This document is a Request for Response (RFR) issued by the Commonwealth of Massachusetts Department of Conservation and Recreation (DCR) for the acquisition of bundled kiln dried firewood for state park campgrounds. DCR is seeking bids from qualified contractors to provide hardwood firewood meeting specific requirements for wood type, size, moisture content, packaging, phytosanitation, and delivery. The target is to award up to three contracts with an initial term of 4 years and a 1-year renewal option. Key dates include a bid release date of 3/25/21, a bid response deadline of 4/12/21, and an estimated contract start date of 4/19/21.
The RFR provides detailed specifications for the firewood, including 100% hardwood, 16-inch lengths, and moisture content not to exceed 20%. Packaging must be .75 cubic foot bundles with a securely affixed carrying handle, and the firewood must be heat-treated to meet phytosanitation regulations. Pricing components to be evaluated include the price per bundle, quantity per pallet, and any large quantity discounts. Bidders are also required to submit a Supplier Diversity Plan. The contract will be open for use by DCR campgrounds statewide, and the vendor will be responsible for unloading and palletizing deliveries as well as removing empty pallets.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| COMMBUYS create-a-quote-v1~4.docx | DOCX document | |
| CASL_Form.rtf | RTF text file | |
| SDP Form2~65.docx | DOCX document | |
| Commonwealth Terms and Conditions for Information Technology Contracts 7-1-20.pdf | ||
| SDP Form1~63.docx | DOCX document | |
| Updated EFT form.pdf | ||
| busreffm.doc | DOC document | |
| SDP Form 3~65.xlsx | XLSX spreadsheet | |
| Standard Contract Form 7-1-20.docx | DOCX document | |
| w-9 form march 2020.pdf | ||
| promptpaydiscountform.docx | DOCX document | |
| eppform~5.docx | DOCX document | |
| DCR_839_Campground_Firewood_Responses_to_Questions_4_9_2021.docx | DOCX document | |
| Standard Contract Form Instructions and Contractor Certifications 7-1-20.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THE COMMONWEALTH OF MASSACHUSETTS
Executive Office of Energy and Environmental Affairs Department of Conservation and Recreation
251 Causeway Street, Suite 600, Boston, MA 02114
Request for Response (RFR)
Document Title: DCR 839 Campground Firewood for Massachusetts State Parks
COMMBUYS Bid#: BD-21-1020-DCRCU-DC250-60236
Agency Document Number: DCR 839 Campground Firewood for Massachusetts State Parks
03/23/21
Document Sensitivity Level: High during development; Low once published.
Revised: October 20, 2020 Procurement Scope and Description
The Commonwealth of Massachusetts Department of Conservation and Recreation is soliciting Bidders for the acquisition of bundled kiln dried firewood for state park campgrounds.
Applicable Procurement Law This Bid is issued under the following law(s):
· MGL c. 7, § 22; c. 30, § 51, § 52; and 801 CMR 21.00 (Goods and Services)
Number of awards The target maximum number of Contractors is three. This is a target number; the SST may award more or fewer Contracts if it is in the best interests of the Commonwealth to do so.
Adding Contractors after initial Contract award If, over the life of the Contract, the Strategic Sourcing Team (SST) determines that additional Contractors should be added, these may first be drawn from qualified companies which responded to this Bid but were not awarded contracts. If necessary, to meet the requirements of the Commonwealth, the Bid may be reopened to obtain additional Quotes.
Eligible Entities Any contract resulting from this Bid will be open for use to the Issuing Entity Only.
Acquisition Method(s) The acquisition method(s) to acquire goods and/or services from this Bid are Outright Purchase.
Contract Duration: The expected duration of this contract is as follows:
| Contract Duration |
| Number of Options |
| Number of Years/Months |
Initial Duration
4 years
Renewal Options
| 1 |
| 1-year option |
Total Maximum Contract Duration
No goods may be ordered and no new leases, rentals, maintenance, or other agreements for services may be executed after the Contract has expired.
Estimated Procurement Calendar
| EVENT |
| DATE |
| Bid Release Date |
| 3/25/21 |
| Deadline for Submission of Questions through COMMBUYS “Bid Q&A” |
| 4/1/21, 5 pm EST |
| Official Answers for Bid Q&A published (Estimated) |
| 4/8/21 |
| Deadline for Quotes/Bid Responses (“Bid Opening Date/Time” in COMMBUYS) |
| 4/12/21 , 5 pm Est |
| Estimated Contract Start Date |
| 4/19/21 |
Times are Eastern Standard/Daylight Savings (US), as displayed on the COMMBUYS system clock displayed to Bidders after logging in. If there is a conflict between the dates in this Procurement Calendar and dates in the Bid’s Header, the dates in the Bid’s Header on COMMBUYS shall prevail. Bidders are responsible for checking the Bid record, including Bid Q&A, on COMMBUYS for Procurement Calendar updates.
Providing Catalog Information The Contractor will be required to work with the SSSL and OSD COMMBUYS staff to develop the data and/or capabilities for specified Eligible Entities to place orders from the Contractor through COMMBUYS.
After contract execution and prior to contract start date, the Contractor will be required to complete an Excel catalog template provided by the SSSL. The template will include, but will not be limited to, the following fields to be complete fully by the Contractor:
· Item description
· UNSPSC Family and Segment numbers
· UNSPSC Class number
· Packaging type (plastic film or biodegradable plastic film)
· Unit of Measure (0.75 ft3 bundles) and (bundles/pallet)
· Unit Price (0.75 ft3 bundles) In completing the catalog template, the Contractor may be required to follow product naming conventions, include keywords and use units of measures specified by the SSSL to ensure consistent use of the resulting catalogs across all Contractors. The Contractors will also be required to revise and resubmit the completed catalog template based on SSSL’s comments. Additional information on this requirement is located in RFR Section 3.7 COMMBUYS Catalog Enablement and Updates.
Specifications
1. Wood Type: 100% Hardwood (i.e. oak, beech, ash, maple, cherry, birch, etc.). No Softwoods or low-density hardwoods such as Pine, Hemlock, Butternut, Basswood, Cottonwood, or Poplar should be included.
2. Wood dimensions: Firewood shall be cut to 16” lengths. A maximum split size must not exceed a 6” in cross section.
3. Moisture Content: Firewood needs to be delivered to the campgrounds with a moisture content no higher than 20% wet-basis. DCR reserves the right to perform tests upon the firewood at the vendor’s plant or upon delivery and reject any product that does not meet specifications.
4. Packaging: Package size is .75 cubic feet of tightly packed sticks of wood per bundle. Packaging should be of shrink wrap or equivalent durable wrapping material with a securely affixed carrying handle. Vendors are encouraged to submit pricing for biodegradable wrapping.
5. Phytosanitation: Firewood needs to be heat treated to meet all current state and federal regulations for forest pests and diseases. Documentation is required for bid evaluation and vendors may be required to attain additional compliance agreements over the life of the contract. Vendors should contact the Massachusetts Department of Agricultural Resources Crop and Pest Services for additional information about compliance agreements.
6. Delivery: Delivery is required to DCR campgrounds statewide. Delivered orders are required to be palletized. The vendor will be responsible for unloading firewood and setting pallets at grade in a location at the discretion of the park supervisor.
7. Pallet Return: Vendor is responsible for removing empty pallets.
8. Order Minimums: The vendor shall not set any minimum order size requirements.
9. Quality Control: Vendor will replace or credit any firewood bundles that DCR feels are defective from the standpoint of packaging, moisture content, inferior species, mold, insect, or other pest infestations, etc.
Commodity Specifications Functional description Kiln Dried Firewood for DCR Campgrounds Eligible commodities Kiln Dried Firewood meeting the specifications in section 2.
Quantity, size, shape, color, material As stated in section 2:
1. Wood Type: 100% Hardwood (i.e. oak, beech, ash, maple, cherry, birch, etc.). No Softwoods or low-density hardwoods such as Pine, Hemlock, Butternut, Basswood, Cottonwood, or Poplar should be included.
2. Wood dimensions: Firewood shall be cut to 16” lengths. A maximum split size must not exceed a 6” in cross section.
3. Moisture Content: Firewood needs to be delivered to the campgrounds with a moisture content no higher than 20% wet-basis. DCR reserves the right to perform tests upon the firewood at the vendor’s plant or upon delivery and reject any product that does not meet specifications.
4. Packaging: Package size is .75 cubic feet of tightly packed sticks of wood per bundle. Packaging should be of shrink wrap or equivalent durable wrapping material with a securely affixed carrying handle. Vendors are encouraged to submit pricing for biodegradable wrapping.
5. Phytosanitation: Firewood needs to be heat treated to meet all current state and federal regulations for forest pests and diseases. Documentation is required for bid evaluation and vendors may be required to attain additional compliance agreements over the life of the contract. Vendors should contact the Massachusetts Department of Agricultural Resources Crop and Pest Services for additional information about compliance agreements.
Other requirements As stated in Section 2:
1. Delivery: Delivery is required to DCR campgrounds statewide. Delivered orders are required to be palletized. The vendor will be responsible for unloading firewood and setting pallets at grade in a location at the discretion of the park supervisor.
2. Pallet Return: Vendor is responsible for removing empty pallets.
3. Order Minimums: The vendor shall not set any minimum order size requirements.
4. Quality Control: Vendor will replace or credit any firewood bundles that DCR feels are defective from the standpoint of packaging, moisture content, inferior species, mold, insect or other pest infestations, etc.
Performance specifications, durability, disclosures and recalls As stated in Section 2:
Quality Control: Vendor will replace or credit any firewood bundles that DCR feels are defective from the standpoint of packaging, moisture content, inferior species, mold, insect or other pest infestations, etc.
Geographic service and delivery areas As stated in Section 2:
Delivery is required to DCR campgrounds statewide.
Disposal services As stated in Section 2:
Pallet Return: Vendor is responsible for removing empty pallets.
Environmental Specifications As stated in Section 2:
Pallet Return: Vendor is responsible for removing empty pallets.
Vendors are encouraged to submit additional pricing for biodegradable firewood bundle wrapping in addition to conventional plastic film.
Executive Order 515, Establishing an Environmental Purchasing Policy Products and services purchased by state agencies must be in compliance with Executive Order 515, issued October 27, 2009. Under this Executive Order, Executive Departments are required to reduce their impact on the environment and enhance public health by procuring environmentally preferable products and services (EPPs) whenever such products and services perform to satisfactory standards and represent best value, consistent with 801 CMR 21.00. In line with this directive, all contracts, whether departmental or statewide, must comply with the specifications and guidelines established by OSD and the EPP Program. EPPs are considered to be products and services that help to conserve natural resources, reduce waste, protect public health and the environment, and promote the use of clean technologies, recycled materials, and less toxic products. Questions concerning the EO or the appropriate specifications may be directed to OSD’s EPP Procurement Program, www.mass.gov/epp. The Order can be seen at https://www.mass.gov/executive-orders/no-515-establishing-an-environmental-purchasing-policy.
Compensation Structure/Pricing Bids must include a price per bundle of delivered firewood. Price must be the same to all campground locations.
Bids must include a standard quantity of bundles per pallet.
Bids must include any price breaks available on large quantity deliveries.
Bids must include language stating that there is no minimum order requirement.
Cost tables Compensation will be based solely on the cost tables or catalogs supplied by the Bidder and accepted by the SSST and incorporated into a catalog on COMMBUYS.
Other Terms Reporting.
Contractors are responsible for compliance with all other contract reporting requirements including, but not limited to, Supplier Diversity Program (SDP) and other contract reports, as required by this contract.
Orders Online/web capability Prior to the Contract Start Date, the Contractor will establish and enable a COMMBUYS-compatible online catalog, which may be hosted in COMMBUYS or by the Contractor. The catalog must utilize the Commonwealth commodity codes based on the United Nations Uniform Product and Service Code (UNSPSC) and must provide specified Eligible Entities with the capability to order only those products and/or services authorized by the vendor’s contract with the Commonwealth from the Contractor using COMMBUYS. The Contractor is required to maintain the catalog for the duration of the contract and must receive prior approval from the SSL before posting any updates or changes to the catalog, which must be consistent with the terms of the contract.
Audit During the term of this Agreement and for a period of six years thereafter, Department of Conservation and Recreation, its auditors, the Operational Services Division, the Office of the Inspector General or other authorized representatives shall be afforded access at reasonable times to Contractor's accounting records, including sales information on any system, reports or files, in order to audit all records relating to goods sold or services performed pursuant to this Agreement. If such an audit indicates that Contractor has materially overcharged Department of Conservation and Recreation, then the Contractor shall remit the overcharged amount and be responsible for payment of any costs associated with the audit.
Evaluation criteria
Bidder scores will be used to rank Bidders and will determine which Bidders will proceed to subsequent stages of the evaluation and/or enter into negotiations with the Commonwealth to receive a Contract award.
Mandatory requirements
Mandatory Specifications must be met in order for a Bid to be evaluated and may be used to disqualify Bidders. In addition, certain mandatory specifications have desirable components to them that may be evaluated by the SST. The SST reserves the right, in its discretion, to determine if non-compliance with a Mandatory Specification is insignificant or can be easily corrected.
Bid sections that include terms such as: “must”, “shall”, “will” and “required” are “mandatory.” Failure to meet the requirements of a mandatory specification without providing an alternate that is acceptable to the evaluators may result in the disqualification of a Bidder's proposal.
1. Wood Type, Size, and Moisture Content:
· 100% Hardwood (i.e. oak, beech, ash, maple, cherry, birch, etc.). No Softwoods or low-density hardwoods such as Pine, Hemlock, Butternut, Basswood, Cottonwood, or Poplar should be included.
· Firewood shall be cut to 16” lengths. A maximum split size must not exceed a 6” in cross section.
· Firewood needs to be delivered to the campgrounds with a moisture content no higher than 20% wet-basis.
2. Packaging:
· Package size is .75 cubic feet of tightly packed sticks of wood per bundle. Packaging should be of shrink wrap or equivalent durable wrapping material with a securely affixed carrying handle.
· Delivered orders are required to be palletized.
3. Phytosanitation:
· Firewood needs to be heat treated to meet all current state and federal regulations for forest pests and diseases. Documentation from MDAR or USDA APHIS is required.
4. Order Minimums: The vendor shall not set any minimum order size requirements.
Evaluation Components The following components will be some of the criteria considered by the SST when evaluating each Quote:
Price Please note that price will carry a significant weight in the evaluation process.
The following price components will be evaluated:
· A price per bundle of delivered firewood. Price must be the same to all campground locations.
· A standard quantity of bundles per pallet.
· Any price breaks available on large quantity deliveries.
· Any additional prices per bundle for firewood with biodegradable wrapping
Prompt Pay Discounts (PPD)
Supplier Diversity Plan (formerly Affirmative Market Plan) (minimum of 10% weight) Bidders responding to this RFR are required to submit a Supplier Diversity Plan. Requirements for the Supplier Diversity Plan are included in Section 9.
HOW TO SUBMIT A quote
All Bidders may begin creating and compiling Quote materials as soon as the Bid with all attachments is in the Sent document status. Bidders are instructed not to submit Quotes before the Bid Amendment Deadline has been reached (see Estimated Procurement Calendar).
Quote Submission Method Online Quote Submission via COMMBUYS is required.
All Bidders must submit Quotes online using tools available only to Sellers registered in COMMBUYS. COMMBUYS provides Seller registration functionality at no charge. To register, go to www.COMMBUYS.com and click on the “Register” link on the front page. All Bidders who are awarded a contract resulting from this Bid, if any, will be required to maintain an active account during the duration of the Contract, by reviewing their registration information regularly and maintaining its accuracy.
COMMBUYS Quote Submission Training and Instructions The following resources are provided to assist Bidders in submitting Quotes:
· Appendix 4, Instructions for Vendors Responding to Bids Electronically through COMMBUYS, which is part of this document.
· Training sessions focused on online Quote submission, if offered, are noted in the Estimated Procurement Calendar;
· An online job aid on How to Create a Quote
· Webcast video on How to Find Bids (Solicitations) and Submit Quotes (Responses) through COMMBUYS.
COMMBUYS Support Technical assistance is available during the procurement process. Every effort is made to respond to inquiries within one business day.
Website: Go to www.mass.gov/osd/commbuys and select the COMMBUYS Resource Center link offered under Key Resources.
Email: Send inquiries to the OSD Help Desk at OSDHelpDesk@mass.gov Telephone: Call the OSD Help Desk at 1-888-MA-STATE (1-888-627-8283). The Help Desk is staffed from 8:00 AM to 5:00 PM Monday through Friday Eastern Standard or Daylight time, as applicable, except on federal and state holidays.
Bidders are advised that COMMBUYS will be unavailable during regularly scheduled maintenance hours of which all users will be notified.
Bid Opening Date/Time All Bids must be received by the Operational Services Division before the specified date, month, year and time displayed as the Bid Opening Date/Time in the Header Information section of the Bid in COMMBUYS. Times are Eastern Standard/Daylight Savings (US), as applicable. All Bidders are advised to allow adequate time for submission by considering potential online submission impediments like Internet traffic, Internet connection speed, file size, and file volume. OSD is not responsible for delays encountered by Bidders or their agents, or for a Bidder’s local hardware failures, such as computers or related networks, associated with bid compilation or submission. Bids submitted via COMMBUYS are time stamped by the COMMBUYS system clock which is considered the official time of record.
Quote Contents Bidders must comply with the requirements below.
Electronic Signatures Quotes submitted via COMMBUYS must be signed electronically by the Bidder or the Bidder’s Agent by accepting the terms and conditions of the bid on the “Terms & Conditions” tab of the Bid in COMMBUYS. By selecting “Save & Continue” on the “Terms and Conditions” tab after accepting the terms and conditions of the bid, the submitter attests that s/he is an agent of the Bidder with authority to sign on the Bidder’s behalf, and that s/he has read and assented to each document’s terms.
Ink Signatures Original ink signatures are required only after contracts have been awarded. The Commonwealth of Massachusetts requires Contractors to submit original ink-signature versions of the following forms:
Standard Contract Form Commonwealth Terms and Conditions/Commonwealth IT Terms and Conditions Contractor Authorized Signatory Listing Request for Taxpayer Identification and Verification (Mass. Substitute W9 Form) Electronic Funds Transfer Sign Up Form
Successful Bidders who agreed to the terms and conditions of these forms electronically via COMMBUYS online Quote submission tool must still submit the above forms with ink signatures within seven (7) calendar days of award notification or their contract may not be executed by the Commonwealth. Bidders who have previous contract(s) with the Commonwealth and have up-to-date, ink-signature versions of the Commonwealth Terms and Conditions and Request for Taxpayer Identification and Verification (Mass. Substitute W9 Form) on file with the Office of the State Comptroller may submit copies of the signed forms. However, a new Standard Contract Form and Contractor Authorized Signatory Listing with original ink signatures must be submitted for each new contract with the Commonwealth.
Limits and Restrictions
File Size Limits The system will not accept files that approach or exceed 10 MB. If a large file fails to upload, the Bidder must save the contents as multiple files. Note the naming convention used above which illustrates distinguishing multi-part files through use of Part 1, Part 2, etc. If a large file fails to upload, bidders must break up the file and append _Part1, _Part2 to the end of the Description and File Name.
File Format Restrictions Bidders must submit file formats readable by MS Word 2000 or later, or by Adobe Acrobat Reader or MS Excel or another format defined by the SSST. All scanned documents must be in .pdf or .gif format and must be scanned in such a way that they can be read on a computer monitor and printed on 81/2” x 11” paper, unless otherwise specified. Forms provided for the Bidder to complete, with the exception of the forms requiring ink signatures, must be completed and submitted in their original formats, NOT scanned and submitted as PDF or other file types.
Withdrawing a Quote Prior to Bid Opening Date/Time Quotes may be withdrawn using the “Withdraw Quote” button offered under the Summary tab of a submitted Quote.
After Bid Opening Date/Time No Quote can be withdrawn after the Bid Opening Date/Time. If the Bidder wants to remove a Quote from consideration, contact the Strategic Sourcing Services Lead for guidance.
Additional Quote Terms Prohibition regarding contract terms Bidders must not, as part of their Quote, propose additional contractual terms, or supplemental or clarifying language pertaining to contractual terms, even if the proposed additions/clarifications are not in conflict with the Commonwealth Terms and Conditions, the Standard Contract Form, or other documents comprising this RFR. It is essential for Contracting Departments that all contractors’ Statewide Contracts can be depended upon to incorporate the same terms and only those terms. Contractors who wish to propose additional non-conflicting contractual terms, or supplemental or clarifying language, may do so ONLY on a case-by-case basis, negotiated for each specific engagement and memorialized in the Project Statement of Work.
Appendix 1 – Required Terms for ALL RFRS General Procurement Information Alterations Bidders may not alter (manually or electronically) the Bid language or any Bid component files, except as directed in the RFR. Modifications to the body of the Bid, specifications, terms and conditions, or which change the intent of this Bid are prohibited and may disqualify a Quote.
Ownership of Submitted Quotes The SST shall be under no obligation to return any Quotes or materials submitted by a Bidder in response to this Bid. All materials submitted by Bidders become the property of the Commonwealth of Massachusetts and will not be returned to the Bidder. The Commonwealth reserves the right to use any ideas, concepts, or configurations that are presented in a Bidder’s Quote, whether or not the Quote is selected for Contract award.
Quotes stored on COMMBUYS in the encrypted lockbox are the file of record. Bidders retain access to a read-only copy of this submission via COMMBUYS, as long as their account is active. Bidders may also retain a traditional paper copy or electronic copy on a separate computer or network drive or separate media, such as CD or DVD, as a backup.
Prohibitions Bidders are prohibited from communicating directly with any employee of the procuring Department or any member of the SST regarding this RFR except as specified in this RFR, and no other individual Commonwealth employee or representative is authorized to provide any information or respond to any question or inquiry concerning this RFR. Bidders may contact the contact person using the contact information provided in the Header Information this Bid in the event that this RFR is incomplete or information is missing. Bidders experiencing technical problems accessing information or attachments stored on COMMBUYS should contact the OSD Help Desk (see the document cover page for contact information).
In addition to the certifications found in the Commonwealth’s Standard Contract Form, by submitting a Quote, the Bidder certifies that the Quote has been arrived at independently and has been submitted without any communication, collaboration, or without any agreement, understanding or planned common course or action with, any other Bidder of the commodities and/or services described in the RFR.
Terms and Requirements Pertaining to Awarded Contracts Commonwealth Tax Exemption Invoices or invoices submitted to Massachusetts government entities must not include sales tax.
Contractor’s Contact Information It is the Contractor’s responsibility to keep the Contractor’s Contract Manager information current. If this information changes, the Contractor must notify the Contract Manager by email immediately, using the address located in the Header Information of the Purchase Order or Master Blanket Purchase Order on COMMBUYS.
The Commonwealth assumes no responsibility if a Contractor’s designated email address is not current, or if technical problems, including those with the Contractor’s computer, network or internet service provider (ISP), cause e-mail communications between the Bidder and the SST to be lost or rejected by any means including email or spam filtering.
Publicity Any Contractor awarded a contract under this Bid is prohibited from selling or distributing any information collected or derived from the Contract, including lists of participating Eligible Entities, Commonwealth employee names, telephone numbers or addresses, or any other information except as specifically authorized by the SST.
Appendix 2 - RFR - Required Specifications
1. Wood Type: 100% Hardwood (i.e. oak, beech, ash, maple, cherry, birch, etc.). No Softwoods or low-density hardwoods such as Pine, Hemlock, Butternut, Basswood, Cottonwood, or Poplar should be included.
2. Wood dimensions: Firewood shall be cut to 16” lengths. A maximum split size must not exceed a 6” in cross section.
3. Moisture Content: Firewood needs to be delivered to the campgrounds with a moisture content no higher than 20% wet-basis. DCR reserves the right to perform tests upon the firewood at the vendor’s plant or upon delivery and reject any product that does not meet specifications.
4. Packaging: Package size is .75 cubic feet of tightly packed sticks of wood per bundle. Packaging should be of shrink wrap or equivalent durable wrapping material with a securely affixed carrying handle. Vendors are encouraged to submit pricing for biodegradable wrapping.
5. Phytosanitation: Firewood needs to be heat treated to meet all current state and federal regulations for forest pests and diseases. Documentation is required for bid evaluation and vendors may be required to attain additional compliance agreements over the life of the contract. Vendors should contact the Massachusetts Department of Agricultural Resources Crop and Pest Services for additional information about compliance agreements.
6. Delivery: Delivery is required to DCR campgrounds statewide. Delivered orders are required to be palletized. The vendor will be responsible for unloading firewood and setting pallets at grade in a location at the discretion of the park supervisor.
7. Pallet Return: Vendor is responsible for removing empty pallets.
8. Order Minimums: The vendor shall not set any minimum order size requirements.
9. Quality Control: Vendor will replace or credit any firewood bundles that DCR feels are defective from the standpoint of packaging, moisture content, inferior species, mold, insect or other pest infestations, etc.
APPENDIX 3 Instructions for Execution and Submission of Commonwealth Standard Forms
Some of the forms listed below can be electronically signed by the Bidder, see Electronic Signatures. However, online Bidders must, if notified of Contract award, submit the following four (4) forms on paper with original ink signatures unless otherwise specified below, within the timeframe referenced in the RFR section entitled Ink Signatures: the Commonwealth Standard Contract Form, the Commonwealth Terms and Conditions, the Request for Taxpayer Identification Number and Certification (Mass. Substitute W9 Form) and the Contractor Authorized Signatory Listing.
Commonwealth Standard Contract Form Sign electronically as described above; if notified of Contract award, complete as directed below and submit on paper with original ink signature and date.
By executing this document or signing it electronically, the Bidder certifies, under the pains and penalties of perjury, that it has submitted a Response to this RFR that is the Bidder’s Offer as evidenced by the execution of its authorized signatory, and that the Bidder’s Response may be subject to negotiation by the SST. Also, the terms of the RFR, the Bidder’s Response and any negotiated terms shall be deemed accepted by the Operational Services Division and included as part of the Contract upon execution of this document by the State Purchasing Agent or his designee.
If the Bidder does not have a Vendor Code beginning with “VC,” or does not know what their Vendor Code is, the Bidder should leave the Vendor Code field blank. The Bidder should NOT enter a Vendor Code assigned prior to May 2004, as new Vendor Codes have been assigned to all companies since that time.
Signature and date MUST be handwritten in ink, and the signature must be that of one of the people authorized to execute contracts on behalf of the Contractor on the Contractor Authorized Signatory Listing (See below).
Commonwealth Terms and Conditions/Commonwealth IT Terms and Conditions Sign electronically as described above; if notified of Contract award, complete as directed below and submit on paper with original ink signature and date, or submit a copy of a previously executed, up-to-date copy of the appropriate form as directed below.
If the Bidder has already executed and filed the appropriate Commonwealth Terms and Conditions form pursuant to another RFR or Contract, a copy of this form may be included in place of an original. If the Bidder’s name, address or Tax ID Number have changed since the Commonwealth Terms and Conditions form was executed, a new Commonwealth Terms and Conditions form is required. The Commonwealth Terms and Conditions are hereby incorporated into any Contract executed pursuant to this RFR.
This form must be unconditionally signed by one of the authorized signatories (see Contractor Authorized Signatory Listing, below), and submitted without alteration. If the provisions in this document are not accepted in their entirety without modification, the entire Proposal offered in response to this Solicitation may be deemed non-responsive.
The company’s correct legal name and legal address must appear on this form and must be identical to the legal name and legal address on the Request for Taxpayer Identification and Certification Number (Mass. Substitute W9 Form).
Request for Taxpayer Identification Number and Certification (Mass. Substitute W9 Form) Sign electronically as described above; if notified of Contract award, complete as directed below and submit on paper with original ink signature and date, or submit a copy of a previously executed, up-to-date copy of the form as directed below.
If a Bidder has already submitted a Request for Taxpayer Identification and Certification Number (Mass. Substitute W9 Form) and has received a valid Massachusetts Vendor Code, an original W-9 form is not required. A copy of the form as filed may be included in place of an original. If the Bidder’s name, address or Tax ID Number have changed since the Mass. Substitute W9 Form was executed, a new Mass. Substitute W9 Form is required. The information on this form will be used to record the Bidder’s legal address and where payments under a State Contract will be sent. The company’s correct legal name and legal address must appear on this form and must be identical to the legal name and legal address on the Commonwealth Terms and Conditions. Please do not use the U.S Treasury’s version of the W9 Form.
Contractor Authorized Signatory Listing Sign electronically as described above; if notified of Contract award, complete as directed below and submit on paper with original ink signature and date.
In the table entitled “Authorized Signatory Name” and “Title,” type the names and titles of those individuals authorized to execute contracts and other legally binding documents on behalf of the Bidder. Bidders are advised to keep this list as small as possible, as Contractors will be required to notify the Procurement Manager of any changes. If the person signing in the signature block on the bottom of the first page of this form will also serve as an “Authorized Signatory,” that person’s name must be included in the typed table.
With regard to the next paragraph, which begins “I certify that I am the President, Chief Executive Officer, Chief Fiscal Officer, Corporate Clerk or Legal Counsel for the Contractor…,” if your organization does not have these titles, cross them out and handwrite the appropriate title above the paragraph.
The signature and date should be handwritten in ink. Title, telephone, fax and email should be typed or handwritten legibly.
The second page of the form (entitled “Proof of Authentication of Signature”) states that the page is optional. However, the “optional” aspect of the form is that Commonwealth Departments are not required to use it. In the case of Statewide Contracts, this page is REQUIRED, not optional. The person signing this page must be the same person signing the Standard Contract Form, the Commonwealth Terms and Conditions, and the RFR Checklist.
Please note that in two places where the form says, “in the presence of a notary,” this should be interpreted to mean “in the presence of a notary or corporate clerk/secretary.” Either a notary or corporate clerk/secretary can authenticate the form; only one is required.
Organizations whose corporate clerks/secretaries authenticate this form are not required to obtain a Corporate Seal to complete this document.
Supplier Diversity Program Plan Form 1 Download this form and complete as directed below; include with online submission. Ink signature is not required.
The specific Supplier Diversity Program (SDP) requirements for this procurement can be found earlier in this document. Bidders are required to state a specific percentage of contract revenues that will represent the SDP annual commitment for the entire contract period, including any renewals.
Current Environmentally Preferable Products / Practices Form Prompt Payment Discount Form Download this form and complete as directed below; include with online submission. Ink signature is not required.
Pursuant to the Prompt Payment Discount terms set forth in the RFR Required Specifications for Contracts and on the Prompt Payment Discount Form itself, all Bidders must execute this form. After entering the “Bidder Name” and “Date of Offer for Prompt/Early Payment Discount”, the Bidder must identify the prompt payment discount(s) terms by indicating the “Percentage Discount off of the Proposed Pricing” and the “Turn-around-time for Payments.” In the event of a hardship that prevents the Bidder from offering a prompt payment discount, the Bidder must document this fact and provide supporting information. If awarded a contract, the final negotiated prompt payment discounts should be reflected on the Commonwealth Standard Contract Form.
appendix 4 Instructions for Vendors Responding to Bids Electronically through COMMBUYS
Introduction COMMBUYS refers to all solicitations, including but not limited to Requests for Proposals (RFP), Invitations for Bid (IFB), Requests for Response (RFR), Requests for Quote (RFQ), as “Bids.” All responses to Bids are referred to as “Quotes.”
Steps for Bidders to Submit a Quote
1. Launch the COMMBUYS website by entering the URL (www.COMMBUYS.com) into the browser.
2. Enter Bidder login credentials and click the Login button on the COMMBUYS homepage. Bidders must be registered in COMMBUYS in order to submit a Quote. Each Vendor has a COMMBUYs Seller Administrator, who is responsible for maintaining authorized user access to COMMBUYS.
3. Upon successful login, the Vendor home page displays with the Navigation and Header Bar as well as the Control Center. The Control Center is where documents assigned to your role are easily accessed and viewed.
4. Click on the Bids tab
5. Clicking on the Bid tab opens four sections:
a. Request for Revision
b. Bids/Bid Amendments
c. Open Bids
d. Closed Bids
6. Click on the blue Open Bid hyperlinks to open and review an open bid
7. A new page opens with a message requesting you acknowledge receipt of the bid. Click Yes to acknowledge receipt of the bid. Bidders should acknowledge receipt to receive any amendments/updates concerning this bid.
8. After acknowledgement, the bid will open.
The top left half of the page contains the following information:
a. Purchaser
b. Department
c. Contact for this bid
d. Type of purchase
i. Open Market
ii. Blanket
e. Pre-Bid Conference details (if applicable)
f. Ship-to and Bill-to addresses
g. Any attachments to the bid, which may include essential bid terms, response forms, etc.
The top right half of the bid includes the following information:
h. Bid Date
i. Required Date
j. Bid Opening Date – date the bid closes and no further quotes will be accepted
k. Informal Bid Flag
l. Date goods/services are required
9. The lower half of the page provides information about the specific goods/services the bid is requesting.
10. Click Create Quote to begin.
11. The General tab for a new quote opens. This page is populated with some information from the bid. Fields available to update include:
a. Delivery days
b. Shipping terms
c. Ship via terms
d. Is “no” bid – select if you will not be submitting a quote for this bid
e. Promised Date
f. Info Contact
g. Comments
h. Discount Percent
i. Freight Terms
j. Payment Terms It is important to note that the bid documents (RFR and attachments) may specify some or all of these terms and may prohibit you from altering these terms in your response. Read the bid documents carefully and fill in only those items that are applicable to the bid to which you are responding.
Update these fields as applicable to the bid and click Save & Continue to save any changes and create a Quote Number. The page refreshes and messages display. Any message in Red is an error and must be resolved before the quote can be submitted. Any message in Yellow is only a warning and will allow processing to continue.
The following messages are received:
Terms & Conditions is not acknowledged – to resolve this, click on the Terms & Conditions tab and accept the terms. Your quote has not been submitted – information message; no action required
12. Click on the Terms & Conditions Tab. This tab refers to the terms and conditions that apply to this bid. The terms and conditions must be accepted before your quote can be submitted. If your acceptance is subject to any exceptions, those exceptions must be identified here. Exceptions cannot contradict the requirements of the RFR or required Commonwealth standard forms and attachments for the bid. For instance, an RFR may specify that exceptions may or will result in disqualification of your bid.
13. Click the Items tab. The Items tab displays information about the items requested in the bid. To view additional details about an item, click the item number (blue hyperlink) to open.
14. The item opens. Input all of your quote information and click Save & Exit.
15. CONFIDENTIAL INFORMATION: If documents uploaded in your quote response contain confidential information (security sensitive, EFT, W9, Commonwealth Terms and Conditions), you must mark each item as confidential. The confidential column on the Attachments view allows the user to select whether the attached form is confidential or not. Place a check box under the confidential column for each confidential attached form.
16. Click on the Attachments Tab. Follow the prompts to upload and name all required attachments and forms and bid response documents in accordance with the instructions contained in the solicitation or bid documents. After uploading each individual file or form, click Save & Continue. After you have uploaded all required documents click Save & Exit. Be sure to review your attachments to make sure each required document has been submitted.
17. Click the Summary tab. Review the information and update/correct, as needed. If the information is correct, click the Submit Quote button at the bottom of the page.
18. A popup window displays asking for verification that you wish to submit your quote. Click OK to submit the quote.
19. The Summary tab redisplays with an updated Status for the quote of Submitted.
20. Your quote submission is confirmed only when you receive a confirmation email from COMMBUYS. If you have submitted a quote and have not received an email confirmation, please contact the OSD Help Desk at OSDHelpDesk@mass.gov. If you wish to revise or delete a quote after submission, you may do so in COMMBUYS: (1) for a formal bid, prior to the bid opening date, or (2) for an informal bid (which may be viewed upon receipt), prior to the opening of your quote by the issuing entity or the bid opening date, whichever is earlier.
Bidders may not submit Multiple Quotes in response to a Bid unless the Bid authorizes Multiple Quote submissions. If you submit multiple quotes in response to a bid that does not allow multiple quotes, only the latest submission prior to the bid opening date will be evaluated.
ANF guideline 801 CMR 21.06(10) states that: Responses that neglect to meet, address, or comply with material necessities, including directions for submission, content, or format will be disqualified. All documents are required to be submitted accurately to Commbuys. In the event that DCR cannot grant the award through Commbuys, the vendor response will be dismissed and considered non-responsive. Please ensure that you have not just uploaded your response, and that you have completed all necessary steps for DCR to make an award through Commbuys. If you need assistance with your submission, please contact the OSD help desk for support
RFR DCR 839/ COMMBUYS
Document Sensitivity Level: High during development; Low once published.
image2.png image2.jpeg image1.png
File details come from the government source that posted it. Updated .