Activity ID Activity Name Original Duration
Start Finish
CPFMD - INTEGRATED PROGRAM SCHEDULE 10/29/18CPFMD - INTEGRATED PROGRAM SCHEDULE 10/29/18 1990 03-16-2016 A 11-01-2023
Renovations, Improvements & Expansions ( RIE )Renovations, Improvements & Expansions ( RIE ) 1990 03-16-2016 A 11-01-2023
Moultrie Courthouse AdditionMoultrie Courthouse Addition 1534 03-16-2016 A 02-01-2022
HCMCB (West) Renovate Health Unit (Permanent LocationHCMCB (West) Renovate Health Unit (Permanent Location 520 11-06-2017 A 11-01-2019 Project ConstructionProject Construction 319 11-06-2017 A 01-24-2019
CON4050 Mobilize for Construction (GC) 0 11-06-2017 A
CON4000 Construction (GC) 258 11-06-2017* 10-31-2018
CON4040 Construction Complete / Turnover Space to CPFMD (GC) 0 11-01-2018*
CON4010 Install FF&E (Vendors) 30 11-02-2018* 12-13-2018
CON4020 Tenant Move In (ASD) 5 12-14-2018* 12-20-2018
CON4030 De-Commission Vacated Space (CPFMD) 14 12-21-2018* 01-09-2019
CON4070 Closeout Construction Contract (GC) 60 11-02-2018* 01-24-2019
CON4080 Contruction Contract Complete 0 01-24-2019*
CON4090 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 01-24-2019*
CON4100 Enter Fixed Assests into Manager Plus (CM/PM) 0 01-24-2019*
CON4110 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 01-24-2019* Project Construction Warranty PeriodProject Construction Warranty Period 261 11-01-2018 11-01-2019
WTY2250 One year warranty Period Begins 0 11-01-2018*
WTY2260 3 month Inspection (CM/PM - O&M Team to conduct) 0 01-30-2019*
WTY2270 6 month Inspection (CM/PM - O&M Team to conduct) 0 04-30-2019*
WTY2280 9 month Inspection (CM/PM - O&M Team to conduct) 0 07-31-2019*
WTY2290 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 11-01-2019* Phase 2APhase 2A 983 03-16-2016 A 12-20-2019 Project ConstructionProject Construction 761 03-16-2016 A 02-13-2019
CON1170 Mobilize for Construction (GC) 0 03-16-2016 A
CON1180 Issue Construction NTP (ASD) 0 03-17-2016 A
CON1130 Install FF&E (Vendors) 30 10-01-2018 11-14-2018
CON1120 Construction (GC) 721 03-17-2016* 12-19-2018
CON1160 Turnover Space to CPFMD (GC) 0 12-20-2018
CON1140 Tenant Move In (ASD) 5 12-21-2018 12-28-2018
CON1150 De-Commission Vacated Space (CPFMD) 14 12-28-2018 01-17-2019
CON1190 Closeout Construction Contract (GC) 39 12-20-2018 02-13-2019
CON1200 Contruction Contract Complete 0 02-13-2019
CON1210 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 02-13-2019
CON1220 Enter Fixed Assests into Manager Plus (CM/PM) 0 02-13-2019
CON1230 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 02-13-2019 Project Construction Warranty PeriodProject Construction Warranty Period 261 12-20-2018 12-20-2019
WTY1050 One year warranty Period Begins 0 12-20-2018
WTY1060 3 month Inspection (CM/PM - O&M Team to conduct) 0 03-20-2019
WTY1070 6 month Inspection (CM/PM - O&M Team to conduct) 0 06-18-2019
WTY1080 9 month Inspection (CM/PM - O&M Team to conduct) 0 09-18-2019
WTY1090 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 12-20-2019 PH2B PREDECESSOR - HCMCB (East/Ste 4485) Renov Int Juv Intake & Re-Config Ment HealthPH2B PREDECESSOR - HCMCB (East/Ste 4485) Renov Int Juv Intake & Re-Config Ment Health 318 10-04-2018 12-24-2019 Project PlanningProject Planning 0 Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 0 10-04-2018 10-04-2018
DPP1370 Award Construction Contract (ASD) 0 10-04-2018* Project ConstructionProject Construction 117 10-04-2018 03-15-2019
CON1530 Mobilize for Construction (GC) 14 10-04-2018 10-23-2018
CON1540 Issue Construction NTP (ASD) 0 10-24-2018
CON1480 Construction (GC) 60 10-24-2018 12-22-2018
CON1520 Turnover Space to CPFMD (GC) 0 12-24-2018
CON1490 Install FF&E (Vendors) 30 12-24-2018 02-01-2019
CON1500 Tenant Move In (ASD) 5 02-04-2019 02-08-2019
CON1510 De-Commission Vacated Space (CPFMD) 14 02-11-2019 02-28-2019
CON1550 Closeout Construction Contract (GC) 60 12-24-2018 03-15-2019
CON1560 Contruction Contract Complete 0 03-15-2019
CON1570 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 03-15-2019
CON1580 Enter Fixed Assests into Manager Plus (CM/PM) 0 03-15-2019
CON1590 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 03-15-2019 Project Construction Warranty PeriodProject Construction Warranty Period 261 12-24-2018 12-24-2019
WTY1200 One year warranty Period Begins 0 12-24-2018
WTY1210 3 month Inspection (CM/PM - O&M Team to conduct) 0 03-25-2019
WTY1220 6 month Inspection (CM/PM - O&M Team to conduct) 0 06-24-2019
WTY1230 9 month Inspection (CM/PM - O&M Team to conduct) 0 09-23-2019
WTY1240 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 12-24-2019 Phase 2BPhase 2B 993 04-12-2018 A 02-01-2022 Project PlanningProject Planning 0 Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 606 04-12-2018 A 08-07-2020
DPP1210 Award Construction Contract (ASD) 0 04-12-2018 A
DPP1230 Solicit FF&E Vendor Contracts (ASD) 186 02-03-2020* 08-06-2020
DPP1240 Award FF&E Vendor Contracts(ASD) 0 08-07-2020 Project ConstructionProject Construction 806 12-03-2018 A 05-13-2021
CON1300 Issue Construction NTP (ASD) 0 12-03-2018 A
CON1290 Mobilize for Construction (GC) 14 02-01-2019* 02-14-2019
CON1240 Construction (GC) 686 02-15-2019 12-31-2020
CON1280 Turnover Space to CPFMD (GC) 0 01-04-2021
CON1310 Closeout Construction Contract (GC) 60 01-04-2021* 03-04-2021
CON1320 Contruction Complete 0 03-05-2021
CON1330 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 03-05-2021
CON1340 Enter Fixed Assests into Manager Plus (CM/PM) 0 03-05-2021
CON1350 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 03-05-2021
CON1250 Install FF&E (Vendors) 90 01-04-2021 04-03-2021
CON1260 Tenant Move In (ASD) 15 04-05-2021 04-23-2021
CON1270 De-Commission Vacated Space (CPFMD) 14 04-26-2021 05-13-2021 Project Construction Warranty PeriodProject Construction Warranty Period 261 02-01-2021 02-01-2022
WTY1100 One year warranty Period Begins 0 02-01-2021*
WTY1110 3 month Inspection (CM/PM - O&M Team to conduct) 0 05-01-2021
WTY1120 6 month Inspection (CM/PM - O&M Team to conduct) 0 08-02-2021
WTY1130 9 month Inspection (CM/PM - O&M Team to conduct) 0 11-01-2021
WTY1140 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 02-01-2022 PH2B SUPPORT - HCMCB (East/C Level) Construct Social Services TDYC & DYRSPH2B SUPPORT - HCMCB (East/C Level) Construct Social Services TDYC & DYRS 521 09-01-2018 09-01-2020 Project PlanningProject Planning 0 09-01-2018 09-01-2018
PP1080 Award AMS Contracts (ASD) 0 09-01-2018* Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 293 10-02-2018 07-22-2019
DPP1700 Issue Design NTP (CPFMD) 0 10-02-2018*
DPP1640 Design (A/E) 90 10-02-2018* 12-30-2018
DPP1650 Develop Construction RFP (CM/PM & ASD) 104 10-02-2018* 01-13-2019
DPP1660 Release Construction RFP for Bid (ASD) 0 01-14-2019
DPP1670 Acquire Building Permit (CM/PM) 30 12-31-2018 01-29-2019
DPP1680 Convene SSEB (ASD) 5 02-13-2019 02-17-2019
DPP1690 Award Construction Contract (ASD) 0 02-18-2019
DPP1710 Solicit FF&E Vendor Contracts (ASD) 60 05-23-2019 07-22-2019 Project ConstructionProject Construction 184 02-18-2019 11-01-2019
CON2020 Issue Construction NTP (ASD) 0 02-18-2019
CON2010 Mobilize for Construction (GC) 14 02-18-2019 03-03-2019
CON1960 Construction (GC) 180 03-04-2019 08-30-2019
CON2000 Turnover Space to CPFMD (GC) 0 09-02-2019
CON1970 Install FF&E (Vendors) 15 09-03-2019 09-23-2019
CON1980 Tenant Move In (ASD) 2 09-24-2019 09-25-2019
CON1990 De-Commission Vacated Space (CPFMD) 14 09-25-2019 10-09-2019
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2016 2017 2018 2019 2020 2021 2022 2023
02-01-2022, Moultrie Courthouse Addition
11-01-2019, HCMCB (West) Renovate Health Unit (Permanent Location
01-24-2019, Project Construction
Mobilize for Construction (GC), 11-06-2017 A
Construction (GC) Construction Complete / Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 11-01-2019, Project Construction Warranty Period
One year warranty Period Begins, 11-01-2018*
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 12-20-2019, Phase 2A
02-13-2019, Project Construction
Mobilize for Construction (GC), 03-16-2016 A
Issue Construction NTP (ASD), 03-17-2016 A
Install FF&E (Vendors)
Construction (GC) Turnover Space to CPFMD (GC), Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 12-20-2019, Project Construction Warranty Period
One year warranty Period Begins, 12-20-2018
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 12-24-2019, PH2B PREDECESSOR - HCMCB (East/Ste 4485) Renov Int Juv Intake & Re-Config Ment Health
10-04-2018, Project Design, Permitting & Procurement
Award Construction Contract (ASD), 10-04-2018*
03-15-2019, Project Construction
Mobilize for Construction (GC) Issue Construction NTP (ASD), 10-24-2018
Construction (GC) Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 12-24-2019, Project Construction Warranty Period
One year warranty Period Begins, 12-24-2018
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 02-01-2022, Phase 2B
08-07-2020, Project Design, Permitting & Procurement
Award Construction Contract (ASD), 04-12-2018 A
Solicit FF&E Vendor Contracts (ASD) Award FF&E Vendor Contracts(ASD), 05-13-2021, Project Construction
Issue Construction NTP (ASD), 12-03-2018 A
Mobilize for Construction (GC)
Construction (GC) Turnover Space to CPFMD (GC), Closeout Construction Contract (GC) Contruction Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD) 02-01-2022, Project Construction Warranty Period
One year warranty Period Begins, 02-01-2021*
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 09-01-2020, PH2B SUPPORT - HCMCB (East/C Level) Construct Social Services TDYC & DYRS
09-01-2018, Project Planning
Award AMS Contracts (ASD), 07-22-2019, Project Design, Permitting & Procurement
Issue Design NTP (CPFMD), 10-02-2018*
Design (A/E)
Develop Construction RFP (CM/PM & ASD) Release Construction RFP for Bid (ASD), 01-14-2019
Acquire Building Permit (CM/PM)
Convene SSEB (ASD) Award Construction Contract (ASD), 02-18-2019
Solicit FF&E Vendor Contracts (ASD) 11-01-2019, Project Construction
Issue Construction NTP (ASD), 02-18-2019
Mobilize for Construction (GC)
Construction (GC) Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
CPFMD - INTEGRATED PROGRAM SCHEDULE 10/29/18 DC Courts Consolidated Schedule 10-30-2018 08:01
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary Page 1 of 6 TASK filter: All Activities
© Oracle Corporation
Start Finish
CON2030 Closeout Construction Contract (GC) 60 09-02-2019 10-31-2019
CON2040 Contruction Contract Complete 0 11-01-2019
CON2050 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 11-01-2019
CON2060 Enter Fixed Assests into Manager Plus (CM/PM) 0 11-01-2019
CON2070 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 11-01-2019 Project Construction Warranty PeriodProject Construction Warranty Period 261 09-02-2019 09-01-2020
WTY1400 One year warranty Period Begins 0 09-02-2019
WTY1410 3 month Inspection (CM/PM - O&M Team to conduct) 0 12-02-2019
WTY1420 6 month Inspection (CM/PM - O&M Team to conduct) 0 03-02-2020
WTY1430 9 month Inspection (CM/PM - O&M Team to conduct) 0 06-01-2020
WTY1440 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 09-01-2020 PH2B SUPPORT - HCMCB (East) Renovate Public Corridor & Upgrade Sprinklers (adjacent to Social Svcs)PH2B SUPPORT - HCMCB (East) Renovate Public Corridor & Upgrade Sprinklers (adjacent to Social Svcs) 629 10-01-2018 03-01-2021 Project PlanningProject Planning 0 10-01-2018 10-01-2018
PP1090 Award AMS Contracts (ASD) 0 10-01-2018* Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 454 11-01-2018 01-29-2020
DPP1780 Issue Design NTP (CPFMD) 0 11-01-2018*
DPP1720 Design (A/E) 180 11-01-2018* 04-29-2019
DPP1730 Develop Construction RFP (CM/PM & ASD) 104 01-30-2019* 05-13-2019
DPP1740 Release Construction RFP for Bid (ASD) 0 05-14-2019
DPP1750 Acquire Building Permit (CM/PM) 30 04-30-2019 05-29-2019
DPP1760 Convene SSEB 5 06-13-2019 06-17-2019
DPP1770 Award Construction Contract (ASD) 0 06-18-2019
DPP1790 Solicit FF&E Vendor Contracts (ASD) 60 11-30-2019 01-29-2020 Project ConstructionProject Construction 225 06-18-2019 04-28-2020
CON2130 Mobilize for Construction (GC) 14 06-18-2019 07-01-2019
CON2140 Issue Construction NTP (ASD) 0 07-02-2019
CON2080 Construction (GC) 240 07-02-2019 02-26-2020
CON2120 Turnover Space to CPFMD (GC) 0 02-27-2020
CON2090 Install FF&E (Vendors) 30 02-28-2020 03-28-2020
CON2100 Tenant Move In (ASD) 5 03-30-2020 04-03-2020
CON2110 De-Commission Vacated Space (CPFMD) 14 04-06-2020 04-23-2020
CON2150 Closeout Construction Contract (GC) 60 02-28-2020 04-27-2020
CON2160 Contruction Contract Complete 0 04-28-2020
CON2170 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 04-28-2020
CON2180 Enter Fixed Assests into Manager Plus (CM/PM) 0 04-28-2020
CON2190 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 04-28-2020 Project Construction Warranty PeriodProject Construction Warranty Period 261 02-28-2020 03-01-2021
WTY1450 One year warranty Period Begins 0 02-28-2020
WTY1460 3 month Inspection (CM/PM - O&M Team to conduct) 0 05-28-2020
WTY1470 6 month Inspection (CM/PM - O&M Team to conduct) 0 08-26-2020
WTY1480 9 month Inspection (CM/PM - O&M Team to conduct) 0 11-26-2020
WTY1490 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 03-01-2021 PH2B SUPPORT - HCMCB (East/C600) Renovate for USMS Admin ConsolidationPH2B SUPPORT - HCMCB (East/C600) Renovate for USMS Admin Consolidation 529 06-29-2018 07-09-2020 Project PlanningProject Planning 0 06-29-2018 06-29-2018
PP1100 Award AMS Contracts (ASD) 0 06-29-2018* Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 304 08-10-2018 06-10-2019
DPP2980 Issue Design NTP (CPFMD) 0 08-10-2018*
DPP2920 Design (A/E) 90 08-10-2018 11-08-2018*
DPP2930 Develop Construction RFP (CM/PM & ASD) 104 08-10-2018* 11-22-2018
DPP2940 Release Construction RFP for Bid (ASD) 0 11-22-2018
DPP2950 Acquire Building Permit (CM/PM) 30 11-08-2018 12-08-2018
DPP2960 Convene SSEB (ASD) 5 12-22-2018 12-27-2018
DPP2970 Award Construction Contract (ASD) 0 12-27-2018
DPP2990 Solicit FF&E Vendor Contracts (ASD) 60 04-11-2019 06-10-2019 Project ConstructionProject Construction 255 12-27-2018 09-08-2019
CON2260 Issue Construction NTP (ASD) 0 12-27-2018
CON2250 Mobilize for Construction (GC) 14 12-27-2018 01-10-2019
CON2200 Construction (GC) 180 01-10-2019 07-09-2019
CON2240 Turnover Space to CPFMD (GC) 0 07-10-2019
CON2210 Install FF&E (Vendors) 30 07-10-2019 08-09-2019
CON2220 Tenant Move In (ASD) 5 08-09-2019 08-14-2019
CON2230 De-Commission Vacated Space (CPFMD) 14 08-14-2019 08-28-2019
CON2270 Closeout Construction Contract (GC) 60 07-10-2019 09-08-2019
CON2280 Contruction Complete 0 09-08-2019
CON2290 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 09-08-2019
CON2300 Enter Fixed Assests into Manager Plus (CM/PM) 0 09-08-2019
CON2310 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 09-08-2019 Project Construction Warranty PeriodProject Construction Warranty Period 365 07-10-2019 07-09-2020
WTY1500 One year warranty Period Begins 0 07-10-2019
WTY1510 3 month Inspection (CM/PM - O&M Team to conduct) 0 10-08-2019
WTY1520 6 month Inspection (CM/PM - O&M Team to conduct) 0 01-06-2020
WTY1530 9 month Inspection (CM/PM - O&M Team to conduct) 0 04-07-2020
WTY1540 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 07-09-2020 PH2B SUPPORT - HCMCB (East/4th Level) Construct Training & Con Rms, Juror's Lounge & Bus CtrPH2B SUPPORT - HCMCB (East/4th Level) Construct Training & Con Rms, Juror's Lounge & Bus Ctr 636 11-01-2018 04-12-2021 Project PlanningProject Planning 0 11-01-2018 11-01-2018
PP1110 Award AMS Contracts (ASD) 0 11-01-2018* Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 302 12-14-2018 02-11-2020
DPP1940 Issue Design NTP (CPFMD) 0 12-14-2018*
DPP1880 Design (A/E) 180 12-14-2018* 06-11-2019
DPP1890 Develop Construction RFP (CM/PM & ASD) 104 03-14-2019* 06-25-2019
DPP1900 Release Construction RFP for Bid (ASD) 0 06-26-2019
DPP1910 Acquire Building Permit (CM/PM) 30 06-12-2019 07-11-2019
DPP1920 Convene SSEB for Construction Contract (ASD) 5 07-26-2019 07-30-2019
DPP1930 Award Construction Contract (ASD) 0 07-31-2019
DPP1950 Solicit FF&E Vendor Contracts (ASD) 60 12-13-2019* 02-11-2020 Project Construction / Post ConstructionProject Construction / Post Construction 225 07-31-2019 06-10-2020
CON2380 Issue Construction NTP (ASD) 0 07-31-2019
CON2370 Mobilize for Construction (GC) 14 07-31-2019 08-13-2019
CON2320 Construction (GC) 240 08-14-2019 04-09-2020
CON2360 Contruction Complete / Turnover Space to CPFMD (GC) 0 04-10-2020
CON2330 Install FF&E (Vendors) 30 04-11-2020 05-10-2020
CON2340 Tenant Move In (ASD) 5 05-11-2020 05-15-2020
CON2350 De-Commission Vacated Space (CPFMD) 14 05-16-2020 05-29-2020
CON2390 Closeout Construction Contract (GC) 60 04-11-2020 06-09-2020
CON2400 Contruction Contract Complete 0 06-10-2020
CON2410 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 06-10-2020
CON2420 Enter Fixed Assests into Manager Plus (CM/PM) 0 06-10-2020
CON2430 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 06-10-2020 Project Construction Warranty PeriodProject Construction Warranty Period 260 04-11-2020 04-12-2021
WTY1550 One year warranty Period Begins 0 04-11-2020
WTY1560 3 month Inspection (CM/PM - O&M Team to conduct) 0 07-10-2020
WTY1570 6 month Inspection (CM/PM - O&M Team to conduct) 0 10-08-2020
WTY1580 9 month Inspection (CM/PM - O&M Team to conduct) 0 01-08-2021
WTY1590 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 04-12-2021 PH2B SUPPORT - HCMCB (East/Suite 1195) Renovate Security Office (Final Location)PH2B SUPPORT - HCMCB (East/Suite 1195) Renovate Security Office (Final Location) 775 10-12-2018 10-01-2021 Project PlanningProject Planning 0 10-12-2018 10-12-2018
PP1120 Award AMS Contracts (ASD) 0 10-12-2018* Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 454 11-26-2018 08-21-2020
DPP2020 Issue Design NTP (CPFMD) 0 11-26-2018
DPP1960 Design (A/E) 180 11-26-2018* 08-02-2019
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2016 2017 2018 2019 2020 2021 2022 2023
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 09-01-2020, Project Construction Warranty Period
One year warranty Period Begins, 09-02-2019
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 03-01-2021, PH2B SUPPORT - HCMCB (East) Renovate Public Corridor & Upgrade Sprinklers (adjacent to Social Svcs)
10-01-2018, Project Planning
Award AMS Contracts (ASD), 01-29-2020, Project Design, Permitting & Procurement
Issue Design NTP (CPFMD), 11-01-2018*
Design (A/E)
Develop Construction RFP (CM/PM & ASD) Release Construction RFP for Bid (ASD), 05-14-2019
Acquire Building Permit (CM/PM)
Convene SSEB Award Construction Contract (ASD), 06-18-2019
Solicit FF&E Vendor Contracts (ASD) 04-28-2020, Project Construction
Mobilize for Construction (GC) Issue Construction NTP (ASD), 07-02-2019
Construction (GC) Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 03-01-2021, Project Construction Warranty Period
One year warranty Period Begins, 02-28-2020
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 07-09-2020, PH2B SUPPORT - HCMCB (East/C600) Renovate for USMS Admin Consolidation
06-29-2018, Project Planning
Award AMS Contracts (ASD), 06-10-2019, Project Design, Permitting & Procurement
Issue Design NTP (CPFMD), 08-10-2018*
Design (A/E)
Develop Construction RFP (CM/PM & ASD) Release Construction RFP for Bid (ASD), 11-22-2018
Acquire Building Permit (CM/PM)
Convene SSEB (ASD) Award Construction Contract (ASD), 12-27-2018
Solicit FF&E Vendor Contracts (ASD) 09-08-2019, Project Construction
Issue Construction NTP (ASD), 12-27-2018
Mobilize for Construction (GC)
Construction (GC) Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 07-09-2020, Project Construction Warranty Period
One year warranty Period Begins, 07-10-2019
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 04-12-2021, PH2B SUPPORT - HCMCB (East/4th Level) Construct Training & Con Rms, Juror's Lounge & Bus Ctr
11-01-2018, Project Planning
Award AMS Contracts (ASD), 02-11-2020, Project Design, Permitting & Procurement
Issue Design NTP (CPFMD), 12-14-2018*
Design (A/E)
Develop Construction RFP (CM/PM & ASD) Release Construction RFP for Bid (ASD), 06-26-2019
Acquire Building Permit (CM/PM)
Convene SSEB for Construction Contract (ASD) Award Construction Contract (ASD), 07-31-2019
Solicit FF&E Vendor Contracts (ASD) 06-10-2020, Project Construction / Post Construction
Issue Construction NTP (ASD), 07-31-2019
Mobilize for Construction (GC)
Construction (GC) Contruction Complete / Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 04-12-2021, Project Construction Warranty Period
One year warranty Period Begins, 04-11-2020
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 10-01-2021, PH2B SUPPORT - HCMCB (East/Suite 1195) Renovate Security Office (Final Location)
10-12-2018, Project Planning
Award AMS Contracts (ASD), 08-21-2020, Project Design, Permitting & Procurement
Issue Design NTP (CPFMD), 11-26-2018
Design (A/E)
CPFMD - INTEGRATED PROGRAM SCHEDULE 10/29/18 DC Courts Consolidated Schedule 10-30-2018 08:01
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary Page 2 of 6 TASK filter: All Activities
Start Finish
DPP1970 Develop Construction RFP (CM/PM & ASD) 104 04-01-2019* 08-22-2019
DPP1980 Release Construction RFP for Bid (ASD) 0 08-23-2019
DPP1990 Acquire Building Permit (CM/PM) 30 08-05-2019 09-13-2019
DPP2000 Convene SSEB for Construction Contract (ASD) 5 10-04-2019 10-10-2019
DPP2010 Award Construction Contract (ASD) 0 10-11-2019
DPP2030 Solicit FF&E Vendor Contracts (ASD) 60 05-29-2020 08-21-2020 Project ConstructionProject Construction 315 10-11-2019 12-24-2020
CON2500 Issue Construction NTP (ASD) 0 10-11-2019
CON2490 Mobilize for Construction (GC) 14 10-11-2019 10-30-2019
CON2440 Construction (GC) 240 10-31-2019 09-30-2020
CON2480 Turnover Space to CPFMD (GC) 0 10-01-2020
CON2450 Install FF&E (Vendors) 30 10-02-2020 11-12-2020
CON2460 Tenant Move In (ASD) 5 11-13-2020 11-19-2020
CON2470 De-Commission Vacated Space (CPFMD) 14 11-20-2020 12-09-2020
CON2510 Closeout Construction Contract (GC) 60 10-02-2020 12-24-2020
CON2520 Contruction Contract Complete 0 12-24-2020
CON2530 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 12-24-2020
CON2540 Enter Fixed Assests into Manager Plus (CM/PM) 0 12-24-2020
CON2550 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 12-24-2020 Project Construction Warranty PeriodProject Construction Warranty Period 261 10-01-2020 10-01-2021
WTY1600 One year warranty Period Begins 0 10-01-2020
WTY1610 3 month Inspection (CM/PM - O&M Team to conduct) 0 12-30-2020
WTY1620 6 month Inspection (CM/PM - O&M Team to conduct) 0 03-30-2021
WTY1630 9 month Inspection (CM/PM - O&M Team to conduct) 0 06-30-2021
WTY1640 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 10-01-2021 PH2B SUPPORT - HCMCB (East/Suite C185) Ren Suite C185 Press Rm, Pre-Trial Svcs & Forensic PsychPH2B SUPPORT - HCMCB (East/Suite C185) Ren Suite C185 Press Rm, Pre-Trial Svcs & Forensic Psych 514 08-10-2018 07-30-2020 Project PlanningProject Planning 0 08-10-2018 08-10-2018
PP1130 Award AMS Contracts (ASD) 0 08-10-2018* Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 244 10-31-2018 07-02-2019
DPP3060 Issue Design NTP (CPFMD) 0 10-31-2018*
DPP3000 Design (A/E) 90 10-31-2018* 01-28-2019
DPP3010 Develop Construction RFP (CM/PM & ASD) 104 10-31-2018* 02-11-2019
DPP3020 Release Construction RFP for Bid (ASD) 0 02-12-2019
DPP3030 Acquire Building Permit (CM/PM) 30 01-29-2019 02-27-2019
DPP3040 Convene SSEB (ASD) 5 03-14-2019 03-18-2019
DPP3050 Award Construction Contract (ASD) 0 03-19-2019
DPP3070 Solicit FF&E Vendor Contracts (ASD) 60 05-03-2019 07-02-2019 Project ConstructionProject Construction 139 03-19-2019 09-30-2019
CON2620 Issue Construction NTP (ASD) 0 03-19-2019
CON2610 Mobilize for Construction (GC) 14 03-19-2019 04-01-2019
CON2560 Construction (GC) 120 04-02-2019 07-30-2019
CON2600 Turnover Space to CPFMD (GC) 0 07-31-2019
CON2570 Install FF&E (Vendors) 30 08-01-2019 08-30-2019
CON2580 Tenant Move In (ASD) 5 08-31-2019 09-04-2019
CON2590 De-Commission Vacated Space (CPFMD) 14 09-05-2019 09-18-2019
CON2630 Closeout Construction Contract (GC) 60 08-01-2019 09-29-2019
CON2640 Contruction Contract Complete 0 09-30-2019
CON2650 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 09-30-2019
CON2660 Enter Fixed Assests into Manager Plus (CM/PM) 0 09-30-2019
CON2670 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 09-30-2019 Project Construction Warranty PeriodProject Construction Warranty Period 365 08-01-2019 07-30-2020
WTY1650 One year warranty Period Begins 0 08-01-2019
WTY1660 3 month Inspection (CM/PM - O&M Team to conduct) 0 10-29-2019
WTY1670 6 month Inspection (CM/PM - O&M Team to conduct) 0 01-27-2020
WTY1680 9 month Inspection (CM/PM - O&M Team to conduct) 0 04-28-2020
WTY1690 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 07-30-2020
Migration from Gallery Place: Building B initial RenovationMigration from Gallery Place: Building B initial Renovation 978 03-01-2019 11-30-2022
GPLEASEENDGallery Place lease End Date 0 11-30-2022* PH2B CONCURRENT - 515 5th Street (Suites 102, 104) Renovate Office of the Auditor MasterPH2B CONCURRENT - 515 5th Street (Suites 102, 104) Renovate Office of the Auditor Master 531 03-01-2019 03-16-2021 Project PlanningProject Planning 0 03-01-2019 03-01-2019
PP1180 Award AMS Contracts (ASD) 0 03-01-2019* Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 318 04-01-2019 02-13-2020
DPP2500 Issue Design NTP (CPFMD) 0 04-01-2019*
DPP2440 Design (A/E) 90 04-01-2019 06-29-2019
DPP2470 Acquire Building Permit (CM/PM) 30 06-30-2019 07-29-2019
DPP2450 Develop Construction RFP (CM/PM & ASD) 104 05-16-2019 08-27-2019
DPP2460 Release Construction RFP for Bid (ASD) 0 08-28-2019
DPP2480 Convene SSEB (ASD) 5 09-27-2019 10-01-2019
DPP2490 Award Construction Contract (ASD) 0 10-02-2019
DPP2510 Solicit FF&E Vendor Contracts (ASD) 60 12-15-2019 02-13-2020 Project ConstructionProject Construction 162 10-02-2019 05-15-2020
CON3220 Issue Construction NTP (ASD) 0 10-02-2019
CON3210 Mobilize for Construction (GC) 14 10-02-2019 10-15-2019
CON3160 Construction (GC) 150 10-16-2019 03-13-2020
CON3200 Turnover Space to CPFMD (GC) 0 03-16-2020
CON3170 Install FF&E (Vendors) 30 03-16-2020 04-14-2020
CON3180 Tenant Move In (ASD) 5 04-15-2020 04-21-2020
CON3190 De-Commission Vacated Space (CPFMD) 14 04-21-2020 05-05-2020
CON3230 Closeout Construction Contract (GC) 60 03-16-2020 05-14-2020
CON3240 Contruction Contract Complete 0 05-15-2020
CON3250 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 05-15-2020
CON3260 Enter Fixed Assests into Manager Plus (CM/PM) 0 05-15-2020
CON3270 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 05-15-2020 Project Construction Warranty PeriodProject Construction Warranty Period 261 03-16-2020 03-16-2021
WTY1900 One year warranty Period Begins 0 03-16-2020
WTY1910 3 month Inspection (CM/PM - O&M Team to conduct) 0 06-15-2020
WTY1920 6 month Inspection (CM/PM - O&M Team to conduct) 0 09-14-2020
WTY1930 9 month Inspection (CM/PM - O&M Team to conduct) 0 12-14-2020
WTY1940 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 03-16-2021 PH2B CONCURRENT - 510 4th Street (B004, B006) Renovate Pro Se OfficesPH2B CONCURRENT - 510 4th Street (B004, B006) Renovate Pro Se Offices 978 03-01-2019 11-30-2022
GPLEASEEND10Gallery Place lease End Date 0 11-30-2022* Project PlanningProject Planning 0 03-01-2019 03-01-2019
PP1140 Award AMS Contracts (ASD) 0 03-01-2019* Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 282 04-15-2019 05-13-2020
DPP2180 Issue Design NTP (CPFMD) 0 04-15-2019
DPP2120 Design (A/E) 180 04-15-2019* 10-11-2019
DPP2130 Develop Construction RFP (CM/PM & ASD) 104 07-14-2019* 10-25-2019
DPP2140 Release Construction RFP for Bid (ASD) 0 10-26-2019
DPP2150 Acquire Building Permit (CM/PM) 30 10-12-2019 11-10-2019
DPP21610 Convene SSEB (ASD) 5 11-25-2019 11-29-2019
DPP2170 Award Construction Contract (ASD) 0 11-30-2019
DPP2190 Solicit FF&E Vendor Contracts (ASD) 60 03-14-2020 05-13-2020 Project ConstructionProject Construction 181 11-30-2019 08-11-2020
CON2740 Issue Construction NTP (ASD) 0 11-30-2019
CON2730 Mobilize for Construction (GC) 14 11-30-2019 12-13-2019
CON2680 Construction (GC) 180 12-14-2019 06-10-2020
CON2720 Turnover Space to CPFMD (GC) 0 06-11-2020
CON2690 Install FF&E (Vendors) 30 06-12-2020 07-11-2020
CON2700 Tenant Move In (ASD) 5 07-12-2020 07-16-2020
CON2710 De-Commission Vacated Space (CPFMD) 14 07-17-2020 07-30-2020
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2016 2017 2018 2019 2020 2021 2022 2023
Develop Construction RFP (CM/PM & ASD) Release Construction RFP for Bid (ASD), 08-23-2019
Acquire Building Permit (CM/PM)
Convene SSEB for Construction Contract (ASD) Award Construction Contract (ASD), 10-11-2019
Solicit FF&E Vendor Contracts (ASD) 12-24-2020, Project Construction
Issue Construction NTP (ASD), 10-11-2019
Mobilize for Construction (GC)
Construction (GC) Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 10-01-2021, Project Construction Warranty Period
One year warranty Period Begins, 10-01-2020
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 07-30-2020, PH2B SUPPORT - HCMCB (East/Suite C185) Ren Suite C185 Press Rm, Pre-Trial Svcs & Forensic Psych
08-10-2018, Project Planning
Award AMS Contracts (ASD), 07-02-2019, Project Design, Permitting & Procurement
Issue Design NTP (CPFMD), 10-31-2018*
Design (A/E)
Develop Construction RFP (CM/PM & ASD) Release Construction RFP for Bid (ASD), 02-12-2019
Acquire Building Permit (CM/PM)
Convene SSEB (ASD) Award Construction Contract (ASD), 03-19-2019
Solicit FF&E Vendor Contracts (ASD) 09-30-2019, Project Construction
Issue Construction NTP (ASD), 03-19-2019
Mobilize for Construction (GC)
Construction (GC) Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 07-30-2020, Project Construction Warranty Period
One year warranty Period Begins, 08-01-2019
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 11-30-2022, Migration from Gallery Place: Building B initial Renovation
Gallery Place lease End Date, 03-16-2021, PH2B CONCURRENT - 515 5th Street (Suites 102, 104) Renovate Office of the Auditor Master
03-01-2019, Project Planning
Award AMS Contracts (ASD), 02-13-2020, Project Design, Permitting & Procurement
Issue Design NTP (CPFMD), 04-01-2019*
Design (A/E)
Acquire Building Permit (CM/PM)
Develop Construction RFP (CM/PM & ASD) Release Construction RFP for Bid (ASD), 08-28-2019
Convene SSEB (ASD) Award Construction Contract (ASD), 10-02-2019
Solicit FF&E Vendor Contracts (ASD) 05-15-2020, Project Construction
Issue Construction NTP (ASD), 10-02-2019
Mobilize for Construction (GC)
Construction (GC) Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 03-16-2021, Project Construction Warranty Period
One year warranty Period Begins, 03-16-2020
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 11-30-2022, PH2B CONCURRENT - 510 4th Street (B004, B006) Renovate Pro Se Offices
Gallery Place lease End Date, 03-01-2019, Project Planning
Award AMS Contracts (ASD), 05-13-2020, Project Design, Permitting & Procurement
Issue Design NTP (CPFMD), 04-15-2019
Design (A/E)
Develop Construction RFP (CM/PM & ASD) Release Construction RFP for Bid (ASD), 10-26-2019
Acquire Building Permit (CM/PM)
Convene SSEB (ASD) Award Construction Contract (ASD), 11-30-2019
Solicit FF&E Vendor Contracts (ASD) 08-11-2020, Project Construction
Issue Construction NTP (ASD), 11-30-2019
Mobilize for Construction (GC)
Construction (GC) Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
CPFMD - INTEGRATED PROGRAM SCHEDULE 10/29/18 DC Courts Consolidated Schedule 10-30-2018 08:01
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary Page 3 of 6 TASK filter: All Activities
Start Finish
CON2750 Closeout Construction Contract (GC) 60 06-12-2020 08-10-2020
CON2760 Contruction Contract Complete 0 08-10-2020
CON2770 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 08-11-2020
CON2790 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 08-11-2020
CON4120 Enter Fixed Assests into Manager Plus (CM/PM) 0 08-11-2020 Project Construction Warranty PeriodProject Construction Warranty Period 261 06-12-2020 06-14-2021
WTY1700 One year warranty Period Begins 0 06-12-2020
WTY1710 3 month Inspection (CM/PM - O&M Team to conduct) 0 09-10-2020
WTY1720 6 month Inspection (CM/PM - O&M Team to conduct) 0 12-09-2020
WTY1730 9 month Inspection (CM/PM - O&M Team to conduct) 0 03-11-2021
WTY1740 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 06-14-2021 PH2B CONCURRENT - 510 4th Street (2nd Fl) Renovate 2nd Fl/CPFMD Offices and Unassigned Office SpacePH2B CONCURRENT - 510 4th Street (2nd Fl) Renovate 2nd Fl/CPFMD Offices and Unassigned Office Space 977 03-01-2019 11-30-2022
GPLEASEEND20Gallery Place lease End Date 0 11-30-2022* Project PlanningProject Planning 0 03-01-2019 03-01-2019
PP1170 Award AMS Contracts (ASD) 0 03-01-2019* Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 385 04-15-2019 10-03-2020
DPP2420 Issue Design NTP (CPFMD) 0 04-15-2019*
DPP2360 Design (A/E) 180 04-15-2019* 10-11-2019
DPP2370 Develop Construction RFP (CM/PM & ASD) 104 07-14-2019 10-25-2019
DPP2380 Release Construction RFP for Bid (ASD) 0 10-26-2019
DPP2390 Acquire Building Permit (CM/PM) 30 10-12-2019 11-10-2019
DPP2400 Convene SSEB (ASD) 5 11-25-2019 11-29-2019
DPP2410 Award Construction Contract (ASD) 0 12-02-2019
DPP2430 Solicit FF&E Vendor Contracts (ASD) 60 08-04-2020 10-03-2020 Project ConstructionProject Construction 284 12-02-2019 01-01-2021
CON3100 Issue Construction NTP (ASD) 0 12-02-2019
CON3090 Mobilize for Construction (GC) 14 12-02-2019 12-15-2019
CON3040 Construction (GC) 321 12-16-2019 10-31-2020
CON3080 Turnover Space to CPFMD (GC) 0 11-01-2020
CON3050 Install FF&E (Vendors) 30 11-02-2020 12-01-2020
CON3060 Tenant Move In (ASD) 5 12-02-2020 12-06-2020
CON3070 De-Commission Vacated Space (CPFMD) 14 12-07-2020 12-20-2020
CON3110 Closeout Construction Contract (GC) 60 11-02-2020 12-31-2020
CON3120 Contruction Contract Complete 0 01-01-2021
CON3130 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 01-01-2021
CON3140 Enter Fixed Assests into Manager Plus (CM/PM) 0 01-01-2021
CON3150 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 01-01-2021 Project Construction Warranty PeriodProject Construction Warranty Period 261 11-02-2020 11-02-2021
WTY1850 One year warranty Period Begins 0 11-02-2020
WTY1860 3 month Inspection (CM/PM - O&M Team to conduct) 0 02-01-2021
WTY1870 6 month Inspection (CM/PM - O&M Team to conduct) 0 05-03-2021
WTY1880 9 month Inspection (CM/PM - O&M Team to conduct) 0 08-02-2021
WTY1890 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 11-02-2021 PH2B CONCURRENT - 510 4th Street (Location TBD) Renovate Interim Social Services, TDYC & DYRSPH2B CONCURRENT - 510 4th Street (Location TBD) Renovate Interim Social Services, TDYC & DYRS 745 03-01-2019 01-07-2022 Project PlanningProject Planning 0 03-01-2019 03-01-2019
PP1150 Award AMS Contracts (ASD) 0 03-01-2019* Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 424 04-15-2019 11-27-2020
DPP2260 Issue Design NTP (CPFMD) 0 04-15-2019
DPP2200 Design (A/E) 150 04-15-2019* 11-08-2019
DPP2210 Develop Construction RFP (CM/PM & ASD) 104 07-08-2019* 11-28-2019
DPP2220 Release Construction RFP for Bid (ASD) 0 11-29-2019
DPP2230 Acquire Building Permit (CM/PM) 30 11-11-2019 12-20-2019
DPP2240 Convene SSEB (ASD) 5 01-10-2020 01-16-2020
DPP2250 Award Construction Contract (ASD) 0 01-17-2020
DPP2270 Solicit FF&E Vendor Contracts (ASD) 60 09-04-2020 11-27-2020 Project ConstructionProject Construction 315 01-17-2020 04-01-2021
CON2860 Issue Construction NTP (ASD) 0 01-17-2020
CON2850 Mobilize for Construction (GC) 14 01-17-2020 02-05-2020
CON2800 Construction (GC) 240 02-06-2020 01-06-2021
CON2840 Turnover Space to CPFMD (GC) 0 01-07-2021
CON2810 Install FF&E (Vendors) 30 01-08-2021 02-18-2021
CON2820 Tenant Move In (ASD) 5 02-19-2021 02-25-2021
CON2830 De-Commission Vacated Space (CPFMD) 14 02-26-2021 03-17-2021
CON2870 Closeout Construction Contract (GC) 60 01-08-2021 04-01-2021
CON2880 Contruction Contract Complete 0 04-01-2021
CON2890 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 04-01-2021
CON2900 Enter Fixed Assests into Manager Plus (CM/PM) 0 04-01-2021
CON2910 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 04-01-2021 Project Construction Warranty PeriodProject Construction Warranty Period 261 01-07-2021 01-07-2022
WTY1750 One year warranty Period Begins 0 01-07-2021
WTY1760 3 month Inspection (CM/PM - O&M Team to conduct) 0 04-07-2021
WTY1770 6 month Inspection (CM/PM - O&M Team to conduct) 0 07-06-2021
WTY1780 9 month Inspection (CM/PM - O&M Team to conduct) 0 10-06-2021
WTY1790 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 01-07-2022 PH2B CONCURRENT - 510 4th Street (3rd Fl) Renovate 3rd Floor/ASD, Budget & Finance OfficePH2B CONCURRENT - 510 4th Street (3rd Fl) Renovate 3rd Floor/ASD, Budget & Finance Office 775 03-01-2019 02-18-2022 Project PlanningProject Planning 0 03-01-2019 03-01-2019
PP1160 Award AMS Contracts (ASD) 0 03-01-2019* Project Design, Permitting & ProcurementProject Design, Permitting & Procurement 454 04-15-2019 01-08-2021
DPP2340 Issue Design NTP (CPFMD) 0 04-15-2019
DPP2280 Design (A/E) 180 04-15-2019* 12-20-2019
DPP2290 Develop Construction RFP (CM/PM & ASD) 104 08-19-2019* 01-09-2020
DPP2300 Release Construction RFP for Bid (ASD) 0 01-10-2020
DPP2310 Acquire Building Permit (CM/PM) 30 12-23-2019 01-31-2020
DPP2320 Convene SSEB (ASD) 5 02-21-2020 02-27-2020
DPP2330 Award Construction Contract (ASD) 0 02-28-2020
DPP2350 Solicit FF&E Vendor Contracts (ASD) 60 10-16-2020 01-08-2021 Project ConstructionProject Construction 315 02-28-2020 05-13-2021
CON2980 Issue Construction NTP (ASD) 0 02-28-2020
CON2970 Mobilize for Construction (GC) 14 02-28-2020 03-18-2020
CON2920 Construction (GC) 240 03-19-2020 02-17-2021
CON2960 Turnover Space to CPFMD (GC) 0 02-18-2021
CON2930 Install FF&E (Vendors) 30 02-19-2021 04-01-2021
CON2940 Tenant Move In (ASD) 5 04-02-2021 04-08-2021
CON2950 De-Commission Vacated Space (CPFMD) 14 04-09-2021 04-28-2021
CON2990 Closeout Construction Contract (GC) 60 02-19-2021 05-13-2021
CON3000 Contruction Contract Complete 0 05-13-2021
CON3010 Deliver Completed Close-out Documents to O&M Team (CM/PM) 0 05-13-2021
CON3020 Enter Fixed Assests into Manager Plus (CM/PM) 0 05-13-2021
CON3030 Enter Moveable and Interior Assests into FM Systems (CM/PM) 0 05-13-2021 Project Construction Warranty PeriodProject Construction Warranty Period 261 02-18-2021 02-18-2022
WTY1800 One year warranty Period Begins 0 02-18-2021
WTY1810 3 month Inspection (CM/PM - O&M Team to conduct) 0 05-19-2021
WTY1820 6 month Inspection (CM/PM - O&M Team to conduct) 0 08-17-2021
WTY1830 9 month Inspection (CM/PM - O&M Team to conduct) 0 11-17-2021
WTY1840 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End 0 02-18-2022
510 4th Street Modernization: Building B Remaining Renovation510 4th Street Modernization: Building B Remaining Renovation 0
Courtroom & Judge's ChambersCourtroom & Judge's Chambers 1974 04-01-2019 11-01-2023
Courtroom & Judge's Chambers ProjectsCourtroom & Judge's Chambers Projects 430 04-01-2019 03-30-2020
A1040 Construction, Install FF&E, TMI - HCMCB (West) Renovate 3rd Floor Courtrooms & Public Corridors 430 04-01-2019* 03-30-2020 Courtroom & Judge's Chambers Projects-1Courtroom & Judge's Chambers Projects-1 1327 10-01-2020 11-01-2023
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2016 2017 2018 2019 2020 2021 2022 2023
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), 06-14-2021, Project Construction Warranty Period
One year warranty Period Begins, 06-12-2020
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 11-30-2022, PH2B CONCURRENT - 510 4th Street (2nd Fl) Renovate 2nd Fl/CPFMD Offices and Unassigned Office Space
Gallery Place lease End Date, 03-01-2019, Project Planning
Award AMS Contracts (ASD), 10-03-2020, Project Design, Permitting & Procurement
Issue Design NTP (CPFMD), 04-15-2019*
Design (A/E)
Develop Construction RFP (CM/PM & ASD) Release Construction RFP for Bid (ASD), 10-26-2019
Acquire Building Permit (CM/PM)
Convene SSEB (ASD) Award Construction Contract (ASD), 12-02-2019
Solicit FF&E Vendor Contracts (ASD) 01-01-2021, Project Construction
Issue Construction NTP (ASD), 12-02-2019
Mobilize for Construction (GC)
Construction (GC) Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 11-02-2021, Project Construction Warranty Period
One year warranty Period Begins, 11-02-2020
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 01-07-2022, PH2B CONCURRENT - 510 4th Street (Location TBD) Renovate Interim Social Services, TDYC & DYRS
03-01-2019, Project Planning
Award AMS Contracts (ASD), 11-27-2020, Project Design, Permitting & Procurement
Issue Design NTP (CPFMD), 04-15-2019
Design (A/E)
Develop Construction RFP (CM/PM & ASD) Release Construction RFP for Bid (ASD), 11-29-2019
Acquire Building Permit (CM/PM)
Convene SSEB (ASD) Award Construction Contract (ASD), 01-17-2020
Solicit FF&E Vendor Contracts (ASD) 04-01-2021, Project Construction
Issue Construction NTP (ASD), 01-17-2020
Mobilize for Construction (GC)
Construction (GC) Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 01-07-2022, Project Construction Warranty Period
One year warranty Period Begins, 01-07-2021
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 02-18-2022, PH2B CONCURRENT - 510 4th Street (3rd Fl) Renovate 3rd Floor/ASD, Budget & Finance Office
03-01-2019, Project Planning
Award AMS Contracts (ASD), 01-08-2021, Project Design, Permitting & Procurement
Issue Design NTP (CPFMD), 04-15-2019
Design (A/E)
Develop Construction RFP (CM/PM & ASD) Release Construction RFP for Bid (ASD), 01-10-2020
Acquire Building Permit (CM/PM)
Convene SSEB (ASD) Award Construction Contract (ASD), 02-28-2020
Solicit FF&E Vendor Contracts (ASD) 05-13-2021, Project Construction
Issue Construction NTP (ASD), 02-28-2020
Mobilize for Construction (GC)
Construction (GC) Turnover Space to CPFMD (GC), Install FF&E (Vendors)
Tenant Move In (ASD)
De-Commission Vacated Space (CPFMD)
Closeout Construction Contract (GC) Contruction Contract Complete, Deliver Completed Close-out Documents to O&M Team (CM/PM), Enter Fixed Assests into Manager Plus (CM/PM), Enter Moveable and Interior Assests into FM Systems (CM/PM), 02-18-2022, Project Construction Warranty Period
One year warranty Period Begins, 02-18-2021
3 month Inspection (CM/PM - O&M Team to conduct), 6 month Inspection (CM/PM - O&M Team to conduct), 9 month Inspection (CM/PM - O&M Team to conduct), 1 Year Inspection (CM/PM - O&M Team to conduct)/ 1 year Warranty End, 03-30-2020, Courtroom & Judge's Chambers Projects
Construction, Install FF&E, TMI - HCMCB (West) Renovate 3rd Floor Courtrooms & Public Corridors
CPFMD - INTEGRATED PROGRAM SCHEDULE 10/29/18 DC Courts Consolidated Schedule 10-30-2018 08:01
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary Page 4 of 6 TASK filter: All Activities
Start Finish
A1320 Construction, Install FF&E, TMI - HCMCB (East/Suite 4475) Refresh/Renovate Swing Space for Magistrate Judges216 10-01-2020* 04-01-2021
A1001 Construction, Install FF&E, TMI - HCMCB (East/Suite 3300) Renovate US Attorneys (Permanent Location)216 10-01-2020* 04-01-2021
A1310 Construction, Install FF&E,…