Design Build Advertisement 24228.pdf
PDF 92 KB Posted
- Attached to
- 751/24228. SAA; Various Locations- Solar Arrays
- Solicitation number
- RFQ 171 250000000414 4
- Issued by
- Washtenaw County, Burt CDP, Michigan
About this file
This is a Design Build Project Advertisement issued by the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration, Design & Construction Division, for the Department of Natural Resources (DNR). The project requests a Design Build Entity (DBE) to provide design and construction services for solar array installations across five locations: DNR Cadillac Customer Service Center, DNR Traverse City Customer Service Center, DNR Gaylord (both Repair Center and Customer Service Center), and DNR Escanaba. The scope includes feasibility studies, placement analysis, design, and construction of new solar arrays with targeted annual energy generation of 110% (32 kW) at Cadillac, 20 kW at Traverse City, 32 kW and 16 kW at Gaylord, and 31 kW at Escanaba. Services required include topography surveys, ground penetrating radar for utility location, push-pull testing, soil borings, structural analysis for roof-mounted installations, and submission of 50% and 90% design review drawings for owner approval. A mandatory pre-proposal meeting is scheduled for 9:00 AM on Thursday, May 15, 2025, via Microsoft Teams, requiring RSVP by 2:00 PM on May 14, 2025. Bids are due Wednesday, May 28, 2025, at 2:00 PM Eastern time, with State Ad Board contract approval anticipated June 23, 2025, and construction commencing in August 2025, with substantial completion targeted for January 3, 2026.
Bid security of 5% is required for submission through the SIGMA VSS online system, with a maximum of two attachments (each under 25 MB) permitted. The contract will be a single award covering all four primary sites, with the Traverse City site designated as a deduct alternate. The DBE must maintain State Project Registration (SPR) and comply with all prevailing wage requirements. All design and construction work must adhere to state and local codes, including SESC and EGLE regulations, with sealed plans submitted to LARA for plan review and permits. The project includes requirements for twice-monthly progress meetings during construction, underground electrical connections for ground-mounted locations, and coordination with local utility companies for interconnection. Questions must be submitted by email to Sheryl Ananich at ananichs@michigan.gov no later than 2:00 PM Eastern on Thursday, May 22, 2025. Project documentation and bid results are available through the SIGMA procurement system at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Gaylord CSC 4.jpg | JPG image | |
| Consumers Cadillac FY24.pdf | ||
| Gaylord CSC 3.jpg | JPG image | |
| Cadillac 3.jpeg | JPEG file | |
| Cadillac 4.jpeg | JPEG file | |
| Gaylord CSC 1.jpg | JPG image | |
| Cadillac 2.jpeg | JPEG file | |
| Consumers Cadillac FY25.pdf | ||
| Cadillac Site Diagram.pdf | ||
| Esc. Dist. Offic Bldg. and Maintenance Garages.pdf | ||
| CHERRYLAND T.C. FY24.pdf | ||
| Escanaba Site Diagram.pdf | ||
| Gaylord CSC 2.jpg | JPG image | |
| Escanaba 3.jpg | JPG image | |
| Cadillac 1.jpeg | JPEG file | |
| Design Build (Rev03-2025).pdf | ||
| Escanaba 1.jpg | JPG image | |
| CHERRYLAND T.C. FY25.pdf | ||
| Escanaba 2.jpg | JPG image |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0415 (R 9/24)
DESIGN BUILD PROJECT ADVERTISEMENT
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
STATE FACILITIES ADMINISTRATION
DESIGN & CONSTRUCTION DIVISION
This form is required for the advertisement of all construction projects. (1984 PA 431)
DTMB FILE NO.
751/24228.SAA
DATE
Monday, May 12, 2025
ADVERTISEMENT DATE
May 12, 2025 – May 28, 2025
BID DUE DATE
Wednesday, May 28, 2025 @ 2:00 p.m. EASTERN time
PROJECT NAME AND LOCATION (INCLUDE STREET ADDRESS)
Department of Natural Resources – Finance and Operations Division – Solar Arrays:
DNR Cadillac Customer Service Center, 8015 Mackinaw Trail, Cadillac, MI 49601 DNR Traverse City Customer Service Center, 2122 M-37, Traverse City, MI 49685 DNR Gaylord, 1732 M-32, Gaylord, MI 49735 DNR Escanaba, 6833 US-2, Gladstone, MI 49837
WALK-THROUGH INSPECTION DATE, TIME, AND LOCATION
A MANDATORY PRE-PROPOSAL MEETING will be conducted at 9:00am on Thursday, May 15, 2025, via a Teams meeting.
Please RSVP to the DTMB-DCD Director prior to 2:00pm on May 14, 2025, and the Project Director will send a Teams meeting link to join the meeting.
MANDATORY Yes No
NOTE: An individual is only permitted to represent one bidder at a mandatory walk-through.
DESCRIPTION OF WORK:
Requesting a Design Build Entity (DBE) to provide services for a study for proposed placement, design and construction of a new solar array at the 4 site locations listed above (plus an additional location at the Repair Center at Gaylord, for a total of 5 locations). Solar panels will be added at each site noting points of interconnect, PV concept, and addressing possible utility location conflicts. Traverse City site to be a Deduct Alternate.
Additional Considerations:
• Ground penetrating radar may be needed to locate existing utilities
• There will be one contract issued for all 4 sites
• All sites will need field verification
• Include topography survey, push-pull testing and soil borings as needed to perform the work
• Target design goals for energy are as follows: Cadillac (target 110% 32 kw annually) Traverse City (20 kw annual utility limit) Gaylord (32 kw Repair Center / 16 kw CSC) Escanaba (31 kw)
• The connection of new service to the existing service shall be underground for ground mounted locations.
DBE to work with local utility company for electrical interconnection
• DBE to provide all items necessary for design and construction, including grading and soil considerations, foundation design, solar array design targeted goals
• DBE to submit 50% and 90% contract document design review drawings for owner review 7 days prior to review meeting. Virtual Teams meetings are acceptable for document review.
• DBE to provide updated schedule at each meeting
• DNR will be responsible for the demolition of any trees, if needed
• All solar arrays are assumed to be located on the roof with the exception of Cadillac, and possibly Escanaba.
Roof mounted panels will require the existing structure will support the solar panel load. This will require a structural analysis at each building.
• Include time for team meetings – twice a month progress meetings are required during the construction phase. Virtual Teams meetings are acceptable.
• Meet State and local codes including SESC and EGLE as required. Submit sealed plans to LARA plan review and permits.
• State Project Registration (SPR) is required. SPR registration information (including Online Certified Payroll Submission through LCP Tracker) is at: LEO - Prevailing Wage
During the term of the contract, the Design Build Entity must maintain a current and valid SPR.
• Additional requirements as outlined in the Design Build Contract
Proposed project schedule:
May 28, 2025, Bids Due June 23, 2025, State Ad Board contract approval July 7, 2025, Design Build Entity under contract August 2025 construction to commence January 3, 2025, Substantial Completion
Attachments:
Site Diagrams FY24 & FY25 Utility bills Escanaba Existing Prints Gaylord Site Existing Prints Electrical panel photos
Please NOTE:
• Bid responses and bid attachments MUST be uploaded to SIGMA VSS.
• Contractors should only submit a maximum of two (2) attachments (both being less than 25 MB) for bid responses. One attachment is to be bid documents (i.e., Bid Summary, Bid Schedule, Bid Bond, Certification forms, Signature Authority, etc.) and if applicable, the other attachment should be Qualified Disabled Veteran (QDV) information (DD214, Proof of 51% Ownership and Proof of Service-Connected Disability).
•• Do not wait until just before the 2:00 p.m. solicitation deadline to submit your bid response. SIGMA VSS will not allow a proposal to be submitted after 2:00 p.m., even if a portion of the bid response has been uploaded.
•• If you experience issues or have questions regarding your electronic submission, you must contact the SIGMA Help Desk for assistance prior to the 2:00 p.m., solicitation deadline. You may contact the SIGMA Help Desk by telephone at 517.284.0540 or toll-free at 888.734.9749.
You may also email the SIGMA Help Desk at sigma-procurement-helpdesk@michigan.gov
• Please email the Design and Construction Contract Specialists if you are having SIGMA VSS issues. Please include your SIGMA ticket number and any supporting documentation (i.e., screenshots) to Anne Watros (WatrosA@michigan.gov) and Don Klein (KleinD4@michigan.gov).
• You may be asked by our contract specialists to email your bid response. Emailed submissions will require DCD approval and will be handled on a case-by-case basis.
• Approved emailed submissions MUST be received prior to 2:00 p.m. deadline to be considered responsive and responsible.
• Bid Responses should not be emailed to the Project Director.
5% BID SECURITY REQUIRED
mailto:sigma-procurement-helpdesk@michigan.gov mailto:WatrosA@michigan.gov mailto:KleinD4@michigan.gov
NIGP CODES: 90625, 90628, 90692, 90921, 92531, 92533, 90524, 92578, 92595, 91016, 91438
ACCEPTING QUESTIONS UNTIL:
Please do not submit online questions via SIGMA VSS. ALL questions should be emailed to Sheryl Ananich at ananichs@michigan.gov address no later than 2:00 p.m., Eastern on Thursday, May 22, 2025.
REFERENCE STANDARDS: This project will comply with all codes, standards, regulations, and workers’ safety rules that are administered by federal agencies (EPA, OSHA and DOT), state agencies (DHHS, EGLE, DNR, and MIOSHA), and any other local regulations and standards that may apply.
Documents & Bid Results may be obtained from:
https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService
Project Director: Sheryl Ananich
Address: 3111 W St Joseph Street, Lansing, MI 48917
Phone: (517) 243-7605
Email: ananichs@michigan.gov
Approved by: Sheryl Ananich mailto:ananichs@michigan.gov https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService
File details come from the government source that posted it. Updated .