Attch_E_Submittal_Log.pdf

PDF 66 KB Posted

Attached to
Mesa Substation Remediation Project Federal contract opportunity
Solicitation number
DE-SOL-0010045
Issued by
Department of Energy Western Area Power Administration

About this file

Attch E Submittal Log

View the file

Other files for this federal contract opportunity

Other files attached to Mesa Substation Remediation Project, newest first.
File Type Posted
Amendment_3.pdf PDF
Amendment_3_Revised_PWS_10_21_16.pdf PDF
Amendment_2.pdf PDF
Amendment_2_Revised_Proposal_Schedule.pdf PDF
Amendment_2_Revised_PWS_10_20_16.pdf PDF
Amendment_1.pdf PDF
Site_Visit.pdf PDF
Attch_B_Drawings.pdf PDF
Attch_H_o442_21.pdf PDF
DE-SOL-0010045.pdf PDF
Attch_D_Soil_Boring_Logs.pdf PDF
Attch_G__Foreign_National_Data_Card.pdf PDF
Attch_A_Mesa_PWS_-_8_29_16.pdf PDF
Attch_C_Sensitive_Area_Drawings.pdf PDF
Attch_I_Primary_and_Secondary_Wage_Determination.pdf PDF
Attch_F_Voluntary_Remediation_Program_REmedial_Work_Plan.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Title: MESA SUBSTATION SOIL REMEDIATION Award Date:

Contract No.: Start Date:

Contractor: Completion Date:

Contractor's Western's Date Submittal Item Date Approved

# # Submittal Item Date Due Submitted Rejected COMMENTS

1 Project Schedule 15-days after Award

2 Community Involvement Plan NLT 30-days after Award

3 Safety and Health Program NLT 10-days prior to start of work

4 Copies of Certifications, Test Records & Technical Data Prior to use

5 - Test Results of Protective Ground Leads Prior to use

6 - Certification of Fabricated Lifting and Rigging Devices Prior to use

7 - Medical Examiner's Certificate Prior to use

8 - Safety Data Sheets Prior to use

9 - Data For Excavation Protective System Prior to use

10 Assurance of Competency in Equipment Operation Prior to use

11 Respiratory Protection Program Prior to work requiring respirator protection

12 Excavation Plan Prior to work commencing on-site

13 Cable Location Plan Prior to work commencing on-site

14 Protective Ground Lead Test Results & Certification Prior to use

15 Earth Material Testing Laboratory 20-days prior to compacting

16 Earth Material Compaction Test Reports Immed. after test complete

17 Earth Backfill Material Prior to refill

18 VRP Site Closure Certification

19 Maricopa County NESHAP Notification

20 Lead-Based Paint Test Results

21 Certifications and Licensing of Key Personnel

22 Copies of Permits

23 Test Results for Waste Characterization & Profiling (Soil) NLT 20-days after test

24 Loads and Manifests (Tracking Sheets)

25 Soil Disposal Records

26 Results of Monitoring for Dust Control

27 Soil Confirmation Test Results

28 Chain-of-Custody Information

29 Results of Laboratory Analysis

30 Asbestos Abatement Confirmation Test Results

31 Documentation of Asbestos Abatement Work Zone Inspection

32 Oil Piping Demolition Confirmation Test Results

33 Photographs

SUBMITTAL TRACKING SHEET

Contractor's Western's Date Submittal Item Date Approved

# # Submittal Item Date Due Submitted Rejected COMMENTS 34 Results of Volatile Organic Vapor Monitoring

35 Test Results of Residual Oils and Liquids

36 Documentation of Disposal (TSCA PCB, 40 CFR Part 761) NLT 20-days after test

37 Final Data Laboratory Report

38 Remedial Completion Report - Draft

39 Remedial Completion Report - Final

40 Preliminary Risk Evaluation 14-days prior to commencing work on-

41 Quality Assurance/Quality Control Program

42 Primary Analysis Laboratory

43 Gravel Surfacing Material Gradation Prior to placing

44 Gravel Surfacing Density & Compaction Test Results NLT 7-days after test complete

45 Herbicide Applicator's References NLT 30-calendar-days prior to application

46 Herbicide Applicator's Certification/License NLT 30-calendar-days prior to application

47 Herbicide Application Plan NLT 30-calendar-days prior to application

48 Herbicide Application Final Report NLT 7-days after application

49 Gravel Base Certification NLT 20-days prior to paving

50 Recycled Materials Quantity Report Prior to final payment

51 Products Containing Recovered Materials Report Prior to final payment

52 Spill Prevention Notification & Cleanup Plan Prior to commencing on-site work

53 Pesticide Use Plan Prior to commencing on-site work

54 Licenses & Permits Prior to commencing on-site work

55 Stormwater Discharge & Water Pollution Permits Prior to commencing on-site work

56 Asbestos Licenses or Certificates Prior to commencing on-site work

57 Dust Control Permit Prior to commencing on-site work

58 Authority to Perform Excavation Prior to commencing on-site work

59 Hauling, Demolition, and Grading and Drainage Permits Prior to commencing on-site work

60 Notice of Intent to Abandon Wells Prior to commencing on-site work

61 Products Containing Recovered Materials Report Prior to final payment

62 PCB Test Reports

63 Oil & Oil-Filled Electrical Equipment Receipt

64 Any other Permits Prior to commencing on-site work

65 Lead Paint Notices Prior to commencing on-site work

66 Clean-up Work Management Plan Prior to commencing on-site work

67 As-Built Drawings NLT 10-days post on-site work completion and prior to final payment

Sheet1

File details come from the government source that posted it. Updated .