This is a Request for Qualifications (RFQ) issued by the Georgia State Financing & Investment Commission (GSFIC) on behalf of the Georgia Department of Community Supervision (DCS) for Design Professional Services for Project No. DCS-016, a Day Reporting Center & Field Office in Columbus, Georgia. The project involves designing a new approximately 12,000 gross square foot field office with functionality, aesthetics, and sustainability as core design pillars. The RFQ follows a two-step selection process: Step I requires submission of Statements of Qualifications by October 21, 2025 at 2:00 PM, with finalist firms announced by October 28, 2025. Step II includes a mandatory pre-proposal site visit on November 6, 2025 at 1:00 PM (to be held remotely as the site has not been finalized), a deadline for written questions on November 12, 2025 at 2:00 PM, and formal interviews with the Selection Committee on November 18, 2025. Design Professional services are anticipated to commence in December 2025, with the design phase completing by March 2026, construction starting in March 2026, material completion in March 2027, and occupancy opening in May 2027. The contract will be executed using the GSFIC Design Professional Contract Agreement without modification, and selected firms must use the Owner's Project Management Program (E-Builder) for contract administration.
The preliminary Stated Cost Limitation (SCL) for construction is estimated at $5,000,000, though this may be revised based on final programmatic requirements and funding availability. The project delivery method will be Construction Manager-at-risk (CM/GC). Evaluation criteria for the RFQ include: 25% firm stability (corporate history, growth, resources, litigation history, and financials); 45% project experience and team qualifications (demonstrated ability on comparable projects, principal and team member experience, and previous performance); and 30% approach and suitability (fit to project type, contract administration plan, design timeline, unique qualifications, and office proximity to the project location). The Statement of Qualifications must not exceed 50 pages (excluding licenses and forms), be submitted electronically in PDF format to the GSFIC Egnyte FTP site, and include three required exhibits: a Certification Form, a Contractor Affidavit under O.C.G.A. 13-10-91(b)(1) regarding E-Verify compliance and immigration authorization, and a Disclosure Statement addressing potential conflicts of interest. The project encourages participation by minority-owned business enterprises (MBE), woman-owned business enterprises (WBE), and small business enterprises (SBE), and firms must be registered to do business in Georgia and not currently debarred, suspended, or in default on any public works contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DCS_016_DP Shortlisted Firms.pdf | ||
| 2WR HighestRankedFirm.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Georgia State Financing & Investment Commission
Request for Qualifications RFQ No. DCS-016-DP
(Step I)
And
Request for Interviews (Step II)
To Provide
Design Professional Services for
Project No. DCS-016 Day Reporting Center & Field Office
Columbus, Georgia
TABLE OF CONTENTS
I. PROJECT FACT SHEET
II. RFQ OVERVIEW
1. GENERAL PROJECT INFORMATION
2. PROCUREMENT PROCESS
3. TERMS
III. REQUEST FOR QUALIFICATIONS (RFQ)
1. QUESTIONS
2. MINIMUM QUALIFICATIONS
3. EVALUATION CRITERIA
4. STATEMENT OF QUALIFICATIONS CONTENTS
5. SUBMITTAL OF STATEMENTS OF QUALIFICATIONS
6. FINALIST NOTIFICATION
IV. REQUEST FOR INTERVIEW (FROM QUALIFIED FINALIST)
1. QUESTIONS
2. PRE-PROPOSAL SITE VISIT
3. INTERVIEW INFORMATION
4. CRITERIA FOR THE EVALUATION OF FIRMS
5. FINAL SELECTION
V. EXHIBITS
1. Exhibit A – Certification Form
2. Exhibit B – Contractor Affidavit Under O.C.G.A §13-10-91(b)(1)
3. Exhibit C – Disclosure Statement
I. PROJECT FACT SHEET
Design Professional Services RFQ No. DCS-016-DP
The following Schedule of Events represents the Owner’s best estimate of the schedule that will be followed.
All times indicated are prevailing times in Atlanta. The Owner reserves the right to adjust the schedule as the Owner deems necessary.
STEP I
Date Time Activity October 1st, 2025 --- RFQ/RFP issued
October 16th, 2025 2:00 PM Deadline for written questions
October 21st, 2025 2:00 PM Statement of Qualifications Due
October 28th, 2025 TBD Evaluation of Qualifications
STEP II
October 28th, 2025 ---- Announcement of finalist firms
November 6th, 2025 1:00 PM Pre-Proposal Site Visit for finalist firms (This will be held remotely due to site not being finalized at this time)
November 12th, 2025 2:00 PM Deadline for written questions
November 18th, 2025 ---- Owner interviews finalist firms
Kelsey Ayers e-mail: Kelsey.ayers@gsfic.ga.gov Phone: 404-270-0207
Upload one (1) electronic copy of the complete package in .pdf format onto the GSFIC / Egnyte ftp site by selecting this link: https://gsfic.egnyte.com/ul/pNZmp64ims and following the upload instructions provided below.
Click on the provided link above, when the page opens, enter name, email address, and company name, click “Continue.”
Drag and drop your file or click the “Browse” button to select a document from your computer. You should see an upload progress bar and when it gets to 100% the upload is complete.
SCHEDULE OF EVENTS
GSFIC POINT OF
CONTACT
EGNYTE UPLOAD
LINK
https://gsfic.egnyte.com/ul/pNZmp64ims
II. RFQ OVERVIEW
Design Professional Services
The Georgia State Financing and Investment Commission (GSFIC), as “Owner”, on behalf the Georgia Department of Community Supervision (“Using Agency” or ''DCS''), is seeking firms interested in providing Design Professional Services for a project known as Project No. DCS-016 – Day Reporting Center & Field Office located in Columbus, Georgia.
1. GENERAL PROJECT INFORMATION
Project Description:
The Georgia Department of Community Supervision plans to build a new Field Office in Columbus, Georgia.
The final site has not yet been determined. It is estimated that the building will be around 12,000 gross sq
ft. DCS has a defined program for this project centered on three core pillars and needs/wants for each area of the field office:
● Functionality: Optimizing space utilization and flow to meet the specific needs of the building's purpose and occupants.
● Aesthetics: Creating a visually appealing structure that complements DCS’s mission and enhances the employee experience.
● Sustainability: Incorporating materials and energy-efficient systems to minimize repairs and reduce long-term operating costs.
Proposed Design Elements:
1. Flooring
● Flooring shall be Polyurea/polyaspartic.
● Cost $6-$12 per sq ft
● Durable and easy to maintain.
● 4-inch black rolled base molding throughout the building.
2. Paint Finishes
● Preferred contract with Sherwin Williams Paint or approved State Contract equal.
● All painting will be primed with two coats of designated paint or stain.
● Exterior Paint: SW7019 Gauntlet Gray
● Interior Pain: SW 7015 Repose Gray Eggshell
● Wood Doors: DB 2107 Driftwood with a clear coat.
● Exterior Doors: SW 7069 Iron Ore
● Outside Trim/Roof: Black Matte
2. Ceilings
● Drop ceiling with 2x2 tiles.
● Sheetrock ceiling in the interview rooms.
● Minimum nine feet ceilings height.
3. Casework & Millwork
● Veneers, laminates, solid surfaces.
● Placement: reception areas, break rooms, interview rooms, bathroom.
4. Hardware & Trim
● Colors and metals: Nickel or stainless steel.
● Consistency across doors, cabinetry, and fixtures.
5. Doors
● Public entrance shall be a glass double door with closer and push bar.
● Employee entrance will be a commercial grade black door with a 7 in x 22 in window with closer.
● Classroom, staff office, breakroom, storage, and conference room doors will be stained with a 7 in x 22 in window.
● Entrance/exit doors, interview rooms on the lobby side, and restrooms will have closers and be stained.
6. Lighting
● 2x4 recessed LEDs.
● Recessed can lights in interview rooms.
● Motion sensors will be installed in all rooms to control the lights.
Specialty Room Design
1. Receptionist Area
● Shall have two windows, 4x4 installed level one glass with a pass through try at the bottom.
● Intercom system for both windows.
● Two file cabinets will be installed underneath the counter tops.
● The counter will extend wall to wall with pass through holes for computer cords.
● Room should have 12 receptacles underneath the counter and four on the back wall.
● Cabinet height is 30 inches x 34 inches deep.
● Intercom system should be installed for each 4x4 window.
● This area will accommodate the phone system.
2. Lobby
● Lobby walls will be constructed of ballistic sheetrock on the public side.
● All walls will have spray foam insulation for soundproofing.
● Chair rails on the walls at a height of 30 inches on the center from the floor.
● Outside of the receptionist area, a counter will be installed 12 inches deep.
3. Interview Rooms
● Each room shall have a LED recessed light, staff-side receptacle, HVAC vent on both sides.
● Light switch for both sides will be located on the staff side.
● Counter will be 30 inches high and 18 inches deep and extend from wall to wall.
● Glass will be level “1” ballistic with the glass intercom (see picture).
● Public access side will be controlled from the receptionist desk with a control panel.
● Each public access door will be solid.
● Staff-side door should have 7 in x 22 in the window.
● Should be sound proof.
● Ballistic sheetrock.
5. Kitchen
● Stainless steel double sink with extended faucet.
● Refrigerator with ice maker hooked up.
● Counter space for microwave and/or air fryer
6. Restrooms
● Staff restroom will have a stainless-steel paper towel dispenser with a trash can.
● Staff restroom will have a cabinet mounted on the wall.
● Public restrooms will have hand dryers only.
● Drug lab will have recessed paper towel dispenser with trash can.
● All toilets will be 1.6 gpm with Zurn flushometer.
7. DRC Drug Lab
● Basic refrigerator will be placed in the room.
● Stainless steel small single sink shall be installed.
● Stainless steel pass through will be installed next to the sink with access to the DRC drug screen restroom at the height of 5 ft center.
● Counter will be 35 inches deep extending wall to wall, black laminate.
● Shall have one dedicated quad receptacle and ethernet cable located above the counter.
● There shall be an eye-wash station in the drug lab.
8. Training/DRC Classrooms
● All rooms will have a chair rail at 30 inches on center height.
● Receptacles will only be located on the wall nearest to the staff desk.
● Each wall shall have fiberglass batton for soundproofing.
● An accordion wall will be installed in a classroom with a recess hideaway.
9. Utility Closet
● On demand electric water heater will be installed below the ceiling.
● Sink basin with rack installed for mops.
● One wall will have metal shelves floor to ceiling.
Supporting Systems
1. HVAC
● Heat Pump Energy Star Unit
● Air Handler be placed in center of ceiling with platform for servicing.
● Drain safeties are installed on each drain pan.
● Return air filters will be accessible from below ceiling.
● Each unit will be labeled at condenser, air handler, and breaker.
● Each air handler will be labeled at its location visible from below the ceiling.
● Lobby thermostat will be located in receptionist area with sensor in the lobby.
● Wired sensors are to be used.
● No thermostat shall be located in classrooms.
● Mini split shall be mounted in the GTA room on the exterior wall. Condenser mounted on a wall bracket.
2. Security, Fire, Camera, Door Readers
● Ultimate Security is the security and fire alarm monitoring contract.
● All alarm pads will be located at the staff rear entrance
● Cameras will have a, wall mounted, 32 inch monitor in reception area out of public view and one connected to a TV in the cubicle area. The main unit will be located in the GTA room and feed out.
3. Fire Extinguishers
● Wall mounted recessed.
● No fire extinguisher in the lobby.
● Locations include kitchen, mechanical room, GTA and electrical room, cubicle area, receptionist, copier area, and one near staff entrance. Must be to code.
4. Locks
● Schlage locks
● Master key way and standard key way for all doors.
● Entrance/Exit and all doors officer key way.
● Key fob Honey Well on all entry doors with the exception of the front door.
● Front entrance will be key master and officer key way.
5. AV Equipment
● Six 85 inch smart tv’s will be installed at designated areas with swivel brackets.
● Top of tv will be a maximum 12 inches from ceiling.
● A receptacle will be installed behind TV along with ethernet cable.
● 48 inch tv will be installed in the lobby with cable from the receptionist desk for a computer feed.
Landscape Design Integration
The landscape design will be seamlessly integrated with the building design to enhance outdoor spaces, manage stormwater, and improve biodiversity. Key elements may include:
● Native Plantings: Utilizing drought-tolerant and low-maintenance native species. Trees should be placed away from the building.
● Smart Paving: Ensuring water is moved away from the building to reduce erosion.
● Outdoor Amenity Spaces: Creating functional and inviting areas for relaxation, recreation, or gatherings.
Outdoor Security
● Black chain link fence will be provided. 8 ft tall with two strands of barbed wire.
● Fence will have a cross member 1.5 inch at top and middle. Bottom will have a tension wire.
● Sliding gate will provide access with a button touch pad with fob access. Mounted camera will monitor.
Gate will have a call intercom with control at the receptionist desk.
● Staff parking to the rear of the building behind the fenced area.
● 12x20 storage shed will be provided in the secured area with a power supply.
● Mailbox will have the ability to lock.
Example Floor Plan (Not to Scale):
Project Delivery Method:
The delivery method for this Project will be Construction Manager-at-risk (CM/GC), and, at a minimum, will employ the services of a Design Professional and a Commissioning Agent, in addition to the services of a
CM/GC.
Project Budget The preliminary Stated Cost Limitation (SCL) or construction cost of the Project is estimated at $5,000,000.
The final SCL may be revised by the Owner due to final programmatic requirements, funding availability or other circumstances.
Project Schedule:
The Design Professional’s services are anticipated to commence in accordance with the project schedule below. (Note: All of the dates indicated in this section are estimates and as such are subject to change.)
Milestone Date
GSFIC posts advertisement: October 1, 2025
Design Professional Selection: November 18, 2025
DP services begin: December 2025
Design Phase complete: March 2026
Construction Start: March 2026
Material Completion: March 2027
Open for occupancy: May 2027
Sustainable Approach:
The project will incorporate the requirements of the Energy Efficiency & Sustainable Construction Act of 2008 (O.C.G.A. 50-8-18) and it is the desire of the Owner to incorporate sustainable design and construction concepts in the project where feasible to do so. Further, Georgia Peach certification is required with commissioning.
Owner’s Project Management Program (e-Builder) The DP shall be required to use the Owner’s free Project Management Program, E-Builder, for contract administration processes including, but not limited to, Requests for Information, Change Orders, Payment Applications, Notices of Non-Compliance and Incumberance Records.
Contract Information The contract for Design Professional Services will be the GSFIC Design Professional Contract Agreement.
The agreement can be located on the Georgia State Financing and Investment Commission’s website:
https://gsfic.georgia.gov/doing-business-gsfic/construction-agreements-agency-request-form
Firms are encouraged to review and become familiar with the terms and conditions of this agreement.
Firms participating in this procurement process agree to execute the GSFIC contract form without modification.
2. PROCUREMENT PROCESS
Selection of the DP will be a multi-step process. GSFIC will generally follow the requirements of Georgia Code Title 50 Chapter 22 with respect to the selection of DP for the proposed project.
https://gsfic.georgia.gov/doing-business-gsfic/construction-agreements-agency-request-form
Step I - Request for Qualifications The selection process starts with the Request for Qualifications (“RFQ”). Interested firms shall submit Statements of Qualifications. Firms meeting the Minimum Qualifications outlined in the RFQ will have their Statements of Qualifications reviewed by Selection Committee consisting of representatives of the Using Agency, GSFIC, and possibly a third-party representative (i.e., another state representative, etc.). The Selection Committee shall score each Statement of Qualifications to create a shortlist of the firms with the most appropriate qualifications for the Project (“Finalist Firms”).
Step II - Request for Interviews Finalist Firms will be invited for Interviews with the Selection Committee. The Selection Committee will score each firm based upon the information previously submitted in Step I and Interviews.
3. TERMS
All respondents to this RFQ are subject to instructions communicated in this document and additional terms and conditions contained herein.
Restriction of Communications From the issue date of this (RFQ) solicitation until a successful proposer is selected and the selection is announced, proposers are not allowed to communicate for any reason with any members of the Selection Committee, the Using Agency, the End-User, or the Architect, except for submission of questions as instructed in the RFQ, or during the proposer’s conference (if applicable), or as provided by any existing work agreement(s). For violation of this provision, the Owner reserves the right to reject the qualifications/proposal of the offending proposer.
Submittal Costs and Confidentiality All expenses for preparing and submitting responses are the sole cost of the party submitting the response.
The Owner is not obligated to any party to reimburse such expenses. All submittals upon receipt become the property of the Owner. Labeling information provided in submittals “proprietary” or “confidential,” or any other designation of restricted use will not protect the information from public view. Subject to the provisions of the Open Records Act, the details of the proposal documents will remain confidential until final award.
Award Conditions This request is not an offer to contract or a solicitation of bids. This request and any proposal submitted in response, regardless of whether the proposal is determined to be the best proposal, is not binding upon GSFIC and does not obligate GSFIC to procure or contract for any services. Neither GSFIC nor any party submitting a response will be bound unless and until a written contract mutually accepted by both parties is negotiated as to its terms and conditions and is signed by GSFIC and a party containing such terms and conditions as are negotiated between those parties. The Owner reserves the right to waive non-compliance with any requirements of this RFQ I and to reject any or all Statements of Qualifications or Proposals submitted in response. Upon receipt and review of responses, the Owner will determine the party(s) and proposal that in the sole judgment of the Owner is in the best interest of the Owner (if any is so determined), with respect to the evaluation criteria stated herein. The Owner then intends to conduct negotiations with such party(s) to determine if a mutually acceptable contract may be reached and in the course of doing so may use ideas expressed in any proposal.
Evaluation of Submittals and Qualifications Evaluation of Statements of Qualifications, Proposals, Interviews will be conducted by a Selection Committee consisting of various project stakeholders. Based upon the predetermined rating criteria contained in the RFQ, the committee will assign a composite rating to each firm. Proposers understand and accept that by responding to this solicitation they are willingly participating in a process that consists to some degree of subjectivity on the part of selection committee members in determining the firm(s) capable of providing the best overall solution.
Reciprocal Preference Law For the purposes of evaluation only, a proposer that resides in the State of Georgia will be granted the same preference over proposers that reside in another State in the same manner, on the same basis, and to the same extent that preference is granted in awarding bids for the same goods or services by such other
State to proposers that reside therein. For the purposes of this law, the definition of a resident proposer is one who maintains a place of business with at least one employee inside the State of Georgia. A P.O. Box address will not satisfy this requirement.
Small and Minority Business Enterprise It is the policy of the state of Georgia that minority-owned business enterprises (MBE), woman-owned business enterprises (WBE) and small business enterprises (SBE), have a fair and equal opportunity to participate in the state purchasing process. Therefore, the Owner encourages all MBE, WBE and SBE to compete for contracts to provide goods, services, and construction, and encourages contractors to solicit MBE, WBE and SBE in procuring subcontractors and suppliers. This desire on the part of the Owner is not intended to restrict or limit competitive bidding or to increase the cost of the work. The Owner supports a healthy free market system that seeks to include responsible businesses and provides ample opportunity for business growth and development.
Contractors and subcontractors who utilize qualified minority subcontractors may qualify for a Georgia state income tax credits for qualified payments made to minority subcontractors. In accordance with O.C.G.A.
48-7-38, when computing taxable net income of a Georgia based corporation, partnership, or individual, there shall be subtracted from federal taxable income or federal adjusted gross income 10 percent of the amount of qualified payments to certified minority subcontractors for state-agency-related construction projects. For more information on filing only, contact the Georgia Department of Revenue at 404-417-2399.
A company cannot receive an MBE Certification with the state of Georgia government without first receiving the DBE certification. To obtain information on the DBE/MBE Certification contact:
Georgia Department of Transportation One Georgia Center 600 West Peachtree NW Atlanta, Georgia 30308 404-631-1990
DOAS Supplier Relations 200 Piedmont Avenue, S.E.
Suite 1308, West Tower Atlanta, Georgia 30334-9010 404-657-6000
Statement of Agreement With submission of a proposal, the Proposer agrees that he/she has carefully examined the Request for Proposal, and the Proposer agrees that it is the Proposer’s responsibility to request clarification on any issue(s) in any section of the Request for Proposal with which the Proposer disagrees or needs clarified.
The Proposer also understands that failure to mention these items in the proposal will be interpreted to mean that the Proposer is in full agreement with the terms, conditions, specifications and requirements in the therein. With submission of a proposal, the Proposer hereby certifies: (a) that this proposal is genuine and is not made in the interest or on behalf of any undisclosed person, firm, or corporation; (b) that Proposer has not directly or indirectly included or solicited any other Proposer to put in a false or insincere proposal;
(c) that Proposer has not solicited or induced any person, firm, or corporation to refrain from sending a proposal.
Debarred, Suspended or Ineligible Firms Contracts will not be executed and bids or proposals will not be solicited or considered from debarred, suspended or ineligible persons or firms during the period of debarment. The list of debarred, suspended or ineligible firms can be located on the Georgia State Financing and Investment Commission’s website at http://www.gsfic.georgia.gov. Once on the website, select the “Doing Business with GSFIC” tab, then select “Procurement Services,” then click on the “Debarred, Suspended or Ineligible Entities” tab for access to the list of those firms currently considered debarred, suspended or ineligible to compete, contract or subcontract for work on projects administered by the Georgia State Financing and Investment Commission.
http://www/
III REQUEST FOR QUALIFICATIONS
Step I – Request for Qualifications. All firms interested in performing DP Services shall submit a Statement of Qualifications in accordance with the terms below.
1. QUESTIONS
The deadline for submission of questions relating to the RFQ is the time and date shown in the Schedule of Events shown above. All relevant and significant questions that have been submitted in writing prior to the deadline will be compiled, and answers will be posted to the project information on the Georgia Procurement Registry at http://ssl.doas.state.ga.us/PRSapp/ . Questions from Design Professionals about any aspect of the RFI, or the project, shall be submitted in writing (e-mail is preferable) to the Point of Contact on the Project Fact Sheet.
2. MINIMUM QUALIFICATIONS
Firms must meet the following Minimum Qualifications in order to have their Statement of Qualifications reviewed and scored by the Selection Committee.
The firm or its principals are not currently ineligible, debarred, suspended, or otherwise excluded from bidding or contracting by any state or federal agency, department, or authority.
The firm or its principals have not been terminated for cause or be currently in default on any public works contract.
Firms must be registered to do business in the State of Georgia with the Georgia Secretary of State.
3. EVALUATION CRITERIA
The Selection Committee will evaluate the Statements of Qualifications which have met the above minimum qualifications according to the Criteria for the evaluation are listed below:
25% - Stability
Stability of the firm, including the firm’s corporate history, growth, resources, form of ownership, litigation history, financials, etc.
45% - Project Experience and Team Qualifications
Firm’s relevant project experience and team qualifications, including the demonstrated ability of firm in creating effective design of projects comparable in complexity, size, and function to the one contemplated hereby as well as Experience of the principal, lead designer, and project manager and team members on completed projects Previous Performance of the firm including level of quality of the services of the firm to previous customers, customer’s statements of that quality, the firm’s ability to meet established time requirements, the firm’s response to project needs during design and construction, the firm’s control of design schedule, quality, and budget. Evaluators may also consider personal or agency past experience with firms.
30% - Approach & Suitability
Firm’s suitability to provide services for the project, including the firm’s apparent fit to the project type and/or needs of the Owner, contract administration plan, proposed design timeline, any unique qualifications, any techniques and/or methodologies offered by the firm that may be particularly suitable for this project type. Current and projected workloads as well as the proximity of office to the project location.
4. STATEMENTS OF QUALIFICATIONS CONTENTS
Statements of Qualifications shall include the following information and required forms.
REQUIRED CONTENTS FOR ALL STATEMENTS OF QUALIFICATIONS
A BASIC INFORMATION AND MINIMUM QUALIFICATIONS
A-1 Provide basic company information of the Firm:
a. State company name, address, name of primary contact, telephone number and e-mail address. (If the firm has multiple offices, the qualification statement shall include information about the parent company and branch office separately.)
b. Identify the office from which the project will be managed and its proximity to the project site (“Project Managing Office or PMO”).
c. Indicate the year the Project Managing Office was established and the number of people staffing that office and their disciplines.
d. Provide form of ownership (LLC, Corporation, Partnership, etc.), including state of residency of incorporation, and the year the company was established.
e. Provide general information about the firm's personnel resources, including disciplines and numbers and classifications of employees, and locations and staffing of offices.
f. List the firm’s annual revenues for the parent office and the local office separately (if applicable) for the past 5 years.
A-2 Describe your experience with ANY litigation with Owners and/or Contractors. State basis of litigation (nonpayment, breach of contract, etc).
A-3 State whether the firm, or a member thereof, has ever been removed from a contract or failed to complete a contract as assigned? If so, provide explanation.
A-4 The firm, in order to be deemed eligible for evaluation, must provide supporting documentation asserting that the firm meets the minimum qualifications required for this project:
a. Provide the name of insurance carrier, types and levels of coverage, and deductible amounts per claim.
b. Firm has all the necessary, valid, and current license to do business in the State of Georgia as issued by the respective State Boards and Government Agencies responsible for regulating and licensing the services to be provided and performed.
Provide copies of relevant licenses. (i.e., Registered Architect, Professional Engineer, Etc.)
A-5 Complete the Certification Form (Exhibit “A” enclosed with the RFQ) and provide a notarized original with response as section “A-5” of the firm’s Statement of Qualifications.
A-6 Complete and submit a “CONTRACTOR AFFIDAVIT UNDER O.C.G.A. § 13-10-91(b)(1)” (Exhibit “B”) with response as Section “A-6” of the firm’s Statement of Qualifications. Failure to submit this form with Statement of Qualifications will result in the firm being eliminated from consideration for this project
A-7 Complete and submit the “Disclosure Statement” (Exhibit “C”) with response as Section “A7” of the firm’s Statement of Qualifications.
B EXPERIENCE AND QUALIFICATIONS
B-1 Describe your proposed design team and include an organizational chart of the team indicating the percentage of time the individual will be committed to this project.
Identify the primary point of contact.
Designate the specific individuals who will fill key roles on the team.
Provide a resume for each of the proposed team members highlighting relevant project experience.
B-2 Provide information of the firm’s experience on projects of similar type, size, function, and complexity:
Describe no more than seven (7) and no less than three (3) projects, in order of most relevant to least relevant, which demonstrate the firm's capabilities to perform the project at hand. (If a project listed was performed by an employee that previously worked at another firm, please indicate as such.)
For each project, the following information should be provided:
a. Project name, location, year completed and project photograph(s).
b. Brief description of project and physical description including project delivery method, (final construction cost, square footage, number of stories, structural or other unique components, etc.).
c. Describe similarities of the completed project to the advertised project.
d. Describe the services performed by your firm and (if multiple offices) the location of the office involved.
e. Respective Owner’s stated satisfaction in construction and service of your firm. Provide any Owner-written letters of reference/recommendation about the firm’s performance on the project.
f. Owner/User/Contractor contact information.
C DESIGN APPROACH
C-1 Provide a statement of your definition of your firm’s proposed overall role in this project, your anticipated level of management responsibility and accountability for project concerns. Describe your process for efficiently resolving issues and maintaining the project commitments while working collaboratively with the Using Agency and others as applicable, without compromising your team commitments. Provide your proposed methods and plans of communication.
C-2 Provide your proposed timeline covering the scope of design, and a detailed work plan for the project. Each milestone must include detailed steps describing the tasks to be done. Describe systems and procedures your firm uses to manage the design schedule. Describe your approach to meeting an accelerated design schedule.
C-3 Describe your plan for applying sustainable design and principles into the project or any services not specifically mentioned herein. Explain the relevance of these services to this project and how they benefit the project
C-4 Describe your overall construction administration process.
D PROJECT SUITABILITY
D-1
Provide any information that may serve to differentiate the firm from other firms in suitability for the project. Suitability may include, but is not limited to, the size and resources of the firm as related to the size and complexity on the Project, any special or unique qualifications for the project and any techniques or methodologies offered by the firm that may be particularly suitable for this project type.
List current and projected workloads with expected completion dates.
D-2 Indicate the proximity of the Project location to the firm’s office that will be managing the project.
5. SUBMITTAL OF STATEMENTS OF QUALIFICATIONS
Firms shall submit/upload one (1) electronic copy in .pdf format of the complete qualifications package to a GSFIC ftp site. Submittals must be prepared in a manner that when printed would typically fit on standard (8 ½” x 11”) paper. (The entire response shall not exceed 50 pages. Licenses and forms do not count against the page count). Submittals that include qualifications of more than one firm shall not exceed the page limits. Emphasis should be on completeness, relevance, and clarity of content. To expedite the review of submittals, it is essential that respondents follow the format and instructions outlined below:
Submit one (1) electronic copy of the complete package in .pdf format onto the GSFIC / Egnyte ftp site.
Uploaded responses (file names) must reference the RFQ No.-DP, the firm’s name, and the word
“QUALIFICATIONS.
The entire submittal should be submitted as ONE (1) file. Please do not submit individual documents or sections separately.
(File Name Example: RFQ No.-DP, ABC Company, Qualifications)
Upload Instructions:
Upload one (1) electronic copy of the complete package in .pdf format onto the GSFIC / Egnyte ftp site by selecting the link listed on the Project Fact Sheet and following the upload instructions provided below.
Click on the provided link above, when the page opens, enter name, email address, and company name, click “Continue.”
Drag and drop your file or click the “Browse” button to select a document from your computer. You should see an upload progress bar and when it gets to 100% the upload is complete.
Proposers are reminded that failure to comply with the following could result in your submission being deemed non-responsive. Non-responsive submittals will not be considered by the selection committee:
• The total page count of the submittal must not exceed 50 pages (licenses and forms do not count against the page count).
• No links to external electronic documents are permitted.
• Be sure to include the following completed exhibits in your submission. (Forms located at the end of this document):
o Exhibit A – Certification Form o Exhibit B – Contractor Affidavit under O.C.G.A. § 13-10-91(b)(l) o Exhibit C – Disclosure Statement
• Statements of Qualifications must be electronically received by the Owner prior to the deadline indicated in the Schedule of Events (located on Project Fact Sheet).
• Printed copies will not be accepted.
• Firms are encouraged to verify with GSFIC that their submittal was received and should do so on the date they are due. Contact the point of contact on the Project Fact Sheet for assistance or confirmation that the file was received.
(Experience with the ftp site indicates that uploads do not always receive the confirmation statement that the file was “successfully uploaded.” Typically, for files ranging in size from 5 – 10 Mb, it should not take more than one or two minutes to complete the upload.)
6. FINALIST NOTIFICATION
Once the Selection Committee has completed the evaluation of the Statements of Qualifications, a list of the finalist firms will be posted on the Georgia Procurement Registry.
End of Section
IV. REQUEST FOR INTERVIEW
(From Finalists Firms)
All firms selected (“Finalist Firms”) during the RFQ Process are invited to interview with the Selection Committee in accordance with the following terms.
1. QUESTIONS
The deadline for submission of questions relating to the RFI is the time and date shown in the Schedule of Events shown above. Questions from Finalist Firms about any aspect of the RFQ, or the project, shall be submitted via e-mail to the Contact on the Project Fact Sheet. All relevant and significant questions that have been submitted in writing prior to the deadline will be compiled, and answers will be provided to all Finalist Firms.
2. PRE-PROPOSAL SITE VISIT
A pre-proposal site visit may be conducted by the Owner and, if so, attendance of finalist firms will be mandatory. The date for the site visit is tentatively listed above. The site visitors will convene at a time and location to be determined and communicated in the Notice to Finalists. Additional information, possibly including some program, plans and drawings, may be available at the site visit for finalist review. The Owner reserves the right to disqualify a proposer from the selection process due to a failure by a proposer to arrive for the site visit by the scheduled time. Failure to attend a mandatory site visit will automatically result in disqualification from the selection process.
3. INTERVIEW INFORMATION
Firms selected to participate in interviews shall be notified by the Notice to Finalists letter issued by the Procurement Representative. The Notice to Finalists letter shall designate a place and time for the interview session and shall contain relevant information regarding the interviews/presentations and site visit.
The intent of the formal interview process is to provide the Selection Committee with in-depth information about the firm to make a final selection of the best-suited firm for the Project. Firms are discouraged from reviewing general company history and experience previously submitted in Statements of Qualifications unless this information is particularly relevant to the presentation. All key personnel should be present at the interview.
The interview sessions will last a total of 60 minutes. The format for the interview will be as follows:
a) Introductions & Project Approach (35 minutes) This portion of the interview is reserved for detailed introductions and presentation time. Firms may use visual aids such as PowerPoint to assist with their presentation. Firms have the flexibility to approach the presentation in a manner of their choosing. Firms should focus their presentations on their plan for managing the following construction issues:
• Specific roles of your team members, their time devoted to this project, their current workload.
• Team members relevant experience
• Construction Administration approach
• Maintaining project budget and quality control
• Unique characteristics or services the firm has to offer.
b) Questions and Answers – (25 minutes)
Twenty-five minutes of the interview time will be reserved for questions from the Selection Committee to help the Selection Committee gain additional insight into the strengths of the teams being proposed and to clarify any information presented in the Interview.
4. CRITERIA FOR THE EVALUATION OF FIRMS:
The Selection Committee will evaluate the firms based upon Qualifications and Interviews according to the Criteria for the evaluation listed below:
50% Qualifications & Experience:
Design Team Qualifications and Experience of the principal, lead designer, and project manager and team members on completed projects of similar size, type, and complexity. Previous Performance of the firm including level of quality of the services of the firm to previous customers, customer’s statements of that quality, the firm’s ability to meet established time requirements, the firm’s response to project needs during design and construction, the firm’s control of design schedule, quality, and budget. The Selection Committee may use references from stakeholders from previous projects of the finalists, as well as information submitted in Step I of this selection process.
25% Project Approach:
Design team’s project approach during design and construction - including, but not limited to, schedule, budget, quality control, and the availability of the proposed team for this project.
25% Overall Impression:
Committee’s Overall Impression of the firm(s) and its team members. The firms’ ability to effectively answer project questions and provide solutions during the interview.
5. FINAL SELECTION
Upon completion of the evaluation and interview process by the Selection Committee, the firms will be ranked in descending order of recommendation. Negotiations will then be initiated with the highest ranked firm to finalize the terms and conditions of the contract. In the event a satisfactory fee agreement cannot be reached with the highest-ranking firm, the Owner will formally terminate the negotiations in writing and enter into negotiations in turn with the second highest ranking firm and so on until a mutual agreement is established and the Owner awards an architectural services contract.
End of Section
(Exhibit A)
CERTIFICATION FORM
I, _, being duly sworn, state that I am _(title) of (firm) and hereby duly certify that I have read and understand the information presented in the attached proposal and any enclosure and exhibits thereto.
I further certify that to the best of my knowledge the information given in response to the request for proposals is full, complete and truthful.
I further certify that the proposer and any principal employee of the proposer has not, in the immediately preceding five years, been convicted of any crime of moral turpitude or any felony offense, nor has had their professional license suspended, revoked or been subjected to disciplinary proceedings.
I further certify that the proposer has not, in the immediately preceding five years, been suspended, debarred, or otherwise excluded or ineligible from contracting with any federal, state or local government agency, and further, that the proposer is not now under consideration for suspension or debarment from any such agency.
I further certify that the proposer has not in the immediately preceding five years been defaulted or terminated for cause in any federal, state, or local government agency contract and further, that the proposer is not now under any notice of intent to default on any such contract.
I acknowledge, agree and authorize, and certify that the proposer acknowledges, agrees and authorizes, that the Owner and/or GSFIC may, by means that either deems appropriate, determine the accuracy and truth of the information provided by the proposer and that the Owner and/or GSFIC may contact any individual or entity named in the Statement of Qualifications for the purpose of verifying the information supplied therein.
I acknowledge and understand the successful Proposer will be required to certify compliance with the
Immigration Reform Act of 1986 (IRCA), D.L. 99-603 and the Georgia Security and Immigration Compliance Act OCGA 13-10-90 et.seq., by meeting or having complied with the provisions in the Act and by executing any affidavits required by the rules and regulations issued by the Georgia Department of Labor set forth at Rule 300- 10-1-.01:
Contractor will also be required to warrant that Contractor has included a similar provision in all written agreements with any subcontractors engaged to perform services under this Contract.
I acknowledge and agree that all of the information contained in the Statement of Qualifications is submitted for the express purpose of inducing the Owner to award a contract.
A material false statement or omission made in conjunction with this proposal is sufficient cause for suspension or debarment from further contracts, or denial of rescission of any contract entered into based upon this proposal thereby precluding the firm from doing business with, or performing work for, the State of Georgia. In addition, such false statement or omission may subject the person and entity making the proposal to criminal prosecution under the laws of the State of Georgia of the United States, including but not limited to O.C.G.A. §16-10-20, 18 U.S.C. §§1001 or 1341.
Signature
Sworn and subscribed before me This day of , 20 .
NOTARY PUBLIC NOTARY SEAL
My Commission Expires:
(Exhibit B)
Contractor Affidavit under O.C.G.A. § 13-10-91(b)(l) The undersigned contractor ("Contractor") executes this Affidavit to comply with O.C.G.A § 13-10-91 related to any Contract to which Contractor is a party that is subject to O.C.G.A. § 13-10-91 and hereby verifies its compliance with O.C.G.A. § 13-10-91, attesting as follows:
a) The Contractor has registered with, is authorized to use and uses the federal work authorization program commonly known as E-Verify, or any subsequent replacement program;
b) The Contractor will continue to use the federal work authorization program throughout the contract period, including any renewal or extension thereof;
c) The Contractor will notify the public employer in the event the Contractor ceases to utilize the federal work authorization program during the contract period, including renewals or extensions thereof;
d) The Contractor understands that ceasing to utilize the federal work authorization program constitutes a material breach of Contract;
e) The Contractor will contract for the performance of services in satisfaction of such contract only with subcontractors who present an affidavit to the Contractor with the information required by O.C.G.A. § 13-10-91(a), (b), and (c);
f) The Contractor acknowledges and agrees that this Affidavit shall be incorporated into any contract(s) subject to the provisions of O.C.G.A. § 13-10- 91 for the project listed below to which Contractor is a party after the date hereof without further action or consent by Contractor;
and
g) Contractor acknowledges its responsibility to submit copies of any affidavits, drivers' licenses, and identification cards required pursuant to O.C.G.A. § 13-10-91 to the public employer within five business days of receipt.
Federal Work Authorization User Identification Number Date of Authorization
Name of Contractor Name of Project
Georgia State Financing and Investment Commission Name of Public Employer
I hereby declare under penalty of perjury that the foregoing is true and correct.
Executed on , 20 in (city), (state).
Signature of Authorized Officer or Agent
Printed Name and Title of Authorized Officer or Agent
SUBSCRIBED AND SWORN BEFORE ME
ON THIS THE DAY OF , 20 ,
NOTARY PUBLIC
My Commission Expires:
Exhibit C
DISCLOSURE STATEMENT
All proposers should be aware that the project you are submitting a proposal on is a public project, and the Owner (GSFIC) is a public agency. Pursuant to the laws, rules and Executive Orders of the State of Georgia, GSFIC shall make every effort to avoid even the appearance of a conflict of interest or any impropriety in both the selection process for this project and the negotiation and performance of any resulting contract. As part of any submittal you intend to make for this project, you must include this Disclosure Statement with your submittal that answers or addresses the following specific statements:
1. Describe any business transactions occurring within the prior two years between your firm and GSFIC, the Using Agency, or the ultimate end-user of the proposed project.
2. Describe any gift, hospitality, or benefit of any sort that your firm has provided to GSFIC, the Using Agency, or the end-user of the proposed project within the prior one-year period.
3. A conflict of interest or potential conflict of interest is defined as any action, decision, or recommendation by a person acting in a capacity as a public official, the effect of which is or could be to the private monetary or financial benefit or detriment of the person, the person’s relative, or any business with which the person or a relative of the person is associated. The potential conflict of interest is viewed from the perspective of a reasonable person who has knowledge of the relevant facts. Based upon this definition, describe any conflict of interest or potential conflict of interest that your firm has with GSFIC, the Using Agency, or the end-user of this project.
This Disclosure Statement should be dated and signed by an authorized signatory for the Proposer and submitted with the Proposer’s Submittal as a deliverable.
Name of Firm
Authorized Signature Date
| Georgia State Financing |
| & Investment Commission |
| I. PROJECT FACT SHEET |
| Project Description: |
| Project Delivery Method: |
| Project Schedule: |
| Sustainable Approach: |
| The project will incorporate the requirements of the Energy Efficiency & Sustainable Construction Act of 2008 (O.C.G.A. 50-8-18) and it is the desire of the Owner to incorporate sustainable design and construction concepts in the project where feasibl... |
| III REQUEST FOR QUALIFICATIONS |
| Contractor Affidavit under O.C.G.A. § 13-10-91(b)(l) |
| I hereby declare under penalty of perjury that the foregoing is true and correct. |
File details come from the government source that posted it. Updated .