| File | Type | Posted |
|---|---|---|
| 22 40 00 - Plumbing Fixtures.pdf | ||
| 36C25921Q0809 0002.docx | DOCX document | |
| Site Visit Meeting Doc.docx | DOCX document | |
| 36C25921Q0809 0001.docx | DOCX document | |
| G2-305 FLOORING PLAN.pdf | ||
| S05- Questions and Answers.docx | DOCX document | |
| 08.AG.102.pdf | ||
| S04- Site Visit Attendance.pdf | ||
| Prosthetics Layout.pdf | ||
| Specs.zip | ZIP file | |
| 36C25921Q0809_1.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Work Item Number:
Room Numbers:
G2‐305
Location/ Partial Floor Plan:
Location:
Reference Docs:
(Including but not limited to)
Drawings:
08.AG.102, G2‐305 FLOORING PLAN
Specs:
09 06 00, 09 06 08, 09 65 16
Functional Intent:
Add flooring into patient facing side of G2‐305.
Scope: 1. Install new sheet vinyl flooring with an integral cove base with metal cap at perimeter.
a. Complete any demo or prep of original flooring to ensure proper install of new flooring
b. See G2‐305 FLOORING PLAN for detail layout of room and flooring specs.
c. New flooring should be installed after new door has been installed (see work item #2) and flooring should run through new door frame with a proper threshold installed for the flooring type change in G2‐305 south room.
2. Patch and paint to match existing as necessary.
Associated Pictures:
RFP INFORMATION
Number:
Room Numbers:
G2‐305
Location/ Partial
Reference Docs:
(Including but not limited to)
Drawings:
08.AG.102, 08.AI.402‐A, XX.AI.731 Prosthetics Layout
Specs:
09 06 00, 09 06 08
Functional Intent:
Add a new “barn door” style sliding door to allow access to the south room of G2‐305 from the north side.
Scope: 1. Install new sliding “barn door” style door that is rated for healthcare use.
a. See attached drawing for approximate location and correct placement/orientation of door within existing space.
b. Door must have the following features and capabilities:
i. Minimum 3’ wide and 7’ tall
ii. Classroom lock functionality
iii. Minimum STC rating of 20
iv. Seal to reduce sound and particulate transmission between rooms around entire system including door bottom
v. Door latching
vi. Soft self closer
vii. Match existing door finishes of campus doors
2. Patch and paint to match existing as necessary
Room Numbers: G2‐305
Location/ Partial
Reference Docs:
(Including but not limited to)
Drawings:
08.AG.101, 08.AG.102, 08.PP.102, 08.PL.101, 08.PL.102, Prosthetics Layout
Specs:
22 05 11, 22 11 00, 22 13 00, 22 40 00, 22 66 00
Functional Intent: A sink is required to allow staff to work with plaster on the south room.
Scope: 1. Add new plaster sink (P‐507) and all necessary associated plumbing at approximate location shown on drawing.
a. Sink must have a plaster trap and be large enough to fill a 5 gallon bucket.
b. New drain line will have to be installed – contractor should be aware that this work will require work high above the existing ceiling grid on the floor below. Contractor should be prepared to do all necessary work to install this new drain line over the course of a weekend as to have the floor below back or original condition before Monday morning.
c. Add either stand alone or integrated eyewash.
2. Patch and paint to match existing as necessary.
New Door
See Item #2
New Sink
Room Numbers: G2‐C10 & G2‐305
Location/ Partial to)
Drawings:
08.AG.102, 08.ES.402
Specs:
08 41 13, 08 71 13, 26 05 11, 26 05 19, 26 05 26, 26 05 33
Functional Intent: Room G2‐305 is now a patient care area with patients coming through the G2‐C10 corridor door. Both doors need to be reconfigured to allow easier access for patients into the space.
Scope: 1. Add new auto door operator to corridor door G2‐C10. Patch and paint as needed.
a. This includes all associated electrical work to add operator to this door. All electrical shutdowns must be coordinated 3 weeks in advance with COR and completed after hours.
2. Remove door closer mechanism from door to G2‐305 and repair door as needed.
1. G2‐C10
East Side West Side
Room Numbers: G3‐315
Location/ Partial to)
Drawings:
08.AG.103, 08.PL.102, 08.PL.103, 08.PP.103
Specs:
22 05 11, 22 11 00, 22 13 00, 22 40 00, 22 66 00
Functional Intent: Current sink is not set up to properly dispose of contaminated dialysate and needs to be changed to a proper sink with a neutralizer tank.
All work will need to be completed during the weekend, minus scope item #6 below.
Contractor must test water pressure for all effected surrounding plumbing lines once water is tied in to ensure adequate water pressure before Monday morning.
Scope: 1. Remove existing sink
2. Install new clinic service sink (P‐505) with a neutralizing tank including new drain line and associated necessary plumbing.
3. Remove stainless steel shelf above floor sink and repair wall as needed.
4. Patch and paint to match existing as necessary.
5. Replace FRP as needed.
6. Repair/replace flooring of room if damaged during construction.
7. Remove and replace the door handle with new push‐button combination lock handle. (Simplex 5066‐B‐WL‐26D) This work should be done during normal business hours during the week to coordinate with VA locksmith.
Remove and replace with P‐505 sink
Existing P‐505 sink for reference