DescriptionOfWork.pdf
PDF 128 KB Posted
- Solicitation number
- 1240LT24R0023
About this file
This document is a Description of Work for a Cattle Guard Replacement contract within the San Juan National Forest in southwest Colorado. The contractor will be responsible for purchasing and installing new pre-cast concrete cattle guard bases and steel running surfaces, as well as disposing of the removed materials off federal land. The work will take place across the Dolores and Columbine Ranger Districts on gravel surfaced Level 3 and 4 roads, with the majority of projects within a 2-hour drive from Durango, Colorado. The typical operating season is May 1 to November 30, with work required to avoid freeze-thaw conditions. The contractor will furnish all labor, equipment, and traffic control necessary to complete the work. Payment will be made based on unit prices for mobilization, removal and disposal of existing cattle guards, aggregate base, and installation of new cattle guards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ColumbineCattleGuard_AS_signed Maps.pdf | ||
| Wage Determination.pdf | ||
| FSSS.pdf | ||
| StandardSpecList.pdf | ||
| Schedule of Items Columbine.xlsx | XLSX spreadsheet | |
| DoloresCattleGuard_AS_signed Maps.pdf | ||
| 1240LT24R0023.pdf | ||
| Schedule of Items Dolores.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESCRIPTION OF WORK FOR CATTLE GUARD REPLACEMENT
SCOPE OF WORK
THIS CATTLE GUARD REPLACEMENT CONTRACT LOCATED WITHIN THE SAN JUAN
NATIONAL FORESTS IS INTENDED TO REPLACE NON-FUNCTIONAL CATTLE GUARDS
ACROSS THE DOLORES AND COLUMBINE RANGER DISTRICTs (SEE ATTACHED ROAD
LISTING). CONTRACTOR WILL BE RESPONSIBLE FOR PURCHASING AND INSTALLING
CATTLE GUARD BASES, RUNNING SURFACES AND WINGS AS WELL AS DISPOSING OF
THE REMOVED MATERIAL OFF OF FEDERAL LAND. BEDDING MATERIAL AND
APPROACH AGGREGATE WILL BE REQUIRED WITH EACH CATTLE GUARD. MINOR
FENCE WORK MAY BE REQUIRED TO TIE THE RANGE ALLOTMENTS INTO THE WINGS.
TRAFFIC CONTROL WILL BE THE RESPONSIBILITY OF THE CONTRACTOR WITH DELAYS
NOT EXCEEDING ½ HOUR.
TERRAIN ACROSS THE FOREST VARIES BETWEEN FLAT MESA TOPS AND STEEP
WINDING MOUNTAIN ROADS. THE MAJORITY OF THIS WORK WILL OCCUR ON GRAVEL
SURFACED LEVEL 3 AND 4 ROADS AS DEFINED IN FSH 7709.58, 12.3. ALL PROJECTS
CAN BE REACHED WITHIN A TWO HOUR DRIVE FROM DURANGO, COLORADO. TYPICAL
OPERATING SEASON IS MAY 1 – NOV. 30. OPERATIONS SHALL AVOID FREEZE THAW
CONDITIONS AND TIMING SHOULD BE APPROVED BY THE CO.
PROJECT LOCATION
THIS WORK IS LOCATED THROUGHOUT THE SAN JUAN NATIONAL FOREST IN
SOUTHWEST COLORADO BETWEEN DOVE CREEK AND WOLF CREEK.
DISPOSAL OF STRUCTURES
OLD CONCRETE BASES AND OLD POSTS WILL BE PROPERLY DISPOSED OF
OFF OF NATIONAL FOREST LANDS. CONTRACTOR HAS THE OPTION OF
LEAVING STEEL RUNNING SURFACES ON SITE TO BE REMOVED BY THE
FOREST SERVICE. DISPOSAL WILL BE PAID FOR UNDER PAY ITEM 203.
CATTLE GUARD INSTALLATION
THE WORK AS OUTLINED WILL CONSIST OF CONCRETE CATTLE GUARD BASES
AND STEEL RUNNING SURFACES AT PREDETERMINED LOCATIONS ACROSS
THE SAN JUAN NATIONAL FOREST. CONTRACTOR WILL REPLACE CATTLE
GUARDS WITH PRE-CAST BASES AND STEEL RUNNING SURFACES. CATTLE
GUARDS SHALL BE PURCHASED FROM BIG R MANUFACTURING, ABC
CONCRETE OR APPROVED EQUAL. LENGTH WILL BE THE STANDARD 7’-9” AND
NOT THE BLM 8’ LENGTH. WIDTHS HAVE BEEN DETERMINED ON THE
ATTACHED SPREADSHEET. CONTRACTOR SHALL CONTROL OPERATIONS TO
ENSURE TO PREVENT DAMAGE TO PROPERTY, STRUCTURES, AND TRAFFIC.
WORK HOURS WILL BE BETWEEN 7:00 A.M. MONDAY TO 7:00 P.M. - FRIDAY,
EXCLUDING FEDERAL HOLIDAYS, UNLESS OTHERWISE AGREED TO IN
WRITING.
CONTRACTOR WILL FURNISH ALL LABOR, EQUIPMENT, TOOLS,
TRANSPORTATION, TRAFFIC CONTROL, SUPPORT VEHICLES AND SUPPLIES
NECESSARY TO COMPLETE THE WORK ACCORDING TO THE SPECIFICATIONS
AND AS SHOWN ON THE DRAWINGS.
ANY ROTTEN OR BROKEN POSTS ON THE SIDES OF THE CATTLE GUARDS WILL
NEED REPLACEMENT.
CATTLE GUARDS THAT SPAN ONLY ½ THE ROAD WIDTH AND HAVE AN
ASSOCIATED BYPASS GATE WILL REQUIRE THE INSTALLATION OF 2 6”X6”X8’
TREATED TIMBER POSTS TO PREVENT MATERIAL FROM SLOUGHING INTO THE
CATTLE GUARD. INSTALLATION WILL BE PAID FOR UNDER PAY ITEM 619.
AGGREGATE
1 INCH MINUS STRUCTURAL BACKFILL SHALL CONFORM TO TABLE 703-2
TARGET VALUE RANGES FOR SUBBASE AND BASE GRADATION. THIS ITEM WILL
BE PAID FOR UNDER PAY ITEM 301.
PAYMENT
THE ACCEPTED QUANTITIES WILL BE PAID FOR AT THE CONTRACT UNIT PRICE
FOR EACH PAY ITEM SHOWN IN THE SCHEDULE OF ITEMS.
PAYMENT WILL BE MADE UNDER:
PAY ITEM PAY UNIT
151 – MOBILIZATION……………………………………………..LS.
203 – REMOVAL OF CATTLE GUARDS AND CONCRETE BASES,
DISPOSAL METHOD 203.05(a)………………………….LS.
301 – AGGREGATE BASE, GRADING 1”-MINUS PI 2-9…….TON.
619 – CATTLE GUARDS………………………………………….EA.
File details come from the government source that posted it. Updated .