This is a Contract Data Requirements List (DD Form 1423-1) that specifies twelve data items the contractor must deliver for an Enterprise UPS System and Turnkey Installation contract (W911QX26QA104) with the United States Army Research Laboratory at Aberdeen Proving Ground, Maryland.

The deliverables include: (A001) Site Preparation Requirements and Installation Plan due within 15 days of contract award; (A002) Environmental Compliance Assessment and Management Program Action Plan/Decommissioning Plan due within 20 days; (A003) Management Plan and Project Schedule due within 15 days; (A004) Quality Program Plan/Quality Control Plan due within 15 days; (A005) As-Built Drawings due within 10 days after installation completion; (A006) Acceptance Test Procedures due 5 business days prior to testing; (A007) Acceptance Test Report due 5 business days after testing; (A008) Training Plan and Materials due 10 business days before scheduled training; (A009) Operations and Maintenance Documentation due at system acceptance; (A010) Warranty Documentation due at system acceptance; (A011) Certificate of Disposal due within 30 days after equipment removal; and (A012) Monthly Status Reports due no later than the 10th day of each following month, with the first report due within 45 days of contract award. All deliverables must be submitted electronically in media selected by the government (FTP, CD-ROM, or DVD-ROM) to the United States Army Research Laboratory point of contact at Aberdeen Proving Ground, MD 21005-5066. Each data item requires a single copy in both draft and final format, with distribution statement A classification.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Template last updated 10/21/2021

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: MGMT

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A001

2. TITLE OF DATA ITEM

SITE PREPARATION REQUIREMENTS AND INSTALLATION PLAN

3. SUBTITLE

SITE ASSESSMENT REPORT

4. AUTHORITY (Data Acquisition Document No.)

DI-MGMT-80033A

5. CONTRACT REFERENCE

C.3.1 & C.5

6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONCE

12. DATE OF FIRST SUBMISSION

NLT 15 DAYS ACA

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

ACA

13. DATE OF SUBSEQUENT

SUBMISSION N/A

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD
1
1
15. TOTAL
1
1

G. PREPARED BY

TBD

H. DATE

8/5/2026

I. APPROVED BY

ARIEL AMEY

J. DATE

8/5/2026

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 01 of Pages 12

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: MGMT

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A002

2. TITLE OF DATA ITEM

ENVIRONMENTAL COMPLIANCE ASSESSMENT AND MANAGEMENT PROGRAM (ECAMP) ACTION PLAN REPORT

3. SUBTITLE

DECOMMISSIONING PLAN

4. AUTHORITY (Data Acquisition Document No.)

DI-MGMT-80898

5. CONTRACT REFERENCE

C.3.2 & C.5

6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONCE

12. DATE OF FIRST SUBMISSION

NLT 20 DAYS ACA

14. DISTRIBUTION

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION N/A

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD

15. TOTAL

G. PREPARED BY

H. DATE

8/5/2026

II. APPROVED BY

ARIEL AMEY

J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 02 of Pages 12

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: MGMT

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A003

2. TITLE OF DATA ITEM

MANAGEMENT PLAN

3. SUBTITLE

PROJECT MANAGEMENT PLAN AND SCHEDULE

4. AUTHORITY (Data Acquisition Document No.)

DI-MGMT-80004A

5. CONTRACT REFERENCE

C3.1.1 & C.5

6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONCE

12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION N/A

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD

15. TOTAL

G. PREPARED BY

H. DATE

8/5/2026

III. APPROVED BY

ARIEL AMEY

J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 03 of Pages 12

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: QCIC

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A004

2. TITLE OF DATA ITEM

QUALITY PROGRAM PLAN (QPP)

3. SUBTITLE

QUALITY CONTROL PLAN

4. AUTHORITY (Data Acquisition Document No.)

DI-QCIC-81722

5. CONTRACT REFERENCE

C.5 & C.14

6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONCE

12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION N/A

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD
1

15. TOTAL

G. PREPARED BY

H. DATE

8/5/2026

IV. APPROVED BY

ARIEL AMEY

J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 04 of Pages 12

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: FACR

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A005

2. TITLE OF DATA ITEM

FACILITIES PLAN

3. SUBTITLE

AS-BUILT DRAWINGS

4. AUTHORITY (Data Acquisition Document No.)
DI-FACR-80976 NOT 2
5. CONTRACT REFERENCE

C3.4.5 & C. 5

6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONCE

12. DATE OF FIRST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

N.A

13. DATE OF SUBSEQUENT

SUBMISSION N/A

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLOCK 12: AS-BUILT DRAWINGS ARE DUE NO LATER THAN TEN (10) DAYS AFTER INSTALLATION IS COMPLETE

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD

15. TOTAL

G. PREPARED BY

H. DATE

8/5/2026

V. APPROVED BY

ARIEL AMEY

J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 05 of Pages 12

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: QCIC

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A006

2. TITLE OF DATA ITEM

ACCEPTANCE TEST PLAN

3. SUBTITLE

ACCEPTANCE TEST PROCEDURES

4. AUTHORITY (Data Acquisition Document No.)
DI-QCIC-80553A
5. CONTRACT REFERENCE

C.3.4 & C.5

6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONCE

12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION N/A

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLOCK 12: ACCEPTANCE TEST PROCEDURES ARE DUE FIVE (5) BUISINESS DAYS PRIOR TO TESTING

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD

15. TOTAL

G. PREPARED BY

H. DATE

8/5/2026

VI. APPROVED BY

ARIEL AMEY

J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 06 of Pages 12

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: QCIC

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A007

2. TITLE OF DATA ITEM

ACCEPTANCE TEST REPORT (ATR)

3. SUBTITLE

ACCEPTANCE TEST REPORT

4. AUTHORITY (Data Acquisition Document No.)
DI-QCIC-81891 NOT 2
5. CONTRACT REFERENCE

C.3.4 & C.5

6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONCE

12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION N/A

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLOCK 12: ACCEPTANCE TEST REPORT ARE DUE FIVE (5) BUISINESS DAYS AFTER TESTING

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD

15. TOTAL

G. PREPARED BY

H. DATE

8/5/2026

VII. APPROVED BY

ARIEL AMEY

J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 07 of Pages 12

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: MGMT

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A008

2. TITLE OF DATA ITEM

POST TRAINING AND OPERATIONS REPORT

3. SUBTITLE

TRAINING PLAN AND MATERIALS

4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81862 NOT 1
5. CONTRACT REFERENCE

C.3.5 & C.5

6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONCE

12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

b. COPIES

8. APP CODE

N/A

11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT

SUBMISSION N/A

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLOCK 12: TRAINING PLAN AND MATERIALS ARE DUE TEN (10) BUISINESS DAYS BEFORE SCHEDULED TRAINING

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD

15. TOTAL

G. PREPARED BY

H. DATE

8/5/2026

VIII. APPROVED BY

ARIEL AMEY

J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 08 of Pages 12

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: MISC

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A009

2. TITLE OF DATA ITEM

OPERATION AND MAINTENANCE INSTRUCTIONS FOR RESEARCH AND DEVELOPMENT (R&D) EQUIPMENT

3. SUBTITLE

OPERATIONS AND MAINTENANCE DOCUMENTATION

4. AUTHORITY (Data Acquisition Document No.)

DI-MISC-81414A

5. CONTRACT REFERENCE

C 3.4.6 & C.5

6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONCE

12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION N/A

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLOCK 12: OPERATIONS AND MAINTENANCE DOCUMENTATION IS DUE AT SYSTEM ACCEPTANCE

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD

15. TOTAL

G. PREPARED BY

H. DATE

8/5/2026

IX. APPROVED BY

ARIEL AMEY

J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 09 of Pages 12

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: MGMT

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A010

2. TITLE OF DATA ITEM

WARRANTY DOCUMENTATION

3. SUBTITLE

WARRANTY DOCUMENTATION

4. AUTHORITY (Data Acquisition Document No.)

N/A

5. CONTRACT REFERENCE

& C.5

6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONCE

12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION N/A

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLOCK 12: WARRANTY DOCUMENTATION IS DUE AT SYSTEM ACCEPTANCE

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD

15. TOTAL

G. PREPARED BY

H. DATE

8/5/2026

X. APPROVED BY

ARIEL AMEY

J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 10 of Pages 12

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP_____ TM ______ OTHER: MGMT

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A011

2. TITLE OF DATA ITEM
CERTIFICATE OF DISPOSAL
3. SUBTITLE

DISPOSAL CERTIFICATIONS

4. AUTHORITY (Data Acquisition Document No.)

DI-MGMT-82372

5. CONTRACT REFERENCE
C.3.2 & C.5
6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

ONCE

12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLOCK 12: DISPOSAL CERTIFICATIONS ARE DUE NO LATER THAN 30 DAYS AFTER EQUIPMENT REMOVAL

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD

15. TOTAL

G. PREPARED BY

H. DATE

8/5/2026

XI. APPROVED BY

ARIEL AMEY

J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 11 of Pages 12

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

C. CATEGORY:

TDP_____ TM ______ OTHER:

D. SYSTEM/ITEM

ENTERPRISE UPS SYSTEM AND TURNKEY INSTALLATION

E. CONTRACT/PR NO.

TBD / 0012429836

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A012

2. TITLE OF DATA ITEM

STATUS REPORT

3. SUBTITLE

MONTHLY STATUS REPORT

4. AUTHORITY (Data Acquisition Document No.)

DI-MGMT-80368A

5. CONTRACT REFERENCE

6. REQUIRING OFFICE

TBD

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

A

10. FREQUENCY

MONTHLY

12. DATE OF FIRST SUBMISSION

NLT 45 DAYS ACA

14. DISTRIBUTION

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION SEE BLK 16

Draft
Final
Reg
Repro

16. REMARKS

BLK 4: REPORT SHALL BE DELIVERED ELECTRONICALLY IN A MEDIA SELECTED BY THE GOVERNMENT AT TIME OF DELIVERY. SOME MEDIA TYPES WHICH CAN BE ACCEPTED INCLUDE: FTP (FILE TRANSFER PROTOCOL), CD-ROM AND DVD-ROM.

BLK 13: SUBSEQUENT SUBMISSIONS SHALL BE MADE NLT THE 10TH DAY OF THE MONTH FOLLOWING THE PERIOD OF PERFORMANCE REPORTING ON.

BLOCK 14: ADDRESSEE – THE COPY OF THE REPORT SHALL BE SENT TO:

UNITED STATES ARMY RESEARCH LABORATORY

POINT OF CONTACT: TBD

EMAIL ADDRESS: TBD

Aberdeen Proving Ground, MD 21005-5066

TBD

15. TOTAL

G. PREPARED BY

H. DATE

8/5/2026

XII. APPROVED BY

ARIEL AMEY

J. DATE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 12 of Pages 12

EXHIBIT A – ATTACHMENT 1

ARMY RESEARCH LABORATORY

Report Title Goes Here Any Subtitles Go Here

By Some Author and Another Author

Month XXXX

Prepared by

Whatever Technology Corporation 0000 Research Drive Anywhere, ST 20006-1000

Under contract

W911QX-XX-C-XXXX

DISTRIBUTION STATEMENT GOES HERE

EXHIBIT A – ATTACHMENT 2

The findings in this report are not to be construed as an official Department of the Army position unless so designated by other authorized documents.

Citation of manufacturer's or trade names does not constitute an official endorsement or approval of the use thereof.

DESTRUCTION NOTICE: For classified documents, follow the procedures in DoD 5220.22-M, National Industrial Security Program Operating Manual, Chapter 5, Section 7. For unclassified, limited documents, destroy by any method that will prevent disclosure of contents or reconstruction of the document.

image1.emf image2.emf

File details come from the government source that posted it. Updated .