Attachment L-1 Current PF Services SOWs.docx

DOCX document 39 KB Posted

Attached to
Request for Information-ESPC Technical Support Federal contract opportunity
Solicitation number
DE-SOL-0001279
Issued by
Department of Energy Headquarters

About this file

Solicitation Attachement L-1

View the file

Other files for this federal contract opportunity

Other files attached to Request for Information-ESPC Technical Support, newest first.
File Type Posted
Attachment L-4 PPIQ Cover Letter.docx DOCX document
Attachment L-2 PWS Template.docx DOCX document
Attachment L-5 Past Performance Reference Information Form.docx DOCX document
Attachment L-3 Base Year Task Order Workload Estimate.docx DOCX document
Attachment 1 Definitions and Acronyms.docx DOCX document
Attachment L-6 Past Performance Information Questionnaire.docx DOCX document
Solicitation_8-20-2010.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DE-SOL-0001279

Attachment L-1

ATTACHMENT L-1

CURRENT PROJECT FACILITATION SERVICES

STATEMENTS OF WORK

Table of Contents

CURRENT MASTER INDEFINITE DELIVERY / INDEFINITE QUANTITY CONTRACT STATEMENT OF WORK FOR PROJECT FACILITATION SERVICES2
SECTION C – DESCRIPTION/SPECS/WORK STATEMENT2
C.1. SPECIFICATIONS /STATEMENT OF WORK - TECHNICAL SUPPORT (PROJECT FACILITATION) SERVICES FOR IMPLEMENTATION OF ALTERNATIVELY FINANCED ENERGY PROJECTS AT FEDERAL FACILITIES2
C.1.1Background2
C.1.2Definitions2
C.1.3Purpose2
C.1.4.Scope of Work2
CURRENT ENERGY SAVINGS PERFORMANCE CONTRACT TASK ORDER STATEMENT OF WORK FOR PROJECT FACILITATION SERVICES5
Base Year - Line Item 001- Preliminary Assessment (P.A.)5
1st Option Year - IGA Development. IAA is required to proceed8
2nd Option Year - Final Proposal Development and Review9
3rd Option Year - Construction Period Support10
4th Option Year - First Measurement and Verification11
CURRENT FIELD VERIFICATION SITE REVIEW TASK ORDER STATEMENT OF WORK FOR PROJECT FACILITATION SERVICES12
I. SCOPE12
Section 1: Background12
Section 2: Statement of Work12
Preparation for Site Field Verification Review12
Conduct the Site Field Verification Review12
Final Report13

CURRENT MASTER INDEFINITE DELIVERY / INDEFINITE QUANTITY CONTRACT STATEMENT OF WORK FOR PROJECT FACILITATION SERVICES

SECTION C – DESCRIPTION/SPECS/WORK STATEMENT

C.1. SPECIFICATIONS /STATEMENT OF WORK - TECHNICAL SUPPORT (PROJECT FACILITATION) SERVICES FOR IMPLEMENTATION OF ALTERNATIVELY FINANCED ENERGY PROJECTS AT FEDERAL FACILITIES

C.1.1 Background The Energy Policy Act of 1992 and Executive Order 13123 directed the Department of Energy's (DOE) Office of Federal Energy Management Program (FEMP) to assist Federal agencies to leverage federal funds to implement energy efficiency, renewable energy and water conservation projects at federal facilities through use of private sector capital sources. To facilitate the identification and implementation of these projects, the FEMP Office provides technical expertise for alternatively financed energy project implementation at Federal facilities. To support the implementation of this directive, the DOE is developing training programs and materials, energy project data collection and analysis, and providing direct federal agency assistance to effectively participate in innovative financing and contracting mechanisms such as Utility Energy Service Contracts (UESC) and Super Energy Savings Performance Contracting (ESPC). This last initiative supports FEMP use of regional and technology specific “Super ESPC” and UESC contracts which are procurement vehicles for use by all federal agencies to streamline and accelerate alternatively financed project implementation. This effort is to provide assistance to FEMP in FEMP’s responsibilities to help Federal energy managers sort through the many energy options available and make the maximum use of their resources at minimal cost, in a wide variety of energy and water efficiency projects.

C.1.2 Definitions The terms Alternatively Financed/Alternative Financing/Financing Alternatives used herein refers to the statutory authority of federal agencies to enter into multiyear contracts for energy services, where the contractor incurs all upfront costs of surveying facilities, designing and installing energy efficiency retrofits or renewable energy projects, financing the contractor capital investment, and operating and maintaining contractor-installed equipment in federally owned buildings. The Federal government does not incur capital costs of energy projects but pays the contractor back out of annual utility cost reductions achieved by contractor-installed equipment. There are two primary alternatives for federal agency energy project private sector financing. The first is called Energy Savings Performance Contracting which is authorized by 42 U.S.C. 8287 allowing agencies a 25 year contracting authority for privately financed energy projects. The second is Utility Incentive Programs authorized by 42 U.S.C. 8256, where agencies can enter into multi-year contracts with serving utility companies for energy services. Alternative Financing is a term established by FEMP to encompass these activities. Alternative financing does not refer in any way to federal agency planning, programming, budgeting processes or other internal fiscal management and accounting practices.

C.1.3 Purpose The purpose of this contract is to procure technical expertise and support to FEMP to facilitate FEMP’s responsibility to assist federal agencies’ examination of ESPC and utility energy savings project options, and, when applicable, support implementation of alternative financing strategies for federal facilities’ energy projects. This facilitation role is extremely important in guiding the agency through a project from start to finish and assisting in the development of a good relationship between the agency, the ESCO, or the utility.

C.1.4. Scope of Work The scope of work is to provide assistance to support FEMP with technical assistance activities including project facilitation and analyses to support Federal agency implementation of alternatively financed energy and water conservation projects. Work to be performed shall consist of specific tasks which will be defined by the FEMP on an asneeded basis. When the DOE’s FEMP Office determines that there is a need for technical support under the terms of this contract, the DOE Contracting Officer’s Representative (COR) located at the appropriate DOE Regional Office will develop and provide the contractor a detailed scope of services which will define the needed result or deliverable for that particular assignment, and include the applicable project subtask number and title. All correspondence, time, and expenses related to the project will refer to the assigned name and subtask number. The COR will forward the requirement to the Contracting Officer for the generation and execution of the Task Order. The Contractor may begin work as soon as the Task Order is signed by the Contracting Officer.

The following areas shall encompass all the typical categories of tasks that may be undertaken:

Task Area 1. Analysis of Energy Savings and Economic Potential of Energy and Water Conservation Projects

Analysis of projects may include data collection, energy technology evaluation, energy load determination, economic analysis, recommended operations and maintenance procedures, and environmental improvements.

Task Area 2. Examine federal project funding and Alternative Financing strategies and recommend Implementation Approach

Funding alternatives may include examination of utility DSM options, impacts of utility restructuring, green power utilization, financing market analysis, or risk assessment of various implementation strategies.

Task Area 3. Collect and Develop Facility Energy Baseline Data

Energy baseline development may include development of metrics or performance indices, review of industry protocols and risk analysis and cost of performance measurement strategies.

Task Area 4. Assist Agency Selection of Facility Project Retrofit Strategies and Performance Requirements

Retrofit strategies may include technology evaluation and status of new technology deployment and commercialization for future opportunities. Other activities may include economic analysis of retrofits.

Task Area 5. Assist Agency with Development of Alternative Financing Procurement Documents

Task Area 6. Assist Agency During Procurement Process Technical Advice for Responses to Industry Questions, Proposal Evaluations, Negotiations, and Contractor Selection

Agency assistance throughout procurement process may include various market assessments, engineering and economic analyses to support agency evaluation and negotiation process as well as reviewing and monitoring regulatory requirements and liability issues to facilitate appropriate risk sharing for project success.

Task Area 7. Engineering and Economic Analysis, Reviews or Inspections During Project Design and Construction Phases

Task Area 8. Project Acceptance and Periodic Measurement and Verification (M&V) of Energy Savings Assistance with Super ESPCs and UESCs. Services may include a mid-year follow-up with the customer on the project.

Task Area 9. Operations and Maintenance Strategies to Ensure Persistence of Savings, where these strategies may include economic analysis.

Task Area 10. Program Outreach and Training Materials, Project Development Guidelines For Transferability of Project Experience to Other Sites

Program Materials and Guidelines tasks may include development, review and analysis of training, marketing, or other customer outreach materials; development of project tools and guidelines to improve project transferability within and among agencies; participation in DOE sponsored training workshops, industry forums, and conferences related to facilitating federal agency participation in alternatively financed projects.

Task Area 11. Other FEMP service and program related activities.

Other services related to the project facilitation services may include attendance at meetings, conferences, participation in M&V Summit, RO/PF Workshops as part of FEMP Services ESPC team, and other related working groups upon request by FEMP HQ.

CURRENT ENERGY SAVINGS PERFORMANCE CONTRACT TASK ORDER STATEMENT OF WORK FOR PROJECT FACILITATION SERVICES

Base Year - Line Item 001- Preliminary Assessment (P.A.)

Task#
Task Title
PF Work Scope
Deliverable
Agency Requirements
1
Energy Savings Potential Assessment
The PF shall analyze available site energy consumption and program information to determine if the Agency specified project site is a good candidate for an ESPC. The PF will provide recommendations as needed to improve project economics for ESPC projects and/or recommend other project implementation strategies. PF will coordinate with NREL to support the agency assembly of preliminary data (screening) for the application of renewable energy and advanced technologies.
Telecon advice and recommendations
Agency will provide site data requested by the PF. Typical data requested is 1-2 years of monthly utility bill, past audits, building list and maintenance records, facility condition assessments. For renewable energy/advanced technology screening the requirement is annual consumption and rates for all energy sources.
2
Needs Assessment & Project Scoping
The PF shall visit the site to establish a working relationship with the site representatives and become familiar with the infrastructure. The PF shall provide telecon advice and consultation to identify Agency resource requirements for project success. Provide recommendations for scope of project to match Agency resources and project requirements with goals/objectives.
Site visit, telecon advice and recommendations
Agency or site energy program/project manager provides the PF draft keypoints of Agency site Requirements (e.g. specific equipment retrofits, improve facility operating conditions) including envisioned project scope (e.g. number of buildings, total square footage, annual energy costs, utility rates) for discussion.
3
Establish Program Objectives and Project Strategy Development
The PF shall provide telecon advice and consultation to support Agency establishment of project requirements/program objectives. The PF shall stress the importance of the risk, responsibility and performance matrix.
Telecon advice and comments on proposed project implementation strategy
Agency develops initial plan and objectives for energy project implementation for review by the PF. Coordinates with key acquisition team members (e.g. Agency/site Contracting Officer) telecons with the PF and DOE ESPC Contracting Officer's Representative to discuss energy project acquisition strategies.
4
Acquisition Team & Other Agency Support Organizations
The PF shall provide telecon advice and background on DOE ESPC TO process and Agency benefits & risks. On site briefing may be provided if required to gain acquisition team commitment to project. On site briefing will be provided when most acquisition team members and decision makers involved in Agency project implementation commitments are present.
DOE ESPC contract process review and site visit to coordinate the requirements in this task and task #5.
Identify and assign personnel to Agency acquisition team. Establish Agency reviewers and decision makers. Distribute and communicate DOE ESPC materials to acquisition team members. Coordinate facility and maximum acquisition team attendance at meeting if held.
5
Goals: Building Agency / Site Understanding, Support and Commitment
The PF shall provide telecon advice and guidance to help establish project goals and objectives for promoting the project within the agency. The PF quote to the Golden Field Office shall include a trip to the site to support the requirements of tasks #4 and #5.
Written Comments and Recommendations. On site briefing and project development meeting with agency acquisition team and discuss pre PA kick-off action plan.
Identify and assign personnel to Agency acquisition team. Establish Agency reviewers and decision makers. Develop and distribute to Agency acquisition team and the PF all proposed project goals, objectives and benefits for review and comment. Coordinate facility and maximum acquisition team attendance at meeting if held.
6
ESCO Selection Support
The PF shall coordinate initial discussions of planning for ESCO selection between the site and the Golden Field Office.The PF shall provide telecon advice and draft written recommendations to help establish project summary descriptions, requirements, goals, objectives and evaluation criteria for ESCO selection. PF may suggest project relevant questions that the site could use in ESCO interviews.
Written recommendations, requested review comments and on site technical support for agency process of ESCO Selection, such as ESCO interviews and or presentations .
Identify and assign personnel to Agency acquisition team to support ESCO Selection. Agency CO leads the process which may include some written ESCO proposal material and ESCO interviews. Establish Agency reviewers and decision makers for evaluation and ESCO selection. Notify DOE ESPC CO of ESCO selection and request support as needed, on notifying selected ESCO for PA development.
7
Requirements Document Development
The PF shall coordinate with GO to assist the site in drafting the technical elements of the agency's anticipated requirements document or statement of objectives. This task includes a 1-2 day site visit. This task will also include suggestions for the development of evaluation criteria.
Verbal and written recommendations for content of agency requirements document, or statement of objectives, evaluation criteria and trip to the site.
Agency will assemble all applicable site information. Agency acquisition team will be available for meetings with the project facilitator to develop a requirements document or statement of objectives and develop ESCO evaluation criteria.
8
Contractor Site Visit Support (IF REQUIRED)
The PF shall assist the agency in organizing a site visit for prospective ESCO(s). The PF shall assist the site with the coordination of the evaluation criteria and the areas of the site that should be included in the meeting at the site with the interested ESCOs. The PF shall assist the site with responses to contractor questions.
Participate in preparing for the site visit and meeting with prospective ESCOs.
Agency will assemble all applicable site information. Agency will coordinate the logistics for the ESCO site visit and meeting with interested ESCOs.
9
Contractor Debrief Support (IF REQUIRED)
The PF shall provide technical suggestions to the site for preparation of debriefing materials with the non- selected ESCOs (up to 15).
Provide technical consultation to the site for debriefing discussions with non-selected ESCOs.
Agency will prepare debriefing remarks/points for each ESCO to be debriefed.
10
Overview & Preliminary Development of TO RFP
The PF shall provide the site with an overview and discussion of the TO RFP prescriptive format and advice for agency development of a site-specific TO RFP.
Provide TO RFP prescriptive format and review with agency at or after the PA kickoff meeting.
Agency will coordinate a 30-minute meeting with agency contracting and technical personnel before or after kickoff meeting. Agency will designate agency POC responsible for development of TO RFP. Agency POC will coordinate TO RFP development telecons with the PF.
11
Preliminary Assessment Review
The PF shall review up to sixteen (16) Preliminary Assessments(s) against format and evaluation criteria cited in the ESPC master IDIQ. The PF shall critically review Preliminary Assessments(s) for content of critical elements such as, the general description of the M&V plan and risk, responsibility and performance matrix. If required, the PF shall prepare comments for the site to submit to the ESCO and travel to the site to in the evaluation of the ESCO's response to the comments. The PF's quote to the golden Field Office shall provide for the review of sixteen (16) PAs.
Telecon and oral advice and/or written comments/ recommendations. The PF quote to the Golden Field Office shall include a trip to the site to complete and coordinate the comments, and provide technical advice to the site.
Agency will provide the PF copies of PA(s). Agency will ensure that applicable acquisition team members review the PA(s) and generate agency/site specific questions or issues prior to scheduled telecons with FEMP Services staff.
12
PF Reporting
The PF shall provide reports as required by their master IDIQ contract and input data into an electronic database monthly, currently referred to as FEMP Central.
Monthly reports and electronic database entries.
13
TO RFP Development - Direct Support
Based upon interviews with site staff and consultation support, the PF shall prepare two drafts of the TO RFP for the site, as follows. The PF shall normally provide onsite review of the first draft TO RFP with site staff as a part of the IGA kickoff. The PF will prepare a 2nd draft TO RFP based on telecon and written site review comments and recommendations. (Note: the PF is allowed the discretion to have the second draft ready for on-site review at the IGA kickoff meeting.)
Two drafts of the TO RFP document. On site review of one draft TO RFP as a part of the IGA kickoff meeting.
Agency staff will be made available for interview and consultation. Agency staff will review draft TO RFP and provide comments to the PF for inclusion into 2nd draft TO RFP document. Agency will revise the second draft TO RFP, as required, for submission to the DOE COR and ESCO. Agency will provide copy of final TO RFP to DOE Golden Field Office.
14
TO Intent to Award Letter Support
The PF shall assist the agency with drafting the Letter of Intent to Award to selected ESCO.
Template, telecon advice and/or written comments.
Agency prepares selection decision documentation and intent to award letter.
15
IGA Kickoff Meeting Support
The PF shall facilitate the IGA kickoff meeting with the site and ESCO (including development of the agenda) to establish roles, responsibilities, expectations, timelines, communications protocol, and coordination of review processes for draft proposals.
Facilitate a one day meeting between agency and ESCO at the project site.
Agency will coordinate the scheduling of the meeting with both the ESCO and the PF, and arrange for appropriate meeting space. Key members of agency acquisition team will attend and provide required data.
16
PF Reporting
The PF shall provide reports as required by their master IDIQ contract and input data into an electronic database, currently referred to as FEMP Central and any other reporting requirements required by the American Recovery and Reinvestment Act of 2009.
Reports and electronic database entries.

1st Option Year - IGA Development. IAA is required to proceed

Task #
Task Title
Work Scope
Deliverable
Agency Requirements
17
IGA - Project Technical and Financial Analysis - Consultation Support
The PF shall participate in periodic project telecons and on site meeting(s) to assist the agency in achieving agreement with the ESCO on feasible ECMs, establishment of facility baseline conditions, and establishment of a site-specific Measurement and Verification (M&V) Plan based on the IGA and the Preliminary Assessment. The PF proposal to the GFO shall include a trip to verify critical site conditions and to assist with the review of an advanced or draft of the IGA.
Telecon advice and/or written comments/ recommendations. One trip to the site.
Agency or ESCO will provide the PF copies of the IGA or preliminary copies of IGA data generated by the ESCO. Agency will ensure applicable acquisition team members review the IGA or draft information and generate agency/site specific questions or issues prior to scheduled telecons.
18
PF Reporting
The PF shall provide reports as required by their master IDIQ contract and input data into an electronic database, currently referred to as FEMP Central and any other reporting requirements required by the American Recovery and Reinvestment Act of 2009.
Reports and electronic database entries.

2nd Option Year - Final Proposal Development and Review

19
Final Proposal Review
The PF shall review the final proposal against format and evaluation requirements cited in the TO RFP. The PF shall closely review the proposed M&V Plan for implementability and auditability. The PF quote to the Golden Field Office shall include a trip to the site to assist in the coordination of comments to the ESCO.
Telecon advice and/or written comments/ recommendations and one trip to the site.
Agency or ESCO will provide the PF a copy of the ESCO final proposal. Agency will ensure applicable acquisition team members review final proposal and generate agency/site specific questions or issues prior to scheduled telecons.
20
Assist Agency with Technical and Price Negotiations up toTask Order Award - Consultation Support
The PF shall provide suggestions for the development of the technical and price negotiation approach and strategy. Provide technical advice and recommendations for agency negotiations, such as advice on opportunities and options, and alternatives to achieve a negotiated agreement. This includes the review of a second submittal of the final proposal, if applicable. The PF quote to the Golden Field Office shall include a trip to the site to provide consultative support during negotiations. The trip shall only be taken if requested by the site.
Telecon advice and/or written comments/ recommendations on the Final Proposal and negotiations. One trip to the site as requested by the site to provide consultative support for the negotiations.
Agency or ESCO to provide copies of first and second, if applicable, versions of the ESCO's technical and price proposals to the PF for review and coordinate telecons with agency Contracting Officer and PF to discuss and review negotiation strategy recommendations.
21
Assist Agency with Revisions to TO RFP to create the TO Award documents
The PF shall provide guidelines and recommendations to agency staff for revising the TO RFP text to match agreements from negotiations of Final Proposal. The objective is to remove solicitation text to convert TO RFP into a TO award document.
Provide guideline, to agency CO and staff, of TO RFP sections to be revised prior to TO award to agency CO.
Agency revises TO RFP requirements to match agreements reached from negotiations and Final Proposal. Include recommended technical TO RFP revisions submitted by the PF in previous task.
22
PF Reporting
The PF shall provide reports as required by their master IDIQ contract and input data into an electronic database, currently referred to as FEMP Central and any other reporting requirements required by the American Recovery and Reinvestment Act of 2009.
Reports and electronic database entries.

3rd Option Year - Construction Period Support

23
Post-Award Kickoff Meeting Support
The PF shall participate in Post-Award kickoff meeting with the site and ESCO to establish construction roles, responsibilities, expectations, milestones, communications protocol, and submittal review process. Support discussion of schedules from TO award through project acceptance and related unique agency contract administration activities.
Telecon comments and recommendations. Trip to site to participate in the Task Order kickoff meeting.
Agency will coordinate and host meeting with ESCO. Coordinate maximum attendance of agency acquisition team, affected facility/building managers, design, engineering, and construction/service contract oversight/inspection team (e.g. environmental, safety and health staff), project facilitator, ESCO design, ESCO engineering, and ESCO construction team. Agency commitment to notify the PF when technical support is needed to Project Acceptance/M&V and 1st year M&V report review required.
24
Installation period support
The PF shall provide consultation and technical support to the site during the ECM installation period (commissioning). The PF shall be available to answer questions developed by the site's construction program personnel including the review of submittals, review of contractor's installation plans (commissioning plans), and provide guidance on Government witnessing.
PF proposals shall include one trip to the site to support these activities.
25
Post-Installation M&V Report Review and Project Acceptance Recommendations
The PF shall provide consultation and technical review of the contractor-generated Post-Installation M&V report (may include commissioning TO documentation or report if agency requested in TO RFP) following installation and acceptance testing of all ECMs for: a) compliance with TO M&V plan and, if required, commissioning plan; and b) review for verification that installed ECMs demonstrate the potential to achieve the contracted annual ECM savings. The PF shall provide suggestions for compliance with the DOE Guides for witnessing. The PF will provide written recommendations relating to ECM savings potential for project acceptance. The PF quote to the golden Field Office shall incude a trip to the site for this task.
Telecon advice and/or written/oral comments.

Documented Project Acceptance recommendations.

Agency or ESCO will provide the PF a copy of Post-Installation M&V Report (include commissioning plan and commissioning TO documentation or report, if required in TO) for review. Agency is responsible for construction inspection, performance verification testing, witnessing and acceptance of ECM equipment installation in accordance with TO. The agency will inspect/observe post-installation system/equipment tests pursuant to TO M&V plan and commissioning plan, if specified in TO. The agency will review post-installation M&V report and commissioning report (if required by TO) submitted by ESCO and generate comments, questions and issues for PF technical advice. The agency will provide the PF copies of comments. questions, issues, generated by agency staff.

26
PF Reporting
The PF shall provide reports as required by their master IDIQ contract and input data into an electronic database, currently referred to as FEMP Central and any other reporting requirements required by the American Recovery and Reinvestment Act of 2009.
Reports and electronic database entries.

4th Option Year - First Measurement and Verification

27
First year operations support
The PF shall maintain working contact with the site during the first year of operations to provide the site with assurance that technical support is available. Activities that the site may require support with during this period include invoices, training, and change order evaluation.
28
1st Year M&V Report Review / Annual Energy Audit Technical Assistance
The PF shall provide assistance and review of the first annual M&V report as required by M&V plan in the Task Order. The PF quote to the Golden Field Office shall include a trip to the site to support this task.
Telecon advice and/or written comments/ recommendations and one trip to the site.
Provide copies of first annual M&V report to the PF. The agency will review the Annual M&V report and generate comments, questions, or issues for PF technical advice. Coordinate PF and acquisition team telecons. Submit agency recommendations to ESCO for action.
29
PF Reporting
The PF shall provide reports as required by their master IDIQ contract and input data into an electronic database, currently referred to as FEMP Central and any other reporting requirements required by the American Recovery and Reinvestment Act of 2009.
Reports and electronic database entries.

CURRENT FIELD VERIFICATION SITE REVIEW TASK ORDER STATEMENT OF WORK FOR PROJECT FACILITATION SERVICES

I. SCOPE

Section 1: Background

The DOE/EERE Golden Field Office (GO) issues and administers Indefinite Delivery Indefinite Quantity Energy Savings Performance Contracts (ESPCs) for use by all Federal agencies. Over 250 Delivery Orders have been issued against these contracts by agencies since 1998. Delivery Orders can have terms up to 25 years. The DOE/GO Federal Energy Management Program (FEMP) provides Project Facilitation assistance to help agencies develop ESPC delivery orders. Assistance is provided up to the first year (one year post construction acceptance) Measurement and Verification (M&V) report.

DOE FEMP and GO have determined there is a need to verify project performance and assist agencies beyond the first year M&V, through the entire term of the Delivery Order projects. FEMP and GO are initiating this effort, known as Life of Contract Service, with field verification project reviews at agencies with delivery orders which are at, or beyond, the second year post construction acceptance performance period annual M&V report.

Section 2: Statement of Work

The Project Facilitators shall perform Site Field Verification Reviews at selected siteswhich, for each site, consist of:

Preparation for Site Field Verification Review

1. Review of the Final Proposal documents including the ECMs, ESCO Management Approach, Risk & Responsibility Matrix, Commissioning Plan, Measurement and Verification Plan, and the annual M&V reports (up to 8), in preparation for the site visit to determine the task order project requirements. The documents will be provided by DOE GO, at least two weeks prior to the site visit. Documents may be provided with less than two weeks notice if agreed to by the PF.

Conduct the Site Field Verification Review

1. Conduct an In-Briefing with Site Staff – Review the site visit agenda and goals, with site personnel to kick off the site review and set expectations. The kickoff will include overview discussions with site staff on the status, performance and management of the site project. The agenda and goals will be developed by DOE and the PF.

Through discussions with site staff and inspection of a representative sample of installed measures:

2. Assess Energy Conservation Measure (ECM) Performance – Determine if measures are installed and performing as specified in the Delivery/Task order. Determine if there have been any issues or problems with equipment or performance. Determine ECM aspects or technologies which are particularly performing well. Provide summary feedback to the site in the out briefing, including comment on potential plans to address performance issues. Provide a written description of the ECM assessment in the final report.

3. Assess the Operation, Preventive Maintenance (PM), and Repair/ Replacement (R/R) of ECMs. Determine if performance is consistent with Delivery Order/Task Order requirements. Determine who is performing these tasks, if training was performed by the ESCO (if required), and if records are up to date. Assess the overall performance and if there are/have been issues and any needed corrective actions. Determine aspects which are particularly working well. Provide summary feedback to the site in the out briefing. Provide a written description of general issues in the final report.

4. Assess the M&V of ECMs. Determine if M&V Reports are up to date, if they are consistent with the M&V Plan in the Delivery order, if measurements are required and being done, if savings guarantees are being met, if savings are persistent, and the status of Government witnessing. Assess the overall performance and if there are/have been issues and any needed corrective actions. Determine aspects which are particularly working well. Provide summary feedback to the site in the out briefing. Provide a written description of the M&V assessment in the final report. Provide comments on the adequacy of the M&V plan and its value to the project in the final report.

5. Determine if there have been issues with site or ESCO personnel turnover, measure or building use changes, or any other unanticipated events which have impacted the project. Refer questions or requests for assistance on these or any other Delivery Order contract administration issues to DOE GO.

6. Conduct On – Site O&M / M&V refresher training. Training requires approximately 1.5 hours. Training content will be provided DOE GO at least two weeks prior to the site visit.

7. Conduct an out-briefing with site staff. Provide summary feedback to site staff on overall results of the Site Field Verification Review including the ECM assessment, Operation, PM, and R/R assessment, M&V assessment, and general observations, issues, and question referrals. Out-briefing material shall be in the form of a Power Point, or equivalent, presentation format. An electronic version shall be provided to the site at the time of the out-briefing, and DOE GO within two calendar days of the out- briefing.

Final Report

8. Provide a written report to DOE GO describing the conduct, assessments, and findings of the Site Field Verification Review. Contents will include the site, date and time of visit, name of PF(s), listing of participating agency, DOE GO, FEMP and contractor personnel involved, a summary of the conduct, assessments, and findings of the site review, details of the conduct, assessments, and findings of the site review, a summary of site feedback, referral questions, and potential actions to address issues or improve Delivery Order/Task Order administration for the remainder of the performance period, and conclusions. Include a separate section with recommendations for improvement in Delivery Order/Task Order project management and contract administration at the site level, IDIQ contract level, or FEMP program level, based on observations from the site review. DOE GO expects the length of the Final Report to be no more than 10 pages in length. The Final Report is due to DOE GO two calendar weeks after the conclusion of the field Site Field Verification Review.