LIQUIDATED DAMAGES

DETERMINATION OF LIQUIDATED DAMAGES:

The estimated damages for the 673rd Civil Engineering Office for first and last days of delay beyond the project completion date are:

1. Inspector 2 hours/day @ $47.92/hour = $ 95.84

2. Project Engineer 2 hours/day @ $57.50/hour = $ 115.00

3. Chief of Engineering 1 hour/day @ $85.05/hour = $ 85.05

Total Civil Engineering Cost = $295.89X2 days= $591.78

The estimated damages for the 673rd Civil Engineering Office for all other days other than the first and last days of delay beyond the project completion date are:

1. Inspector 2 hours/day @ $47.92/hour = $95.84

2. Project Engineer 2 hours/day @ $57.50/hour = $115.00

Total Civil Engineering Cost = $210.84/day

Warren Colburn Project Manager 673d CES/CENMP

2020-03-20T13:22:59-0800
COLBURN.WARREN.L.1161890070