Demo Bldg 8124_ AF66.xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- Demolition of Building 8124 Federal contract opportunity
- Solicitation number
- FA5000-22-Q-0023
About this file
This document contains a schedule of material submittals and a solicitation for the demolition of Building 8124 located on Joint Base Elmendorf-Richardson in Alaska.
The schedule of material submittals outlines 19 items requiring submission at various dates prior to or during contract performance. These include plans for hazardous communication, environmental protection, lead and asbestos abatement if needed, utility disconnections, hazardous material sampling and training records. Daily reports, safety data sheets, medical certifications if needed, landfill approvals and testing laboratory information are also required.
The solicitation seeks offers for the demolition of Building 8124 to include all labor, materials and equipment. A mandatory site visit will be held on March 9th, 2022 and interested offerors must RSVP by March 3rd. The work must be completed in accordance with the performance work statement and provided specifications/drawings. The contracting agency is the Department of the Air Force Pacific Air Forces.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF66- Material Submittals
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER : | PROJECT TITLE: | SOLICITATION/CONTRACT NO.: | |||||||||||||||||||
| FXSB 21-1048 | Demolition, Bldg 8124 | |||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | NO. OF COPIES REQUIRED | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING/ENVIRONMENTAL | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |||||||||||
| CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SAFETY DATA SHEETS | OTHER | |||||||||||||
| APPROVED | DIS- APPROVED | |||||||||||||||||||||
| 1 | HAZ-Communication Plan; Environmental Protection JBER | x | 20 Days Prior to work start | |||||||||||||||||||
| 2 | HAZMAT Approval; Open Market General Specifications | x | NLT 10 working days prior to material being brought onto installation | |||||||||||||||||||
| 3 | HAZMAT Usage Report; Environmental Protection on JBER | x | NLT 7 Working Days After Final Acceptance | |||||||||||||||||||
| 4 | Environmental Protection Plan(EPP); Environmental Protection on JBER | x | NPT+ 15 days | |||||||||||||||||||
| 5 | Environmental Preconstruction Checklist | x | NTP + 10 days | |||||||||||||||||||
| 6 | Site Specific Safety Plan; PWS | x | 20 Days Prior to work start | |||||||||||||||||||
| 7 | Lead Waste Management Plan (If needed)* Environmental Protection on JBER | x | x | 30 Days prior to abatement work start | ||||||||||||||||||
| 8 | Asbestos Abatement Plan (If needed)* Environmental Protection Plan on JBER | x | 31 Days prior to abatement work start | |||||||||||||||||||
| 9 | Utilities Disconnect Work Plan (Water, Sewer, Gas, Electric, Comm, etc.) | |||||||||||||||||||||
| *PWS | x | x | 30 Days Prior to work start | |||||||||||||||||||
| 10 | Hazardous material Sampling and analysis plan and schedule. (If needed) | |||||||||||||||||||||
| *PWS | x | x | 30 Days Prior to work start | |||||||||||||||||||
| 11 | Record of Training for Contractor Employees | |||||||||||||||||||||
| *PWS | x | x | 30 Days Prior to work start | |||||||||||||||||||
| 12 | Daily Reports | |||||||||||||||||||||
| *PWS | x | Daily upon award of contract | ||||||||||||||||||||
| 13 | Safety Data Sheets (SDSs) | |||||||||||||||||||||
| *PWS | x | x | 30 Days Prior to work start | |||||||||||||||||||
| 14 | Medical Certification; Environmental Protection on JBER (If needed) | x | 30 Days Prior to work start | |||||||||||||||||||
| 15 | Landfill Approval; PWS | x | 30 Days Prior to work start | |||||||||||||||||||
| 16 | Testing Laboratory; Environmental Protection on JBER (If needed) | x | x | 30 Days Prior to work start | ||||||||||||||||||
| 17 | Accumulation point daily and weekly inspection summary sheets | |||||||||||||||||||||
| *PWS/ Environmental Protection on JBER | x | x | Daily and weekly upon work start | |||||||||||||||||||
| 18 | Chain Of Custody Documents On Hazardous Materials; Environmental Protection on JBER(If Needed) | |||||||||||||||||||||
| x | 30 Days after project completion | |||||||||||||||||||||
| 19 | Seeding Submittals; PWS | x | 30 Days Prior to work start |