Amendment_2_Revised_Proposal_Schedule.pdf
PDF 69 KB Posted
- Attached to
- Mesa Substation Remediation Project Federal contract opportunity
- Solicitation number
- DE-SOL-0010045
About this file
Amendment 2 Revised Proposal Schedule
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_3.pdf | ||
| Amendment_3_Revised_PWS_10_21_16.pdf | ||
| Amendment_2_Revised_PWS_10_20_16.pdf | ||
| Amendment_2.pdf | ||
| Site_Visit.pdf | ||
| Amendment_1.pdf | ||
| Attch_G__Foreign_National_Data_Card.pdf | ||
| Attch_A_Mesa_PWS_-_8_29_16.pdf | ||
| Attch_I_Primary_and_Secondary_Wage_Determination.pdf | ||
| Attch_E_Submittal_Log.pdf | ||
| Attch_F_Voluntary_Remediation_Program_REmedial_Work_Plan.pdf | ||
| Attch_C_Sensitive_Area_Drawings.pdf | ||
| Attch_B_Drawings.pdf | ||
| Attch_H_o442_21.pdf | ||
| DE-SOL-0010045.pdf | ||
| Attch_D_Soil_Boring_Logs.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 2
SECTION B
SUPPLIES OR SERVICES AND PRICES
PROPOSAL SCHEDULE
MESA SUBSTATION SOIL REMEDIATION
CLIN Work or Material Quantity Unit Unit Price Amount
SAMPLING
0001 Contaminated Surficial Soil Excavation, Disposal, Confirmation Monitoring and Sampling
50 EA $________ $________
0002 Oil Piping Demolition, Confirmation, Monitoring, and Sampling
200 EA $________ $________
0003 Sump and Floor Drain Confirmation, Monitoring, and Sampling
10 EA $________ $________
0004 Septic System Confirmation, Monitoring, and Sampling
10 EA $________ $________
0005 Remedial Completion Report LS $________
REMEDIATION
0006 Mobilization and Demobilization LS $________
0007 Community Involvement Plan LS $________
0008 Rock Mulch 40,640 SY $________ $________
0009 Piping and Sump/Floor Drain Liquids Collection and Disposal
1,200 GAL $________ $________
0010 Well Abandonment LS $________
0011 Septic System Removal LS $________
0012 ACM Oil Piping and Electrical Conduit Abatement, and Steel Water Piping
11,357 LF $________ $________
0013 Control Building Asbestos-Containing Material Abatement
4,870 SF $________ $________
0014 Concrete Structure Demolition 821 CY $________ $________
Amendment 2
SECTION B
SUPPLIES OR SERVICES AND PRICES
PROPOSAL SCHEDULE
MESA SUBSTATION SOIL REMEDIATION
CLIN Work or Material Quantity Unit Unit Price Amount
0016 Contaminated Soil Excavation and Disposal
2,693 BCY $________ $________
0016 Concrete Pad and Cable Trench Demolition
612 CY $________ $________
0017 Building Demolition LS $________
0018 Backfilling / Site Grading 4,592 BCY $________ $________
TOTAL $________
ABBREVIATIONS
CY = Cubic Yards EA – Each LF = Linear Feet LS = Lump Sum BCY = Bank Cubic Yards GAL = Gallon CLIN = Contract Line Item Number