Delta Grenade Pits Contract SOW.docx
DOCX document 40 KB Posted
- Attached to
- Delta Range Grenade Pits Fort Devens MA
- Solicitation number
- W15QKN26QA138
About this file
This is a Statement of Work (SOW) for the Delta Grenade Pits construction project at Devens RFTA in Massachusetts, supporting the United States Army Garrison Fort Devens. The project requires professional services to construct three concrete grenade pits measuring 2.7 meters x 2.7 meters x 1.5 meters each, featuring a 0.6-meter rear wall, 0.25-meter front overhang, textured and slightly inclined floors with internal drainage, and a 1-meter x 10-meter wall with matching overhang specifications. All work must comply with Training Circular TC 3-23.30 standards and related Army regulations including TC 25-8, TC 25-1, Department of the Army Pamphlet 385-63, AR 350-19, and AR 530-1.
The contractor shall execute four primary tasks: preconstruction planning including site visits, utility assessments, and material determination; construction services encompassing earthwork, fill and aggregate work, composite post emplacement, hydro seeding, and site restoration; installation and signage placement; and acceptance phase inspections coordinated with the Contracting Officer Representative (COR) or On-Site COR. Deliverables include a project kickoff meeting within 14 days of Notice to Proceed, weekly construction reports, pre-final inspection notification ten days prior to completion, and acceptance letters upon task completion. The period of performance is one year from Notice to Proceed, with work performed at Devens RFTA during daily access hours 0630-1600, though holiday and non-business hours work may be coordinated as needed. The Government will provide facilities, utilities, environmental coordination, and utility protection, while excluding contractor responsibility for environmental permits, hazardous material handling, antiterrorism requirements, and fire protection unless subsequently mandated. All contractor personnel must pass security requirements, complete AT Level I and iWatch training within specified timeframes, and complete OPSEC Awareness training per AR 530-1.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment W15QKN26QA1380001 SF 30.pdf | ||
| Delta Hand Grenade Reduced.pdf | ||
| Contractor Cost Breakdown.xlsx | XLSX spreadsheet | |
| DBA MA20260001 05182026.pdf | ||
| SF1413 Statement of Acknowledgement.pdf | ||
| Solicitation - W15QKN26QA138 Professional Appearance.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Delta Grenade Pits
Statement of Work (SOW)
Project Title: Delta Grenade Pits For: Devens RFTA, Massachusetts
1.0 Background: As the major Army Reserve presence in Massachusetts, Devens RFTA provides operational, training and logistic resources to tenant, transient training and stationed units and area customers; provides standardized, effective and efficient services, facilities, infrastructure and quality of life to Soldiers, Family Members, Retirees, and Civilian Employees as applicable to support the training, readiness and operational capability for all components and branches of the joint force accomplished through responsible execution of funds and effective conservation of natural resources.
1.1 Problem Statement: The grenade range has been moved to Range Delta and the grenade pits are currently made from wood. For safety of the soldiers training concrete forms should be poured to TC 3-23.30 standards.
2.0 Scope: This Statement of Work (SOW) requires the procurement of professional services to construct 3 concrete forms 2.7 meters x 2.7 meters x 1.5 meters with a .6 meter wall to the rear of the mold and a .25 meter overhang to the front of the pit. The floor of the mold should be textured and at a slight incline towards the front of the pit. Drainage is required inside of the pit. A 1 meter x 10 meter wall and a .25 meter overhang to the front of the wall is to be constructed as well.
3.0 Applicable Documents/References: Training Circular (TC) 25-8 - Ranges, TC 25-1 - Training Land, Department of the Army Pamphlet 385-63 - Range Safety, Army Regulation (AR) 350-19 - The Army Sustainable Range Program, AR 530-1 - Operations Security, Huntsville Corps of Engineer Range Design Manuals, and Devens RFTA Range Development Plan.
4.0 Tasks:
4.1 Task 1: Preconstruction:
4.1.1 Planning:
4.1.1.1 The Contractor shall conduct a site visit to determine the following:
4.1.1.1.1 Determine specific requirements for post/site access by Contractor and equipment.
4.1.1.1.2 Determine distance and accessibility of utilities.
4.1.1.1.3 Determine the required materials, amount of concrete needed to construct all of the grenade pit.
4.1.3 The Contractor shall coordinate a kickoff meeting (Date TBD) within fourteen (14) days after the Notice to Proceed is issued to establish the project communication matrix in preparation for deliveries needed and a cohesive construction schedule to Range Control. This may be accomplished through field inspections, discussions with appropriate personnel, and by checking previous work.
4.2 Task 2: Construction: The Contractor shall provide the necessary professional services, all supervision, equipment, labor, tools, and furnish all materials, not provided by the Government, necessary to construct the target trenches and all necessary signage placement.
4.2.1 General Project Requirements: The major components of the project include:
4.2.1.1 Earthwork (clearing and grubbing as required)
4.2.1.2 Fill and aggregate
4.2.1.4 Composite 4x4 posts emplacement
4.2.1.5 Hydro seeding
4.2.1.6 Site restoration
4.2.2 Site Prep: The Contractor shall provide the necessary professional services, all supervision, equipment, labor, tools, and furnish all materials, not provided by the Government, necessary to prepare the site per the Government approved design.
4.2.2.1 Stormwater Pollution Prevention Plan (SWPPP): The Government will provide the Contractor with their Record of Environmental Consideration (REC) at the beginning of the proposal process to enable inclusion of SWPPP requirements. If required by the REC, the Contractor shall develop and implement a SWPPP in accordance with their general construction submittals. Best Management Practices (BMP) shall be applied for Stormwater Management by the Contractor.
4.2.3 Delivery: The Contractor shall notify the Government of the delivery of components constructed off-site ten (10) workdays prior to delivery date. The Government in conjunction with the Contractor shall collaborate on the delivery of the components. All deliveries shall be during normal business hours IAW paragraph 6.0 below.
4.2.4 Installation: The Contractor shall provide the necessary professional services, all supervision, equipment, labor, tools, and furnish all materials, not provided by the Government, necessary to construct the target trenches and all necessary signage placement.
4.2.5 Site Restoration: The Contractor shall provide the necessary professional services, all supervision, equipment, labor, tools, and furnish all materials, not provided by the Government, necessary to restore the construction site to preexisting conditions.
4.4 Task 4: Acceptance Phase:
4.4.1 Upon substantial completion of each range, the Contractor shall coordinate with the COR/OSCOR to schedule a range inspection of the range to ensure that all construction meets the required standards.
4.4.2 The Contractor, when complete shall coordinate with the COR/OSCOR ten (10) days prior and conduct a final acceptance of the range berms. As part of the transfer of responsibility, the Contractor shall assist the Government in completing the DD Form 1354.
5.0 Deliverables and Schedule of Items:
| Deliverable/Paragraph Reference |
| Transmittal Form and Quantity |
| Schedule |
| Deliver To |
| Project Kickoff Meeting Para 4.1.3 |
| Contractor format E-mail |
| NLT Sixty (60) Days post Task Order Award |
| COR/OSCOR |
| Pre-final inspection Para 4.4.1 |
| Contractor format E-mail |
| Ten (10) days prior to |
Completion of Primary Construction
COR/OSCOR
| Acceptance Letters Para 17.0 |
| Contractor format E-mail |
| Upon completion of a SOV task/CLIN. The Government must sign Acceptance Letters within five (5) business days. |
| COR/OSCOR |
6.0 Place of Performance and Hours of Operation:
6.1 Place of Performance. Tasks under this contract shall be performed at Government-owned facilities at Devens RFTA, MA.
6.2 Hours of Operations. The Contractor is permitted to work holidays and non-business hours as coordinated with COR/OSCOR. Daily access schedule 0630-1600
7.0 Period of Performance (PoP): The POP shall be one (1) year from date of Notice to Proceed.
8.0 Travel: N/A
9.0 Contractor Excluded Responsibilities:
9.1 Environmental Permits, to include a National Pollutant Discharge Elimination System Permit (NPDES), or the State’s equivalent, are not required by the Contractor.
9.2 Testing, handling, and disposal of any hazardous materials.
9.3 Considering the recommendation of the United States Army Engineering and Support Center, Huntsville, this Training Range Facility is exempt from Unified Facilities Criteria (UFC) 4-01001 Depart of Defense Antiterrorism (AT)/Force Protection (FP) requirements. If the Garrison Commander deems this facility requires UFC 4-010-01 AT/FP minimum standards, a modification to this SOW will be required and additional costs applied appropriately.
9.4 If the Garrison Commander and/or Installation Fire Marshal deem fire protection to be a requirement for the facility, a modification to this SOW will be required and additional costs applied appropriately.
10.0 Government Furnished Property (GFP) and Responsibilities: The Government will provide only the facilities, utilities, equipment, parts, supplies, and materials not delineated as furnished in the SOW described herein as GFP. GFP consists of Government-Furnished Facilities (GFF), Government-Furnished Utilities (GFU), Government-Furnished Equipment (GFE), Government-Furnished Materials (GFM), and Government Furnished Information (GFI).
10.1 The Government will not designate a borrow site for fill a material.
10.2 The Government will assist the Contractor with identification and protection of existing utilities.
10.3 The Government will ensure there are no unexploded ordnance (UXO) in the construction area.
10.4 The Government will provide the REC to the DPW environmental section as well as the contractors.
11.0 Reports:
11.1 The Contractor shall provide a Weekly Construction Report after the first day of construction until Government acceptance of the project.
11.2 The Government will review all reports and provide comments as needed within ten (10) calendar days. The Contractor shall incorporate Government comments and provide revised reports within ten (10) calendar days after receiving Government comments.
12.0 Hazardous Information: All areas within the project footprint and adjacent areas are currently active with military personnel. Range Control will deny non-contractor personnel access to the project area during all phases of construction. The Contractor shall remain vigilant with Range Control to work within the construction area to reduce impacts on training exercises. There is no requirement to handle any hazardous material.
13.0 Personnel:
13.1 If an employee is removed from the job site or dismissed from the premises, the Contractor is not relieved of the requirement to provide sufficient personnel to perform the services as required by this SOW. IAW 18 USC 1382 and AR 380-49, the authority of the Installation Commander to control and deny an employee entry to all or part of the installation is absolute. The individual concerned has no right to appeal.
13.2 All personnel must be able to read, write, speak, and comprehend the English language. The Contractor shall provide a workforce possessing the skills, knowledge, and training to satisfactorily perform the services required by this contract. Personnel performing work under this SOW shall not be considered employees of the Government.
14.0 Contracting Officer Representative (COR)/On-Site Contracting Officer Representative (OSCOR):
14.1 COR:
Name: Daniel Sanchez Address: 4260 Jackson Rd, Devens, MA 01434 Office: 978-615-6897 Email: Daniel.j.sanchez76.civ@army.mil
15.0 Security Requirements:
15.1 Employees selected for this SOW must be able to pass all security requirements IAW the Provost Marshall’s Policy to gain access to the installation.
15.2 All Contractors requiring access to Army installations shall complete AT Level I awareness training within thirty (30) calendar days after employee start date. Certificates of completion shall be submitted to the COR or to the KO. AT level I awareness training is available at http://jko.jten.mil/courses/atl1/launch.html.
15.3 All Contractor shall attend iWatch training. This training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within ten (10) calendar days of start of work. The iWatch training: http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx.
15.4 Per AR 530-1, the Contractor shall complete Level I OPSEC Awareness training available at https://securityawareness.usalearning.gov/opsec/. New employees must be trained within thirty (30) calendar days of their reporting for duty and annually thereafter.
16.0 Installation Access:
16.1 The Contractor shall be able to pass all security requirements IAW the Provost Marshall’s Policy to gain access to the installation.
16.2 The Contractor shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.
16.3 The Government will assist the Contractor with installation access however, it is the Contractor’s responsibility to gain lawful access to the installation IAW Provost Marshal’s policies.
17.0 Payment: Provide progress payment invoicing according to the Schedule of Values (SOV) which shall be submitted as indicated in the Purchase Order. The Government will review SOVs with the Contractor before Acceptance Letters are submitted. The Government will sign and return Acceptance Letters within five (5) business days to the Contractor IAW the SOVs and as the Government agrees that the work has been completed.
| Devens RFTA, MA | Page 1 of 12 Vehicle Recovery Site Bleacher Enclosure SOW |
| Devens RFTA, MA | Page 1 of 12 Vehicle Recovery Site Bleacher Enclosure SOW |
| Devens RFTA, MA | Page 1 of 12 Delta Grenade Pits |