The provided file is a detailed technical specification document for the Dearborn Training Center renovation project, prepared by DSD (project number 24-1312) and dated July 29, 2025. The comprehensive document contains a detailed table of contents spanning multiple divisions including existing conditions, concrete, masonry, carpentry, thermal and moisture protection, openings, finishes, specialties, mechanical systems (plumbing, HVAC), and electrical systems. The specifications outline precise requirements for materials, installation methods, product standards, and performance criteria for various building components and systems to be used in the renovation.

The specification document does not include specific pricing information, funding sources, or contract terms. Instead, it provides extensive technical guidance for contractors, including precise specifications for materials like concrete, masonry, insulation, doors, hardware, roofing accessories, and mechanical/electrical systems. The document appears designed to ensure high-quality, standardized construction practices by providing detailed technical requirements for each building system and component. The specifications cover everything from surface preparation and installation techniques to material composition, performance standards, and quality assurance measures, suggesting a comprehensive approach to the facility renovation project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

DEARBORN TRAINING CENTER

DEARBORN, MICHIGAN

DSD PROJECT NO.24-1312

Date: July 29, 2025

ISSUED FOR BID

TABLE OF CONTENTS

TOC-1

DSD 24-1312

DIVISION 02 - EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION ..................................................................................................... 024119-5

024200 CONSTRUCTION WASTE MANAGEMENT ......................................................................... 024200-6

DIVISION 03 - CONCRETE

033015 CONCRETE FOR BUILDING CONSTRUCTION ................................................................... 033000-8

033543 POLISHED CONCRETE ......................................................................................................... 033543-14

DIVISION 04 - MASONRY

040110 MASONRY CLEANING ........................................................................................................... 040110-7

042000 UNIT MASONRY .................................................................................................................... 042000-16

042200 CONCRETE UNIT MASONRY .............................................................................................. 042200-12

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

061000 ROUGH CARPENTRY .............................................................................................................. 061000-6

061600 SHEATHING .............................................................................................................................. 061600-7

062023 INTERIOR FINISH CARPENTRY ........................................................................................... 062023-8

064116 PLASTIC LAMINATE CLAD ARCHITECTURAL CABINETS ............................................ 064116-7

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

072100 THERMAL INSULATION ........................................................................................................ 072100-6

072119 FOAMED-IN PLACE INSULATION ....................................................................................... 072119-2

072600 VAPOR RETARDERS ............................................................................................................... 072600-2

076200 SHEET METAL FLASHING AND TRIM .............................................................................. 076200-14

077200 ROOF ACCESSORIES .............................................................................................................. 077200-8

079200 JOINT SEALANTS .................................................................................................................... 079200-9

DIVISION 08 - OPENINGS

081113 HOLLOW METAL DOORS AND FRAMES ......................................................................... 081113-11

081416 FLUSH WOOD DOORS .......................................................................................................... 081416-16

084113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS ........................................... 084113-11

087100 DOOR HARDWARE ............................................................................................................... 087100-11

088000 GLAZING ................................................................................................................................... 088000-8

TOC-2

DIVISION 09 - FINISHES

092216 NON-STRUCTURAL METAL FRAMING .............................................................................. 092216-7

092900 GYPSUM BOARD ..................................................................................................................... 092900-8

093013 CERAMIC TILING .................................................................................................................. 093013-23

095113 ACOUSTICAL PANEL CEILINGS .......................................................................................... 095113-4

096513 RESILIENT BASE AND ACCESSORIES ................................................................................ 096513-7

096813 TILE CARPETING .................................................................................................................... 096813-5

099113 EXTERIOR PAINTING ............................................................................................................ 099113-5

099123 INTERIOR PAINTING ............................................................................................................ 099123-47

DIVISION 10 - SPECIALTIES

101400 SIGNAGE ................................................................................................................................... 101100-5

102113 TOILET COMPARTMENTS ..................................................................................................... 102113-4

102810 TOILET AND BATH ACCESSORIES ..................................................................................... 102810-5

MECHANICAL

DIVISION 22 - PLUMBING

220513 COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT ............................ 220513-1

220517 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING ................................................ 220517-1

220518 ESCUTCHEONS FOR PLUMBING PIPING............................................................................ 220518-1

220523.12 BALL VALVES FOR PLUMBING PIPING ........................................................................ 220523.12-1

220523.14 CHECK VALVES FOR PLUMBING PIPING ..................................................................... 220523.14-1

220523.15 GATE VALVES FOR PLUMBING PIPING ........................................................................ 220523.15-1

220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIP. 220529-

220553 IDENTIFICATION OF PLUMBING PIPING AND EQUIPMENT ......................................... 220553-1

220716 PLUMBING EQUIPMENT INSULATION............................................................................... 220716-1

220719 PLUMBING PIPING INSULATION ......................................................................................... 220719-1

221116 DOMESTIC WATER PIPING ................................................................................................... 221116-1

221119 DOMESTIC WATER PIPING SPECIALTIES.......................................................................... 221119-1

224213.13 COMMERCIAL WATER CLOSETS ................................................................................... 224213.13-1

224216.13 COMMERCIAL LAVATORIES .......................................................................................... 224216.13-1

224216.16 COMMERCIAL SINKS ........................................................................................................ 224216-16-1

224713 DRINKING FOUNTAINS AND WATER COOLERS ............................................................. 224700-1

DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING

230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT ...................................... 230513-1

230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT ............................... 230529-1

TOC-3

230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT ................................................ 230553-1

230593 TESTING, ADJUSTING AND BALANCING FOR HVAC ..................................................... 230593-1

230700 HVAC EQUIPMENT INSULATION ........................................................................................ 230716-1

230713 DUCT INSULATION ................................................................................................................ 230713-1

230923 DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC ............................................... 230923-1

233113 METAL DUCTS ......................................................................................................................... 233113-1

233300 AIR DUCT ACCESSORIES ...................................................................................................... 233300-1

233423 HVAC POWER VENTILATORS .............................................................................................. 233423-1

233713.13 AIR DIFFUSERS ................................................................................................................... 233713.13-1

238233 CONVECTORS .......................................................................................................................... 238233-1

DIVISION 26 – ELECTRICAL

260500 COMMON WORK RESULTS FOR ELECTRICAL ................................................................. 260500-3

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES ......................... 260519-2

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS .......................................... 260526-2

260533 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS .................................................... 260533-4

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS ................................................................ 260553-1

260573 OVERCURRENT PROTECTION DEVICE COORDINATION AND ARC FLASH HAZARD

STUDY ....................................................................................................................................... 260573-6

260800 COMMISSIONING OF ELECTRICAL SYSTEMS.................................................................. 260800-5

260923 LIGHTING CONTROL DEVICES ............................................................................................ 260923-3

262400 PANELBOARDS ....................................................................................................................... 262400-3

262726 WIRING DEVICES .................................................................................................................... 262726-3

262813 FUSES......................................................................................................................................... 262813-1

262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS .......................................................... 262816-2

262913 ENCLOSED CONTROLLERS .................................................................................................. 262913-2

263213 ENGINE GENERATORS ........................................................................................................ 263213-10

263600 TRANSFER SWITCHES ........................................................................................................... 263600-4

265100 LIGHTING ................................................................................................................................. 265100-2

DIVISION 27 - COMMUNICATION

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

DIVISION 31 - EARTHWORK

DIVISION 32 - EXTERIOR IMPROVEMENTS

DIVISION 33 – UTILITIES

END OF TABLE OF CONTENTS

SELECTIVE DEMOLITION

024119 - 1

DEARBORN TRAINING FACILITY

DSD 24-1312

SECTION 024119 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure.

2. Demolition and removal of selected site elements.

3. Salvage of existing items to be reused or recycled.

1.2 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.

1. Carefully salvage in a manner to prevent damage and promptly return to Owner.

1.3 PREINSTALLATION MEETINGS

A. Predemolition Conference: Conduct conference at Project site.

1.4 INFORMATIONAL SUBMITTALS

A. Engineering Survey: Submit engineering survey of condition of building.

B. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, for dust control, and for noise control. Indicate proposed locations and construction of barriers.

C. Schedule of selective demolition activities with starting and ending dates for each activity.

D. Predemolition photographs or video.

E. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician.

1.5 CLOSEOUT SUBMITTALS

A. Inventory of items that have been removed and salvaged.

024119 - 2

DEARBORN TRAINING FACILITY

DSD 24-1312

1.6 QUALITY ASSURANCE

A. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.

1.7 FIELD CONDITIONS

A. Owner may occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

1. Before selective demolition, Owner will remove the following items:

a. To be determined during pre-demolition, on-site meeting.

C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

1. Hazardous materials will be removed by Owner before start of the Work.

2. If suspected hazardous materials are encountered, do not disturb; immediately notify Architect and Owner. Hazardous materials will be removed by Owner under a separate contract.

E. Storage or sale of removed items or materials on-site is not permitted.

F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

G. Arrange selective demolition schedule so as not to interfere with Owner's operations.

1.8 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials and using approved contractors so as not to void existing warranties.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

024119 - 3

DEARBORN TRAINING FACILITY

DSD 24-1312

B. Standards: Comply with ASSE A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Perform an engineering survey of condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective building demolition operations.

C. Inventory and record the condition of items to be removed and salvaged.

3.2 PREPARATION

A. Refrigerant: Before starting demolition, remove refrigerant from mechanical equipment according to 40 CFR 82 and regulations of authorities having jurisdiction.

3.3 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Owner will arrange to shut off indicated services/systems when requested by Contractor.

2. Arrange to shut off utilities with utility companies.

3. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

4. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated on Drawings to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place.

c. Equipment to Be Removed: Disconnect and cap services and remove equipment.

d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.

f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.

g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material and leave in place.

024119 - 4

DEARBORN TRAINING FACILITY

DSD 24-1312

3.4 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

B. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

C. Remove temporary barricades and protections where hazards no longer exist.

3.5 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

4. Maintain fire watch during and for at least two hours after flame-cutting operations, then verify area is safe prior to leaving the area.

5. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

6. Dispose of demolished items and materials promptly. Comply with requirements in Section 017419 "Construction Waste Management and Disposal."

B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

C. Removed and Salvaged Items:

1. Clean salvaged items.

2. Pack or crate items after cleaning. Identify contents of containers.

3. Store items in a secure area until delivery to Owner.

4. Transport identified items to Owner's storage area designated by Owner.

5. Protect items from damage during transport and storage.

D. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

024119 - 5

DEARBORN TRAINING FACILITY

DSD 24-1312

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

3.6 CLEANING

A. Remove demolition waste materials from Project site and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction and recycle or dispose of them according to Section 017419 "Construction Waste Management and Disposal."

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

4. Comply with requirements specified in Section 017419 "Construction Waste Management and

Disposal."

B. Burning: Do not burn demolished materials.

C. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 024119

CONSTRUCTION WASTE MANAGEMENT

024200 - 1

DEARBORN TRAINING FACILITY

DSD 24-1312

SECTION 024200– CONSTRUCTION WASTE MANAGEMENT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections, apply to this section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for the following:

1. Salvaging nonhazardous demolition and construction waste.

2. Recycling nonhazardous demolition and construction waste.

3. Disposing of nonhazardous demolition and construction waste.

B. Related sections include the following:

1. Division 01 Section “General Requirements – Temporary Facilities and Controls.”

1.3 DEFINITIONS

A. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.

B. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations and clearing debris including soil, vegetation, and rocks are not to be included.

C. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.

D. Recycle: Collect, reprocess and reuse of materials diverted or recovered from solid waste stream.

E. Salvage: Recovery of demolition or construction materials from existing buildings or construction sites and subsequent sale or reuse in another facility.

F. Salvage and Reuse: Recovery of demolition or construction materials from existing buildings or construction sites and subsequent incorporation into the Work.

1.4 PERFORMANCE GOALS

A. General: Develop waste management plan that results in end-of-Project rates for salvage/recycling of 50 (75) percent by weight of total waste generated by the Work.

1.5 SUBMITTALS

A. Waste Management Plan: Submit 3 copies of plan within 14 days of date established for commencement of the Work

024200 - 2

DEARBORN TRAINING FACILITY

DSD 24-1312

B. Waste Reduction Progress Reports: Concurrent with each Application for Payment, submit 2 copies of report. Include separate reports for demolition and construction waste. Include the following information:

1. Material category.

2. Generation point of waste.

3. Total quantity of waste in tons.

4. Quantity of waste salvaged, both estimated and actual in tons or cubic yards.

5. Quantity of waste recycled, both estimated and actual in tons or cubic yards.

6. Total quantity of waste recovered (salvaged plus recycled) in tons or cubic yards.

7. Total quantity of waste recovered (salvaged plus recycled) as a percentage of total waste.

C. Waste Reduction Calculations: Before request for Substantial Completion, submit 2 copies of calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of total waste generated by the Work.

D. Records of Donations: Indicate receipt and acceptance of salvageable waste donated to individuals and organizations. Indicate whether organization is tax exempt.

E. Records of Sales: Indicate receipt and acceptance of salvageable waste sold to individuals and organizations. Indicate whether organization is tax exempt.

F. Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.

G. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licenses to accept them. Include manifests, weight tickets, receipts, and invoices.

H. LEED Submittal: LEED letter template for Credit 2, signed by Contractor, tabulating total waste material, quantities and weight (tons) diverted and means by which it is diverted, and statement that requirements for the credit have been met.

1.6 QUALITY ASSURANCE

A. Waste Management Coordinator Qualifications: LEED Accredited Professional by U.S. Green Building Council, or person familiar and experienced with LEED construction waste management requirements.

B. Regulatory Requirements: Comply with hauling and disposal regulations of authorities having jurisdiction.

C. Waste Management Conference: Conduct conference at Project site to comply with requirements in Division 01 Section. Review methods and procedures related to waste management including, but not limited to, the following:

1. Review and discuss waste management plan including responsibilities of Waste Management Coordinator.

2. Review requirements for documenting quantities of each type of waste and its disposition.

3. Review and finalize procedures for materials separation and verify availability of containers and bins needed to avoid delays.

024200 - 3

DEARBORN TRAINING FACILITY

DSD 24-1312

4. Review procedures for periodic waste collection and transportation to recycling and disposal facilities.

5. Review waste management requirements for each trade.

1.7 WASTE MANAGEMENT PLAN

A. General: Develop plan consisting of waste identification, waste reduction plan, and cost/revenue analysis. Include separate sections in plan for demolition and construction waste. Indicate quantities by weight or volume, but use same units of measure throughout waste management plan.

B. Waste Identification: Indicate anticipated types and quantities of construction waste generated by the Work. Include estimated quantities and assumptions for estimates.

C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Include points of waste generation, total quantity of each type of waste, quantity for each means of recovery, and handling and transportation procedures.

1. Salvaged Materials for Reuse: For materials that will be salvaged and reused in this Project, describe methods for preparing salvaged materials before incorporation into the Work.

2. Salvaged Materials for Sale: For materials that will be sold to individuals and organizations, include list of their names, addresses and telephone numbers.

3. Salvaged Materials for Donation: For materials that will be donated to individuals and organizations, include list of their names, addresses and telephone numbers.

4. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept. Include names, addresses, and telephone numbers.

5. Disposed materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number for each landfill and incinerator facility.

6. Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location on Project site where materials separation will be located.

D. Plan for and describe the means for securing waste containers from unauthorized users.

E. Cost/Revenue Analysis: Indicate total cost of waste disposal as if there was no waste management plan and net additional cost or net savings resulting from implementing waste management plan. Include the following:

1. Total quantity of waste.

2. Estimated cost of disposal (cost per unit). Include hauling and tipping fees and cost of collection containers for each type of waste.

3. Total cost of disposal (with no waste management).

4. Revenue from salvaged materials.

5. Revenue from recycled materials.

6. Savings in hauling and tipping fees by donating materials.

7. Savings in hauling and tipping fees that are avoided.

8. Handling and transportation costs. Include cost of collection containers for each type of waste.

9. Net additional cost or net savings from waste management plan.

PART 2 - PRODUCTS (Not Used)

024200 - 4

DEARBORN TRAINING FACILITY

DSD 24-1312

PART 3 - EXECUTION

3.1 PLAN IMPLEMENTATION

A. General: Implement waste management plan as approved by Owner. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.

1. Comply with Division 01 Section “Temporary Facilities and Controls” for operation, termination, and removal requirements.

2. Observe and follow site measures that prevent cross-contamination of waste. Cross-contamination could render some portion of waste to be non-recyclable, thereby disqualifying the Project from earning LEED Credit MR 2, and the exemplary performance credit of diverting 95% of waste from landfill.

B. Waste Management Coordinator: Engage a waste management coordinator to be responsible for implementing, monitoring, and reporting status of waste management work plan. Coordinator shall be present at Project site full time for duration of Project. The Construction Superintendent may perform the role of the Waste Management Coordinator.

C. Training: Train workers, subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work occurring at the Project site.

a. Distribute waste management plan to everyone concerned within three days of submittal return.

b. Distribute waste management plan to entities upon execution of their contracts. Review plan procedures and locations established for salvage, recycling, and disposal.

D. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

a. Designate and label specific areas on Project site necessary for separating materials that are to be salvaged, recycled, reused, donated, and sold.

b. Comply with Division 01 Section “Temporary Facilities and Controls” for controlling dust and dirt, environmental protection, and noise control.

3.2 SALVAGING DEMOLITION WASTE

A. Salvaged Items for Reuse in the Work:

1. Clean salvaged items.

2. Pack or crate items after cleaning. Identify contents of containers.

3. Store items in a secure area until installation.

4. Protect items from damage during transport and storage.

5. Install salvaged items to comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make items functional for use indicated.

B. Salvaged Items for Sale and Donation: Not permitted on Project site.

C. Salvaged Items for Owner’s Use:

a. Clean salvaged items.

024200 - 5

DEARBORN TRAINING FACILITY

DSD 24-1312

b. Pack or crate items after cleaning. Identify contents of containers.

c. Store items in a secure area until delivery to Owner.

d. Transport items to Owner’s storage area off-site designated by Owner.

e. Protect items from damage during transport and storage.

D. Doors and Hardware: Brace open end of door frames. Except for removing door closes, leave door hardware attached to doors.

3.3 RECYCLING DEMOLITION AND CONTRUCTION WASTE, GENERAL

A. General:

a. Recycle paper and beverage containers used by on-site workers.

b. Concrete, masonry, or asphalt crushed and reused are to be identified and include in calculations.

c. Exclude hazardous waste from calculations.

B. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall accrue to Contractor.

C. Procedures: Separate recyclable waste from other waste materials, trash, and debris. Separate recyclable waste by type at Project site to the maximum extent practical.

a. Provide appropriately marked containers or bins for controlling recyclable waste until they are removed from Project site. Include list of acceptable and unacceptable materials at each container and bin.

i. Inspect containers and bins for contamination and remove contaminated materials if found.

b. Stockpile processed materials on-site without intermixing with other materials. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.

c. Stockpile materials away from construction area. Do not store within drip line of remaining trees.

d. Store components off the ground and protect from the weather.

e. Remove recyclable waste off Owner’s property and transport to recycling receiver or processor.

3.4 RECYCLING CONSTRUCTION WASTE

A. Packaging:

a. Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store in a dry location.

b. Polystyrene Packaging: Separate and bag materials.

c. Pallets: As much as possible, require deliveries using pallets to remove pallets from

Project site. For pallets that remain on-site, break down pallets into component wood pieces and comply with requirements for recycling wood.

d. Crates: Break down crates into component wood pieces and comply with requirements for recycling wood.

B. Wood Materials:

024200 - 6

DEARBORN TRAINING FACILITY

DSD 24-1312

a. Clean Cut-Offs of Lumber: Grind or chip into small pieces.

b. Clean Sawdust; Bag sawdust that does not contain painted or treated wood.

C. Gypsum Board: Stack large clean pieces on wood pallets and store in a dry location.

a. Clean Gypsum board: Grind scraps of clean gypsum board using small mobile chipper or hammer mill. Screen out paper after grinding.

D. Metals: Separate metal by type or to meet requirements of recycling receiver or processor.

3.5 DISPOSAL OF WASTE

A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.

a. Except as otherwise specified, do not allow excessive on-site accumulation of waste materials.

b. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

c. Coordinate with each product manufacturer for take-back programs. Set aside scrap to be returned to manufacturer for recycling into new product.

B. Burning: Do not burn waste materials.

C. Disposal: Transport waste materials off Owner’s property and legally dispose of them.

END OF SECTION 024200

CAST-IN-PLACE CONCRETE FOR BUILDING

CONSTRUCTION

033015-1

SECTION 033015 – CAST-IN-PLACE CONCRETE FOR BUILDING CONSTRUCTION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections, apply to this section.

1.2 SUMMARY

A. This section includes the furnishing and placement of cast-in-place concrete.

B. ACI Standard 347, “Guide to Formwork for Concrete”, shall establish minimum requirements when not otherwise specified in this section.

C. Nothing in this standard should be considered to apply to streets, pedestrian walkways, curbs, steam tunnels, or other concrete that is not part of a building. See Division 32 Sections “Curbs and Gutters” and “Concrete Pavement.”

D. A vapor barrier shall be installed under a slab on grade if required by the flooring manufacturer’s warranty and will comply with that requirement.

1.3 QUALITY ASSURANCE

A. Testing Agency Qualifications: An independent agency, acceptable to DSD and any other authority having jurisdiction, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated, as documented according to ASTM E 548.

B. Source Limitations: Obtain each type or class of cementitious material of the same brand from the same manufacturer's plant, obtain aggregate from one source, and obtain admixtures through one source from a single manufacturer.

C. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents:

1. ACI 117, "Specifications for Tolerances for Concrete Construction and Materials."

2. ACI 301, "Specification for Structural Concrete."

1.4 DELIVERY, STORAGE, AND HANDLING

A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and damage.

Avoid damaging coatings on steel reinforcement.

B. Waterstops: Store waterstops under cover to protect from moisture, sunlight, dirt, oil, and other contaminants.

PART 2 - PRODUCTS

2.1 FORM MATERIALS

A. Wood, plastic, fiberglass or metal, complete with shores, bracing etc. as required, conform to the shapes, lines, and dimensions of the members indicated on the Drawings.

033015-2

B. Forms for exposed concrete shall be constructed of metal or smooth plywood, or other material to provide a smooth surface finish.

C. Form-Release Agent: Use commercially formulated form-release agent that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces. Use a form-release agent formulated with rust inhibitor for steel form-facing materials.

2.2 STEEL REINFORCEMENT

A. Bar reinforcement: ASTM A615, Grade 60.

B. Welded wire fabric: ASTM A185. Provide in flat sheets only.

C. Epoxy coated reinforcing bar and applicable installation techniques are recommended for exterior concrete with no further coatings or sealers, especially in areas subject to salt exposure.

D. Wire, bar and chain type reinforcement supports shall be corrosive resistant, hot dipped galvanized, epoxy, or plastic coated in accordance with CRSI recommendations.

2.3 CONCRETE MATERIALS

A. Portland Cement: ASTM C 150, Type I shall be used unless otherwise indicated in the reviewed mix design.

B. Normal-Weight Aggregates: ASTM C 33.

1. Coarse aggregate shall be well graded gravel and crushed stone of hard, durable, uncoated particles, or limestone if specifically required. Other materials such as fly ash and ground blast furnace slag may be included subject to Owner’s approval. Gradation and physical requirements to conform to MDOT Specification 6AA (ASTM C 33 one inch maximum size) or as included in the reviewed mix design.

2. Fine Aggregate: Shall conform to the MDOT Specifications for Sand 2NS (ASTM C33).

C. Water: ASTM C 94 and potable.

2.4 ADMIXTURES

A. Admixtures will be allowed as indicated in this section or as included in the mix designs reviewed by the Engineer responsible for the structural integrity of the Project.

B. Air-Entraining Admixture: ASTM C 260.

C. Bonding Admixtures. Specify latex or acrylic bonding agents when placing new concrete against existing concrete. Mix bonding agents in concrete mix in accordance with manufacturer’s recommendations when patches require thin and/or feathered sections.

2.5 WATERSTOPS

A. Flexible PVC Waterstops: CE CRD-C 572, for embedding in concrete to prevent passage of fluids through joints. Factory fabricate corners, intersections, and directional changes.

1. Manufacturers:

033015-3

a. Greenstreak.

b. Vinylex Corp.

c. Or as approved.

2. Profile: Serrated, split, with center bulb.

3. Extruded vinyl made only from virgin raw materials, highly resistant to alkalis, acids, oxygen, ozone, and waterborne chemicals.

B. Other waterstop materials may be used with the specific prior written approval of the Owner.

2.6 CURING MATERIALS

A. Damp curing is preferred over using curing compounds to avoid incompatibility with the many finish materials, hardeners, and sealers. Curing compounds shall be used where required by weather, approved construction schedules, and construction that is not adaptable to damp curing.

B. The sodium silicate base curing compounds that follow are compatible with the preferred sealer, most resilient floor covering adhesives, and many paint finishes.

1. “Gardseal”; Lambert Corporation

2. “Sonosil”; Sonnebore Building Products Div. (BASF Building Systems)

C. Utilize other curing compounds as approved by the manufacturer of the finish materials to be installed.

Curing compounds should contain a fugitive dye, or, when hot weather conditions dictate, a fugitive heat reflecting pigment.

D. The use of hardeners should be considered for special areas, but the incidental hardening of most curing compounds and sealers has been adequate. Magnesium zinc fluoresilicate hardener is generally compatible with the sodium silicate curing compounds listed above, but is not recommended for finished areas because the surface is often rough and mottled.

2.7 RELATED MATERIALS

A. Dovetail Anchor Slots: Stainless steel sheet, not less than 0.0336 inch thick, with bent tab anchors.

Temporarily fill or cover face opening of slots to prevent intrusion of concrete or debris.

2.8 EXPANSION JOINT FILLERS

A. Interior Applications: Where expansion filler materials are required by design, foam expansion joint material shall generally be used. Interior joint fillers are needed in isolation joints, such as around column block outs in slabs on grade and between slabs on grade and walls, where the floor finish will not be compromised by the filler.

B. Exterior Applications:

1. Asphalt impregnated expansion joint fillers: Premolded rigid cane fiber board product, uniformly impregnated with an asphalt compound to prevent degradation. Joint filler shall meet or exceed ASTM D994 or D1781.

2. Polyvinyl chloride expansion joint fillers: Closed cell, non-extruding PVC or polyurethane foam, or equal. Joint filler should normally be 1/2 inch thick.

033015-4

3. Polyethylene expansion joint fillers: Ultraviolet stable and of closed cell sheet material with a density of 2.5-3.0 lbs./cu.ft. and shall have a water absorption rate of less than 2% after 48 hours with 10 ft. of head.

2.9 CONCRETE MIXTURES, GENERAL

A. The concrete mix design criteria shall be specified by the Architect or Engineer to meet the project design conditions and minimum loading conditions indicated in these standards. The mix design shall be submitted to the Architect or Engineer for review.

B. Unless specified otherwise by the Engineer, a maximum allowable slump before the addition of water reducer (if any) shall be 4-1/2 inches, air entrainment shall be 5% to 7%, and compressive strength shall be 4,000 psi with a minimum of six sacks of cementitious products per cubic yard of concrete.

Use non-air entrained concrete for interior concrete slabs.

C. The Contractor shall provide the Project Representative with delivery tickets which shall list slump, sack mix, percent of air entraining agent, time the truck left the plant, time of arrival on the job site, and time of departure from the job site.

D. When requested, the Contractor shall provide documentation from the concrete supplier certifying the concrete meets the specifications of this section.

E. Retempering of concrete will not be allowed.

F. Where conditions make consolidation or finishing of concrete difficult, or where reinforcement is congested, separate concrete mix designs shall be specified, submitted, and reviewed prior to placement. For example, specify concrete with smaller coarse aggregate for concrete fill of metal pan stairs.

2.10 FABRICATING REINFORCEMENT

A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."

B. Welding of reinforcing steel is not permitted.

PART 3 - EXECUTION

3.1 FORMWORK

A. Formwork design shall be the responsibility of the Contractor.

B. Design, erect, shore, brace, and maintain formwork according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied until structure can support such loads.

C. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117.

D. Construct forms tight enough to prevent loss of concrete mortar.

E. Fabricate forms for easy removal without hammering or prying against concrete surfaces. Provide crush or wrecking plates where stripping may damage cast concrete surfaces. Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical.

033015-5

1. Install keyways, reglets, recesses, and the like, for easy removal.

2. Do not use rust-stained steel form-facing material.

F. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces. Provide and secure units to support screed strips; use strike-off templates or compacting-type screeds.

G. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar. Locate temporary openings in forms at inconspicuous locations.

H. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, ice, snow, dirt, and other debris just before placing concrete. The Project Representative shall inspect forms prior to placing the concrete.

I. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment.

J. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement.

K. Forms shall be cleaned and treated each time they are used.

3.2 EMBEDDED ITEMS

A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

3.3 STEEL REINFORCEMENT

A. The latest publication of the following standards shall establish the minimum requirements when not otherwise specified in this section:

1. “Placing Reinforcing Bars”: CRSI.

2. “Manual of Standard Practice”: CRSI.

3. “Manual of Structural and Placing Drawings for Reinforced Concrete Structures”: ACI 315R.

B. Fasten the reinforcement securely to supports unless required otherwise by the joint design. At control joints the reinforcement shall be held 1-1/2-inch short of the joint. Reinforcement cover shall conform to ACI 318 requirements.

C. When reinforcing a slab on grade use one of the following methods:

1. Place half the thickness of concrete followed by the laying of the flat reinforcement, followed by the second half thickness and vibrate it into the first.

2. Provide supports for the flat reinforcement to prevent it sinking in the pour.

3.4 WATERSTOPS

033015-6

A. Below grade construction joints in concrete shall have waterstops.

B. Waterstops shall be centered in concrete with half of the waterstop embedded in the first pour of concrete. The other half shall be spread open and stapled or nailed to the bulkhead. After removing the first pour formwork, the split flange shall be joined by rings or staple and then the second pour made.

C. Waterstop splices shall be heat sealed according to manufacturer’s directions.

3.5 EXPANSION JOINTS

A. Install expansion joint fillers slightly below the finished surface. Foam expansion joint fillers shall be placed to allow for a well designed bead of sealant. Asphalt impregnated joint fillers shall not be caulked over.

3.6 CONCRETE PLACEMENT

A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections have been performed.

B. Placing the concrete shall not commence until the subgrade, reinforcing, and forms have been approved. A sufficient quantity of forms shall be in place to accommodate all of the concrete that is scheduled to be placed at any one time. Concrete shall be deposited with a minimum of rehandling and shall be consolidated, particularly adjacent to forms and joints. In the case of isolation joints, concrete shall be placed simultaneously against both sides of the joint.

C. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete will be placed on concrete that has hardened enough to cause seams or planes of weakness.

If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation.

D. Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of construction joints, until placement of a panel or section is complete.

E. Slope surfaces uniformly to drains where required.

F. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.

1. When average high and low temperature is expected to fall below 40 deg F for three successive days, maintain delivered concrete mixture temperature within the temperature range required by

ACI 301.

2. Do not use frozen materials or materials containing ice or snow. Do not place concrete on frozen subgrade or on subgrade containing frozen materials.

3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs.

G. Hot-Weather Placement: Comply with ACI 301 and as follows:

1. Maintain concrete temperature below 90 deg.F at time of placement. Chilled mixing water or chopped ice may be used to control temperature, provided water equivalent of

033015-7 ice is calculated to total amount of mixing water. Using liquid nitrogen to cool concrete is contractor's…