Spicer- Project Manager Michael Barry- Project Engineer Daniel Kobzar – New England District COR Ryan King- Contracting Specialist Crystal Harbin – Deputy for Small Business
”The views, opinions and findings contained in this report are those of the author(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
Introduction
Please ensure that you have signed in Company Name, POC Name, Email, Phone Are you interested in being the Prime or Subcontractor If you’re interested in being a Subcontractor, state the Type of Work you are interested in (Electrical, Mechanical, etc.)
No recording (please turn off or put away all mobile devices)
This briefing and the attendee roster will be posted to SAM.gov
Please be advised that none of the information discussed today is contractually-binding
ADMINISTRATIVE ANNOUNCEMENTS
Design Overview Procurement Process Small Business Opportunities Questions
AGENDA
Project: Construct a 300-bed open-bay Collective Training Enlisted Barracks.
Location: Devens, Ma
Includes: Army Reserve Center Building 46,000 SF
Construct a 300-bed open-bay Collective Training Enlisted Barracks on Devens Reserve Forces Training Area (RFTA), Massachusetts. The barracks will consist of open bay sleeping rooms, storage, team rooms, laundry, restrooms, and showers. The project will include information systems, fire protection, alarm systems, and energy monitoring control systems. Supporting facilities include site development, utilities with connections, lighting, paving, sidewalks, curbs and gutters, storm drainage, landscaping and signage. Sustainability/Energy and cybersecurity measures are included. Demolition of two (2) adjacent buildings.
Project scope
Unit storage / kitchen
Project site
PROCUREMENT PROCESS OVERVIEW
Ryan King
CONTRACT SPECIALIST
USACE-LOUISVILLE DISTRICT
Jesse Scharlow
CONTRACTING OFFICER
USACE-LOUISVILLE DISTRICT
Request for Proposal (RFP) issued for offers for this Design-Bid-Build (D-B-B) project
Unrestricted (full and open) procurement
LRL will conduct a Single-Phase Source Selection Evaluation Board (SSEB) to evaluate offerors’ proposals based on specific factors as defined in the RFP Package
“Best Value Trade-off” process used that allows us to award to the offeror whose proposal offers the best value to the government
Proposals must be submitted on time.
The Louisville District is located within the Eastern time zone.
THE PROCUREMENT PROCESS
This project will be a Single-Phase Design-Bid-Build Unrestricted procurement.
System for Award Management (SAM) at www.SAM.gov
Solicitation Number W912QR26RA051 – FOLLOW!
Solicitations for USACE-Louisville begin with W912QR Search using Keyword Search Feature (Select “Any Words” or “All Words”): Fort Devens Collective Training Barracks
Register as an Interested Vendor and view the Interested Vendors List if you are looking to partner with another company of firm to compete for this project
Register to receive notifications and updates / amendments*
RFP Technical Information (i.e., Plans and Specs) will be available for download from www.SAM.gov
HOW TO OBTAIN THE SOLICITATION
Pre-Solicitation Notice
– Minimum 15 days prior to Solicitation
Advertisement
– Minimum 30 days to prepare Proposals Amendments issued to the RFP will also be posted on www.SAM.gov
DOCUMENTS / NOTICES POSTED to SAM.gov
Requirements to Download Technical Data Package:
Register for a SAM account and Sign-In to:
- “Follow” to receive email notifications (i.e., amendments)
- View interested vendors list
- Sign up as an Interested Vendor
Locate and access the Solicitation notice in the SAM database.
- Go to the “Attachments/Links” section to download the solicitation and all technical documents.
OBTAINING SOLICITATION DOCUMENTS
Requirements to Submit Proposals:
All proposals will be submitted through the PIEE Solicitation Module. Please note proposals must be submitted on time.
Offerors must register in advance for a user ID and Password to access this system.
Register your business entity (you as an individual or your organization) to be able to propose on contracts as the Prime.
SUBMITTING YOUR PROPOSAL
Source Selection Evaluation Criteria for Volume I may consist of the following elements (subject to change)
1) Volume I – Factor I: Past Performance Evaluation Project(s) completed as the Prime Contractor (maximum 3) Relevancy - Recent projects, similar in size, scope, magnitude of effort & complexities Quality of performance on submitted projects Other sources of relevant past performance information (i.e., CPARS, FAPIIS)
Volume I – Factors II & III: Technical Factors (e.g. Management Plan, Schedule Narrative)
PROPOSAL REQUIREMENTS
Technical Evaluation Factors
Section 00 22 12 will contain the proposal submission requirements and evaluation criteria. Follow the format described in Section 00 22 12 to keep the proposal in order, success is in the details. Please pay close attention to the requirements of the RFP.
For the Past Performance Factor, we will evaluate both the relevancy of experience and performance quality of prior experience. We will, at a minimum, review CPARS information available but reserve the right to check any and all sources of past performance information. This review will result in an overall assessment of confidence in performance.
For the Technical Evaluation Factors (Management Plan and Commissioning Plan), consider providing specifically tailored approaches for the solicited project. Don’t just tell us how you generally execute construction projects; tell us how you plan to execute this specific project and mitigate project specific risks (schedule, environmental, labor, etc.).
Source Selection Evaluation Criteria for a Volume II consists of the following elements:
3) Volume II – Pro Forma (& Price) Information Tab A: Standard Form 1442 Tab B: Joint Venture Agreements (if applicable) Tab C: Evidence of Ability to Obtain Bonding & Proof of Financial Ability Tab D: Pre-Award Information (i.e., Reps & Certs, offeror information, etc.)
As a reminder, the Small Business Participation Plan is a rated evaluation factor and applies to all businesses, both large and small, and is based on total contract value. Only large businesses are required to submit a Subcontracting Plan.
Technical Factors listed in relative order of importance (example):
| Volume I – Factor I: Past Performance | Most Important |
| Volume I – Factor II: Management Plan | Equal to Factor III |
| Volume I – Factor III: Schedule Narrative | Equal to Factor II |
All Technical Evaluation Factors, other than Price, when combined are considered approximately equal to Price.
Submit your best proposal the 1st time. If we receive an initial proposal that is awardable, discussions may not be opened.
The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary.
PROPOSAL REQUIREMENTS
Instructions for submitting a Request for Information (RFI) will be included in the Solicitation.
RFIs for these projects will be received and answered through the ProjNet system: www.ProjNet.org
Any RFIs submitted/emailed directly to the Project Team will NOT receive a response, and offerors will be directed to the ProjNet system.
A ProjNet Bidder’s Key included in the solicitation’s Project Instructions section of the RFP, which is used to post your RFIs/questions.
RFIs and their responses will be available for public review through ProjNet.
Optional Site Visit held to familiarize Offerors with the jobsite and conditions, not for the purposes of answering questions.
An Optional Site Visit will be held solely to provide the Offerors with an opportunity to familiarize themselves with the jobsite and conditions to be encountered and is not for the purpose of answering questions. All questions and inquiries shall be submitted via ProjNet only, in accordance with the Solicitation instructions provided in Section 00 21 00, PROJNET
INSTRUCTIONS, OFFEROR’S QUESTIONS AND COMMENTS.
We will utilize the Electronic Receipt of Proposal process – Instructions will be in Section 00 21 00 of the solicitation package
Proposals are uploaded to and submitted through PIEE Solicitation Module Recommend performing a test run well in advance
Don’t wait until the last minute to upload your proposal. Late is Late - No exceptions!
PROPOSAL SUBMISSION
As mentioned earlier, all proposals will be submitted through the PIEE Solicitation Module on time. Therefore, offerors must register in advance for a user ID and Password to access this system.
****Note: Attachments will not be available in PIEE, and will be downloadable from SAM. The Solicitation and Amendments take time to fully process from PIEE to SAM. If you see the solicitation or amendment without attachments in SAM, please continue to check periodically as they will be available by the close of business (COB).
PROCUREMENT SCHEDULE
Dates are approximate AND SUBJECT TO CHANGE
ISSUE SOLICIATION APRIL 2026
SOLICITATION CLOSES MAY 2026
EVALUATION BOARD MAY / JUNE 2026
AWARD JUNE 2026
File Name
Crystal Harbin Deputy for Small Business Louisville District
SBO-LRL@usace.army.mil
Courtney Luckett Small Business Professional Louisville District
NETWORKING
Networking is an important part of preparing for the upcoming project. Please post the below information in the chat:
Company Name POC Name, Email, Phone Are you interested in being the Prime or Subcontractor If you’re interested in being a subcontractor, state the type of work you are interested (Electrical, Mechanical, Roofing, etc.)
The sign-in sheet and presentation slides will be posted to the www.SAM.gov notice following the close of this industry day. Please be sure to use this information to network with other firms and build your team.
Interested Vendors List in SAM
Small Business Participation plan & Subcontracting PLAN The Small Business Participation Plan is a rated evaluation factor in all unrestricted procurements Both large and small business offerors must submit a participation plan.
The participation plan is based on total contract value.
The Small Business Participation Plan must meet the minimum Total Small Business Participation goal. The percentage will be included the solicitation.
Small Business prime self-performance counts as Small Business Participation.
Large Business offerors must submit a Small Business Subcontracting Plan Mandated by FAR 19.702 This is not a rated element as a part of the Source Selection process but the offeror shall submit an acceptable plan prior to award The subcontracting plan is based on total subcontracted dollars Failure to comply in good faith is in material breach of the contract
Obtain information Attend Site Visits, Pre-Proposal Conferences, & Industry Days Obtain copies of attendee roster for subcontracting opportunities
Register as an Interested Vendor on SAM
Attend Workshops and Conferences Louisville District Open House
Construction & IDIQ Forecast is maintained on the Business with Us page of the Great Lakes and Ohio River Division website, https://www.lrd.usace.army.mil/Opportunity-Forecast/ opportunities We anticipate executing approximately $1.5B in FY26 through both small and large businesses.
Contracting opportunities are posted in the System for Award Management (SAM) website at www.sam.gov. Use “W912QR” to search for Louisville District projects.
Actively Respond to Sources Sought Notices (Market Surveys) posted to SAM
Actively Respond to Competitive Requirements posted to SAM
Thank you for your time and interest!